HomeMy WebLinkAboutFORT COLLINS JEEP - FDP - FDP170035 - SUBMITTAL DOCUMENTS - ROUND 1 - DRAINAGE REPORTFINAL DRAINAGE REPORT
Fort Collins Jeep Dealership
Fort Collins, Colorado
Project #PDP170013
November 6, 2017
PREPARED FOR:
Commercial Building Services
7561 S. Grant Street, Suite A-4
Littleton, CO 80122
Contact: Steve Morel
(303) 730-3001
PREPARED BY:
PARAGON ENGINEERING CONSULTANTS, INC.
7852 South Elati Street, Suite 106
Littleton, CO, CO. 80120
(303) 794-8604
Paragon Project No. 16-018
Paragon Engineering Consultants, Inc. Page 1
Table of Contents
I. GENERAL LOCATION AND DESCRIPTION............................................................. 2
A. Site Location .................................................................................................................... 2
B. Description of Property .................................................................................................... 3
C. Floodplain Submittal Requirements ................................................................................. 4
II. MAJOR DRAINAGE BASINS AND SUB-BASINS ...................................................... 4
A. Major Drainage Basins ..................................................................................................... 4
B. Sub-basins ........................................................................................................................ 4
III. DRAINAGE DESIGN CRITERIA .................................................................................. 5
A. Regulations ....................................................................................................................... 5
B. Directly Connected Impervious Area ............................................................................... 6
C. Development Criteria Reference and Constraints ............................................................ 6
D. Hydrologic Criteria .......................................................................................................... 6
E. Hydraulic Criteria ............................................................................................................. 6
F. Floodplain Regulations Compliance ................................................................................ 7
G. Modifications of Criteria .................................................................................................. 7
IV. DRAINAGE FACILITY DESIGN ................................................................................... 7
A. General Concept ............................................................................................................... 7
B. Specific Details ................................................................................................................ 7
V. CONCLUSIONS ................................................................................................................ 8
VI. REFERENCES ................................................................................................................... 8
Appendix A – Vicinity Map, Soils Map, Floodplain Checklist
Appendix B – Hydrologic Computations
Appendix C – Hydraulic Calculations
Paragon Engineering Consultants, Inc. Page 2
I. GENERAL LOCATION AND DESCRIPTION
A. Site Location
Fort Collins Jeep Dealership is located on a site currently containing 4.48 acres northwest of the
intersection of South Mason Street and West County Road 38 in the City of Fort Collins, Larimer
County, Colorado. The site lies in the Southeast ¼ of Section 35, Township 7 North, Range 69
West of the 5
th
Principal Meridian. It is bounded on the north by an existing car dealership
(Pedersen Volvo), on the east by South Mason Street with existing commercial development
beyond, on the south by existing West County Road 38, with existing educational development
beyond, and on the west by existing bus road, with railroad with existing railway, greenbelt and
residential area beyond.
Paragon Engineering Consultants, Inc. Page 3
B. Description of Property
The existing site was built as a lumber yard, but has not been used for that purpose for some time.
Detention appears not to have been required for the site when it was built in 1974, as none is in
evidence.
Paragon Engineering Consultants, Inc. Page 4
The current area of the site is 4.48 acres. However, South Mason Street is slated for “midtown”
redevelopment, and an additional 0.13 acres of additional right-of-way is being requested by the
City of Fort Collins to expand South Mason Street.
The main building of the site will remain (will be remodeled), with two areas of expansion, one
on the west side of the building, and one on the north. An outdoor lumber storage area on the east
side of the existing building will be removed, as well as a raised concrete loading dock on the west
side of the site and other concrete pad areas. The aging pavement on the site will be removed and
replaced. The proposed use is car dealership.
Soils on the site, according to USDA National Soil Conservation website, consist of Nunn clay
loam- Hydrologic Soil Type C (94% of site) with a small area of Altvan-Satanta loams (6%) –
Hydrologic Soil Type B, in the northeast corner of the site. Fort Collins Jeep Dealership is located
outside the 100-year floodplain, according to FEMA FIRM map panel 08069C1000F (Map Panel
Not Printed.)
C. Floodplain Submittal Requirements
Fort Collins Jeep Dealership is located outside the 100-year floodplain, according to FEMA FIRM
map panel 08069C1000F (Map Panel Not Printed). See “City of Fort Collins Floodplain Review
Checklist 50% Development Review Submittals” in Appendix A.
II. MAJOR DRAINAGE BASINS AND SUB-BASINS
A. Major Drainage Basins
The site is located within the Mail Creek Basin, a basin of approximately 1,676 acres in southwest
Fort Collins. To the east of the site is College Avenue, which runs north-south and consists of
commercial development along the length. The remainder of the basin consists of mixed-use
residential development. The basin generally drains west to east to the confluence of Mail Creek
and Fossil Creek, and ultimately to Fossil Creek Reservoir. (City of Fort Collins 2017)
B. Sub-basins
The current drainage pattern consists of a large shallow swale within the west parking area of the
site, which directs runoff south to W. County Road 38 via an existing sidewalk chase. The east
side of the site slopes to the east from the east side of the main building, towards South Mason
Street via a drive entrance located near the south end of the South Mason Street frontage. Both
streets drain to the intersection of South County Road 38, and South Mason Street to an existing
10’ Type R inlet located on the South Mason Street side of the intersection. This inlet will be
moved west approximately 7’ to be in line with the proposed street widening of South Mason
Street There is also a low area in the southwest corner of the site, with no apparent outlet.
Proposed Sub-basins
The proposed grading will follow a similar pattern. The entrance locations will both change. The
W. County Road 38 entrance will be reduced in width to accommodate a bus pullout proposed to
Paragon Engineering Consultants, Inc. Page 5
be built immediately west of the drive (eliminating traffic hazard from buses stopping in the lane
of this busy street.)
The South Mason Street entrance will be moved approximately 300 feet north to near the northeast
corner of the site. The runoff which previously drained to the entrance will be re-routed to South
Mason Street with a small channel and chase section located near the southeast corner of the new
proposed parking lot.
A low area in the southwest corner of the site, with no apparent outlet, will be raised such that the
runoff can be directed to the sidewalk chase at the low point in the parking area east of the West
County Road 38 drive entrance.
Proposed Basin A (0.22 acres of pavement) sheet flows to a 2-foot wide concrete pan which directs
runoff to Bioretention Pond A.
Proposed Basin B (0.33 acres of pavement) sheet flows to a 2-foot wide concrete pan which directs
runoff to Bioretention Pond B.
Proposed Basin C (1.72 acres of pavement and roof) sheet flows to a 2-foot wide concrete pan
which directs runoff to Bioretention Pond C.
Proposed Basin D (0.15 acres of pavement) sheet flows to a 2-foot wide sidewalk chase which
directs runoff to the north flowline of West Harmony Road. Runoff then flows east to the relocated
Type R inlet at the NW corner of West Harmony Road and South Mason Street.
Proposed Basin E (0.39 acres of pavement and roof) sheet flows to a 2-foot wide sidewalk chase
which directs runoff to the west flowline of South Mason Street. Runoff the flows south to the
relocated Type R inlet at the NW corner of West Harmony Road and South Mason Street.
Proposed Basin F (0.42 acres of pavement and roof) sheet flows to a 2-foot wide sidewalk chase
which directs runoff to the west flowline of South Mason Street. Runoff the flows south to the
relocated Type R inlet at the NW corner of West Harmony Road and South Mason Street.
Proposed Basin G (0.56 acres of pavement and roof) sheet flows to a 2-foot wide sidewalk chase
which directs runoff to the north flowline of West Harmony Road. Runoff then flows east to the
relocated Type R inlet at the NW corner of West Harmony Road and South Mason Street.
III. DRAINAGE DESIGN CRITERIA
A. Regulations
The design of the proposed stormwater management system was done in compliance with Fort
Collins Amendments to the Urban Drainage and Flood Control District, Urban Storm Drainage
Criteria Manual Volumes 1, 2 and 3. (UDFCD 2017)
When improvements are proposed to an existing developed site and there is an increase in
Paragon Engineering Consultants, Inc. Page 6
impervious area greater than 1000 square feet, onsite detention is required. The existing site
impervious area is 158,473 square feet and the proposed impervious area is 159,188 resulting in a
net increase in impervious area of 715 square feet therefore detention is not required. Low Impact
Development (LID) requirements are required on all redeveloped property. 75% of all newly added
or modified impervious are must be treated by LID techniques. There is 122,865 square feet of
redeveloped area onsite and 75% of this area is 92,149 square feet or 2.12 acres. This area will be
treated with three onsite Rain Gardens aka Bioretention Ponds. The Bioretention Ponds will drain
to the 10’ Type R Inlet at the SE corner of the site via a common 6” HPDE outfall pipe.
B. Directly Connected Impervious Area
The existing site will be redeveloped with a minimum increase in Directly Connected Impervious
Area. The increase in impervious area is 715 square feet, a 0.45% increase.
C. Development Criteria Reference and Constraints
The existing site has no stormwater management infrastructure, and drains undetained off-site.
The proposed stormwater management improvements meet Low Impact Development
requirements and will improve water quality and impact.
D. Hydrologic Criteria
Design rainfall values from “Table RA-8 – City of Forst Collins Rainfall Intensity-Duration-
Frequency Table for Use with the Rational Method” were used for the design rainfall. (Fort Collins
2016)
The Rational Method was used to determine peak runoff from sub-basins A, B, and C, for which
the methodology and tables as presented in the Urban Storm Drainage Criteria Manual were used
to determine Rational “C” coefficients, and time of concentrations. Calculations can be found in
Appendix B of this report.
E. Hydraulic Criteria
The UDFCD spreadsheet titled “UD-Detention” (Version 3.07, February 2017) was used to
calculate both the required water quality capture volume for the three rain gardens and the
geometry of the rain gardens. In accordance with LID requirements, Water Quality will be
provided for 75% of the redeveloped area, 2.12 acres. The Water Quality Volume is calculated on
a per basin basis. The calculations can be found in Appendix C of this report.
Autodesk Hydroflow Express was used to calculate the sizing of the rain garden underdrain. The
calculation can be found in Appendix C of this report.
Paragon Engineering Consultants, Inc. Page 7
F. Floodplain Regulations Compliance
Fort Collins Jeep Dealership is located outside the 100-year floodplain, according to FEMA FIRM
map panel 08069C1000F (Map Panel Not Printed). See “City of Fort Collins Floodplain Review
Checklist 50% Development Review Submittals” in Appendix A.
G. Modifications of Criteria
No modifications of the criteria are proposed.
IV. DRAINAGE FACILITY DESIGN
A. General Concept
The general drainage concept is to capture 75% of the redeveloped impervious area and treat it by
LID techniques via rain gardens. Sub-basins A, B, and C have been designed to total this area.
Runoff will drain to these three rain gardens, where it will be treated. Treated water will discharge
via a 6” HPDE storm pipe to the existing storm sewer at West County Road 38 and South Mason
Street.
Sub-basins D, E, F, and G will not be detained or treated and will drain off-site.
B. Specific Details
Surface runoff from sub-basins A, B, and C will sheet flow over pavement to concrete pans, then
collect in rain garden bioretention BMPs. The rain gardens are individually sized to the water
quality capture volume (WQCV) of their associated basins.
The three rain garden bioretention BMPs will be constructed with an impermeable liner on the
bottom, a 4” slotted PVC under-drain pipe embedded in a 6” thick layer of CDOT Class B filter
material, and an 18” layer of filter media on top. The 4” under-drain will have 4” cleanouts to
provide maintenance access. A concrete outlet structure will have inlet(s) to receive discharge from
the under-drain pipe(s) to receive discharge from the WQCV and an inlet grate to receive discharge
in excess of the WQCV. A 6” HDPE outlet pipe will discharge from the outlet structure to a
proposed 10’ Type R Inlet at the intersection of West County Road 38 and South Mason Street.
The storm water will then discharge to the existing storm sewer via a proposed manhole
constructed on the existing storm sewer.
In accordance with the LID techniques pertinent to the site, only the WQCV must be detained and
treated, and only for 75% of the total redeveloped area. Runoff in excess of the WQCV will pond
and discharge into the outlet structure inlet grate. If the ponding capacity is exceeded, the runoff
discharge off-site to West County Road 38.
Sub-basins D, E, F, and G will not be detained or treated and will drain off-site. These areas do
not require detention or treatment, as the LID requirement is satisfied by the rain garden
bioretention BMPs for sub-basins A, B, and C. Sub-basins D and G will discharge to West County
Road 38 via a curb cut. Sub-basins E and F will discharge to South Mason Street via the driveway
Paragon Engineering Consultants, Inc. Page 8
at the northeast corner of the site.
V. CONCLUSIONS
The stormwater management system for the site has been designed in compliance to the Fort
Collins Amendments to the Urban Storm Drainage Criteria Manual Volumes 1, 2, and 3. Low
Impact Development (LID) requirements were followed to determine BMP requirements.
The development of the site will increase the impervious area of the site from 158,473 square feet
to 159,188 square feet, an increase of 715 square feet. The stormwater management system will
capture and treat stormwater in accordance with the above criteria, and overall will improve the
water quality of stormwater and reduce the discharge off-site into the roadway.
VI. REFERENCES
1. City of Fort Collins, 2017. Mail Creek. Retrieved July 17, 2017, from
https://www.fcgov.com/utilities/what-we-do/stormwater/drainage-basins/mail-creek-
basin
2. Urban Drainage and Flood Control District (UDFCD). 2017. Drainage Criteria Manual,
Volumes 1, 2, & 3, Urban Drainage and Flood Control District.
3. City of Fort Collins, 2016. Fort Collins Amendments to the Urban Drinage and Flood
Control District Criteria Manual.
Appendix A – Vicinity Map, Soils Map, Floodplain Checklist
Hydrologic Soil Group—Larimer County Area, Colorado
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/12/2017
Page 1 of 4
4485860 4485880 4485900 4485920 4485940 4485960 4485980 4486000 4486020 4486040 4486060
4485860 4485880 4485900 4485920 4485940 4485960 4485980 4486000 4486020 4486040 4486060
493170 493190 493210 493230 493250 493270 493290 493310
493170 493190 493210 493230 493250 493270 493290 493310
40° 31' 31'' N
105° 4' 50'' W
40° 31' 31'' N
105° 4' 44'' W
40° 31' 24'' N
105° 4' 50'' W
40° 31' 24'' N
105° 4' 44'' W
N
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 13N WGS84
0 45 90 180 270
Feet
0 10 20 40 60
Meters
Map Scale: 1:1,010 if printed on A portrait (8.5" x 11") sheet.
Soil Map may not be valid at this scale.
MAP LEGEND MAP INFORMATION
Area of Interest (AOI)
Area of Interest (AOI)
Soils
Soil Rating Polygons
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Soil Rating Lines
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Soil Rating Points
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Water Features
Streams and Canals
Transportation
Rails
Interstate Highways
US Routes
Major Roads
Local Roads
Background
Aerial Photography
The soil surveys that comprise your AOI were mapped at
1:24,000.
Warning: Soil Map may not be valid at this scale.
Enlargement of maps beyond the scale of mapping can cause
misunderstanding of the detail of mapping and accuracy of soil
line placement. The maps do not show the small areas of
contrasting soils that could have been shown at a more detailed
scale.
Please rely on the bar scale on each map sheet for map
measurements.
Source of Map: Natural Resources Conservation Service
Web Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator
projection, which preserves direction and shape but distorts
distance and area. A projection that preserves area, such as the
Albers equal-area conic projection, should be used if more
accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as
Hydrologic Soil Group
Hydrologic Soil Group— Summary by Map Unit — Larimer County Area, Colorado (CO644)
Map unit symbol Map unit name Rating Acres in AOI Percent of AOI
4 Altvan-Satanta loams, 3
to 9 percent slopes
B 0.2 5.0%
74 Nunn clay loam, 1 to 3
percent slopes
C 4.4 92.1%
75 Nunn clay loam, 3 to 5
percent slopes
C 0.1 2.8%
Totals for Area of Interest 4.7 100.0%
Description
Hydrologic soil groups are based on estimates of runoff potential. Soils are
assigned to one of four groups according to the rate of water infiltration when the
soils are not protected by vegetation, are thoroughly wet, and receive
precipitation from long-duration storms.
The soils in the United States are assigned to four groups (A, B, C, and D) and
three dual classes (A/D, B/D, and C/D). The groups are defined as follows:
Group A. Soils having a high infiltration rate (low runoff potential) when
thoroughly wet. These consist mainly of deep, well drained to excessively
drained sands or gravelly sands. These soils have a high rate of water
transmission.
Group B. Soils having a moderate infiltration rate when thoroughly wet. These
consist chiefly of moderately deep or deep, moderately well drained or well
drained soils that have moderately fine texture to moderately coarse texture.
These soils have a moderate rate of water transmission.
Group C. Soils having a slow infiltration rate when thoroughly wet. These consist
chiefly of soils having a layer that impedes the downward movement of water or
soils of moderately fine texture or fine texture. These soils have a slow rate of
water transmission.
Group D. Soils having a very slow infiltration rate (high runoff potential) when
thoroughly wet. These consist chiefly of clays that have a high shrink-swell
potential, soils that have a high water table, soils that have a claypan or clay
layer at or near the surface, and soils that are shallow over nearly impervious
material. These soils have a very slow rate of water transmission.
If a soil is assigned to a dual hydrologic group (A/D, B/D, or C/D), the first letter is
for drained areas and the second is for undrained areas. Only the soils that in
their natural condition are in group D are assigned to dual classes.
Hydrologic Soil Group—Larimer County Area, Colorado
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/12/2017
Page 3 of 4
Rating Options
Aggregation Method: Dominant Condition
Component Percent Cutoff: None Specified
Tie-break Rule: Higher
Hydrologic Soil Group—Larimer County Area, Colorado
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/12/2017
Page 4 of 4
City of Fort Collins Floodplain Review Checklist
50% Development Review Submittals
Instructions: Complete this checklist by marking all boxes that have been adequately
completed. Put an “NA” next to any items that are not applicable to this particular
submittal. Any boxes that are left blank and do not have an “NA” marked next to them
are considered incomplete.
Date of Review:_____________ Reviewer’s Name:____________________________
Plat Map
The following required items are on the plat:
100-year floodplain boundary
City
FEMA
Floodway boundary
City
FEMA
The benchmark number and elevation of benchmark
These items match the FIRM. (FEMA Basin)
These items match the Master Plan. (City Basin)
The benchmark number and elevation match with those published in the City of Fort
Collins benchmark system.
Site Plan
The following required items are on the site plan:
100-year floodplain boundary- FEMA and City
500-year floodplain boundary (if proposed structure is a “critical facility”
and a 500-year floodplain is mapped)
Floodway boundary
Erosion buffer zones
Restriction related to use (i.e. critical facility or no residential use of lower
floor if floodproofed mixed-use structure)
Drainage and/or Grading Plan (or a separate Floodplain Sheet if it is too cluttered on
Drainage and Grading Plan)
The following required items are on the drainage and/or grading plan:
100-year floodplain boundary- FEMA and City
500-year floodplain boundary (if proposed structure is a “critical facility”
and a 500-year floodplain is mapped)
Floodway boundary
Erosion buffer zones
Cross-section locations
BFE lines
Regulatory Flood Protection Elevation for individual lots or groups of lots
if structures are to be built in the floodplain.
The floodplain and floodway boundaries are in the correct location and labeled
properly.
The cross-section and BFE lines are in the correct location and labeled properly.
Elevations are referred to the appropriate datum:
FEMA basins – list in both NGVD 29 and NAVD 88
City basins – list only in NGVD 29
Floodway regulations have been met.
No fill in the floodway unless a hydraulic analysis shows “no-rise”.
No manufactured homes, except in an existing park, can be placed in the
floodway.
No changing a nonconforming non-residential or mixed use structure to a
residential structure.
Landscaping meets requirements for no encroachment in the floodway
without a hydraulic analysis to show “no-rise”.
No storage of materials or equipment.
Critical facilities regulations have been met:
100 year – No life safety, emergency response, or hazardous material
critical facilities
500 year Poudre – No life safety or emergency response critical facilities
Any items in the floodway that can float (Example: picnic tables, bike racks, etc.) are
noted as being anchored.
Erosion Buffer Zone requirements have been met:
Design of any allowed development minimizes disturbance to channel bed
and banks.
No structures allowed.
No additions to existing structures allowed.
Any fencing is split-rail design and break-away, but cabled. Must be
oriented parallel to general flow direction.
No detention or water quality ponds.
No bike or pedestrian paths or trails except as required to cross streams or
waterways.
Road, bicycle and pedestrian bridges must span erosion buffer zone.
No fill.
No outdoor storage of non-residential materials or equipment.
No driveways or parking areas.
No irrigated vegetation and non-native trees, grasses, or shrubs.
No utilities except as necessary to cross streams or waterways.
No grading or excavation except as required for permitted activities in
erosion buffer zone.
No construction traffic except as required for permitted activities in
erosion buffer zone.
Any construction in the erosion buffer zone shows that it will not impact
the channel stability.
Any necessary floodplain modeling has been submitted and approved. All modeling
must follow the City’s floodplain modeling guidelines.
Special Poudre River Regulations
Poudre River Floodway Regulations have been met.
No construction of new residential, non-residential or mixed-use
structures.
No redevelopment of residential, non-residential or mixed-use structures.
No additions to residential, non-residential or mixed-use structures.
No fill unless hydraulic analysis shows “no-rise”.
Poudre River floodplain regulations have been met
No construction of new residential or mixed-use structures
No additions to residential structures
No additions to mixed-use structures if there is an expansion in the
residential-use area of the structure.
No floatable materials on non-residential sites
Information Related to Structures in the Floodplain
The regulatory flood protection elevation shown on the plans is at least 2 ft above the
BFE for the Poudre River and at least 18” above the BFE for new development and
redevelopment, 6” above the BFE for additions, substantial improvement and
accessory structures for all other floodplains.
A note is on the plans that the lowest floor (including basement or crawl space) and
HVAC will be required to be elevated above the regulatory flood protection
elevation. Non-residential structures can be floodproofed instead of elevated to the
regulatory flood protection elevation.
A typical drawing detail is included for each foundation type proposed (slab-on-
grade, basement, crawl space) showing the elevation of the HVAC and lowest floor
elevation (which includes bottom of the basement or crawl space) relative to the BFE.
If garages are not going to be elevated to the regulatory flood protection elevation,
then a note is included stating the following requirements:
There shall be 1 square inch of venting for every 1 square foot of enclosed
area.
The bottom of the venting shall not be higher than 1 foot above grade.
The venting shall be on at least two sides, preferably on upstream and
downstream sides. (Does not have to be divided equally).
For manufactured homes, a note is included stating that all submittal requirements on
separate sheet titled “Installation of a Mobile Home Located in a Floodplain:
Submittal Requirements” shall be met.
A note is on the plans stating that a floodplain use permit will be required for each
structure and each site construction element (detention ponds, bike paths, parking
lots, utilities, etc.) in the floodplain.
A note is on the plans stating that a FEMA elevation or floodproofing certificate will
be completed and approved before the CO is issued for any structures in the
floodplain. This is required even if property is only in a City floodplain.
Drainage Report
The site is described as being in the floodplain. Floodplain name and if the floodplain
is a FEMA or City-designated is described. Any floodway or erosion buffer zones on
the site are described.
The FEMA FIRM panel # and date and/or the Master Plan information is cited.
A copy of the FIRM panel with the site location marked is included in the report.
If a floodplain modeling report has been submitted, that report is referenced. The
reason for the floodplain modeling report is described.
If a FEMA CLOMR or LOMR is going to be needed, the reason for the CLOMR or
LOMR is described.
If a FEMA LOMR is required after construction, this is stated in the report.
The location of the structures relative to the floodplain is described. If there is both a
FEMA and a City floodplain on the site, the location of the structures relative to both
is described.
The use of the structures is described. This is to determine if the structure is
residential, non-residential, or mixed-use. Also, structures in all 100- year and Poudre
River 500-year floodplains cannot be used as a critical facility. (See Chapter 10 of
City Code for definitions.)
The report describes how the development will be in compliance with the applicable
floodplain regulations (Chapter 10 of City Code). (Examples: elevation of lowest
floor above regulatory flood protection elevation, floodproofing, floodway
regulations, erosion buffer zone regulations, no-rise, etc.)
The type of foundation construction for the structures (i.e. slab-on-grade, crawl space,
basement, etc.) is discussed in the report.
The type of foundation matches with the details shown on the grading plan.
The report states that the lowest floor (including basement or crawl space) and HVAC
will be required to be elevated above the regulatory flood protection elevation. Non-
residential structures can be floodproofed instead of elevated to the regulatory flood
protection elevation.
If garages are not going to be elevated to the regulatory flood protection elevation,
then a note is included stating the following requirements:
There shall be 1 square inch of venting for every 1 square foot of enclosed
area.
There bottom of the venting shall not be higher than 1 foot above grade.
The venting shall be on at least two sides, preferably on upstream and
downstream sides. (Does not have to be divided equally).
If a non-residential structure is to be floodproofed, then a note is included stating that
all requirements on separate sheet titled “Floodproofing Guidelines” shall be met.
(Floodproofing guidelines can be obtained at http://fcgov.com/stormwater/pdf/fp-
floodproofing.pdf)
For manufactured homes, a note is included stating that all submittal requirements on
separate sheet titled “Installation of a Mobile Home Located in a Floodplain:
Submittal Requirements” shall be met. (Mobile Home guidelines can be obtained at
http://fcgov.com/stormwater/pdf/fp-mobilhome.pdf)
The report states that a floodplain use permit will be required for each structure and
each site construction element (detention ponds, bike paths, parking lots, utilities,
etc.) in the floodplain.
A note is in the report stating that a FEMA elevation or floodproofing certificate will
be completed and approved before the CO is issued.
In the compliance section, Chapter 10 of City Code is listed.
FEMA CLOMR Approval
If a FEMA CLOMR is required, the necessary modeling has been submitted and
approved by the City.
Additional Comments:
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
Updated 11/29/2007
Terms to Note
Lowest Floor Elevation – Elevation of the lowest floor of the lowest enclosed area
(including bottom of basement or crawlspace). This is not the same as finished floor. The
lowest floor should be distinguished from finished floor on plans and reports.
Regulatory Flood Protection Elevation – For all floodplains except the Poudre River, the
regulatory flood protection elevation is eighteen (18) inches above the base flood
elevation. For the Poudre River floodplain, the regulatory flood protection elevation is
twenty-four (24) inches above the base flood elevation. If there is both a FEMA and a
City BFE, the higher BFE should be used to determine the regulatory flood protection
elevation.
Additional floodplain terminology is defined in Chapter 10 of City Code.
NOTE: Issues specific to individual sites may arise that result in additional
requirements. These will be discussed during initial meetings with the applicant.
Appendix B – Hydrologic Computations
RUNOFF COEFFICIENTS - DEVELOPED
Fort Collins Jeep DATE:
16-018
MSG
TWD
Type D Soils
Historic / Open Space Roof Tract / Open Space Pavement
2-Yr Coeff. 0.71 0.02 0.89
5-YEAR Coeff. 0.73 0.08 0.90 Note: Runoff coefficients shown were obtained from City of Fort Collins
100-YEAR Coeff. 0.81 0.35 0.96 Stormwater Criteria Manual Amendments Table RO-3, RO-5
Impervious 90% 0% 100%
Historic / Open Space Roof Tract / Open Space Pavement
Design Design Area Area Area Area Area
Basin Point (AC) (AC) (AC) (AC) (AC) CC2
CC5
CC100
% Imp.
A 1 0.000 0.005 0.215 0.22 0.87 0.88 0.95 98%
B 2 0.02 0.31 0.33 0.83 0.84 0.92 93%
C 3 0.35 0.11 1.25 1.72 0.80 0.81 0.89 91%
D 4 0.00
E 5 0.00
F 6 0.00
G 7 0.00
0.00 0.35 0.14 1.78 2.27 0.81 0.82 0.90 92%
0.0% 15.6% 6.2% 78.3% 100%
0.00 0.35 0.14 1.78 2.27 0.81 0.82 0.90 92.3%
0.0% 15.6% 6.2% 78.3% 0.0%
TOTAL STUDY AREA
SUBTOTAL FOR BASIN A
November 6, 2017
Type B Soils
PROJECT NUMBER:
CALCULATED BY:
CHECKED BY:
PROJECT NAME:
Fort Collins Jeep DATE:
16-018
MSG
TWD
FINAL
tc
DESIGN AREA C5
LENGTH SLOPE Ti
LENGTH SLOPE Cv
Land Surface VEL Tt
COMP. TOTAL tc=(L/180)+10 C10 C100
BASIN Ac Ft % Min. Ft. % fps Min. tc LENGTH Min. Min.
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15)
A 0.22 0.88 60 2.2% 2.4 105 0.42% 20.0 Paved Areas 1.3 1.4 3.7 165 10.9 5.0 0.88 0.95
B 0.33 0.84 70 2.4% 3.0 130 44.00% 20.0 Paved Areas 13.3 0.2 3.1 200 11.1 5.0 0.84 0.92
C 1.72 0.81 70 1.1% 4.3 350 0.68% 20.0 Paved Areas 1.7 3.5 7.8 420 12.3 7.8 0.81 0.89
STANDARD FORM SF-2 - DEVELOPED
tc CHECK
(URBANIZED BASINS)
PROJECT NAME:
PROJECT NUMBER:
DATA
INITIAL
TIME (Ti
)
TRAVEL TIME
(Tt
)
CALCULATED BY:
CHECKED BY:
Time of Concentration
SUB-BASIN
November 6, 2017
1 / 3
0 . 395 ( 1 . 1 ) 1 / 2
S
C L
Ti
= − T
L
V
t =
60
Fort Collins Jeep DATE:
16-018 P1 (1-Hour Rainfall) = 0.82
MSG
TWD
DESIGN
BASIN
AREA
(AC)
RUNOFF
COEFF C5
tc (min)
C*A(ac)
I
(in/hr)
Q
(cfs)
tc(min)
∑(C*A)
(ac)
I
(in/hr)
Q
(cfs)
SLOPE
(%)
STREET
FLOW(cfs)
DESIGN
FLOW(cfs)
SLOPE
(%)
PIPE
SIZE (in)
LENGTH
(ft)
VELOCITY
(fps)
tt
(min)
(2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20) (21) (22)
C 1.72 0.80 7.8 1.37 2.43 3.33
B 0.33 0.83 5.0
5.0 0.19 2.78 0.53
0.27 2.78 0.76
TOTAL RUNOFF STREET
STANDARD FORM SF-3 - DEVELOPED
STORM DRAINAGE DESIGN - RATIONAL METHOD 2-YEAR EVENT
PROJECT NAME: November 6, 2017
PROJECT NUMBER:
CALCULATED BY:
PIPE TRAVEL TIME REMARKS
(1)
A 0.22 0.87
CHECKED BY:
STORM LINE
DESIGN
POINT
DIRECT RUNOFF
Fort Collins Jeep DATE:
16-018 P1 (1-Hour Rainfall) = 1.10
MSG
TWD
DESIGN
BASIN
AREA
(AC)
RUNOFF
COEFF C5
tc (min)
C*A(ac)
I
(in/hr)
Q
(cfs)
tc(min)
∑(C*A)
(ac)
I
(in/hr)
Q
(cfs)
SLOPE
(%)
STREET
FLOW(cfs)
DESIGN
FLOW(cfs)
SLOPE
(%)
PIPE
SIZE (in)
LENGTH
(ft)
VELOCITY
(fps)
tt
(min)
(2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20) (21) (22)
B 0.33 0.84
STANDARD FORM SF-3 - DEVELOPED
STORM DRAINAGE DESIGN - RATIONAL METHOD 5-YEAR EVENT
PROJECT NAME: November 6, 2017
PROJECT NUMBER:
CALCULATED BY:
PIPE TRAVEL TIME REMARKS
CHECKED BY:
STORM LINE
DESIGN
POINT
DIRECT RUNOFF TOTAL RUNOFF STREET
0.88
16-022
5.0 0.19 3.73 0.72
5.0 0.28 3.73 1.04
A 0.22
C 1.72 0.81 7.8 1.40 3.26 4.55
Fort Collins Jeep DATE:
16-018 P1 (1-Hour Rainfall) = 2.86
MSG
TWD
DESIGN
BASIN
AREA
(AC)
RUNOFF
COEFF C100
tc (min)
C*A(ac)
I
(in/hr)
Q
(cfs)
tc(min)
∑(C*A)
(ac)
I
(in/hr)
Q
(cfs)
SLOPE
(%)
STREET
FLOW(cfs)
DESIGN
FLOW(cfs)
SLOPE
(%)
PIPE
SIZE (in)
LENGTH
(ft)
VELOCITY
(fps)
tt
(min)
(2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20) (21) (22)
CHECKED BY:
DESIGN
POINT
DIRECT RUNOFF TOTAL RUNOFF
C 1.72 0.89 7.8 1.53 8.47
5.0 0.21
STANDARD FORM SF-3 - DEVELOPED
STORM DRAINAGE DESIGN - RATIONAL METHOD 100-YEAR EVENT
PROJECT NAME: November 6, 2017
PROJECT NUMBER:
CALCULATED BY:
(1)
A 0.22 0.95
PIPE TRAVEL TIME REMARKS
9.70
STREET
2.02
B 0.33
12.96
0.92 5.0 0.30 9.70 2.94
Appendix C – Hydraulic Calculations
Project:
Basin ID:
Depth Increment = 0.1 ft
Required Volume Calculation Media Surface -- 0.00 -- -- -- 282 0.006
Selected BMP Type = RG -- 0.10 -- -- -- 282 0.006 28 0.001
Watershed Area = 0.22 acres -- 0.20 -- -- -- 282 0.006 54 0.001
Watershed Length = 178 ft -- 0.30 -- -- -- 282 0.006 82 0.002
Watershed Slope = 0.005 ft/ft -- 0.40 -- -- -- 282 0.006 110 0.003
Watershed Imperviousness = 90.00% percent -- 0.50 -- -- -- 282 0.006 138 0.003
Percentage Hydrologic Soil Group A = 0.0% percent -- 0.60 -- -- -- 282 0.006 166 0.004
Percentage Hydrologic Soil Group B = 0.0% percent -- 0.70 -- -- -- 282 0.006 195 0.004
Percentage Hydrologic Soil Groups C/D = 100.0% percent -- 0.80 -- -- -- 282 0.006 223 0.005
Desired WQCV Drain Time = 12.0 hours -- 0.90 -- -- -- 282 0.006 251 0.006
Location for 1-hr Rainfall Depths = User Input WQCV -- 0.91 -- -- -- 282 0.006 254 0.006
Water Quality Capture Volume (WQCV) = 0.006 acre-feet -- 1.00 -- -- -- 282 0.006 279 0.006
Excess Urban Runoff Volume (EURV) = 0.020 acre-feet -- -- -- --
2-yr Runoff Volume (P1 = 0.99 in.) = 0.016 acre-feet 0.99 inches -- -- -- --
5-yr Runoff Volume (P1 = 1.1 in.) = 0.019 acre-feet 1.10 inches -- -- -- --
10-yr Runoff Volume (P1 = 1.4 in.) = 0.024 acre-feet 1.40 inches -- -- -- --
25-yr Runoff Volume (P1 = 1.99 in.) = 0.035 acre-feet 1.99 inches -- -- -- --
50-yr Runoff Volume (P1 = 2.15 in.) = 0.038 acre-feet 2.15 inches -- -- -- --
100-yr Runoff Volume (P1 = 2.86 in.) = 0.052 acre-feet 2.86 inches -- -- -- --
500-yr Runoff Volume (P1 = 3.89 in.) = 0.073 acre-feet 3.89 inches -- -- -- --
Approximate 2-yr Detention Volume = 0.015 acre-feet -- -- -- --
Approximate 5-yr Detention Volume = 0.017 acre-feet -- -- -- --
Approximate 10-yr Detention Volume = 0.022 acre-feet -- -- -- --
Approximate 25-yr Detention Volume = 0.029 acre-feet -- -- -- --
Approximate 50-yr Detention Volume = 0.029 acre-feet -- -- -- --
Approximate 100-yr Detention Volume = 0.035 acre-feet -- -- -- --
-- -- -- --
Stage-Storage Calculation -- -- -- --
Zone 1 Volume (WQCV) = 0.006 acre-feet
-- -- -- --
Select Zone 2 Storage Volume (Optional) = acre-feet
-- -- -- --
Select Zone 3 Storage Volume (Optional) = acre-feet
-- -- -- --
Total Detention Basin Volume = 0.006 acre-feet
-- -- -- --
Initial Surcharge Volume (ISV) = N/A ft^3
-- -- -- --
Initial Surcharge Depth (ISD) = N/A ft
-- -- -- --
Total Available Detention Depth (Htotal
) = user ft
-- -- -- --
Depth of Trickle Channel (HTC) = N/A ft
-- -- -- --
Slope of Trickle Channel (STC
) = N/A ft/ft
-- -- -- --
Slopes of Main Basin Sides (Smain
) = user H:V
-- -- -- --
Basin Length-to-Width Ratio (RL/W
) = user -- -- -- --
-- -- -- --
Initial Surcharge Area (AISV) = user ft^2
-- -- -- --
Surcharge Volume Length (LISV) = user ft
1 User Defined Stage-Area Boolean for Message
1 Equal Stage-Area Inputs Watershed L:W
1 CountA
0 Calc_S_TC
H_FLOOR
33.6556 L_FLOOR_OTHER
0.00 ISV 0.00 ISV
0.00 Floor 0.00 Floor
0.91 Zone 1 (WQCV) 0.91 Zone 1 (WQCV)
0.00 Zone 2 0.00 Zone 2
0.00 Zone 3 0.00 Zone 3
DETENTION BASIN STAGE-STORAGE TABLE BUILDER
UD-Detention, Version 3.07 (February 2017)
0.000
0.005
0.010
0.015
0.020
0.000
0.005
0.010
0.015
0.020
0.00 0.50 1.00 1.50 2.00
Volume (ac-ft)
Area (acres)
Stage (ft.)
Area (acres) Volume (ac-ft)
0
100
200
300
400
0
5
10
15
20
0.00 0.50 1.00 1.50 2.00
Area (sq.ft.)
Length, Width (ft.)
Stage (ft)
Length (ft) Width (ft) Area (sq.ft.)
Bioretention Pond A.xlsm, Basin 11/6/2017, 4:41 PM
Project:
Basin ID:
Stage (ft) Zone Volume (ac-ft) Outlet Type
Zone 1 (WQCV) 0.91 0.006 Filtration Media
Zone 2
Zone 3
0.006 Total
User Input: Orifice at Underdrain Outlet (typically used to drain WQCV in a Filtration BMP) Calculated Parameters for Underdrain
Underdrain Orifice Invert Depth = 2.00 ft (distance below the filtration media surface) Underdrain Orifice Area = 0.0 ft
2
Underdrain Orifice Diameter = 0.38 inches Underdrain Orifice Centroid = 0.02 feet
User Input: Orifice Plate with one or more orifices or Elliptical Slot Weir (typically used to drain WQCV and/or EURV in a sedimentation BMP) Calculated Parameters for Plate
Invert of Lowest Orifice = ft (relative to basin bottom at Stage = 0 ft) WQ Orifice Area per Row = N/A ft
2
Depth at top of Zone using Orifice Plate = ft (relative to basin bottom at Stage = 0 ft) Elliptical Half-Width = N/A feet
Orifice Plate: Orifice Vertical Spacing = inches Elliptical Slot Centroid = N/A feet
Orifice Plate: Orifice Area per Row = inches Elliptical Slot Area = N/A ft
2
User Input: Stage and Total Area of Each Orifice Row (numbered from lowest to highest)
Row 1 (optional) Row 2 (optional) Row 3 (optional) Row 4 (optional) Row 5 (optional) Row 6 (optional) Row 7 (optional) Row 8 (optional)
Stage of Orifice Centroid (ft)
Orifice Area (sq. inches)
Row 9 (optional) Row 10 (optional) Row 11 (optional) Row 12 (optional) Row 13 (optional) Row 14 (optional) Row 15 (optional) Row 16 (optional)
Stage of Orifice Centroid (ft)
Orifice Area (sq. inches)
User Input: Vertical Orifice (Circular or Rectangular) Calculated Parameters for Vertical Orifice
Not Selected Not Selected Not Selected Not Selected
Invert of Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Area = ft
2
Depth at top of Zone using Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Centroid = feet
Vertical Orifice Diameter = inches
User Input: Overflow Weir (Dropbox) and Grate (Flat or Sloped) Calculated Parameters for Overflow Weir
Not Selected Not Selected Not Selected Not Selected
Overflow Weir Front Edge Height, Ho = ft (relative to basin bottom at Stage = 0 ft) Height of Grate Upper Edge, Ht
= feet
Overflow Weir Front Edge Length = feet Over Flow Weir Slope Length = feet
Overflow Weir Slope = H:V (enter zero for flat grate) Grate Open Area / 100-yr Orifice Area = should be > 4
Horiz. Length of Weir Sides = feet Overflow Grate Open Area w/o Debris = ft
2
Overflow Grate Open Area % = %, grate open area/total area Overflow Grate Open Area w/ Debris = ft
2
Debris Clogging % = %
User Input: Outlet Pipe w/ Flow Restriction Plate (Circular Orifice, Restrictor Plate, or Rectangular Orifice) Calculated Parameters for Outlet Pipe w/ Flow Restriction Plate
Not Selected Not Selected Not Selected Not Selected
Depth to Invert of Outlet Pipe = ft (distance below basin bottom at Stage = 0 ft) Outlet Orifice Area = ft
2
Circular Orifice Diameter = inches Outlet Orifice Centroid = feet
Half-Central Angle of Restrictor Plate on Pipe = N/A N/A radians
User Input: Emergency Spillway (Rectangular or Trapezoidal) Calculated Parameters for Spillway
Spillway Invert Stage= ft (relative to basin bottom at Stage = 0 ft) Spillway Design Flow Depth= feet
Spillway Crest Length = feet Stage at Top of Freeboard = feet
Spillway End Slopes = H:V Basin Area at Top of Freeboard = acres
Freeboard above Max Water Surface = feet
Routed Hydrograph Results
Design Storm Return Period = WQCV EURV 2 Year 5 Year 10 Year 25 Year 50 Year 100 Year 500 Year
One-Hour Rainfall Depth (in) = 0.53 1.07 0.99 1.10 1.40 1.99 2.15 2.86 3.89
Calculated Runoff Volume (acre-ft) = 0.006 0.020 0.016 0.019 0.024 0.035 0.038 0.052 0.073
OPTIONAL Override Runoff Volume (acre-ft) =
Inflow Hydrograph Volume (acre-ft) = 0.006 0.020 0.016 0.019 0.023 0.034 0.038 0.051 0.072
Predevelopment Unit Peak Flow, q (cfs/acre) = 0.00 0.00 0.01 0.06 0.19 0.58 0.73 1.15 1.83
COUNTA for Basin Tab = 1 Ao Dia WQ Plate Type Vert Orifice 1 Vert Orifice 2
Count_Underdrain = 1 0.11(diameter = 3/8 inch) 1 1 1
Count_WQPlate = 0 0.14(diameter = 7/16 inch)
Count_VertOrifice1 = 0 0.18(diameter = 1/2 inch) Outlet Plate 1 Outlet Plate 2 Drain Time Message Boolean
Count_VertOrifice2 = 0 0.24(diameter = 9/16 inch) 1 1 5yr, <72hr 0
Count_Weir1 = 0 0.29(diameter = 5/8 inch) >5yr, <120hr 1 0
Count_Weir2 = 0 0.36 (diameter = 11/16 inch) Max Depth Row
Count_OutletPipe1 = 0 0.42(diameter = 3/4 inch) WQCV 67 Watershed Constraint Check
Count_OutletPipe2 = 0 0.50 (diameter = 13/16 inch) 2 Year 100 Slope 0.010
COUNTA_2 (Standard FSD Setup)= 0 0.58(diameter = 7/8 inch) EURV 100 Shape 3.31
MaxPondDepth_Error? FALSE 0.67 (diameter = 15/16 inch) 5 Year 100
Hidden Parameters & Calculations 0.76 (diameter = 1 inch) 10 Year 100 Spillway Depth
(diameter 0.86 = 1-1/16 inches) 25 Year 100
WQ Plate Flow at 100yr depth = 0.00 0.(diameter 97 = 1-1/8 inches) 50 Year 100
CLOG #1= 0% (diameter 1.08 = 1-3/16 inches) 100 Year 100 1 Z1_Boolean
Cdw #1
= 1.(diameter 20 = 1-1/4 inches) 500 Year 100 1 Z2_Boolean
Cdo #1
= (diameter 1.32 = 1-5/16 inches) Zone3_Pulldown Message 1 Z3_Boolean
Overflow Weir #1 Angle = 1.(diameter 45 = 1-3/8 inches) 1 Opening Message
CLOG #2= 0% (diameter 1.59 = 1-7/16 inches) Draintime Running
Cdw #2
= 1.(diameter 73 = 1-1/2 inches) Outlet Boolean Outlet Rank Total (1 to 4)
Cdo #2
= (diameter 1.88 = 1-9/16 inches) Vertical Orifice 1 0 0 0
Overflow Weir #2 Angle = 2.(diameter 03 = 1-5/8 inches) Vertical Orifice 2 0 0 Boolean
Underdrain Q at 100yr depth = 0.01 (diameter 2.20 = 1-11/16 inches) Overflow Weir 1 0 0 0 Max Depth
VertOrifice1 Q at 100yr depth = 0.00 2.(diameter 36 = 1-3/4 inches) Overflow Weir 2 0 0 0 500yr Depth
VertOrifice2 Q at 100yr depth = 0.00 (diameter 2.54 = 1-13/16 inches) Outlet Pipe 1 0 0 0 Freeboard
EURV_draintime_user = 2.(diameter 72 = 1-7/8 inches) Outlet Pipe 2 0 0 0 Spillway
Count_User_Hydrographs 0 (diameter 2.90 = 1-15/16 inches) 0 Spillway Length
CountA_3 (EURV & 100yr) = 0 3.09(diameter = 2 inches) Button Visibility Boolean FALSE Time Interval
CountA_4 (100yr Only) = 0 (use 3.29 rectangular openings) 1 Button_Trigger
1 Underdrain
0 WQCV Plate
0 EURV-WQCV Plate
0 EURV-WQCV VertOrifice
0 Outlet 90% Qpeak
0 Outlet Undetained
S-A-V-D Chart Axis Override X-axis Left Y-Axis Right Y-Axis
minimum bound
maximum bound
Detention Basin Outlet Structure Design
UD-Detention, Version 3.07 (February 2017)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
0.1 1 10
FLOW [cfs]
TIME [hr]
500YR IN
500YR OUT
100YR IN
Outflow Hydrograph Workbook Filename:
Storm Inflow Hydrographs
The user can override the calculated inflow hydrographs from this workbook with inflow hydrographs developed in a separate program.
SOURCE WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK
Time Interval TIME WQCV [cfs] EURV [cfs] 2 Year [cfs] 5 Year [cfs] 10 Year [cfs] 25 Year [cfs] 50 Year [cfs] 100 Year [cfs] 500 Year [cfs]
7.30 min 0:00:00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0:07:18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Hydrograph 0:14:36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Constant 0:21:54 0.00 0.01 0.01 0.01 0.01 0.02 0.02 0.03 0.04
0.685 0:29:12 0.01 0.03 0.02 0.03 0.03 0.05 0.06 0.07 0.10
0:36:30 0.02 0.07 0.06 0.07 0.09 0.13 0.14 0.19 0.27
0:43:48 0.06 0.20 0.17 0.20 0.24 0.36 0.39 0.53 0.73
0:51:06 0.07 0.24 0.19 0.22 0.28 0.41 0.45 0.61 0.85
0:58:24 0.06 0.22 0.18 0.21 0.26 0.39 0.43 0.57 0.80
1:05:42 0.06 0.20 0.16 0.19 0.24 0.35 0.39 0.52 0.73
1:13:00 0.05 0.17 0.14 0.17 0.21 0.31 0.34 0.46 0.64
1:20:18 0.04 0.15 0.12 0.14 0.17 0.26 0.29 0.39 0.54
1:27:36 0.04 0.13 0.10 0.12 0.15 0.23 0.25 0.34 0.48
1:34:54 0.03 0.12 0.09 0.11 0.14 0.20 0.23 0.31 0.43
1:42:12 0.02 0.09 0.07 0.09 0.11 0.16 0.18 0.25 0.35
1:49:30 0.02 0.07 0.06 0.07 0.09 0.13 0.14 0.20 0.28
1:56:48 0.01 0.05 0.04 0.05 0.06 0.09 0.10 0.14 0.20
2:04:06 0.01 0.04 0.03 0.03 0.04 0.07 0.07 0.10 0.15
2:11:24 0.01 0.03 0.02 0.03 0.03 0.05 0.06 0.08 0.11
2:18:42 0.01 0.02 0.02 0.02 0.03 0.04 0.04 0.06 0.09
2:26:00 0.01 0.02 0.01 0.02 0.02 0.03 0.04 0.05 0.07
2:33:18 0.00 0.02 0.01 0.02 0.02 0.03 0.03 0.04 0.06
2:40:36 0.00 0.01 0.01 0.01 0.02 0.03 0.03 0.04 0.05
2:47:54 0.00 0.01 0.01 0.01 0.02 0.02 0.03 0.03 0.05
2:55:12 0.00 0.01 0.01 0.01 0.01 0.02 0.02 0.03 0.05
3:02:30 0.00 0.01 0.01 0.01 0.01 0.02 0.02 0.02 0.03
3:09:48 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.02 0.02
3:17:06 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.01 0.02
3:24:24 0.00 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.01
3:31:42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.01
3:39:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01
3:46:18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3:53:36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:00:54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:08:12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:15:30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:22:48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:30:06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:37:24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:44:42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:52:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:59:18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:06:36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:13:54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:21:12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:28:30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:35:48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:43:06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:50:24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:57:42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:05:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:12:18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:19:36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:26:54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Summary Stage-Area-Volume-Discharge Relationships
The user can create a summary S-A-V-D by entering the desired stage increments and the remainder of the table will populate automatically.
The user should graphically compare the summary S-A-V-D table to the full S-A-V-D table in the chart to confirm it captures all key transition points.
Stage Area Area Volume Volume
Total
Outflow
[ft] [ft^2] [acres] [ft^3] [ac-ft] [cfs]
For best results, include the
stages of all grade slope
changes (e.g. ISV and Floor)
from the S-A-V table on
Sheet 'Basin'.
Also include the inverts of all
outlets (e.g. vertical orifice,
overflow grate, and spillway,
where applicable).
Detention Basin Outlet Structure Design
Stage - Storage
Description
UD-Detention, Version 3.07 (February 2017)
Project:
Basin ID:
Depth Increment = 0.1 ft
Required Volume Calculation Media Surface -- 0.00 -- -- -- 393 0.009
Selected BMP Type = RG -- 0.10 -- -- -- 393 0.009 39 0.001
Watershed Area = 0.33 acres -- 0.20 -- -- -- 393 0.009 75 0.002
Watershed Length = 195 ft -- 0.30 -- -- -- 393 0.009 114 0.003
Watershed Slope = 0.005 ft/ft -- 0.40 -- -- -- 393 0.009 153 0.004
Watershed Imperviousness = 90.00% percent -- 0.50 -- -- -- 393 0.009 193 0.004
Percentage Hydrologic Soil Group A = 0.0% percent -- 0.60 -- -- -- 393 0.009 232 0.005
Percentage Hydrologic Soil Group B = 0.0% percent -- 0.70 -- -- -- 393 0.009 271 0.006
Percentage Hydrologic Soil Groups C/D = 100.0% percent -- 0.80 -- -- -- 393 0.009 310 0.007
Desired WQCV Drain Time = 12.0 hours -- 0.90 -- -- -- 393 0.009 350 0.008
Location for 1-hr Rainfall Depths = User Input -- 0.95 -- -- -- 393 0.009 369 0.008
Water Quality Capture Volume (WQCV) = 0.009 acre-feet WQCV -- 0.98 -- -- -- 393 0.009 381 0.009
Excess Urban Runoff Volume (EURV) = 0.029 acre-feet -- 1.00 -- -- -- 393 0.009 389 0.009
2-yr Runoff Volume (P1 = 0.99 in.) = 0.024 acre-feet 0.99 inches -- -- -- --
5-yr Runoff Volume (P1 = 1.1 in.) = 0.028 acre-feet 1.10 inches -- -- -- --
10-yr Runoff Volume (P1 = 1.4 in.) = 0.036 acre-feet 1.40 inches -- -- -- --
25-yr Runoff Volume (P1 = 1.99 in.) = 0.053 acre-feet 1.99 inches -- -- -- --
50-yr Runoff Volume (P1 = 2.15 in.) = 0.058 acre-feet 2.15 inches -- -- -- --
100-yr Runoff Volume (P1 = 2.86 in.) = 0.078 acre-feet 2.86 inches -- -- -- --
500-yr Runoff Volume (P1 = 3.87 in.) = 0.108 acre-feet 3.87 inches -- -- -- --
Approximate 2-yr Detention Volume = 0.022 acre-feet -- -- -- --
Approximate 5-yr Detention Volume = 0.026 acre-feet -- -- -- --
Approximate 10-yr Detention Volume = 0.033 acre-feet -- -- -- --
Approximate 25-yr Detention Volume = 0.044 acre-feet -- -- -- --
Approximate 50-yr Detention Volume = 0.043 acre-feet -- -- -- --
Approximate 100-yr Detention Volume = 0.053 acre-feet -- -- -- --
-- -- -- --
Stage-Storage Calculation -- -- -- --
Zone 1 Volume (WQCV) = 0.009 acre-feet
-- -- -- --
Select Zone 2 Storage Volume (Optional) = acre-feet
-- -- -- --
Select Zone 3 Storage Volume (Optional) = acre-feet
-- -- -- --
Total Detention Basin Volume = 0.009 acre-feet
-- -- -- --
Initial Surcharge Volume (ISV) = N/A ft^3
-- -- -- --
Initial Surcharge Depth (ISD) = N/A ft
-- -- -- --
Total Available Detention Depth (Htotal
) = user ft
-- -- -- --
Depth of Trickle Channel (HTC) = N/A ft
-- -- -- --
Slope of Trickle Channel (STC
) = N/A ft/ft
-- -- -- --
Slopes of Main Basin Sides (Smain
) = user H:V
-- -- -- --
Basin Length-to-Width Ratio (RL/W
) = user -- -- -- --
-- -- -- --
Initial Surcharge Area (AISV) = user ft^2
-- -- -- --
Surcharge Volume Length (LISV) = user ft
1 User Defined Stage-Area Boolean for Message
1 Equal Stage-Area Inputs Watershed L:W
1 CountA
0 Calc_S_TC
H_FLOOR
69.4549 L_FLOOR_OTHER
0.00 ISV 0.00 ISV
0.00 Floor 0.00 Floor
0.98 Zone 1 (WQCV) 0.98 Zone 1 (WQCV)
0.00 Zone 2 0.00 Zone 2
0.00 Zone 3 0.00 Zone 3
DETENTION BASIN STAGE-STORAGE TABLE BUILDER
UD-Detention, Version 3.07 (February 2017)
0.000
0.005
0.010
0.015
0.020
0.000
0.005
0.010
0.015
0.020
0.00 0.50 1.00 1.50 2.00
Volume (ac-ft)
Area (acres)
Stage (ft.)
Area (acres) Volume (ac-ft)
0
100
200
300
400
0
5
10
15
20
0.00 0.50 1.00 1.50 2.00
Area (sq.ft.)
Length, Width (ft.)
Stage (ft)
Length (ft) Width (ft) Area (sq.ft.)
Bioretention Pond B.xlsm, Basin 11/6/2017, 4:43 PM
Project:
Basin ID:
Stage (ft) Zone Volume (ac-ft) Outlet Type
Zone 1 (WQCV) 0.98 0.009 Filtration Media
Zone 2
Zone 3
0.009 Total
User Input: Orifice at Underdrain Outlet (typically used to drain WQCV in a Filtration BMP) Calculated Parameters for Underdrain
Underdrain Orifice Invert Depth = 2.00 ft (distance below the filtration media surface) Underdrain Orifice Area = 0.0 ft
2
Underdrain Orifice Diameter = 0.46 inches Underdrain Orifice Centroid = 0.02 feet
User Input: Orifice Plate with one or more orifices or Elliptical Slot Weir (typically used to drain WQCV and/or EURV in a sedimentation BMP) Calculated Parameters for Plate
Invert of Lowest Orifice = ft (relative to basin bottom at Stage = 0 ft) WQ Orifice Area per Row = N/A ft
2
Depth at top of Zone using Orifice Plate = ft (relative to basin bottom at Stage = 0 ft) Elliptical Half-Width = N/A feet
Orifice Plate: Orifice Vertical Spacing = inches Elliptical Slot Centroid = N/A feet
Orifice Plate: Orifice Area per Row = inches Elliptical Slot Area = N/A ft
2
User Input: Stage and Total Area of Each Orifice Row (numbered from lowest to highest)
Row 1 (optional) Row 2 (optional) Row 3 (optional) Row 4 (optional) Row 5 (optional) Row 6 (optional) Row 7 (optional) Row 8 (optional)
Stage of Orifice Centroid (ft)
Orifice Area (sq. inches)
Row 9 (optional) Row 10 (optional) Row 11 (optional) Row 12 (optional) Row 13 (optional) Row 14 (optional) Row 15 (optional) Row 16 (optional)
Stage of Orifice Centroid (ft)
Orifice Area (sq. inches)
User Input: Vertical Orifice (Circular or Rectangular) Calculated Parameters for Vertical Orifice
Not Selected Not Selected Not Selected Not Selected
Invert of Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Area = ft
2
Depth at top of Zone using Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Centroid = feet
Vertical Orifice Diameter = inches
User Input: Overflow Weir (Dropbox) and Grate (Flat or Sloped) Calculated Parameters for Overflow Weir
Not Selected Not Selected Not Selected Not Selected
Overflow Weir Front Edge Height, Ho = ft (relative to basin bottom at Stage = 0 ft) Height of Grate Upper Edge, Ht
= feet
Overflow Weir Front Edge Length = feet Over Flow Weir Slope Length = feet
Overflow Weir Slope = H:V (enter zero for flat grate) Grate Open Area / 100-yr Orifice Area = should be > 4
Horiz. Length of Weir Sides = feet Overflow Grate Open Area w/o Debris = ft
2
Overflow Grate Open Area % = %, grate open area/total area Overflow Grate Open Area w/ Debris = ft
2
Debris Clogging % = %
User Input: Outlet Pipe w/ Flow Restriction Plate (Circular Orifice, Restrictor Plate, or Rectangular Orifice) Calculated Parameters for Outlet Pipe w/ Flow Restriction Plate
Not Selected Not Selected Not Selected Not Selected
Depth to Invert of Outlet Pipe = ft (distance below basin bottom at Stage = 0 ft) Outlet Orifice Area = ft
2
Circular Orifice Diameter = inches Outlet Orifice Centroid = feet
Half-Central Angle of Restrictor Plate on Pipe = N/A N/A radians
User Input: Emergency Spillway (Rectangular or Trapezoidal) Calculated Parameters for Spillway
Spillway Invert Stage= ft (relative to basin bottom at Stage = 0 ft) Spillway Design Flow Depth= feet
Spillway Crest Length = feet Stage at Top of Freeboard = feet
Spillway End Slopes = H:V Basin Area at Top of Freeboard = acres
Freeboard above Max Water Surface = feet
Routed Hydrograph Results
Design Storm Return Period = WQCV EURV 2 Year 5 Year 10 Year 25 Year 50 Year 100 Year 500 Year
One-Hour Rainfall Depth (in) = 0.53 1.07 0.99 1.10 1.40 1.99 2.15 2.86 3.87
Calculated Runoff Volume (acre-ft) = 0.009 0.029 0.024 0.028 0.036 0.053 0.058 0.078 0.108
OPTIONAL Override Runoff Volume (acre-ft) =
Inflow Hydrograph Volume (acre-ft) = 0.008 0.029 0.023 0.027 0.035 0.052 0.057 0.078 0.108
Predevelopment Unit Peak Flow, q (cfs/acre) = 0.00 0.00 0.01 0.07 0.21 0.63 0.80 1.24 1.96
COUNTA for Basin Tab = 1 Ao Dia WQ Plate Type Vert Orifice 1 Vert Orifice 2
Count_Underdrain = 1 0.11(diameter = 3/8 inch) 1 1 1
Count_WQPlate = 0 0.14(diameter = 7/16 inch)
Count_VertOrifice1 = 0 0.18(diameter = 1/2 inch) Outlet Plate 1 Outlet Plate 2 Drain Time Message Boolean
Count_VertOrifice2 = 0 0.24(diameter = 9/16 inch) 1 1 5yr, <72hr 0
Count_Weir1 = 0 0.29(diameter = 5/8 inch) >5yr, <120hr 1 0
Count_Weir2 = 0 0.36 (diameter = 11/16 inch) Max Depth Row
Count_OutletPipe1 = 0 0.42(diameter = 3/4 inch) WQCV 73 Watershed Constraint Check
Count_OutletPipe2 = 0 0.50 (diameter = 13/16 inch) 2 Year 100 Slope 0.010
COUNTA_2 (Standard FSD Setup)= 0 0.58(diameter = 7/8 inch) EURV 100 Shape 2.65
MaxPondDepth_Error? FALSE 0.67 (diameter = 15/16 inch) 5 Year 100
Hidden Parameters & Calculations 0.76 (diameter = 1 inch) 10 Year 100 Spillway Depth
(diameter 0.86 = 1-1/16 inches) 25 Year 100
WQ Plate Flow at 100yr depth = 0.00 0.(diameter 97 = 1-1/8 inches) 50 Year 100
CLOG #1= 0% (diameter 1.08 = 1-3/16 inches) 100 Year 100 1 Z1_Boolean
Cdw #1
= 1.(diameter 20 = 1-1/4 inches) 500 Year 100 1 Z2_Boolean
Cdo #1
= (diameter 1.32 = 1-5/16 inches) Zone3_Pulldown Message 1 Z3_Boolean
Overflow Weir #1 Angle = 1.(diameter 45 = 1-3/8 inches) 1 Opening Message
CLOG #2= 0% (diameter 1.59 = 1-7/16 inches) Draintime Running
Cdw #2
= 1.(diameter 73 = 1-1/2 inches) Outlet Boolean Outlet Rank Total (1 to 4)
Cdo #2
= (diameter 1.88 = 1-9/16 inches) Vertical Orifice 1 0 0 0
Overflow Weir #2 Angle = 2.(diameter 03 = 1-5/8 inches) Vertical Orifice 2 0 0 Boolean
Underdrain Q at 100yr depth = 0.01 (diameter 2.20 = 1-11/16 inches) Overflow Weir 1 0 0 0 Max Depth
VertOrifice1 Q at 100yr depth = 0.00 2.(diameter 36 = 1-3/4 inches) Overflow Weir 2 0 0 0 500yr Depth
VertOrifice2 Q at 100yr depth = 0.00 (diameter 2.54 = 1-13/16 inches) Outlet Pipe 1 0 0 0 Freeboard
EURV_draintime_user = 2.(diameter 72 = 1-7/8 inches) Outlet Pipe 2 0 0 0 Spillway
Count_User_Hydrographs 0 (diameter 2.90 = 1-15/16 inches) 0 Spillway Length
CountA_3 (EURV & 100yr) = 0 3.09(diameter = 2 inches) Button Visibility Boolean FALSE Time Interval
CountA_4 (100yr Only) = 0 (use 3.29 rectangular openings) 1 Button_Trigger
1 Underdrain
0 WQCV Plate
0 EURV-WQCV Plate
0 EURV-WQCV VertOrifice
0 Outlet 90% Qpeak
0 Outlet Undetained
S-A-V-D Chart Axis Override X-axis Left Y-Axis Right Y-Axis
minimum bound
maximum bound
Detention Basin Outlet Structure Design
UD-Detention, Version 3.07 (February 2017)
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
0.1 1 10
FLOW [cfs]
TIME [hr]
500YR IN
500YR OUT
100YR IN
100YR OUT
Outflow Hydrograph Workbook Filename:
Storm Inflow Hydrographs
The user can override the calculated inflow hydrographs from this workbook with inflow hydrographs developed in a separate program.
SOURCE WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK
Time Interval TIME WQCV [cfs] EURV [cfs] 2 Year [cfs] 5 Year [cfs] 10 Year [cfs] 25 Year [cfs] 50 Year [cfs] 100 Year [cfs] 500 Year [cfs]
6.78 min 0:00:00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0:06:47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Hydrograph 0:13:34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Constant 0:20:20 0.01 0.02 0.01 0.02 0.02 0.03 0.03 0.05 0.06
0.737 0:27:07 0.02 0.05 0.04 0.04 0.06 0.08 0.09 0.12 0.16
0:33:54 0.03 0.12 0.09 0.11 0.14 0.21 0.23 0.31 0.42
0:40:41 0.10 0.32 0.26 0.30 0.39 0.58 0.63 0.85 1.17
0:47:28 0.11 0.37 0.30 0.35 0.45 0.66 0.72 0.98 1.35
0:54:14 0.10 0.35 0.28 0.33 0.43 0.63 0.68 0.93 1.29
1:01:01 0.09 0.32 0.25 0.30 0.39 0.57 0.62 0.84 1.17
1:07:48 0.08 0.28 0.22 0.26 0.34 0.50 0.55 0.74 1.03
1:14:35 0.07 0.23 0.19 0.22 0.29 0.42 0.46 0.63 0.88
1:21:22 0.06 0.20 0.16 0.19 0.25 0.37 0.41 0.55 0.77
1:28:08 0.05 0.18 0.15 0.17 0.23 0.34 0.37 0.50 0.70
1:34:55 0.04 0.15 0.12 0.14 0.18 0.27 0.29 0.40 0.56
1:41:42 0.03 0.12 0.09 0.11 0.14 0.21 0.23 0.32 0.45
1:48:29 0.02 0.08 0.07 0.08 0.10 0.16 0.17 0.24 0.34
1:55:16 0.02 0.06 0.05 0.06 0.07 0.11 0.12 0.17 0.24
2:02:02 0.01 0.04 0.04 0.04 0.06 0.08 0.09 0.13 0.18
2:08:49 0.01 0.04 0.03 0.03 0.04 0.07 0.07 0.10 0.14
2:15:36 0.01 0.03 0.02 0.03 0.04 0.06 0.06 0.08 0.12
2:22:23 0.01 0.03 0.02 0.02 0.03 0.05 0.05 0.07 0.10
2:29:10 0.01 0.02 0.02 0.02 0.03 0.04 0.05 0.06 0.09
2:35:56 0.01 0.02 0.02 0.02 0.03 0.04 0.04 0.06 0.08
2:42:43 0.01 0.02 0.02 0.02 0.02 0.04 0.04 0.05 0.08
2:49:30 0.00 0.01 0.01 0.01 0.02 0.03 0.03 0.04 0.05
2:56:17 0.00 0.01 0.01 0.01 0.01 0.02 0.02 0.03 0.04
3:03:04 0.00 0.01 0.01 0.01 0.01 0.01 0.02 0.02 0.03
3:09:50 0.00 0.01 0.00 0.00 0.01 0.01 0.01 0.01 0.02
3:16:37 0.00 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.01
3:23:24 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.01 0.01
3:30:11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01
3:36:58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3:43:44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3:50:31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3:57:18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:04:05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:10:52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:17:38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:24:25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:31:12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:37:59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:44:46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:51:32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:58:19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:05:06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:11:53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:18:40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:25:26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:32:13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:39:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:45:47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:52:34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:59:20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Summary Stage-Area-Volume-Discharge Relationships
The user can create a summary S-A-V-D by entering the desired stage increments and the remainder of the table will populate automatically.
The user should graphically compare the summary S-A-V-D table to the full S-A-V-D table in the chart to confirm it captures all key transition points.
Stage Area Area Volume Volume
Total
Outflow
[ft] [ft^2] [acres] [ft^3] [ac-ft] [cfs]
For best results, include the
stages of all grade slope
changes (e.g. ISV and Floor)
from the S-A-V table on
Sheet 'Basin'.
Also include the inverts of all
outlets (e.g. vertical orifice,
overflow grate, and spillway,
where applicable).
Detention Basin Outlet Structure Design
Stage - Storage
Description
UD-Detention, Version 3.07 (February 2017)
Project:
Basin ID:
Depth Increment = 0.1 ft
Required Volume Calculation Media Surface -- 0.00 -- -- -- 1,926 0.044
Selected BMP Type = RG -- 0.10 -- -- -- 1,926 0.044 193 0.004
Watershed Area = 1.57 acres -- 0.20 -- -- -- 1,926 0.044 366 0.008
Watershed Length = 453 ft -- 0.30 -- -- -- 1,926 0.044 559 0.013
Watershed Slope = 0.005 ft/ft -- 0.40 -- -- -- 1,926 0.044 751 0.017
Watershed Imperviousness = 90.00% percent -- 0.50 -- -- -- 1,926 0.044 944 0.022
Percentage Hydrologic Soil Group A = 0.0% percent -- 0.60 -- -- -- 1,926 0.044 1,136 0.026
Percentage Hydrologic Soil Group B = 0.0% percent -- 0.70 -- -- -- 1,926 0.044 1,329 0.031
Percentage Hydrologic Soil Groups C/D = 100.0% percent -- 0.80 -- -- -- 1,926 0.044 1,522 0.035
Desired WQCV Drain Time = 12.0 hours -- 0.90 -- -- -- 1,926 0.044 1,714 0.039
Location for 1-hr Rainfall Depths = Erie WQCV -- 0.96 -- -- -- 1,926 0.044 1,830 0.042
Water Quality Capture Volume (WQCV) = 0.042 acre-feet -- 1.00 -- -- -- 1,926 0.044 1,907 0.044
Excess Urban Runoff Volume (EURV) = 0.140 acre-feet -- -- -- --
2-yr Runoff Volume (P1 = 0.99 in.) = 0.113 acre-feet 0.99 inches -- -- -- --
5-yr Runoff Volume (P1 = 1.1 in.) = 0.133 acre-feet 1.10 inches -- -- -- --
10-yr Runoff Volume (P1 = 1.4 in.) = 0.171 acre-feet 1.40 inches -- -- -- --
25-yr Runoff Volume (P1 = 1.99 in.) = 0.251 acre-feet 1.99 inches -- -- -- --
50-yr Runoff Volume (P1 = 2.15 in.) = 0.274 acre-feet 2.15 inches -- -- -- --
100-yr Runoff Volume (P1 = 2.86 in.) = 0.373 acre-feet 2.86 inches -- -- -- --
500-yr Runoff Volume (P1 = 3.89 in.) = 0.519 acre-feet inches -- -- -- --
Approximate 2-yr Detention Volume = 0.106 acre-feet -- -- -- --
Approximate 5-yr Detention Volume = 0.125 acre-feet -- -- -- --
Approximate 10-yr Detention Volume = 0.158 acre-feet -- -- -- --
Approximate 25-yr Detention Volume = 0.208 acre-feet -- -- -- --
Approximate 50-yr Detention Volume = 0.204 acre-feet -- -- -- --
Approximate 100-yr Detention Volume = 0.251 acre-feet -- -- -- --
-- -- -- --
Stage-Storage Calculation -- -- -- --
Zone 1 Volume (WQCV) = 0.042 acre-feet
-- -- -- --
Select Zone 2 Storage Volume (Optional) = acre-feet
-- -- -- --
Select Zone 3 Storage Volume (Optional) = acre-feet
-- -- -- --
Total Detention Basin Volume = 0.042 acre-feet
-- -- -- --
Initial Surcharge Volume (ISV) = N/A ft^3
-- -- -- --
Initial Surcharge Depth (ISD) = N/A ft
-- -- -- --
Total Available Detention Depth (Htotal
) = user ft
-- -- -- --
Depth of Trickle Channel (HTC) = N/A ft
-- -- -- --
Slope of Trickle Channel (STC
) = N/A ft/ft
-- -- -- --
Slopes of Main Basin Sides (Smain
) = user H:V
-- -- -- --
Basin Length-to-Width Ratio (RL/W
) = user -- -- -- --
-- -- -- --
Initial Surcharge Area (AISV) = user ft^2
-- -- -- --
Surcharge Volume Length (LISV) = user ft
1 User Defined Stage-Area Boolean for Message
1 Equal Stage-Area Inputs Watershed L:W
1 CountA
0 Calc_S_TC
H_FLOOR
176.192 L_FLOOR_OTHER
0.00 ISV 0.00 ISV
0.00 Floor 0.00 Floor
0.96 Zone 1 (WQCV) 0.96 Zone 1 (WQCV)
0.00 Zone 2 0.00 Zone 2
0.00 Zone 3 0.00 Zone 3
DETENTION BASIN STAGE-STORAGE TABLE BUILDER
UD-Detention, Version 3.07 (February 2017)
0.000
0.015
0.030
0.045
0.060
0.000
0.015
0.030
0.045
0.060
0.00 0.50 1.00 1.50 2.00
Volume (ac-ft)
Area (acres)
Stage (ft.)
Area (acres) Volume (ac-ft)
0
100
200
300
400
0
5
10
15
20
0.00 0.50 1.00 1.50 2.00
Area (sq.ft.)
Length, Width (ft.)
Stage (ft)
Length (ft) Width (ft) Area (sq.ft.)
Bioretention Pond C.xlsm, Basin 11/6/2017, 4:40 PM
Project:
Basin ID:
Stage (ft) Zone Volume (ac-ft) Outlet Type
Zone 1 (WQCV) 0.96 0.042 Filtration Media
Zone 2
Zone 3
0.042 Total
User Input: Orifice at Underdrain Outlet (typically used to drain WQCV in a Filtration BMP) Calculated Parameters for Underdrain
Underdrain Orifice Invert Depth = 2.00 ft (distance below the filtration media surface) Underdrain Orifice Area = 0.0 ft
2
Underdrain Orifice Diameter = 1.02 inches Underdrain Orifice Centroid = 0.04 feet
User Input: Orifice Plate with one or more orifices or Elliptical Slot Weir (typically used to drain WQCV and/or EURV in a sedimentation BMP) Calculated Parameters for Plate
Invert of Lowest Orifice = ft (relative to basin bottom at Stage = 0 ft) WQ Orifice Area per Row = N/A ft
2
Depth at top of Zone using Orifice Plate = ft (relative to basin bottom at Stage = 0 ft) Elliptical Half-Width = N/A feet
Orifice Plate: Orifice Vertical Spacing = inches Elliptical Slot Centroid = N/A feet
Orifice Plate: Orifice Area per Row = inches Elliptical Slot Area = N/A ft
2
User Input: Stage and Total Area of Each Orifice Row (numbered from lowest to highest)
Row 1 (optional) Row 2 (optional) Row 3 (optional) Row 4 (optional) Row 5 (optional) Row 6 (optional) Row 7 (optional) Row 8 (optional)
Stage of Orifice Centroid (ft)
Orifice Area (sq. inches)
Row 9 (optional) Row 10 (optional) Row 11 (optional) Row 12 (optional) Row 13 (optional) Row 14 (optional) Row 15 (optional) Row 16 (optional)
Stage of Orifice Centroid (ft)
Orifice Area (sq. inches)
User Input: Vertical Orifice (Circular or Rectangular) Calculated Parameters for Vertical Orifice
Not Selected Not Selected Not Selected Not Selected
Invert of Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Area = ft
2
Depth at top of Zone using Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Centroid = feet
Vertical Orifice Diameter = inches
User Input: Overflow Weir (Dropbox) and Grate (Flat or Sloped) Calculated Parameters for Overflow Weir
Not Selected Not Selected Not Selected Not Selected
Overflow Weir Front Edge Height, Ho = ft (relative to basin bottom at Stage = 0 ft) Height of Grate Upper Edge, Ht
= feet
Overflow Weir Front Edge Length = feet Over Flow Weir Slope Length = feet
Overflow Weir Slope = H:V (enter zero for flat grate) Grate Open Area / 100-yr Orifice Area = should be > 4
Horiz. Length of Weir Sides = feet Overflow Grate Open Area w/o Debris = ft
2
Overflow Grate Open Area % = %, grate open area/total area Overflow Grate Open Area w/ Debris = ft
2
Debris Clogging % = %
User Input: Outlet Pipe w/ Flow Restriction Plate (Circular Orifice, Restrictor Plate, or Rectangular Orifice) Calculated Parameters for Outlet Pipe w/ Flow Restriction Plate
Not Selected Not Selected Not Selected Not Selected
Depth to Invert of Outlet Pipe = ft (distance below basin bottom at Stage = 0 ft) Outlet Orifice Area = ft
2
Circular Orifice Diameter = inches Outlet Orifice Centroid = feet
Half-Central Angle of Restrictor Plate on Pipe = N/A N/A radians
User Input: Emergency Spillway (Rectangular or Trapezoidal) Calculated Parameters for Spillway
Spillway Invert Stage= ft (relative to basin bottom at Stage = 0 ft) Spillway Design Flow Depth= feet
Spillway Crest Length = feet Stage at Top of Freeboard = feet
Spillway End Slopes = H:V Basin Area at Top of Freeboard = acres
Freeboard above Max Water Surface = feet
Routed Hydrograph Results
Design Storm Return Period = WQCV EURV 2 Year 5 Year 10 Year 25 Year 50 Year 100 Year 500 Year
One-Hour Rainfall Depth (in) = 0.53 1.07 0.99 1.10 1.40 1.99 2.15 2.86 3.89
Calculated Runoff Volume (acre-ft) = 0.042 0.140 0.113 0.133 0.171 0.251 0.274 0.373 0.519
OPTIONAL Override Runoff Volume (acre-ft) =
Inflow Hydrograph Volume (acre-ft) = 0.042 0.139 0.113 0.132 0.170 0.250 0.273 0.372 0.518
Predevelopment Unit Peak Flow, q (cfs/acre) = 0.00 0.00 0.01 0.07 0.20 0.60 0.76 1.19 1.89
COUNTA for Basin Tab = 1 Ao Dia WQ Plate Type Vert Orifice 1 Vert Orifice 2
Count_Underdrain = 1 0.11(diameter = 3/8 inch) 1 1 1
Count_WQPlate = 0 0.14(diameter = 7/16 inch)
Count_VertOrifice1 = 0 0.18(diameter = 1/2 inch) Outlet Plate 1 Outlet Plate 2 Drain Time Message Boolean
Count_VertOrifice2 = 0 0.24(diameter = 9/16 inch) 1 1 5yr, <72hr 0
Count_Weir1 = 0 0.29(diameter = 5/8 inch) >5yr, <120hr 1 0
Count_Weir2 = 0 0.36 (diameter = 11/16 inch) Max Depth Row
Count_OutletPipe1 = 0 0.42(diameter = 3/4 inch) WQCV 75 Watershed Constraint Check
Count_OutletPipe2 = 0 0.50 (diameter = 13/16 inch) 2 Year 100 Slope 0.010
COUNTA_2 (Standard FSD Setup)= 0 0.58(diameter = 7/8 inch) EURV 100 Shape 3.00
MaxPondDepth_Error? FALSE 0.67 (diameter = 15/16 inch) 5 Year 100
Hidden Parameters & Calculations 0.76 (diameter = 1 inch) 10 Year 100 Spillway Depth
(diameter 0.86 = 1-1/16 inches) 25 Year 100
WQ Plate Flow at 100yr depth = 0.00 0.(diameter 97 = 1-1/8 inches) 50 Year 100
CLOG #1= 0% (diameter 1.08 = 1-3/16 inches) 100 Year 100 1 Z1_Boolean
Cdw #1
= 1.(diameter 20 = 1-1/4 inches) 500 Year 100 1 Z2_Boolean
Cdo #1
= (diameter 1.32 = 1-5/16 inches) Zone3_Pulldown Message 1 Z3_Boolean
Overflow Weir #1 Angle = 1.(diameter 45 = 1-3/8 inches) 1 Opening Message
CLOG #2= 0% (diameter 1.59 = 1-7/16 inches) Draintime Running
Cdw #2
= 1.(diameter 73 = 1-1/2 inches) Outlet Boolean Outlet Rank Total (1 to 4)
Cdo #2
= (diameter 1.88 = 1-9/16 inches) Vertical Orifice 1 0 0 0
Overflow Weir #2 Angle = 2.(diameter 03 = 1-5/8 inches) Vertical Orifice 2 0 0 Boolean
Underdrain Q at 100yr depth = 0.05 (diameter 2.20 = 1-11/16 inches) Overflow Weir 1 0 0 0 Max Depth
VertOrifice1 Q at 100yr depth = 0.00 2.(diameter 36 = 1-3/4 inches) Overflow Weir 2 0 0 0 500yr Depth
VertOrifice2 Q at 100yr depth = 0.00 (diameter 2.54 = 1-13/16 inches) Outlet Pipe 1 0 0 0 Freeboard
EURV_draintime_user = 2.(diameter 72 = 1-7/8 inches) Outlet Pipe 2 0 0 0 Spillway
Count_User_Hydrographs 0 (diameter 2.90 = 1-15/16 inches) 0 Spillway Length
CountA_3 (EURV & 100yr) = 0 3.09(diameter = 2 inches) Button Visibility Boolean FALSE Time Interval
CountA_4 (100yr Only) = 0 (use 3.29 rectangular openings) 1 Button_Trigger
1 Underdrain
0 WQCV Plate
0 EURV-WQCV Plate
0 EURV-WQCV VertOrifice
0 Outlet 90% Qpeak
0 Outlet Undetained
S-A-V-D Chart Axis Override X-axis Left Y-Axis Right Y-Axis
minimum bound
maximum bound
UD-Detention, Version 3.07 (February 2017)
Detention Basin Outlet Structure Design
0
1
2
3
4
5
6
7
0.1 1 10
FLOW [cfs]
TIME [hr]
500YR IN
500YR OUT
100YR IN
100YR OUT
50YR IN
Outflow Hydrograph Workbook Filename:
Storm Inflow Hydrographs
The user can override the calculated inflow hydrographs from this workbook with inflow hydrographs developed in a separate program.
SOURCE WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK
Time Interval TIME WQCV [cfs] EURV [cfs] 2 Year [cfs] 5 Year [cfs] 10 Year [cfs] 25 Year [cfs] 50 Year [cfs] 100 Year [cfs] 500 Year [cfs]
7.07 min 0:00:00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0:07:04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Hydrograph 0:14:08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Constant 0:21:13 0.02 0.08 0.06 0.07 0.09 0.13 0.15 0.20 0.27
0.707 0:28:17 0.06 0.20 0.16 0.19 0.25 0.36 0.39 0.53 0.73
0:35:21 0.16 0.52 0.42 0.49 0.63 0.92 1.00 1.36 1.88
0:42:25 0.45 1.43 1.17 1.36 1.74 2.54 2.76 3.74 5.16
0:49:29 0.51 1.67 1.36 1.58 2.03 2.97 3.24 4.40 6.10
0:56:34 0.48 1.59 1.29 1.50 1.93 2.83 3.09 4.19 5.82
1:03:38 0.44 1.44 1.17 1.36 1.75 2.58 2.81 3.82 5.30
1:10:42 0.39 1.28 1.03 1.21 1.56 2.29 2.50 3.40 4.73
1:17:46 0.33 1.09 0.88 1.03 1.33 1.96 2.14 2.92 4.07
1:24:50 0.29 0.95 0.77 0.90 1.16 1.71 1.87 2.55 3.55
1:31:55 0.26 0.86 0.70 0.82 1.05 1.55 1.69 2.31 3.22
1:38:59 0.21 0.70 0.56 0.66 0.86 1.27 1.39 1.90 2.65
1:46:03 0.16 0.56 0.45 0.53 0.69 1.03 1.12 1.54 2.16
1:53:07 0.12 0.42 0.34 0.40 0.52 0.78 0.85 1.18 1.66
2:00:11 0.08 0.30 0.24 0.29 0.38 0.57 0.62 0.87 1.23
2:07:16 0.06 0.23 0.18 0.21 0.28 0.42 0.46 0.63 0.89
2:14:20 0.05 0.18 0.14 0.17 0.22 0.33 0.36 0.49 0.69
2:21:24 0.04 0.15 0.12 0.14 0.18 0.27 0.29 0.41 0.57
2:28:28 0.04 0.13 0.10 0.12 0.15 0.23 0.25 0.35 0.48
2:35:32 0.03 0.11 0.09 0.10 0.14 0.20 0.22 0.30 0.43
2:42:37 0.03 0.10 0.08 0.09 0.12 0.18 0.20 0.27 0.38
2:49:41 0.03 0.09 0.08 0.09 0.11 0.17 0.19 0.25 0.35
2:56:45 0.02 0.07 0.06 0.06 0.08 0.12 0.14 0.19 0.26
3:03:49 0.01 0.05 0.04 0.05 0.06 0.09 0.10 0.14 0.19
3:10:53 0.01 0.04 0.03 0.03 0.04 0.07 0.07 0.10 0.14
3:17:58 0.01 0.03 0.02 0.02 0.03 0.05 0.05 0.07 0.10
3:25:02 0.01 0.02 0.01 0.02 0.02 0.03 0.04 0.05 0.07
3:32:06 0.00 0.01 0.01 0.01 0.02 0.02 0.03 0.04 0.05
3:39:10 0.00 0.01 0.01 0.01 0.01 0.02 0.02 0.03 0.04
3:46:14 0.00 0.01 0.00 0.01 0.01 0.01 0.01 0.02 0.02
3:53:19 0.00 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.01
4:00:23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01
4:07:27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:14:31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:21:35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:28:40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:35:44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:42:48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:49:52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4:56:56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:04:01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:11:05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:18:09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:25:13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:32:17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:39:22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:46:26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5:53:30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:00:34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:07:38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:14:43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Summary Stage-Area-Volume-Discharge Relationships
The user can create a summary S-A-V-D by entering the desired stage increments and the remainder of the table will populate automatically.
The user should graphically compare the summary S-A-V-D table to the full S-A-V-D table in the chart to confirm it captures all key transition points.
Stage Area Area Volume Volume
Total
Outflow
[ft] [ft^2] [acres] [ft^3] [ac-ft] [cfs]
UD-Detention, Version 3.07 (February 2017)
Detention Basin Outlet Structure Design
Stage - Storage
Description
For best results, include the
stages of all grade slope
changes (e.g. ISV and Floor)
from the S-A-V table on
Sheet 'Basin'.
Also include the inverts of all
outlets (e.g. vertical orifice,
overflow grate, and spillway,
where applicable).
M
W
W
W
W W W W
4
X
X X
X
X
X
X
X
X X X
X
X X
X
X
SS
SS
S
S
S
S
S
S
W W W
W
W
W
W
W
W W
S S
S
S S S
W W W W W W W W
W W W W W
S
S S S S
ONLY
ONLY
.
.
.
.
.
.
.
.
.
.
.
.
.
.
..
.
.
.
..
.
..
..
....
..
.
....
...
....
.
..
...
.
....
..
....
......
..
....
.
.
.
.
....
.
.
.
.
.
.
.
..
.
...
...
.
..............
.
..
.......
..
...
.
.
.
.
.
...
.
.
....
.....
.
.........
..
......
.
.
.
.
.
....................................
......
.
.....
.
....................
......
.
.....................
.
..........
.
.
.
...
............
............
.
.....
....
...
.
.
..
...............
..
.
..
..
...
..
...
.
......
...
..........
..
...........
.
..
............
.
..
.
..
.
.
.
A
0.22 0.93
1.16
E
0.39 N/A
N/A
F
0.42 N/A
N/A
G
0.56 N/A
N/A
C
1.72 0.89
B 1.12
0.33 0.89
1.11
.
.
.
.
..
.
.
.
D
0.15 N/A
N/A
.
.
..
.
.
..
.
..
.
.
..
.
..
.
.......
.
..
.
.
.
.
.
....
.
....
.
....
.
.
.
....
..
...
.
.
.
.
.
.
.
.
.
..
..
.
.
.
.
....
.
.
..
..
.
..
.
..
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5045
5043
5044
5045
5044
5046
5045
5046
5047
5045
5044
5041
5042
5040
5045
5039
5041
5042
5043
5044
5045
5046
1
2
3
5045
5045
5043
5043
5044
5044
5046
5046
5040
5039
5039
5041
5042
4.43%
2.63%
3.14%
2.44%
1.56%
1.10%
1.63%
1.66%
4.51%
5045
5044
5045.59 FL
5045.07 FL
5044.49 FL
5044.42 FL
5043.76 FL
5044.12 FL
5043.59 FL
5043.3 FL
5043.48 FL
5043.7 FL
5043.9 FL
5043.4 FL
5043.95 FL
5044.63 FL
5044.05 FL
5044.18 FL
5042.37 FG
5041.58 FG
WQ RELEASE STRUCTURE
WQ RELEASE STRUCTURE
WQ RELEASE STRUCTURE
6" 90° BEND
6" - TEE
6"-90° BEND
6" CLEANOUT
6" - 11.25° Bend
6" - Tee and
6" - 11.25° Bend
15 LF~ 6" HDPE
100 LF~ 6" HDPE
100 LF~ 6" HDPE 135 LF~ 6" HDPE
16 LF~ 6" HDPE
8 LF~ 6" 6" HDPE PIPE
43 LF~ 6" HDPE 99 LF~ 6" HDPE
15 LF~ 6" HDPE
31 LF~ 6" HDPE
113 LF~ 6" HDPE
4" CLEANOUT
4" CLEANOUT
26 LF~ 4" A-2000 SLOTTED PIPE
90 LF~ 4" A-2000 SLOTTED PIPE 88 LF~ 4" A-2000 SLOTTED PIPE
62 LF~ 4" A-2000 SLOTTED PIPE
5047.2 EOA
5045.76 FL
5045.10 FL
5044.52 FL
5042.36 FL
??? FG
??? FG
5045.97 FL
5044.54 FL
5044.88 FG
5044.78 FL
5045.04 FL
5045.88 FG
5045.90 FG
18 LF~ 4" A-2000
SLOTTED PIPE
18 LF~ 4" A-2000
SLOTTED PIPE
WQ/BIORETENTION BASIN A
VOLUME REQUIRED = 0.006 AC-FT
VOLUME PROVIDED = 0.006 AC-FT
WQ/BIORETENTION BASIN B
VOLUME REQUIRED = 0.009 AC-FT
VOLUME PROVIDED = 0.009 AC-FT
WQ/BIORETENTION BASIN C
VOLUME REQUIRED = 0.042 AC-FT
VOLUME PROVIDED = 0.042 AC-FT
0.39%
0.04%
0.49%
0.50%
0.43%
0.46%
1.85%
1.59%
1.63%
1.67%
0.46%
0.42%
0.03%
1.26%
0.31% 0.37%
0.61%
1.00%
Runoff Analysis Data Table
Basin ID C2 C100 Q2 (cfs) Q100 (cfs)
A 0.87 0.95 0.53 2.02
B 0.83 0.92 0.76 2.94
C 0.80 0.89 3.33 12.96
PROPOSED 15' TYPE R INLET
PROPOSED 4' DIA. STORM MANHOLE
CONNECT AND OUTLET TO EXISTING STORM SEWER
EXISTING STORM SEWER
REVISIONS
DESIGN: SCALE:
DRAWN: PROJECT NO:
DATE:
SHEET
PARAGON ENGINEERING CONSULTANTS, INC.
LITTLETON, CO 80120 303-794-8604
7852 SOUTH ELATI STREET, SUITE 106
Know what'sbelow.
Call before you dig.
R FORT COLLINS JEEP
DRAINAGE PLAN
TWD 11/16/2017 1" = 30'
MSG 16-018
C-19
A SUBMITTED TO FTC 03/15/2017
B SUBMITTED TO FTC 07/19/2017
C SUBMITTED TO FTC 09/08/2017
D SUBMITTED TO FTC 11/16/17
Feet
0 30 60
INFORMATION
SHOWN IS
SUBJECT
TO CHANGE. NOT
FOR
CONSTRUCTION
DRAINAGE LEGEND
BASIN NAME
2yr C VALUE
BASIN ACREAGE 100yr C VALUE
5820
5820
EX. MAJOR CONTOUR
EX. MINOR CONTOUR
PR. MAJOR CONTOUR
PR. MINOR CONTOUR
PROPOSED BASIN BOUNDARY LINE
1
BASIN
AREA 2yr
100yr
PR. STORM
EX. STORM
BASIN LABEL
DESIGN POINT
PROPOSED CONCRETE
6:21:47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:28:51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:35:55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:42:59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:50:04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:57:08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:04:12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:11:16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:18:20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:25:25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:32:29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:39:33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:46:37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:53:41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:00:46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:07:50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:14:54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:21:58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:29:02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
UD-Detention, Version 3.07 (February 2017)
Detention Basin Outlet Structure Design
50YR OUT
25YR IN
25YR OUT
10YR IN
10YR OUT
5YR IN
5YR OUT
2YR IN
2YR OUT
EURV IN
EURV OUT
WQCV IN
WQCV OUT
0
0.2
0.4
0.6
0.8
1
1.2
0.1 1 10 100
PONDING DEPTH [ft]
DRAIN TIME [hr]
500YR
100YR
50YR
25YR
10YR
5YR
2YR
EURV
WQCV
0.00
0.01
0.01
0.02
0.02
0.03
0.03
0.04
0.04
0.05
0.05
0
500
1,000
1,500
2,000
2,500
0.00 0.20 0.40 0.60 0.80 1.00 1.20
OUTFLOW [cfs]
AREA [ft^2], VOLUME [ft^3]
PONDING DEPTH [ft]
User Area [ft^2]
Interpolated Area [ft^2]
Summary Area [ft^2]
Volume [ft^3]
Summary Volume [ft^3]
Outflow [cfs]
Summary Outflow [cfs]
Predevelopment Peak Q (cfs) = 0.0 0.0 0.0 0.1 0.3 0.9 1.2 1.9 3.0
Peak Inflow Q (cfs) = 0.5 1.7 1.4 1.6 2.0 3.0 3.2 4.4 6.1
Peak Outflow Q (cfs) = 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Ratio Peak Outflow to Predevelopment Q = N/A N/A N/A 0.5 0.1 0.0 0.0 0.0 0.0
Structure Controlling Flow = Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media
Max Velocity through Grate 1 (fps) = N/A N/A N/A N/A N/A N/A N/A N/A N/A
Max Velocity through Grate 2 (fps) = N/A N/A N/A N/A N/A N/A N/A N/A N/A
Time to Drain 97% of Inflow Volume (hours) = 12 36 30 34 44 64 69 94 130
Time to Drain 99% of Inflow Volume (hours) = 12 37 30 35 45 65 71 96 133
Maximum Ponding Depth (ft) = 0.75 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Area at Maximum Ponding Depth (acres) = 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Maximum Volume Stored (acre-ft) = 0.033 0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044
Detention Basin Outlet Structure Design
UD-Detention, Version 3.07 (February 2017)
16-018 Fort Collins Jeep
Bioretention Pond C
Example Zone Configuration (Retention Pond)
-- -- -- --
Surcharge Volume Width (WISV) = user ft
-- -- -- --
Depth of Basin Floor (HFLOOR) = user ft
-- -- -- --
Length of Basin Floor (LFLOOR) = user ft
-- -- -- --
Width of Basin Floor (WFLOOR) = user ft
-- -- -- --
Area of Basin Floor (AFLOOR) = user ft^2
-- -- -- --
Volume of Basin Floor (VFLOOR) = user ft^3
-- -- -- --
Depth of Main Basin (HMAIN) = user ft
-- -- -- --
Length of Main Basin (LMAIN) = user ft
-- -- -- --
Width of Main Basin (WMAIN) = user ft
-- -- -- --
Area of Main Basin (AMAIN) = user ft^2
-- -- -- --
Volume of Main Basin (VMAIN) = user ft^3
-- -- -- --
Calculated Total Basin Volume (Vtotal) = user acre-feet
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
DETENTION BASIN STAGE-STORAGE TABLE BUILDER
Optional
Override
Area (ft^2)
Length
(ft)
Optional
Override
Stage (ft)
Stage
(ft)
Stage - Storage
Description
Area
(ft^2)
Width
(ft)
16-018 Fort Collins Jeep
Bioretention Pond C
UD-Detention, Version 3.07 (February 2017)
Volume
(ft^3)
Volume
(ac-ft)
Area
(acre)
Optional User Override
1-hr Precipitation
Total detention volume
is less than 100-year
volume.
Example Zone Configuration (Retention Pond)
Bioretention Pond C.xlsm, Basin 11/6/2017, 4:40 PM
6:06:07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:12:54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:19:41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:26:28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:33:14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:40:01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:46:48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:53:35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:00:22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:07:08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:13:55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:20:42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:27:29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:34:16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:41:02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:47:49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:54:36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:01:23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:08:10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Detention Basin Outlet Structure Design
UD-Detention, Version 3.07 (February 2017)
50YR IN
50YR OUT
25YR IN
25YR OUT
10YR IN
10YR OUT
5YR IN
5YR OUT
2YR IN
2YR OUT
EURV IN
EURV OUT
WQCV IN
WQCV OUT
0
0.2
0.4
0.6
0.8
1
1.2
0.1 1 10 100
PONDING DEPTH [ft]
DRAIN TIME [hr]
500YR
100YR
50YR
25YR
10YR
5YR
2YR
EURV
WQCV
0.00
0.00
0.00
0.01
0.01
0.01
0.01
0
50
100
150
200
250
300
350
400
450
0.00 0.20 0.40 0.60 0.80 1.00 1.20
OUTFLOW [cfs]
AREA [ft^2], VOLUME [ft^3]
PONDING DEPTH [ft]
User Area [ft^2]
Interpolated Area [ft^2]
Summary Area [ft^2]
Volume [ft^3]
Summary Volume [ft^3]
Outflow [cfs]
Summary Outflow [cfs]
Predevelopment Peak Q (cfs) = 0.0 0.0 0.0 0.0 0.1 0.2 0.3 0.4 0.6
Peak Inflow Q (cfs) = 0.1 0.4 0.3 0.3 0.5 0.7 0.7 1.0 1.4
Peak Outflow Q (cfs) = 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Ratio Peak Outflow to Predevelopment Q = N/A N/A N/A 0.4 0.1 0.0 0.0 0.0 0.0
Structure Controlling Flow = Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media
Max Velocity through Grate 1 (fps) = N/A N/A N/A N/A N/A N/A N/A N/A N/A
Max Velocity through Grate 2 (fps) = N/A N/A N/A N/A N/A N/A N/A N/A N/A
Time to Drain 97% of Inflow Volume (hours) = 12 37 30 34 45 65 71 96 133
Time to Drain 99% of Inflow Volume (hours) = 12 37 31 35 46 67 72 98 136
Maximum Ponding Depth (ft) = 0.73 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Area at Maximum Ponding Depth (acres) = 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Maximum Volume Stored (acre-ft) = 0.007 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009
Detention Basin Outlet Structure Design
UD-Detention, Version 3.07 (February 2017)
16-018 Fort Collins Jeep
Bioretention Pond B
Example Zone Configuration (Retention Pond)
-- -- -- --
Surcharge Volume Width (WISV) = user ft
-- -- -- --
Depth of Basin Floor (HFLOOR) = user ft
-- -- -- --
Length of Basin Floor (LFLOOR) = user ft
-- -- -- --
Width of Basin Floor (WFLOOR) = user ft
-- -- -- --
Area of Basin Floor (AFLOOR) = user ft^2
-- -- -- --
Volume of Basin Floor (VFLOOR) = user ft^3
-- -- -- --
Depth of Main Basin (HMAIN) = user ft
-- -- -- --
Length of Main Basin (LMAIN) = user ft
-- -- -- --
Width of Main Basin (WMAIN) = user ft
-- -- -- --
Area of Main Basin (AMAIN) = user ft^2
-- -- -- --
Volume of Main Basin (VMAIN) = user ft^3
-- -- -- --
Calculated Total Basin Volume (Vtotal) = user acre-feet
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
Optional User Override
1-hr Precipitation
Total detention volume
is less than 100-year
volume.
Volume
(ft^3)
Volume
(ac-ft)
Area
(acre)
DETENTION BASIN STAGE-STORAGE TABLE BUILDER
Optional
Override
Area (ft^2)
Length
(ft)
Optional
Override
Stage (ft)
Stage
(ft)
Stage - Storage
Description
Area
(ft^2)
Width
(ft)
16-018 Fort Collins Jeep
Bioretention Pond B
UD-Detention, Version 3.07 (February 2017)
Example Zone Configuration (Retention Pond)
Bioretention Pond B.xlsm, Basin 11/6/2017, 4:43 PM
6:34:12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:41:30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:48:48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6:56:06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:03:24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:10:42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:18:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:25:18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:32:36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:39:54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:47:12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7:54:30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:01:48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:09:06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:16:24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:23:42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:31:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:38:18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8:45:36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Detention Basin Outlet Structure Design
UD-Detention, Version 3.07 (February 2017)
100YR OUT
50YR IN
50YR OUT
25YR IN
25YR OUT
10YR IN
10YR OUT
5YR IN
5YR OUT
2YR IN
2YR OUT
EURV IN
EURV OUT
WQCV IN
WQCV OUT
0
0.2
0.4
0.6
0.8
1
1.2
0.1 1 10 100
PONDING DEPTH [ft]
DRAIN TIME [hr]
500YR
100YR
50YR
25YR
10YR
5YR
2YR
EURV
WQCV
0.00
0.00
0.00
0.00
0.00
0.01
0.01
0.01
0
50
100
150
200
250
300
0.00 0.20 0.40 0.60 0.80 1.00 1.20
OUTFLOW [cfs]
AREA [ft^2], VOLUME [ft^3]
PONDING DEPTH [ft]
User Area [ft^2]
Interpolated Area [ft^2]
Summary Area [ft^2]
Volume [ft^3]
Summary Volume [ft^3]
Outflow [cfs]
Summary Outflow [cfs]
Predevelopment Peak Q (cfs) = 0.0 0.0 0.0 0.0 0.0 0.1 0.2 0.3 0.4
Peak Inflow Q (cfs) = 0.1 0.2 0.2 0.2 0.3 0.4 0.5 0.6 0.8
Peak Outflow Q (cfs) = 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Ratio Peak Outflow to Predevelopment Q = N/A N/A N/A 0.5 0.2 0.1 0.0 0.0 0.0
Structure Controlling Flow = Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media Filtration Media
Max Velocity through Grate 1 (fps) = N/A N/A N/A N/A N/A N/A N/A N/A N/A
Max Velocity through Grate 2 (fps) = N/A N/A N/A N/A N/A N/A N/A N/A N/A
Time to Drain 97% of Inflow Volume (hours) = 12 36 30 35 43 63 70 93 130
Time to Drain 99% of Inflow Volume (hours) = 12 37 30 36 44 65 71 95 133
Maximum Ponding Depth (ft) = 0.67 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Area at Maximum Ponding Depth (acres) = 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Maximum Volume Stored (acre-ft) = 0.004 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006
Detention Basin Outlet Structure Design
UD-Detention, Version 3.07 (February 2017)
16-018 Fort Collins Jeep
Bioretention Pond A
Example Zone Configuration (Retention Pond)
-- -- -- --
Surcharge Volume Width (WISV) = user ft
-- -- -- --
Depth of Basin Floor (HFLOOR) = user ft
-- -- -- --
Length of Basin Floor (LFLOOR) = user ft
-- -- -- --
Width of Basin Floor (WFLOOR) = user ft
-- -- -- --
Area of Basin Floor (AFLOOR) = user ft^2
-- -- -- --
Volume of Basin Floor (VFLOOR) = user ft^3
-- -- -- --
Depth of Main Basin (HMAIN) = user ft
-- -- -- --
Length of Main Basin (LMAIN) = user ft
-- -- -- --
Width of Main Basin (WMAIN) = user ft
-- -- -- --
Area of Main Basin (AMAIN) = user ft^2
-- -- -- --
Volume of Main Basin (VMAIN) = user ft^3
-- -- -- --
Calculated Total Basin Volume (Vtotal) = user acre-feet
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
-- -- -- --
Optional User Override
1-hr Precipitation
Total detention volume
is less than 100-year
volume.
Volume
(ft^3)
Volume
(ac-ft)
Area
(acre)
DETENTION BASIN STAGE-STORAGE TABLE BUILDER
Optional
Override
Area (ft^2)
Length
(ft)
Optional
Override
Stage (ft)
Stage
(ft)
Stage - Storage
Description
Area
(ft^2)
Width
(ft)
16-018 Fort Collins Jeep
Bioretention Pond A
UD-Detention, Version 3.07 (February 2017)
Example Zone Configuration (Retention Pond)
Bioretention Pond A.xlsm, Basin 11/6/2017, 4:41 PM
of the version date(s) listed below.
Soil Survey Area: Larimer County Area, Colorado
Survey Area Data: Version 11, Sep 23, 2016
Soil map units are labeled (as space allows) for map scales
1:50,000 or larger.
Date(s) aerial images were photographed: Apr 22, 2011—Apr
28, 2011
The orthophoto or other base map on which the soil lines were
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
Hydrologic Soil Group—Larimer County Area, Colorado
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/12/2017
Page 2 of 4