HomeMy WebLinkAboutTHE HUB ON CAMPUS - PDP - PDP160038 - SUBMITTAL DOCUMENTS - ROUND 4 - UTILITY PLANS
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
ORIGINAL FIELD SURVEY:
JAMES S. DAVENPORT
PARTNER ENGINEERING AND SCIENCE, INC.
CAXTON BUILDING
812 HURON RD., SUITE 690
CLEVELAND, OH 44115
DATE: 09/29/2016
REVISED: 02/07/2017
SUBSURFACE EXPLORATION BY:
DAVID RICHER
EARTH ENGINEERING CONSULTANTS, LLC
4396 GREENFIELD DRIVE
WINDSOR, CO 80550
DISCLAIMER STATEMENT:
THESE PLANS HAVE BEEN REVIEWED BY THE CITY OF FORT COLLINS FOR CONCEPT ONLY. THE
REVIEW DOES NOT IMPLY RESPONSIBILITY BY THE REVIEWING DEPARTMENT, THE CITY OF FORT
COLLINS ENGINEER, OR THE CITY OF FORT COLLINS FOR ACCURACY AND CORRECTNESS OF THE
CALCULATIONS. FURTHERMORE, THE REVIEW DOES NOT IMPLY THAT QUANTITIES OF ITEMS ON
THE PLANS ARE THE FINAL QUANTITIES REQUIRED. THE REVIEW SHALL NOT BE CONSTRUED FOR
ANY REASON AS ACCEPTANCE OF FINANCIAL RESPONSIBILITY BY THE CITY OF FORT COLLINS FOR
ADDITIONAL QUANTITIES OF ITEMS SHOWN THAT MAY BE REQUIRED DURING THE CONSTRUCTION
PHASE.
CERTIFICATION STATEMENT:
I HEREBY AFFIRM THAT THESE FINAL CONSTRUCTION PLANS WERE PREPARED UNDER MY DIRECT
SUPERVISION, IN ACCORDANCE WITH ALL APPLICABLE CITY OF FORT COLLINS AND STATE OF
COLORADO STANDARDS AND STATUTES, RESPECTIVELY; AND THAT I AM FULLY RESPONSIBLE FOR
THE ACCURACY OF ALL DESIGN, REVISIONS, AND RECORD CONDITIONS THAT I HAVE NOTED ON
THESE PLANS.
CONTACT INFORMATION
PROJECT TEAM:
OWNER
CHAD MATESI
CORE FORT COLLINS 1415 ELIZABETH, LLC
2234 W. NORTH AVENUE
CHICAGO, IL 60647
TEL: 773-969-5748
APPLICANT
SAM COUTTS
RIPLEY DESIGN, INC.
419 CANYON AVE., #200
FORT COLLINS, CO 80521
TEL: 970-224-5828
ARCHITECT
GRANT BRANDENBURG
WARE MALCOMB
1600 CHAMPA STREET, SUITE 350
DENVER, CO 80202
TEL: 630-570-6765
LANDSCAPE ARCHITECT
SAM COUTTS
RIPLEY DESIGN, INC.
419 CANYON AVE., #200
FORT COLLINS, CO 80521
TEL: 970-224-5828
SITE ENGINEER
LESLEY NETZER
2 OF 16
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
GENERAL NOTES
Know what's below.
Call before you dig.
² ²
TWO STORY FRAME SPLIT
LEVEL W/WALKOUT
648$5()((7
BUILDING HEIGHT: 34.5'
1415 WEST ELIZABETH STREET
LOT 2
FAIRVIEW SHOPPING CENTER
LOT 2,
POTT'S P.U.D.
TWO STORY BRICK W/FRAME
648$5()((7
BUILDING HEIGHT: 28.3'
1415 WEST ELIZABETH STREET
ASPHALT
ASPHALT
SS MH
RIM=44.39
INV IN (8" W)=36.04
INV IN (8" S)=36.14
INV OUT (8" E)=35.99
ASPHALT
ASPHALT
ASPHALT
ASPHALT
ASPHALT
TRANSFORMER
SPRINKLER CONTROLLER
STEPS
WALK WALK
WALK
WALK
WALK WALK
L/S
L/S
L/S L/S
L/S L/S
L/S L/S
L/S
L/S
L/S L/S
L/S L/S
CONCRETE
WALK
WALK
WALK
L/S L/S
L/S
WALK
L/S
L/S
STEPS
WALK WALK
CONCRETE
PATIO
SHED
RAILROAD TIES
CONCRETE CONCRETE
COLUMN (TYPICAL)
PARK BENCH
HANDICAP
LEGEND
GENERAL NOTES
ELIZABETH STREET
PRIVATE DRIVE
RESIDENTIAL BUILDING
FFE = 45.50
RETAIL USE
6)
FFE = 40.50
PROPOSED GARAGE
FFE: 40.50
RESIDENTIAL LOBBY
FFE = 40.50
4 OF 16
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
THE HUB ON CAMPUS FORT COLLINS
DIMENSION
CONTROL AND
PAVING PLAN
NORTH
Know what's below.
Call before you dig.
KEY NOTES
TRANSFORMER
SPRINKLER CONTROLLER
TRANSFORMER
TELEPHONE BOX
2" DRAIN
PIPES
STM INLET
RIM=41.17
INV (4" W)=39.34
BOTTOM=37.89
STM MH
RIM=39.23
INV IN (12" W)=34.88
INV IN (15" S)=34.45
INV OUT (15" E)=34.38
STM GRATE
GRATE=5939.05
INV (4" SE)=5938.36
FULL OF SILT
STM GRATE
GRATE=38.84
INV (10" S)=36.26
STM INLET
RIM=41.12
INV (3" E)=39.54
BOTTOM=37.89
STM GRATE
GRATE=36.89
INV OUT (NE 6")=34.4
STM MANHOLE
RIM=40.82
INV IN (15" S)=37.47
INV OUT (15" E)=37.37
STM MH
NO EVIDENCE FOUND
ST MH
RIM=40.01
INV IN (15" S)=35.01
INV IN (15" W)=36.16
INV IN (15" E)=35.11
INV OUT (15" N)=34.96
STM AREA DRAIN
GRATE=38.32
INV IN (6" E)=36.62
INV OUT (6" N)=36.59
STM MH
RIM=40.85
INV IN (12" S)=36.10
INV IN (12" W)=35.85
INV OUT (12" E)=35.80
PRIVATE DRIVE
ELIZABETH STREET
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
THE HUB ON CAMPUS FORT COLLINS
NORTH
Know what's below.
Call before you dig.
ELIZABETH STREET
PRIVATE DRIVE
RESIDENTIAL BUILDING
FFE = 45.50
RETAIL USE
6)
FFE = 40.50
PROPOSED GARAGE
FFE: 40.50
RESIDENTIAL LOBBY
FFE = 40.50
UTILITY ACCESS PLATES
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
THE HUB ON CAMPUS FORT COLLINS
NORTH
EROSION CONTROL LEGEND
6 OF 16
FINAL EROSION
CONTROL PLAN
Know what's below.
Call before you dig.
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
THE HUB ON CAMPUS FORT COLLINS
7 OF 16
EROSION CONTROL
NOTES AND
DETAILS
2" X 2" X 36" WOODEN
STAKES (OR SANDBAGS
WHEN ON PAVEMENT)
PLACED 5' O.C.
SECTION
PLAN
NOTES:
1. ALL MATERIAL TO MEET
FILTREXX SPECIFICATIONS.
2. FILTER MEDIA FILL TO MEET
APPLICATION REQUIREMENTS.
3. COMPOST MATERIAL TO BE
DISPERSED ON SITE, AS
DETERMINED BY ENGINEER.
12" MIN
BLOWN/PLACED FILTER
MEDIA
WORK AREA AREA TO BE PROTECTED
WORK AREA
AREA TO BE
PROTECTED
2" X 2" X 36" WOODEN STAKES (OR SANDBAGS
WHEN ON PAVEMENT) PLACED 5' O.C.
FILTREXX
SOXX (12"
WATER FLOW TYPICAL) OR EQUAL
FILTREXX SOXX (12"
TYPICAL) OR EQUAL
Mobilization Demolition Grading CITY OF FORT COLLINS EROSION CONTROL NOTES
Utilities
Installation
Flat work
Installation
Vertical
Installation Landscape Demobilization (Construction Phases)
Best Management Practices (BMPs)
Structural "Installation"
Silt Fence Barriers*
Contour Furrows (Ripping / Disking)
Sediment Trap / Filter
Vehicle Tracking Pad*
Flow Barriers (Wattles)*
Inlet Filter Bags*
Any prior inlets
that could use
protecting
Rock Bags*
Any prior inlets
that could use
protecting
Terracing
LOT 2
FAIRVIEW SHOPPING CENTER
LOT 2,
POTT'S P.U.D.
SS MH
RIM=44.39
INV IN (8" W)=36.04
INV IN (8" S)=36.14
INV OUT (8" E)=35.99
SS MH
RIM=40.02
INV.IN (6" E)=32.32
INV IN (6" W)=32.17
INV IN (8" S)=32.12
INV.OUT (8" N)=32.07
SS MH
RIM=38.88
INV IN (8" S)=31.10
INV IN (8" N)=31.70
INV OUT (8" E)=30.97
WATER MH
SS MH
RIM=39.78
INV IN (8" S)=32.48
INV IN (8" W)=32.58
INV OUT (8" N)=32.38
WATER MH
RIM=38.43
INV THRU=33.45
BOTTOM=33.03
STM INLET
RIM=41.17
INV (4" W)=39.34
BOTTOM=37.89
STM MH
RIM=39.23
INV IN (12" W)=34.88
INV IN (15" S)=34.45
INV OUT (15" E)=34.38
STM GRATE
GRATE=5939.05
INV (4" SE)=5938.36
FULL OF SILT
STM GRATE
GRATE=38.84
INV (10" S)=36.26
STM INLET
RIM=41.12
INV (3" E)=39.54
BOTTOM=37.89
STM GRATE
GRATE=36.89
INV OUT (NE 6")=34.4
STM MANHOLE
RIM=40.82
INV IN (15" S)=37.47
INV OUT (15" E)=37.37
STM MH
NO EVIDENCE FOUND
ST MH
ST MH
RIM=41.01
INV IN (12" W)=35.01
INV IN (15" S)=34.91
INV OUT (15" N)=34.86
ELIZABETH STREET
PRIVATE DRIVE
AREA 1
AREA: 0.11 AC
C-MINOR: 0.66
C-MAJOR: 0.82
AREA 3
AREA: 0.35 AC
C-MINOR: 0.90
C-MAJOR: 1.00
AREA 9
AREA: 0.50 AC
C-MINOR: 0.79
C-MAJOR: 0.99
PRIVATE DRIVE:
0.07 AC
C-MINOR: 0.84
C-MAJOR: 1.00
OFFSITE
AREA: 0.05 AC
C-MINOR: 0.15
C-MAJOR: 0.19
RETAIL USE
FFE = 40.50
RESIDENTIAL
LOBBY
FFE = 40.50
AREA 8
AREA: 0.07 AC
C-MINOR: 0.49
C-MAJOR: 0.62
AREA 5
AREA: 0.41 AC
C-MINOR: 0.89
C-MAJOR: 1.00
AREA 4
AREA: 0.15 AC
C-MINOR: 0.74
C-MAJOR: 0.92
AREA 2
AREA: 0.12 AC
C-MINOR: 0.75
C-MAJOR: 0.94
RAIN GARDEN 1
WQv: 515 CF
RAIN GARDEN 2
WQv: 533 CF
RAIN GARDEN 3
WQv: 480 CF
DRAINAGE BASIN AREA
(AC)
IMPERVIOUS
AREA (AC)
LANDSCAPED
AREA (AC)
ST MH
RIM=41.01
INV IN (12" W)=35.01
ELIZABETH STREET
PRIVATE DRIVE
RESIDENTIAL BUILDING
FFE = 45.50
RETAIL USE
6)
FFE = 40.50
RESIDENTIAL LOBBY
FFE = 40.50
10 OF 16
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
THE HUB ON CAMPUS FORT COLLINS
GRADING PLAN
GRADING NOTES
NORTH
GRADING LEGEND
Know what's below.
Call before you dig.
PARKWAY GRADING DETAIL
SCALE: 1" = 10'
RAMP GRADING DETAIL 1
SCALE: 1" = 10'
RAMP GRADING DETAIL 3
SCALE: 1" = 10'
RAMP GRADING DETAIL 2
SCALE: 1" = 10'
STORM STRUCTURE TABLE STORM STRUCTURE TABLE STORM STRUCTURE TABLE
ST MH
RIM=41.01
INV IN (12" W)=35.01
INV IN (15" S)=34.91
INV OUT (15" N)=34.86
STM AREA DRAIN
GRATE=38.32
INV IN (6" E)=36.62
INV OUT (6" N)=36.59
STM MH
RIM=40.85
INV IN (12" S)=36.10
INV IN (12" W)=35.85
INV OUT (12" E)=35.80
ELIZABETH STREET
PRIVATE DRIVE
RETAIL USE
FFE = 40.50
RESIDENTIAL
LOBBY
FFE = 40.50
PARKING GARAGE
FFE = 40.50
RESIDENTIAL BUILDING
FFE = 45.50
STORM STRUCTURE TABLE
11 OF 16
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
THE HUB ON CAMPUS FORT COLLINS
STORM
SEWER PLAN
NORTH
Know what's below.
Call before you dig.
DRAINAGE LEGEND
STORM SEWER NOTES
SANITARY STRUCTURE TABLE SANITARY STRUCTURE TABLE
UTILITY LEGEND UTILITY NOTES
SS MH
RIM=44.47
INV IN (8" S)=36.37
INV OUT (8" N)=36.27
ELIZABETH STREET
PRIVATE DRIVE
MIXED USE BUILDING
FFE = 40.50
RESIDENTIAL BUILDING
FFE = 45.50
PARKING GARAGE
FFE = 40.50
WATER STRUCTURE TABLE
12 OF 16
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
THE HUB ON CAMPUS FORT COLLINS
UTILITY PLAN
NORTH
Know what's below.
Call before you dig.
UTILITY CROSSING LEGEND
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
THE HUB ON CAMPUS FORT COLLINS
13 OF 16
CROSS
SECTION
PROFILE PLAN
CURB-CURB PAVERS B-B
N.T.S.
CURB-BUILDING PAVERS C-C
N.T.S.
WATER PROFILE 1
N.T.S.
WATER PROFILE 2
N.T.S.
WATER PROFILE 3
N.T.S.
UPTOWN PROFILE A-A
N.T.S.
14 OF 16
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
CONSTRUCTION
DETAILS
6" CURB & 12" GUTTER
N.T.S.
ASPHALTIC PAVEMENT SECTION
N.T.S.
CONCRETE PAVEMENT SECTION
N.T.S.
CONCRETE SIDEWALK
N.T.S.
STANDARD 30X30 RED
STOP SIGN
"J" 30"x30"
ɕ
6" CURB & 24" GUTTER
N.T.S.
STANDARD SIGN BASE
N.T.S.
PAINTED CROSSWALK DETAIL
N.T.S.
15 OF 16
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
CONSTRUCTION
DETAILS
BEDDING REQUIRMENTS
WW-1
SERVICE WYE DETAIL
WW-9
STANDARD MANHOLE
WW-3
Minimum 8" Thick Layer of
CDOT No. 4 Aggregate
Minimum 4" Perforated
PVC Pipe (Optional
Depending on Underlying
Soil Conditions)
Minimum 30-mil
HDPE Impervious
Membrane
(Required for
Building Protection)
12" Ponding Depth
Minimum 12" Thick Layer
of Bioretention Sand Media
(see Bioretention Sand
Media Specification from
City of Fort Collins)
Minimum 6" Thick Layer of
Pea Gravel Diaphragm
Parking/Building
Water Surface
Minimum CDOT
No. 4 Aggregate
Above and Below
PVC Pipe
Undisturbed Soil
Overflow
Structure
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
16 OF 16
CONSTRUCTION
DETAILS
STORM STRUCTURE D10
N.T.S.
RIP RAP DETAIL
N.T.S.
PERVIOUS
PAVERS (AC)
CMINOR
(C2, C10)
CMAJOR
(C100 =
Cf*CMINOR)
TC (MIN)
AREA 1 0.11 0.05 0.02 0.04 0.66 0.82 5.00
AREA 2 0.12 0.07 0.01 0.04 0.75 0.94 5.00
AREA 3 0.35 0.33 0.02 0.00 0.90 1.00 5.00
AREA 4 0.15 0.08 0.01 0.06 0.74 0.92 5.00
AREA 5 0.41 0.38 0.03 0.00 0.89 1.00 5.00
AREA 6 0.05 0.01 0.01 0.03 0.55 0.69 5.00
AREA 7 0.05 0.02 0.00 0.03 0.71 0.89 5.00
AREA 8 0.07 0.01 0.02 0.04 0.49 0.62 5.00
AREA 9 0.50 0.40 0.10 0.00 0.79 0.99 5.00
PRIVATE DRIVE 0.07 0.06 0.01 0.00 0.84 1.00 5.00
OFFSITE 0.05 0.00 0.05 0.00 0.15 0.19 5.00
TOTAL 1.93 1.41 0.28 0.24 0.78 0.98 N.A
9 OF 16
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
PROPOSED
DRAINAGE PLAN
NORTH
DRAINAGE LEGEND
Know what's below.
Call before you dig.
HUB ON CAMPUS FT. COLLINS
x
x
x
x
x
x
x
x
x
x
DRAINAGE BASIN AREA
(AC)
IMPERVIOUS
AREA (AC)
LANDSCAPED
AREA (AC)
AREA 1 0.11 0.05 0.02
AREA 2 0.12 0.07 0.01
AREA 4 0.15 0.08 0.01
AREA 6 0.05 0.01 0.01
AREA 7 0.05 0.02 0.00
AREA 8 0.07 0.01 0.02
RAIN GARDEN
DRAINA
GE
BASIN
AREA (AC) WQv VOL
REQUIRED (CF)
1 AREA 3 0.35 445
2 AREA 5 0.41 511
3 AREA 9 0.50 477
DRAINAGE AREA COEFFICIENTS AND RUNOFF VALUES
PERVIOUS PAVERS RUN-ON RATIO CALCULATIONS
RAIN GARDEN WATER QUALITY CALCULATIONS
RIM=40.01
INV IN (15" S)=35.01
INV IN (15" W)=36.16
INV IN (15" E)=35.11
INV OUT (15" N)=34.96
ST MH
RIM=41.01
INV IN (12" W)=35.01
INV IN (15" S)=34.91
INV OUT (15" N)=34.86
STM AREA DRAIN
GRATE=38.32
INV IN (6" E)=36.62
INV OUT (6" N)=36.59
STM MH
RIM=40.85
INV IN (12" S)=36.10
INV IN (12" W)=35.85
INV OUT (12" E)=35.80
EX1
AREA: 0.63 AC
C-MINOR: 0.81
C-MAJOR: 1.00
EX4
AREA: 0.05 AC
C-MINOR: 0.79
C-MAJOR:0.99
ELIZABETH STREET
PRIVATE DRIVE
EX2
AREA: 0.13 AC
C-MINOR: 0.95
C-MAJOR: 1.00
EX3
AREA: 0.25 AC
C-MINOR: 0.89
C-MAJOR: 1.00
EX5
AREA: 0.14 AC
C-MINOR: 0.95
C-MAJOR: 1.00
OFFSITE 1
AREA: 0.02 AC
C-MINOR: 0.15
C-MAJOR:0.19
OFFSITE 2
AREA: 0.01 AC
C-MINOR: 0.95
C-MAJOR:1.00
OFFSITE 3
AREA: 0.02 AC
C-MINOR: 0.55
C-MAJOR:0.69
OFFSITE 4
AREA: 0.33 AC
C-MINOR: 0.83
C-MAJOR: 1.00
OFFSITE 5
AREA: 0.35 AC
C-MINOR: 0.90
C-MAJOR: 1.00
DRAINAGE
BASIN AREA (AC)
IMPERVIOUS
AREA (AC)
PERVIOUS
AREA (AC)
CMINOR
(C2, C10)
CMAJOR
(C100 =
Cf*CMINOR)
TC (MIN) Q2 (CFS) Q10
(CFS)
Q100
(CFS) OUTLET POINT
EX1 0.63 0.52 0.11 0.81 1.00 5.00 1.45 2.49 6.27 EXISTING STORM GRATE
EX2 0.13 0.13 0.00 0.95 1.00 5.00 0.35 0.60 1.29 BUILDING ROOF
EX3 0.25 0.23 0.02 0.89 1.00 5.00 0.63 1.08 2.49 EXISTING STORM GRATE
EX4 0.05 0.04 0.01 0.79 0.99 5.00 0.11 0.19 0.49 EXISTING STORM GRATE
EX5 0.14 0.14 0.00 0.95 1.00 5.00 0.38 0.65 1.39 BUILDING ROOF
OFFSITE 1 0.02 0.00 0.02 0.15 0.19 5.00 0.01 0.01 0.04 OFFSITE - SOUTH
OFFSITE 2 0.01 0.01 0.00 0.95 1.00 5.00 0.03 0.05 0.10 OFFSITE - WEST
OFFSITE 3 0.02 0.01 0.01 0.55 0.69 5.00 0.03 0.05 0.14 OFFSITE - WEST
OFFSITE 4 0.33 0.28 0.05 0.83 1.00 5.00 0.78 1.33 3.28 OFFSITE - NORTH
OFFSITE 5 0.35 0.33 0.02 0.90 1.00 5.00 0.90 1.54 3.48 OFFSITE STORM GRATE - EAST
TOTAL 1.93 1.69 0.24 0.85 1.00 N/A 4.68 7.99 18.97
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
DRAINAGE LEGEND THE HUB ON CAMPUS FORT COLLINS
8 OF 16
EXISTING
DRAINAGE PLAN
NORTH
Know what's below.
Call before you dig.
x
x
x
x
x
x
x
x
x
x
Stream Flow Diversion*
Rip Rap
Collecting Asphalt / Concrete Saw Cutting Waste
*All BMPs to be Removed once Construction is Complete.
Vegetative
Temporary Seeding Planting
Any time the
site will sit
dorment
longer than
30 Days.
Mulching/Sealant
Any time the
site will sit
dorment
longer than
30 Days.
Permanent Seeding Planting
Sod Installation
Rolled Products : Netting/Blankets/Mats
Any time the
site will sit
dorment
longer than
30 Days.
Other:
EROSION CONTROL NOTES
5 OF 16
INITIAL EROSION
CONTROL PLAN
EROSION CONTROL LEGEND
EROSION CONTROL SCHEDULE AND SEQUENCING:
RAMP
MONUMENT
SIGN
TRANSFORMER
TELEPHONE BOX
L/S
L/S
TRASH
ENCLOSURE
BUILDING OVERHANG
(TYPICAL)
BUILDING OVERHANG
(TYPICAL)
L/S
2" DRAIN
PIPES
ADJACENT BUILDING
ADJACENT
BUILDING
ADJACENT BUILDING
CONCRETE WALL
WOOD TRELLIS
BUILDING OVERHANG
(TYPICAL)
ADJACENT BUILDING
AREA UNDER
CONSTRUCTION
STM MH
RIM=39.23
INV IN (12" W)=34.88
INV IN (15" S)=34.45
MONUMENT INV OUT (15" E)=34.38
SIGN
DRIVE THRU
SIGN
CHASE
ACCESS
SPEED BUMP
TRASH
ENCLOSURE
AREA OBSTRUCTED
ELIZABETH STREET
EXISTING
TACO BELL
PRIVATE DRIVE
DEMOLITION LEGEND
WALK
L/S
L/S
L/S L/S
TRASH
ENCLOSURE
THE HUB ON CAMPUS
FORT COLLINS
FORT COLLINS, CO 80521
THE HUB ON CAMPUS FORT COLLINS
3 OF 16
DEMOLITION
PLAN
Know what's below.
NORTH Call before you dig.
DEMOLITION DETAIL
1" = 10'
DEMOLITION NOTES
³ ´
KIMLEY-HORN AND ASSOCIATES, INC.
4582 SOUTH ULSTER STREET
SUITE 1500
DENVER, CO 80237
TEL: 630-487-5555
SURVEYOR
JAMES S. DAVENPORT
PARTNER ENGINEERING AND SCIENCE, INC.
CAXTON BUILDING
812 HURON RD., SUITE 690
CLEVELAND, OH 44115
TEL: 440-987-1001
TRAFFIC ENGINEER
CURTIS ROWE
KIMLEY-HORN AND ASSOCIATES, INC.
4582 SOUTH ULSTER STREET
SUITE 1500
DENVER, CO 80237
TEL: 303-228-2304
GEOTECHNICAL ENGINEER
DAVID RICHER
EARTH ENGINEERING CONSULTANTS, LLC
4396 GREENFIELD DRIVE
WINDSOR, CO 80550
TEL: 970-545-3908
UTILITY CONTACTS:
GAS
TERRY STENCEL
XCEL ENERGY
TEL: (970) 225-7857
ELECTRIC
TYLER SIEGMUND
CITY OF FORT COLLINS LIGHT & POWER
TEL: (970) 416-2772
CABLE
DON KAPPERMAN
COMCAST
TEL: (970) 567-0425
TELECOMMUNICATIONS
WILLIAM JOHNSON
CENTURYLINK
TEL: (970) 377-6401
WATER
HEATHER McDOWELL
CITY OF FORT COLLINS
TEL: (970) 224-6065
WASTEWATER
HEATHER McDOWELL
CITY OF FORT COLLINS
TEL: (970) 224-6065
STORMWATER
HEATHER McDOWELL
CITY OF FORT COLLINS
TEL: (970) 224-6065
UTILITY PLANS FOR
THE HUB ON CAMPUS FORT COLLINS
LOT 1, CORE FORT COLLINS SUBDIVISION
SITUATED IN THE NORTHWEST 1
4 OF THE SOUTHEAST
1
4 OF SECTION 15,
TOWNSHIP 7 NORTH RANGE 69 WEST OF THE SIXTH PRINCIPAL MERIDIAN,
CITY OF FORT COLLINS, COUNTY OF LARIMER, STATE OF COLORADO.
NOVEMBER 2017
PROJECT BENCHMARKS:
COVER SHEET
PROJECT DATUM: NAVD88
BENCHMARK #20-97 AT THE SOUTHWEST CORNER OF WEST ELIZABETH AND CONSTITUTION AVE. ON A
CONCRETE TRAFFIC SIGNAL BASE.
ELEVATION: 5050.15 FEET
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING DEVELOPMENTS
HAVE USED NGVD29 UNADJUSTED FOR THEIR VERTICAL DATUMS.
IF NVGD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE THE FOLLOWING EQUATION SHOULD BE
USED: NGVD29 UNADJUSTED = NAVD88 - 3.18'.
N
SPRINGFIELD DR.
CONSTITUTION AVE.
PLUM ST.
BENNETT RD.
W. ELIZABETH ST.
S. SHIELDS ST.
COLORADO
STATE
UNIVERSITY
CITY PARK AVE.
PROJECT
LOCATION
Know what's below.
Call before you dig.
LARIMER COUNTY CANAL #2
NEW MERCER CANAL
Sheet List Table
Sheet Number Sheet Title
1 OF 16 COVER SHEET
2 OF 16 GENERAL NOTES
3 OF 16 DEMOLITION PLAN
4 OF 16 DIMENSION CONTROL AND PAVING PLAN
5 OF 16 INITIAL EROSION CONTROL PLAN
6 OF 16 FINAL EROSION CONTROL PLAN
7 OF 16 EROSION CONTROL NOTES AND DETAILS
8 OF 16 EXISTING DRAINAGE PLAN
9 OF 16 PROPOSED DRAINAGE PLAN
10 OF 16 GRADING PLAN
11 OF 16 STORM SEWER PLAN
12 OF 16 UTILITY PLAN
13 OF 16 CROSS SECTION PROFILE PLAN
14 OF 16 CONSTRUCTION DETAILS
15 OF 16 CONSTRUCTION DETAILS
16 OF 16 CONSTRUCTION DETAILS
1 OF 16