HomeMy WebLinkAboutTHE STANDARD AT FORT COLLINS - FDP - FDP170023 - SUBMITTAL DOCUMENTS - ROUND 2 - PROJECT NARRATIVEID Task Name Duration Start Finish Predecessors Successors Notes 1 Prospect and Whitcomb Turn Lane 2 Due Diligence 155 days Mon 5/15/17 Fri 12/15/17 3 Collect Survey Data 3 days Mon 5/15/17 Wed 5/17/17 8 4 Geotechnical Report 25 days Mon 11/13/17 Fri 12/15/17 19,5SS+5 days 5 Geotechnical Field Work 3 days Mon 11/20/17 Wed 11/22/17 15,4SS+5 days To be completed during Fall Recess 6 7 Preliminary Plan Development and Review 129 days Thu 5/18/17 Tue 11/14/17 8 Prepare preliminary plans 20 days Thu 5/18/17 Wed 6/14/17 3 9 9 Submit preliminary plans to City of Fort Collins for review and coordination with CSU 0 days Wed 6/14/17 Wed 6/14/17 8 10 10 Initial review by City/CSU and coordination on right-of-way acquisition 59 days Thu 6/15/17 Tue 9/5/17 9 11 11 Meeting between Applicant, City, and CSU to review project and submittal process 0 days Tue 9/5/17 Tue 9/5/17 10 12 12 Applicant prepares additional information for City/CSU review 10 days Wed 9/6/17 Tue 9/19/17 11 13 13 2nd review of preliminary plans by City/CSU and coordination on right-of-way acquisition 40 days Wed 9/20/17 Tue 11/14/17 12 14 14 Approval of preliminary plan by City/CSU 0 days Tue 11/14/17 Tue 11/14/17 13 18,19,15 15 Authorization to proceed with Geotechnical work on CSU property 0 days Tue 11/14/17 Tue 11/14/17 14 5 16 17 Final Plan Development and Review 201 days Wed 11/15/17 Wed 8/22/18 18 Prepare Site/Utility plans 20 days Wed 11/15/17 Tue 12/12/17 14 19 Prepare Structural plans 18 days Mon 12/18/17 Wed 1/10/18 4,14 20 20 Submit Final Plans to City/CSU 0 days Wed 1/10/18 Wed 1/10/18 19 21 21 Initial FDP Review and City/CSU coordination 40 days Thu 1/11/18 Wed 3/7/18 20 22 22 Applicant revises and resubmits plans 15 days Thu 3/8/18 Wed 3/28/18 21 23 23 2nd FDP Review and City/CSU coordination 40 days Thu 3/29/18 Wed 5/23/18 22 24 24 Finalizing Plans and Development Agreement 30 days Thu 5/24/18 Wed 7/4/18 23 25 25 Recording Mylars and Development Agreement 25 days Thu 7/5/18 Wed 8/8/18 24 26 26 Process Development Construction Permit 10 days Thu 8/9/18 Wed 8/22/18 25 29 27 CSU Board of Governors approve right-of-way dedication 29 28 29 Turn Lane Construction 45 days Mon 6/3/19 Fri 8/2/19 26,27 To be completed between end of Spring 2019 semester and start of Fall 2019 Semester 30 31 The Standard at Fort Collins 32 Initial FDP Review 21 days Wed 8/9/17 Wed 9/6/17 33FS+9 days 33 2nd FDP Review 15 days Wed 9/20/17 Tue 10/10/17 32FS+9 days 34 34 Finalizing Plans, Plat, and Development Agreement 30 days Wed 10/11/17 Tue 11/21/17 33 35 35 Recording Mylars and Development Agreement 25 days Wed 11/22/17 Tue 12/26/17 34 36 36 Process Development Construction Permit 10 days Wed 12/27/17 Tue 1/9/18 35 37,39 37 Process address assignment request 10 days Wed 1/10/18 Tue 1/23/18 36 38 38 Building Plan Review 80 days Wed 1/24/18 Tue 5/15/18 37 39 Construction Phase 599 days Tue 5/1/18 Fri 8/14/20 36 40 40 Certificate of Occupancy Issued 0 days Fri 8/14/20 Fri 8/14/20 39 2 6/14 9/5 11/14 11/14 1/10 8/14 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2018 2019 2020 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: Prospect and Whitcom Date: Mon 9/18/17