HomeMy WebLinkAboutTHE STANDARD AT FORT COLLINS - FDP - FDP170023 - SUBMITTAL DOCUMENTS - ROUND 2 - PROJECT NARRATIVEID Task Name Duration Start Finish Predecessors Successors Notes
1 Prospect and Whitcomb Turn Lane
2 Due Diligence 155 days Mon 5/15/17 Fri 12/15/17
3 Collect Survey Data 3 days Mon 5/15/17 Wed 5/17/17 8
4 Geotechnical Report 25 days Mon 11/13/17 Fri 12/15/17 19,5SS+5 days
5 Geotechnical Field Work 3 days Mon 11/20/17 Wed 11/22/17 15,4SS+5 days To be completed during Fall Recess
6
7 Preliminary Plan Development and Review 129 days Thu 5/18/17 Tue 11/14/17
8 Prepare preliminary plans 20 days Thu 5/18/17 Wed 6/14/17 3 9
9 Submit preliminary plans to City of Fort Collins for
review and coordination with CSU
0 days Wed 6/14/17 Wed 6/14/17 8 10
10 Initial review by City/CSU and coordination on
right-of-way acquisition
59 days Thu 6/15/17 Tue 9/5/17 9 11
11 Meeting between Applicant, City, and CSU to
review project and submittal process
0 days Tue 9/5/17 Tue 9/5/17 10 12
12 Applicant prepares additional information for
City/CSU review
10 days Wed 9/6/17 Tue 9/19/17 11 13
13 2nd review of preliminary plans by City/CSU and
coordination on right-of-way acquisition
40 days Wed 9/20/17 Tue 11/14/17 12 14
14 Approval of preliminary plan by City/CSU 0 days Tue 11/14/17 Tue 11/14/17 13 18,19,15
15 Authorization to proceed with Geotechnical work
on CSU property
0 days Tue 11/14/17 Tue 11/14/17 14 5
16
17 Final Plan Development and Review 201 days Wed 11/15/17 Wed 8/22/18
18 Prepare Site/Utility plans 20 days Wed 11/15/17 Tue 12/12/17 14
19 Prepare Structural plans 18 days Mon 12/18/17 Wed 1/10/18 4,14 20
20 Submit Final Plans to City/CSU 0 days Wed 1/10/18 Wed 1/10/18 19 21
21 Initial FDP Review and City/CSU coordination 40 days Thu 1/11/18 Wed 3/7/18 20 22
22 Applicant revises and resubmits plans 15 days Thu 3/8/18 Wed 3/28/18 21 23
23 2nd FDP Review and City/CSU coordination 40 days Thu 3/29/18 Wed 5/23/18 22 24
24 Finalizing Plans and Development Agreement 30 days Thu 5/24/18 Wed 7/4/18 23 25
25 Recording Mylars and Development Agreement 25 days Thu 7/5/18 Wed 8/8/18 24 26
26 Process Development Construction Permit 10 days Thu 8/9/18 Wed 8/22/18 25 29
27 CSU Board of Governors approve right-of-way
dedication
29
28
29 Turn Lane Construction 45 days Mon 6/3/19 Fri 8/2/19 26,27 To be completed between end of Spring 2019
semester and start of Fall 2019 Semester
30
31 The Standard at Fort Collins
32 Initial FDP Review 21 days Wed 8/9/17 Wed 9/6/17 33FS+9 days
33 2nd FDP Review 15 days Wed 9/20/17 Tue 10/10/17 32FS+9 days 34
34 Finalizing Plans, Plat, and Development Agreement 30 days Wed 10/11/17 Tue 11/21/17 33 35
35 Recording Mylars and Development Agreement 25 days Wed 11/22/17 Tue 12/26/17 34 36
36 Process Development Construction Permit 10 days Wed 12/27/17 Tue 1/9/18 35 37,39
37 Process address assignment request 10 days Wed 1/10/18 Tue 1/23/18 36 38
38 Building Plan Review 80 days Wed 1/24/18 Tue 5/15/18 37
39 Construction Phase 599 days Tue 5/1/18 Fri 8/14/20 36 40
40 Certificate of Occupancy Issued 0 days Fri 8/14/20 Fri 8/14/20 39
2
6/14
9/5
11/14
11/14
1/10
8/14
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2018 2019 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Prospect and Whitcom
Date: Mon 9/18/17