HomeMy WebLinkAboutTRAIL HEAD TRACTS F & G TOWNHOMES - PDP - PDP170035 - SUBMITTAL DOCUMENTS - ROUND 1 - SUPPLEMENTAL INFORMATIONDEVELOPMENT PHASING STATEMENT • The Trail Head Cottage Neighborhood is proposed to be constructed as two separate phases of development and shall include the following: Phase I: Tract G (5.19 Acres) construction is expected to begin at the end of the 2nd quarter of 2018. Phase I shall include the construction of 45 Townhomes, associated private alleys with wet/dry utilities as well as Green Lake Drive curb, gutter, sidewalk, asphalt pavement and all wet/dry utilities from Wagon Trail Road to Greenfields Drive. Phase II: Tract F (5.54 Acres) construction is expected to begin in the 1st quarter of 2020. Phase II shall include the construction of 44 Townhomes, associated private alleys with wet/dry utilities as well as Green Lake Drive curb, gutter, sidewalk, asphalt pavement and all wet/dry utilities from Greenfields Drive to Campfire Drive.