HomeMy WebLinkAboutLINCOLN CORRIDOR HOTEL - PDP - PDP170026 - SUBMITTAL DOCUMENTS - ROUND 1 - GEOTECHNICAL (SOILS) REPORTGEOTECHNICAL SUBSURFACE EXPLORATION REPORT
PROPOSED STAYBRIDGE HOTEL
LOT 1, BALDWIN MINOR SUBDIVISION
301 EAST LINCOLN AVENUE, FORT COLLINS, COLORADO
SOILOGIC # 16-1213
September 21, 2016
Soilogic, Inc.
3050 67th Avenue, Suite 200 • Greeley, CO 80634 • (970) 535-6144
P.O. Box 1121 • Hayden, CO 81639 • (970) 276-2087
September 21, 2016
Willco XIV, LLLP
4836 S. College Avenue, Suite 11
Fort Collins, Colorado 80525
Attn: Mrs. Moira Bright
Re: Geotechnical Subsurface Exploration Report
Proposed Staybridge Hotel – Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue
Fort Collins, Colorado
Soilogic Project # 16-1213
Mrs. Bright:
Soilogic, Inc. (Soilogic) personnel have completed the geotechnical subsurface
exploration you requested for the proposed Staybridge Hotel to be constructed on Lot 1 in
the Baldwin Minor Subdivision and a small portion of the adjacent Lot 1 in the
Woodward Technology Center, located at 301 East Lincoln Avenue in Fort Collins,
Colorado. The results of our subsurface exploration and pertinent geotechnical
engineering recommendations are included with this report.
In general, the subsurface materials encountered in the completed site borings can be
summarized as follows. A thin layer of vegetation and topsoil was encountered at the
surface at the locations of borings B-2, B-4 and B-9. Approximately 2½ inches of
existing asphalt pavement was encountered at the surface at the location of boring B-7.
Dark brown/brown/rust clayey to silty sand containing varying amounts of gravel was
encountered underlying the vegetative soil layer, asphalt pavement or at the surface at the
locations of the remaining site borings. A portion of the near-surface clayey/silty sand
extending to a depth of about 2½ feet below ground surface at the location of boring B-6
was somewhat mottled in color and was identified as probable existing fill material which
may have been placed to develop finish site grade. The clayey/silty sand varied from
loose to medium dense in terms of relative density, exhibited no swell potential at current
moisture and density conditions and extended to depths between approximately 1 and 6
feet below ground surface, where it transitioned to cleaner, brown/rust sand with varying
amounts of silt, gravel and possible cobbles. The sand with silt and gravel varied from
loose to very dense in relative density, would be expected to be non-expansive based on
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
2
the physical properties and engineering characteristics of the material and extended to the
bottom of all borings at a depth of approximately 15 feet below present site grades.
Groundwater was encountered in borings B-1 through B-5 at depths of approximately 11
to 13 feet below ground surface during drilling. When checked immediately after
completion of drilling, groundwater was measured at depths of 12½ and 11 feet below
ground surface in borings B-2 and B-3 respectively. Dry cave-ins were measured at
depths of about 10, 7½ and 6 feet below ground surface in borings B-1, B-4 and B-5
respectively at that time. No groundwater was encountered to the depth explored (10 feet
below ground surface) at the locations of borings B-6 through B-9 at the time of drilling.
Borings B-2, B-3, B-4 and B-9 were left open to allow for a subsequent groundwater
level measurement. The remainder of the site borings were backfilled upon completion.
When checked two (2) days after drilling, groundwater was measured at depths of about
12 and 10 feet below ground surface in borings B-2 and B-3 respectively. Dry cave-ins
were measured at depths of approximately 7 and 6 feet below ground surface in borings
B-4 and B-9 at that time.
Based on the subsurface conditions encountered, results of laboratory testing and type of
construction proposed, it is our opinion the proposed hotel building and associated site
improvements could be constructed with conventional spread footing foundations bearing
on natural, undisturbed clayey/silty sand, sand and gravel and/or removal area excavation
backfill consisting of the site soils (where required).
The site clayey/silty sand and sand and gravel soils would be considered low volume-
change (LVC) potential soils and could be used as fill to develop the site. The
reconditioned near-surface site clayey/silty sand and properly placed and compacted fill
consisting of on-site soils and/or similar import LVC soils could be used for support of
the building floor slabs, exterior flatwork and site pavements. Pavement section design
options for the site drive and parking area pavements are included with this report. Other
opinions and recommendations concerning design criteria and construction details for the
proposed site improvements are also provided.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
3
We appreciate the opportunity to be of service to you on this project. If you have any
questions concerning the enclosed information or if we can provide any further
assistance, please do not hesitate to contact us.
Very Truly Yours,
Soilogic, Inc. Reviewed by:
Darrel DiCarlo, P.E. Wolf von Carlowitz, P.E.
Senior Project Engineer Principal Engineer
44271 36746
GEOTECHNICAL SUBSURFACE EXPLORATION REPORT
PROPOSED STAYBRIDGE HOTEL
LOT 1, BALDWIN MINOR SUBDIVISION
301 EAST LINCOLN AVENUE, FORT COLLINS, COLORADO
SOILOGIC # 16-1213
September 21, 2016
INTRODUCTION
This report contains the results of the completed geotechnical subsurface exploration for
the proposed Staybridge Hotel to be constructed on Lot 1 in the Baldwin Minor
Subdivision and a small portion of the adjacent Lot 1 in the Woodward Technology
Center in Fort Collins, Colorado. The purpose of our exploration was to describe the
subsurface conditions encountered in the completed site borings and develop the test data
necessary to provide recommendations concerning design and construction of the hotel
building, trash enclosure, gazebo, porte-cochere, retaining wall, in-ground pool and high-
mast lighting foundations and support of floor slabs, exterior flatwork and site
pavements. Pavement section design recommendations are also provided. The
conclusions and recommendations outlined in this report are based on results of the
completed field and laboratory testing and our experience with subsurface conditions in
this area.
PROPOSED CONSTRUCTION
We understand the proposed hotel building will be a 3-story wood-frame structure
constructed as slab-on-grade. Foundation loads for the structure are expected to be light
to moderate, with continuous wall loads on the order of 3.5 to 5 kips per lineal foot and
individual column loads on the order of 150 kips or less. Trash enclosure, high-mast
lighting, retaining wall and indoor pool construction are also anticipated. Paved drive
and parking area pavements will be constructed as part of the proposed site
improvements. Traffic loading on site pavements is expected to consist of low volumes
of light passenger vehicles, with occasional trash and delivery truck traffic. Small grade
changes (on the order of 4 feet or less) are anticipated to develop finish site grades in the
building and pavement areas.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
2
SITE DESCRIPTION
The development property includes Lot 1 of the Baldwin Minor Subdivision (an
approximate 4-acre parcel) and a small portion of the adjacent Lot 1 in the Woodward
Technology Center, located at 301 East Lincoln Avenue in south Fort Collins, Colorado.
At the time of our site exploration, the existing Hydro Construction facility occupied the
property. A single-story, wood-frame at-grade office, single-story at-grade brick
shop/garage and other small single-story at-grade outbuildings were present on the site.
Portions of the ground surface across the property were paved with asphalt concrete or
gravel-surfacing, while limited areas contained a sparse to moderate growth of native
grass and weed vegetation. The proposed development area extending onto the adjacent
Lot 1 in the Woodward Technology Center was mostly paved with asphaltic concrete.
Limited areas of this site to the south of the existing parking lot contained a sparse to
moderate growth of native grass and weed vegetation or appeared barren. The site was
observed to be relatively level, with a gentle overall slope downward to the south. The
maximum difference in ground surface elevation across the development site is estimated
to be less than 10 feet based on review of available USGS topographic maps of the area.
The Cache la Poudre River was also noted near the southern property boundary.
SITE EXPLORATION
Field Exploration
To develop site specific subsurface information, a total of nine (9) soil borings were
completed across the site. Five (5) borings were drilled in the area of the proposed hotel
building to a depth of approximately 15 feet below present site grades. Four (4) borings
were drilled in areas of proposed drive lanes/parking areas to a depth of approximately 10
feet below present site grades. The boring locations were established in the field by
Soilogic personnel based on a concept plan provided by the client dated June 7, 2016,
using a mechanical surveyor’s wheel and estimating angles from identifiable site
references. The boring locations should be considered accurate only to the degree
implied by the methods used to make the field measurements. A diagram indicating the
approximate boring locations is included with this report. Graphic logs of each of the
auger borings are also included.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
3
The test holes were advanced using 4-inch diameter continuous flight auger powered by a
truck-mounted CME-45 drill rig. Samples of the subsurface materials were obtained at
regular intervals using California barrel and split-spoon sampling procedures in general
accordance with ASTM specification D-1586. As part of the D-1586 sampling
procedure, the standard sampling barrels are driven into the substrata using a 140-pound
hammer falling a distance of 30 inches. The number of blows required to advance the
samplers a distance of 12 inches is recorded and helpful in estimating the consistency,
relative density of the soils encountered. In the California barrel sampling procedure,
lesser disturbed samples are obtained in removable brass liners. Samples of the
subsurface materials obtained in the field were sealed and returned to the laboratory for
further evaluation, classification and testing.
Laboratory Testing
The samples collected were tested in the laboratory to measure natural moisture content
and were visually and/or manually classified in accordance with the Unified Soil
Classification System (USCS). The USCS group symbols are indicated on the attached
boring logs. An outline of the USCS classification system is included with this report.
As part of the laboratory testing, a calibrated hand penetrometer (CHP) was used to
estimate the unconfined compressive strength of essentially-cohesive specimens. The
CHP also provides a more reliable estimate of soil consistency than tactual observation
alone. Dry density, Atterberg limits, -200 wash and swell/consolidation tests were
completed on selected samples to help establish specific soil characteristics. Atterberg
limits tests are used to determine soil plasticity. The percent passing the #200 size sieve
(-200 wash test) is used to determine the percentage of fine-grained materials (clay and
silt) in a sample. Swell/consolidation tests are performed to evaluate soil volume change
potential with variation in moisture content. The results of the completed laboratory tests
are outlined on the attached boring logs and swell/consolidation test summaries. Water
Soluble Sulfates (WSS) tests were also completed on two (2) selected soil samples to
evaluate corrosive soil characteristics with respect to buried concrete and results
discussed subsequently in this report.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
4
SUBSURFACE CONDITIONS
The subsurface materials encountered in the completed site borings can be summarized as
follows. A thin layer of vegetation and topsoil was encountered at the surface at the
locations of borings B-2, B-4 and B-9. Approximately 2½ inches of existing asphalt
pavement was encountered at the surface at the location of boring B-7. Dark
brown/brown/rust clayey to silty sand containing varying amounts of gravel was
encountered underlying the vegetative soil layer, asphalt pavement or at the surface at the
locations of the remaining site borings. A portion of the near-surface clayey/silty sand
extending to a depth of about 2 ½ feet below ground surface at the location of boring B-6
was somewhat mottled in color and was identified as probable existing fill material which
may have been placed to develop finish site grade. The clayey/silty sand varied from
loose to medium dense in terms of relative density, exhibited no swell potential at current
moisture and density conditions and extended to depths between approximately 1 and 6
feet below ground surface, where it transitioned to cleaner, brown/rust sand with varying
amounts of silt, gravel and possible cobbles. The sand with silt and gravel varied from
loose to very dense in relative density, would be expected to be non-expansive based on
the physical properties and engineering characteristics of the material and extended to the
bottom of all borings at a depth of approximately 15 feet below present site grades.
The stratigraphy indicated on the included boring logs represents the approximate
location of changes in soil and bedrock types. Actual changes may be more gradual than
those indicated.
Groundwater was encountered in borings B-1 through B-5 at depths of approximately 11
to 13 feet below ground surface during drilling. When checked immediately after
completion of drilling, groundwater was measured at depths of 12½ and 11 feet below
ground surface in borings B-2 and B-3 respectively. Dry cave-ins were measured at
depths of about 10, 7½ and 6 feet below ground surface in borings B-1, B-4 and B-5
respectively at that time. No groundwater was encountered to the depth explored (10 feet
below ground surface) at the locations of borings B-6 through B-9 at the time of drilling.
Borings B-2, B-3, B-4 and B-9 were left open to allow for a subsequent groundwater
level measurement. The remainder of the site borings were backfilled upon completion.
When checked two (2) days after drilling, groundwater was measured at depths of about
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
5
12 and 10 feet below ground surface in borings B-2 and B-3 respectively. Dry cave-ins
were measured at depths of approximately 7 and 6 feet below ground surface in borings
B-4 and B-9 at that time.
Groundwater levels will vary seasonally and over time based on weather conditions, site
development, irrigation practices and other hydrologic conditions. Perched and/or
trapped groundwater conditions may also be encountered at times throughout the year.
Perched water is commonly encountered in soils overlying less permeable soil layers
and/or bedrock. The location and amount of perched/trapped water can also vary over
time.
ANALYSIS AND RECOMMENDATIONS
Demolition and Site Development
We understand the existing office, shop/garage, outbuildings and other associated site
improvements will be razed prior to construction of the hotel building. Within the new
structure, exterior flatwork and pavement areas, all existing foundations, floor slabs/
flatwork, pavements and other site improvements should be completely removed. Care
will be needed to ensure all in-place fill/backfill materials associated with the existing
site improvements are also completely removed at this time. In addition, all tree root
systems and dry and desiccated soils associated with the tree root systems should be
completely removed from within the area of the proposed hotel building and beneath
exterior flatwork and site pavements. The depth and extent of required removal can best
be established at the time of excavation through openhole observation. If/where required,
the excavated/removed materials should be replaced as controlled and compacted fill as
outlined below.
After stripping and completing all cuts and existing fill/backfill removal procedures and
prior to placement of any new fill/backfill or flatwork concrete, we recommend the
exposed subgrade soils be scarified to a depth of 9 inches, adjusted in moisture content
and compacted to at least 95% of the materials standard Proctor maximum dry density.
The moisture content of the scarified soils should be adjusted to be within the range of
±2% of standard Proctor optimum moisture content at the time of compaction. If some
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
6
backfilling of existing structure removal excavations is required to develop foundation
bearing and/or finish floor slab subgrade elevations, we recommend the excavation be
continuously benched during backfilling in order to reduce the potential for development
of a shear plane between the natural site soils and controlled backfill.
Fill and removal area backfill soils required to develop the site should consist of
approved, low-volume-change (LVC) soils free from organic matter, debris and other
objectionable materials. Based on results of the completed laboratory testing, it is our
opinion existing fill (if any) and natural site clayey/silty sand and sand and gravel could
be used as fill and backfill provided the proper moisture content is developed in those
materials at the time of placement and compaction. Cobble-sized materials (greater than
3 inches in any dimension) should not be used as fill within 12 inches of finish floor slab,
exterior flatwork and pavement subgrade elevations to reduce the potential for point-
loading. If required, imported soils could consist of approved essentially-granular
structural fill soils free from organic matter, debris and other objectionable materials.
Import structural fill consistent with Colorado Department of Transportation (CDOT)
Class 6 or 7 Aggregate Base Course specifications could be considered and would be
suitable for use as engineered fill below foundations. Suitable fill and backfill soils
should be placed in loose lifts not to exceed 9 inches thick, adjusted in moisture content
and compacted as recommended for the scarified soils above.
Care should be taken to avoid disturbing all subgrade soils prior to placement of any
overlying improvements. Soils which are allowed to dry out or become wet and softened
or disturbed by the construction activities should be removed and replaced or reworked in
place prior to concrete placement.
Hotel Building Foundations
Based on the subsurface conditions encountered, results of laboratory testing and type of
construction proposed, it is our opinion the proposed hotel building and associated site
improvements (including the lightly-loaded detached trash enclosure) could be
constructed with conventional spread footing foundations bearing on natural, undisturbed
clayey/silty sand, sand and gravel and/or removal area excavation backfill consisting of
the onsite soils (where required). For design of continuous spread footing and isolated
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
7
column pad foundations bearing on loose to dense clayey/silty sand, sand and gravel
and/or properly placed and compacted removal area backfill, we recommend using a
maximum net allowable soil bearing pressure of 1,500 psf.
For design of footing foundations and foundation walls to resist lateral movement, a
passive equivalent fluid pressure value of 350 pcf could be used for the site clayey/silty
sand, sand and gravel or similar soils. A coefficient of friction of 0.45 could be used
between floor slab concrete and the bearing/subgrade soils to resist sliding. The
recommended passive equivalent fluid pressure value and coefficients of friction do not
include a factor of safety.
Exterior footings should bear a minimum of 30 inches below finished adjacent exterior
grade to provide frost protection. We recommend formed strip footings have a minimum
width of 12 inches and isolated pad foundations have a minimum width of 24 inches in
order to facilitate construction and reduce the potential for development of eccentrically
loaded footings. Actual footing widths should be designed by a structural engineer.
We estimate settlement of footing foundations designed and constructed as outlined
above and resulting from the assumed structural loads would be on the order of 1 inch.
Differential settlement could approach the amount of total settlement estimated above.
Gazebo & High-mast Light Standard Foundations
We anticipate the gazebo and high-mast light standards planned as part of site
development will be constructed using shallow drilled shaft foundations. For design of
shallow drilled shaft foundations bearing on loose to dense site clayey/silty sand and/or
sand and gravel, we recommend using a maximum net allowable soil bearing pressure of
1,500 psf. Additional pier capacity can be developed by accounting for friction capacity
between the drilled pier and surrounding clayey/silty sand and sand and gravel stratum.
An allowable skin friction value of 150 psf could be used for that portion of the pier
concrete in contact with the site sand soils below frost depth. Skin friction should be
neglected within the top 30 inches of depth below finish grade due to the potential for
frost action.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
8
Drilled shaft foundations shall bear a minimum of 30 inches below finished adjacent
exterior grade to provide frost protection. For design of the foundation systems to resist
overturning, a passive equivalent fluid pressure of 350 pcf could be used for that portion
of the foundation system extended below frost depth. The top 30 inches of soil could be
considered a surcharge load but should not be used in passive resistance calculations. A
coefficient of friction of 0.45 could be used between foundation concrete and sand and
gravel bearing soils to resist sliding. The recommended passive equivalent fluid pressure
value and coefficient of friction do not include a factor of safety. For design of uplift
resistance, an in-place soil unit weight of 120 pcf and angle of internal friction value of
30° could be used. Typically, light-pole base foundations are constructed with a
minimum embedment length on the order of seven (7) feet below grade in accordance
with current building code.
We expect the pier excavations could be completed using conventional augering
techniques. Based on the presence of essentially-granular subgrade soils, pier
excavations extended more than about 5 to 6 feet below ground surface would not be
expected to remain stable for short periods during construction such that temporary
casing of the drilled shafts or mudded (bentonite slurry) construction procedures may be
required. The presence of cobble-sized materials encountered at some locations within
the sand and gravel strata may also present difficulty during drilling. Pier concrete
should have a slump in the range of 5 to 7 inches and be placed in the pier holes
immediately after the completion of drilling, cleaning and placement of reinforcing steel.
We estimate settlement of gazebo and light-pole standard foundations designed and
constructed as outlined above and resulting from the assumed structural loads would be
less than 1 inch. If water from any source is allowed to infiltrate the foundation soils,
additional movement of the foundations could occur.
Foundation Backfill
Backfill placed adjacent to foundation walls should consist of approved LVC soils free
from organic matter, debris and other objectionable materials. Based on results of the
completed field and laboratory testing, it is our opinion the existing fill and native site
clayey/silty sand and sand and gravel could be used as backfill in this area provided care
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
9
is taken to develop the proper moisture content in those materials at the time of
placement and compaction. Cobble-sized materials should be screened and removed
prior to use as foundation wall backfill. We recommend the existing fill, natural site
clayey/silty sand and sand and gravel or similar soils be placed in loose lifts not to exceed
9 inches thick, adjusted in moisture and compacted as previously outlined in the
“Demolition and Site Development” section of this report.
Excessive lateral stresses can be imposed on un-braced foundation walls when using
heavier mechanical compaction equipment. We recommend compaction of unbalanced
foundation wall backfill soils be completed using light mechanical or hand compaction
equipment.
Seismicity
Based on our review of the International Building Code (2003), a soil profile type D
could be used for the site strata. Based on our review of United States Geologic Survey
(USGS) mapped information, design spectral response acceleration values of SDS = .282
(28.2%) and SD1 = .119 (11.9%) could be used.
Floor Slabs and Exterior Flatwork
The building floor slab and exterior flatwork could be supported on reconditioned natural
site soils or properly placed and compacted fill and/or removal area backfill developed as
outlined in the “Demolition and Site Development” section of this report. Care should be
taken to avoid placing floor slab concrete directly on cobble-sized materials in order to
reduce the potential for development of point loads on the slabs. A modulus of subgrade
reaction (k) value of 250 pci could be used for design of floor slabs supported on
reconditioned natural site clayey/silty sand and sand and gravel soils or similar
essentially-granular import LVC fill materials. Disturbed subgrades or subgrade soils
that have been allowed to dry out or become wet and softened should be removed and
replaced or reconditioned in place prior to floor slab and exterior flatwork construction.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
10
Floor slabs should designed and constructed as floating slabs, separated from foundation
walls, columns and plumbing and mechanical penetrations by the use of block outs or
appropriate isolation material. Additionally, we recommend all partition walls supported
above slabs-on-grade be constructed as floating walls to help reduce the potential for
differential slab-to-foundation movement causing distress in upper sections of the
structure. A minimum one and one-half (1½) inch void space is recommended beneath
all floating walls. Special attention to door and stair framing, drywall installation and
trim carpentry should be taken to isolate those elements from the floor slabs, allowing for
some differential floor slab-to-foundation movement to occur without transmitting
stresses to the overlying structure.
Depending on the type of floor covering and floor covering adhesive used in finished
slab-on-ground areas, a vapor barrier may be required immediately beneath the floor
slabs to maintain flooring product manufacturer warranties. A vapor barrier would help
reduce the transmission of moisture through floor slabs. However, the unilateral moisture
release caused by placing concrete on an impermeable surface can increase slab curl.
The amount of slab curl can be reduced by careful selection of an appropriate concrete
mix and proper placement and curing procedures. Slab curl cannot be eliminated.
Soilogic recommends the owner, architect and flooring contractor consider the
performance of the slab in conjunction with the proposed flooring products to help
determine if a vapor barrier will be required and where best to position the vapor barrier
in relation to the floor slab. Additional guidance and recommendations concerning slab-
on-grade design can be found in American Concrete Institute (ACI) section 302.
Exterior flatwork will experience some movement subsequent to construction as the
subgrade soils increase in moisture content. Based on results of the completed field and
laboratory testing, we expect the amount of movement of exterior flatwork supported on
reconditioned natural site soils and/or properly placed and compacted fill would be
limited. Care should be taken to ensure that when exterior flatwork moves, positive
drainage will be maintained away from the structure.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
11
Retaining Walls
We understand concrete retaining walls may also be constructed as part of the site
development. For design of retaining wall footing foundations bearing on natural,
undisturbed loose to medium dense clayey/silty sand and sand and gravel with no to low
swell potential, we recommend using a maximum net allowable soil bearing pressure of
1,500 psf. The retaining wall footing foundation should bear a minimum of 30 inches
below grade at the front (unretained earth) side of the wall to provide frost protection.
We estimate settlement of the retaining wall footing foundation resulting from the
assumed structural loads would be less than 1 inch. Differential settlement along the
length of the wall could approach the amount of total settlement estimated above.
Care should be taken to prevent the development of unbalanced hydrostatic loads on site
retaining walls. A drainage blanket consisting of 12 inches of free-draining rock placed
behind the wall and extending the full height of the wall from approximate grade at the
front of the wall to approximately 12 to 18 inches below finish grade on the retained soil
side of the wall should be constructed. We recommend ¾-inch or larger washed rock be
used to construct the drainage blanket. The top 12 to 18 inches of retaining wall backfill
should consist of an essentially-cohesive soil to reduce the potential for immediate
surface water infiltration into the wall backfill. The near-surface site clayey sand would
be suitable for use in this area. A filter fabric should be employed between all free-
draining aggregate and adjacent soil interfaces to reduce the potential for the migration of
finer-grained soils into the gap-graded rock.
Weep holes or other approved methods should be employed to help transfer any collected
water to the front of the wall. A water collection system, similar to a perimeter drain
system could also be considered. A typical collection drain system would consist of 4-
inch diameter rigid perforated pipe surrounded by a minimum of 6 inches of the free-
draining aggregate and placed at the base of the retained soils side of the wall. The invert
of the drain pipe at the high point of the system should be placed at approximate front-of-
wall grade and sloped a minimum of ⅛-inch per foot to facilitate efficient water removal
to an appropriate outfall. Flap gates or other approved methods should be employed at all
free outfalls to reduce the potential for animal access and reverse flow in the system.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
12
Retaining wall backfill should consist of approved low-volume-change (LVC) and
essentially-granular materials free from organic matter and debris. Essentially-granular
soils offer better stacking characteristics and are less prone to movements associated with
freezing through the face of the walls than finer-grained materials. Materials consistent
with Colorado Department of Transportation (CDOT) Class 6 or 7 aggregate base course
or Class I structure backfill could be used as retaining wall backfill. Cobble-sized
materials should not be used as retaining wall backfill. Retaining wall backfill should be
placed in loose lifts not to exceed 9 inches thick, adjusted in moisture content and
compacted to at least 95% of the materials standard Proctor maximum dry density. The
moisture content of the backfill soils should be adjusted to within ±2% of standard
Proctor optimum moisture content at the time of compaction.
Excessive lateral stresses can be imposed on retaining walls during backfilling when
using heavier mechanical compaction equipment. We recommend compaction of
retaining wall backfill be completed using light mechanical or hand compaction
equipment.
For design of retaining walls protected from hydrostatic loading and backfilled with
select granular fill, we recommend using an angle of internal friction of Φ=30° and active
equivalent fluid pressure value of 40 pounds per cubic foot in addition to any surcharge
loads. The equivalent fluid pressure value outlined above is based on an active stress
distribution analysis in which some rotation of the retaining wall is assumed. The angle
of internal friction and equivalent fluid pressure values outlined above do not include a
factor of safety. Sloped backfill geometry, surcharge loads on the retained soil side of the
walls or point loads developed in the wall backfill can add to the lateral forces on
retaining walls. If parking areas are anticipated at the top of site retaining walls, we
recommend the walls be designed to include surcharge loads from parked vehicles in
these areas.
The lateral driving forces on the walls will be resisted through a combination of the
sliding friction of the footing foundations and passive earth pressure against the
embedded portion of the wall below frost depth. A passive equivalent fluid pressure
value of 350 pcf could be used for that portion of the wall extended below frost depth,
considered to be 30 inches in this area. A coefficient of friction of 0.45 could be used
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
13
between foundation concrete and the bearing soils to resist sliding. The recommended
passive equivalent fluid pressure value and coefficient of friction do not include a factor
of safety.
Indoor Pool
We understand an indoor, in-ground pool will be constructed extending to a maximum
depth in the range of approximately 5 to 6 feet below present site grades. Based on the
materials encountered in the completed site borings and results of laboratory testing, it is
our opinion the lightly-loaded swimming pool could be supported on natural, undisturbed
clayey/silty sand and sand and gravel. For design of the pool foundation bearing on
natural, undisturbed loose to medium dense clayey/silty sand and sand and gravel, we
recommend using a maximum net allowable soil bearing pressure of 1,500 psf.
Care should be taken to avoid developing unbalanced hydrostatic loads on the pool walls
and pool bottom. Pressure relief valves could be considered to avoid developing uplift
and excessive horizontal hydrostatic loads. For design of the below-grade pool walls
protected from unilateral hydrostatic loading, we recommend using an active equivalent
fluid pressure value of 40 pounds per cubic foot. Some rotation of the pool walls must
occur to develop the active earth pressure state. That rotation can result in cracking of
the walls typically in between corners and other restrained points. The amount of
deflection of the top of the wall required to develop the “active” state can be estimated at
0.5% times the height of the wall. An equivalent fluid pressure value of 60 pounds per
cubic foot could be used for restrained conditions.
Variables that affect active lateral earth pressures include but are not limited to the swell
potential of the backfill soils, backfill compaction and geometry, wetting of the backfill
soils, surcharge loads and point loads developed in the backfill materials. The
recommended equivalent fluid pressure values do not include a factor of safety or an
allowance for hydrostatic loading. Use of expansive soil backfill, excessive compaction
of the wall backfill or surcharge loads placed adjacent to the pool walls can add to the
lateral earth pressures causing the equivalent fluid pressure values used in design to be
exceeded.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
14
If backfill is required adjacent to any below-grade pool walls, we recommend those
materials consist of approved low-volume change (LVC) soils free from organic matter,
debris and other objectionable materials. We understand pea gravel is typically used as
pool wall backfill due to the limited area that backfill will extend and inability to access
these areas with compaction equipment. If site clayey/silty sand and sand and gravel
soils will be used as backfill adjacent to the pool and access with compaction equipment
is possible, backfill soils should be placed in loose lifts not to exceed 9 inches thick,
adjusted to in moisture and compacted as outlined in the “Demolition and Site
Development” section of this report. Cobble-sized materials should not be used as
backfill adjacent to pool walls.
Excessive lateral stresses can be imposed on below grade walls when using heavier
mechanical compaction equipment. We recommend compaction of unbalanced pool wall
backfill soils be completed using light mechanical or hand compaction equipment.
The essentially-granular site clayey/silty sand and sand and gravel soils would be
particularly susceptible to caving and sloughing, therefore excavation of vertical pool
walls may be difficult or impossible. In addition, loose clayey/silty sand and sand and
gravel soils were encountered near-surface in the completed site borings and may be
encountered in the pool excavation. The site soils would be expected to be loose near-
surface and could be easily disturbed by the construction activities. Care should be taken
at the time of construction to avoid disturbing the foundation bearing subgrade soils and
the need for corrective action. Materials which are loosened or disturbed by the
construction activities or materials which become dry and desiccated or wet and softened
should be removed and replaced or reworked in place prior to placement of pool
concrete. We estimate the long-term total and differential settlement of the pool
constructed as outlined above would be less than 1 inch.
Pavements
Pavement subgrades should be develop as outlined in the “Demolition and Site
Development” portion of this report. Care should be taken to avoid disturbing the
reconditioned subgrade soils prior to placement of site pavements and exterior flatwork.
In addition, efforts to maintain the proper moisture content in the subgrade soils should
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
15
be made. If subgrade soils are disturbed or allowed to dry out or become elevated in
moisture content, those materials should be reworked in place or removed and replaced
prior to paving or concrete placement.
We anticipate the site drive and parking areas will be surfaced with asphaltic concrete
and/or Portland cement concrete (PCC). The pavement subgrades are expected to consist
of reconditioned clayey/silty sand and sand and gravel. The clayey/silty sand and sand
and gravel soils classify as A-2-4 and A-4 soils in accordance with the American
Association of State and Highway Transportation Officials (AASHTO) classification
system and would be subject to moderate remolded shear strength. A resistance value
(R-value) of 20 was estimated for the clayey/silty sand subgrade soils and used in the
pavement section design. Traffic loading on the site pavements is expected to consist of
areas of low volumes of automobiles and light trucks, as well as areas receiving heavier
trash and delivery truck traffic. Equivalent 18-kip single axle loads (ESAL’s) were
estimated for the quantity of site traffic anticipated. Two (2) general pavement design
categories are outlined below in Table I. Standard duty pavements could be considered
in automobile drive and parking areas. Heavy duty pavements should be considered for
access drives and other areas of the site expected to receive heavy trash and delivery
truck traffic. Thicker pavements sections may be appropriate in some areas. We would
be happy to complete a pavement section design based on the actual type and quantity of
heavy truck traffic anticipated to utilize site pavements.
Proofrolling of the pavement subgrades should be completed to help identify unstable
areas. Areas which pump or deform excessively should be stabilized prior to surfacing.
Depending on the in-place moisture content of the subgrade soils immediately prior to
paving, the time of year when construction occurs and other hydrologic conditions,
stabilization of the subgrade soils may become necessary to develop a suitable paving
platform. Isolated areas of subgrade instability can be mended on a case-by-case basis.
If overall instability of the subgrade soils is observed at the time of proofrolling, chemical
stabilization of the subgrade soils could be considered to develop a suitable paving
platform. If required, we recommend consideration be given to stabilization of the
pavement subgrades with Class C fly ash. With the increase in support strength
developed by the fly ash stabilization procedures, it is our opinion some credit for the
stabilized zone could be included in the pavement section design, reducing the required
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
16
thickness of overlying asphaltic concrete and aggregate base course. Chemical
stabilization can also eliminate some of the uncertainty associated with attempting to
pave during periods of inclement weather. Pavement section design options
incorporating some structural credit for the chemically-stabilized subgrade soils are
outlined below in Table 1.
TABLE 1 – PAVEMENT SECTION DESIGN
Standard Duty Heavy Duty
Option A – Composite
Asphaltic Concrete (Grading S or SX)
Aggregate Base (Class 5 or 6)
4”
6”
5”
8”
Option B – Composite on Stabilized Subgrade
Asphaltic Concrete (Grading S or SX)
Aggregate Base (Class 5 or 6)
Fly Ash Stabilized Subgrade
3”
4”
12”
4”
6”
12”
Option C - Portland Cement Concrete Pavement
PCCP
5”
6”
Asphaltic concrete should consist of a bituminous plant mix composed of a mixture of
aggregate, filler, binders and additives (if required) meeting the design requirements of
the City of Fort Collins. Aggregate used in the asphaltic concrete should meet specific
gradation requirements such as Colorado Department of Transportation (CDOT) grading
S (¾-inch minus) or SX (½-inch minus) specifications. Hot mix asphalt designed using
“Superpave” criteria should be compacted to within 92 to 96% of the materials Maximum
Theoretical Density. Aggregate base should be consistent with CDOT requirements for
Class 5 or Class 6 aggregate base, placed in loose lifts not to exceed 9 inches thick and
compacted to at least 95% of the materials standard Proctor maximum dry density.
If chemical stabilization procedures will be completed, we recommend the addition of
12% Class ‘C’ fly ash based on component dry unit weights. A 12-inch thick stabilized
zone should be constructed by thoroughly blending the fly ash with the in-place subgrade
soils. Some “fluffing” of the finish subgrade level should be expected with the
stabilization procedures. The blended materials should be adjusted in moisture content to
within the range of ±2% of standard Proctor optimum moisture content and compacted to
at least 95% of the material’s standard Proctor maximum dry density within two (2) hours
of fly ash addition.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
17
For areas subjected to truck turning movements and/or concentrated and repetitive
loading such as dumpster or truck parking and loading areas, we recommend
consideration be given to the use of Portland cement concrete pavement with a minimum
thickness of 6 inches. The concrete used for site pavements should be air entrained and
have a minimum 28-day compressive strength of 4,200 psi. Woven wire mesh or fiber
entrained concrete should be considered to help in the control of shrinkage cracking.
Areas of the site expected to receive higher volumes of heavy truck traffic may require
thicker pavement sections. We would be happy to complete a pavement section design
based on the actual type and quantity of heavy truck traffic anticipated.
The proposed pavement section designs do not include an allowance for excessive
loading conditions imposed by heavy construction vehicles or equipment. Heavily
loaded concrete or other building material trucks and construction equipment can cause
some localized distress to site pavements. The recommended pavement sections are
minimums and periodic maintenance efforts should be expected. A preventative
maintenance program can help increase the service life of site pavements.
Corrosive Soil Characteristics
We measured the soluble sulfate concentration of two (2) representative samples of the
subsoils which will likely be in contact with structural concrete. The sulfate
concentrations measured in the samples fell within the range of 0 to 150 parts per million.
ACI rates the measured concentrations as being a ‘negligible’ to risk of concrete sulfate
attack; therefore Type I cement should be suitable for concrete members on and below
grade. As an added precaution, Type I/II Portland cement could be considered for
additional sulfate resistance of construction concrete. Foundation concrete should be
designed in accordance with the provisions of the ACI Design Manual, Section 318,
Chapter 4.
Drainage
Positive drainage is imperative for satisfactory long-term performance of the proposed
building, trash enclosure, gazebo and other associated site improvements. We
recommend positive drainage be developed away from the structures during construction
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
18
and maintained throughout the life of the site improvements, with twelve (12) inches of
fall in the first 10 feet away from the buildings, where possible. Shallower slopes could
be considered in hardscape areas. In the event that some settlement of the building
backfill soils occurs and/or poor or negative drainage develops over time, the original
grade and associated positive drainage outlined above should be immediately restored.
Care should be taken in the planning of landscaping to avoid features which could result
in the fluctuation of the moisture content of the foundation bearing and flatwork and
pavement subgrade soils. We recommend watering systems be placed a minimum of 5
feet away from the perimeter of the site structure and be designed to discharge away from
all site improvements. Gutter systems should be considered to help reduce the potential
for water ponding adjacent to the structures, with the gutter downspouts, roof drains or
scuppers extended to discharge a minimum of 5 feet away from structural, flatwork and
pavement elements. Water which is allowed to pond adjacent to site improvements can
result in unsatisfactory performance of those improvements over time.
LIMITATIONS
This report was prepared based upon the data obtained from the completed site
exploration, laboratory testing, engineering analysis and any other information discussed.
The completed borings provide an indication of subsurface conditions at the boring
locations only. Variations in subsurface conditions can occur in relatively short distances
away from the borings. This report does not reflect any variations which may occur
across the site or away from the borings. If variations in the subsurface conditions
anticipated become evident, the geotechnical engineer should be notified immediately so
that further evaluation and supplemental recommendations can be provided.
The scope of services for this project does not include either specifically or by
implication any biological or environmental assessment of the site or identification or
prevention of pollutants or hazardous materials or conditions. Other studies should be
completed if concerns over the potential of such contamination or pollution exist.
Geotechnical Subsurface Exploration Report
Staybridge Hotel - Lot 1, Baldwin Minor Subdivision
301 East Lincoln Avenue, Fort Collins, Colorado
Soilogic # 16-1213
19
The geotechnical engineer should be retained to review the plans and specifications so
that comments can be made regarding the interpretation and implementation of our
geotechnical recommendations in the design and specifications. The geotechnical
engineer should also be retained to provide testing and observation services during
construction to help determine that the design requirements are fulfilled.
This report has been prepared for the exclusive use of our client for specific application
to the project discussed and has been prepared in accordance with the generally accepted
standard of care for the profession. No warranties express or implied, are made. The
conclusions and recommendations contained in this report should not be considered valid
in the event that any changes in the nature, design or location of the project as outlined in
this report are planned, unless those changes are reviewed and the conclusions of this
report modified and verified in writing by the geotechnical engineer.
LOG OF BORING B-1
1/1 CME-45
4" CFA
Automatic
BMc/ZG
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
-
SC CLAYEY SAND 1
dark brown, rust -
medium dense 2
-
3 CS 15 0.9 112.0 N/A - - NL NP 8.3%
-
4
-
5 CS 31 1.2 110.9 N/A - - - - -
-
6
-
7
-
SM SAND with varying amouts 8
SP-SM of SILT and GRAVEL -
brown, rust 9
medium dense to very dense -
10 SS 50/11" 1.6 - N/A - - - - -
-
11
-
12
-
13
-
14
-
15 SS 50/7" 11.6 - N/A - - - - -
-
BOTTOM OF BORING @ 15.5' 16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
STAYBRIDGE HOTEL
Atterberg Limits
LOG OF BORING B-2
1/1 CME-45
4" CFA
Automatic
BMc/ZG
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
0 - 4" VEGETATION & TOPSOIL -
1
-
2
-
SC-SM CLAYEY to SILTY SAND 3
dark brown, brown, rust -
loose 4
-
5 CS 9 18.0 102.8 N/A None <500 NL NP 54.6%
-
6
-
7
-
8
-
9
-
SM SAND with varying amouts 10 CS 50/9" 2.4 111.9 N/A - - - - -
SP-SM of SILT and GRAVEL -
brown, rust 11
medium dense to dense -
12
-
13
-
14
-
15 CS 24 8.1 95.8 N/A - - - - -
BOTTOM OF BORING @ 15.0' -
16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
LOG OF BORING B-3
1/1 CME-45
4" CFA
Automatic
BMc/ZG
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
-
SC CLAYEY SAND with GRAVEL 1
dark brown, rust -
2
-
3
-
4
-
5 CS 9 20.7 108.1 N/A None <500 - - -
-
6
-
7
-
8
SM SAND with varying amouts -
SP-SM of SILT and GRAVEL 9
dark brown, brown, rust -
loose to medium dense 10 SS 10 3.3 - N/A - - - - -
-
11
-
12
-
13
-
14
-
15 SS 19 8.1 - N/A - - - - -
-
BOTTOM OF BORING @ 15.5' 16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
LOG OF BORING B-4
1/1 CME-45
4" CFA
Automatic
BMc/ZG
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
0 - 4" VEGETATION & TOPSOIL -
1
-
2
-
3 CS 45 1.6 = N/A - - - - -
-
4
-
5 SS 50/11" 2.4 = N/A - - NL NP 11.1%
-
6
-
SM SAND with varying amouts 7
SP-SM of SILT and GRAVEL -
brown, rust 8
medium dense to very dense -
9
-
10 SS 31 2.5 - N/A - - - - -
-
11
-
12
-
13
-
14
-
15 SS 34 7.8 - N/A - - - - -
-
BOTTOM OF BORING @ 15.5' 16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
LOG OF BORING B-5
1/1 CME-45
4" CFA
Automatic
BMc/ZG
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
SC CLAYEY SAND with GRAVEL -
dark brown, brown, rust 1
-
2
-
3 CS 24 0.8 128.9 N/A - - - - -
-
4
-
5 SS 39 1.3 - N/A - - - - 8.8%
-
6
-
SM SAND with varying amouts 7
SP-SM of SILT, GRAVEL and COBBLES -
brown, rust 8
medium dense to very dense -
9
-
10 SS 27 2.6 - N/A - - - - -
-
11
-
12
-
13
-
14
-
15 SS 50/10" 9.5 - N/A - - - - -
-
BOTTOM OF BORING @ 15.5' 16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
LOG OF BORING B-6
1/1 CME-45
4" CFA
Automatic
BMc/ZG
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
PROBABLE EXISTING FILL MATERIAL; -
SC-SM SILTY to CLAYEY SAND with GRAVEL 1
brown, rust -
loose 2
-
SC CLAYEY SAND 3 CS 8 13.9 106.6 N/A None <500 NL NP 46.4%
dark brown, brown -
loose 4
-
5 CS 29 0.9 - N/A - - - - -
-
6
SM SAND with varying amouts -
SP-SM of SILT and GRAVEL 7
brown, rust -
medium dense 8
-
9
-
10 SS 13 2.2 - N/A - - - - -
-
BOTTOM OF BORING @ 10.5' 11
-
12
-
13
-
14
-
15
-
16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
LOG OF BORING B-7
1/1 CME-45
4" CFA
Automatic
BMc/ZG
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
2.5" ASPHALT PAVEMENT -
1
-
2
SC CLAYEY SAND with GRAVEL -
brown, rust 3 CS 25 5.6 106.1 N/A None <500 - - -
medium dense -
4
-
5 CS 27 6.4 107.8 N/A None <500 NL NP 32.8%
-
6
-
SM SAND with varying amouts 7
SP-SM of SILT and GRAVEL -
brown, rust 8
very dense -
9
-
10 SS 50/11" 1.6 - N/A - - - - -
-
BOTTOM OF BORING @ 10.5' 11
-
12
-
13
-
14
-
15
-
16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
LOG OF BORING B-8
1/1 CME-45
4" CFA
Automatic
BMc/ZG
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
CLAYEY SAND with GRAVEL -
dark brown, brown 1
-
2
-
3 CS 11 1.9 - N/A - - - - -
-
4
-
5 CS 20 0.5 103.9 N/A - - - - -
SM SAND with varying amouts -
SP-SM of SILT and GRAVEL 6
brown, rust -
loose to medium dense 7
-
8
-
9
-
10 SS 23 1.3 - N/A - - - - -
-
BOTTOM OF BORING @ 10.5' 11
-
12
-
13
-
14
-
15
-
16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
LOG OF BORING B-9
1/1 CME-45
4" CFA
Automatic
BMc/ZG
Estimated Swell % Passing
SOIL DESCRIPTION Depth "N" MC DD qu % Swell @ Pressure # 200 Sieve
(ft) (%) (pcf) (psf) 500 psf (psf) LL PI (%)
0 - 4" VEGETATION & TOPSOIL -
SC CLAYEY SAND with GRAVEL 1
-
2
-
3 CS 29 0.8 - N/A - - - - -
-
4
-
5 CS 37 0.6 121.7 N/A - - - - -
SM SAND with varying amouts -
SP-SM of SILT and GRAVEL 6
brown, rust -
medium dense 7
-
8
-
9
-
10 SS 18 2.8 - N/A - - - - -
-
BOTTOM OF BORING @ 10.5' 11
-
12
-
13
-
14
-
15
-
16
-
17
-
18
-
19
-
20
-
21
-
22
-
23
-
24
-
25
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
Liquid Limit NL
Plasticity Index NP
% Passing #200 54.6%
Dry Density (pcf) 102.8
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
Project # 16-1213
September 2016
SWELL/CONSOLIDATION TEST SUMMARY
Sample ID: B-2 @ 4'
Sample Description: Dark Brown/Brown Clayey Sand (SC)
(swell only)
Initial Moisture 18.0%
Final Moisture 25.6%
% Swell @ 500 psf None
Swell Pressure (psf) <500
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
10 100 1000 10000 100000
---------
Applied Load (psf)
Liquid Limit -
Plasticity Index -
% Passing #200 -
Dry Density (pcf) 108.1
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
Project # 16-1213
September 2016
SWELL/CONSOLIDATION TEST SUMMARY
Sample ID: B-3 @ 4'
Sample Description: Dark Brown/Brown Silty Sand (SM) with Gravel
(swell only)
Initial Moisture 20.7%
Final Moisture 16.9%
% Swell @ 500 psf None
Swell Pressure (psf) <500
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
10 100 1000 10000 100000
---------
Applied Load (psf)
Liquid Limit NL
Plasticity Index NP
% Passing #200 46.4%
Dry Density (pcf) 106.6
Final Moisture 24.4%
% Swell @ 500 psf None
Swell Pressure (psf) <500
Sample ID: B-6 @ 2'
Sample Description: Dark Brown/Brown Clayey Sand (SC) with Gravel
(swell only)
Initial Moisture 13.9%
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
Project # 16-1213
September 2016
SWELL/CONSOLIDATION TEST SUMMARY
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
10 100 1000 10000 100000
---------
Applied Load (psf)
Liquid Limit -
Plasticity Index -
% Passing #200 -
Dry Density (pcf) 106.1
Final Moisture 14.9%
% Swell @ 500 psf None
Swell Pressure (psf) <500
Sample ID: B-7 @ 2'
Sample Description: Dark Brown/Brown/Rust Clayey Sand (SC) with Gravel
(swell only)
Initial Moisture 5.6%
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
Project # 16-1213
September 2016
SWELL/CONSOLIDATION TEST SUMMARY
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
10 100 1000 10000 100000
---------
Applied Load (psf)
Liquid Limit NL
Plasticity Index NP
% Passing #200 32.8%
Dry Density (pcf) 107.8
Final Moisture 16.6%
% Swell @ 500 psf None
Swell Pressure (psf) <500
Sample ID: B-7 @ 4'
Sample Description: Dark Brown/Brown Clayey Sand (SC) with Gravel
(swell only)
Initial Moisture 6.4%
STAYBRIDGE HOTEL
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
Project # 16-1213
September 2016
SWELL/CONSOLIDATION TEST SUMMARY
-12
-10
-8
-6
-4
-2
0
2
4
6
8
10
12
10 100 1000 10000 100000
---------
Applied Load (psf)
UNIFIED SOIL CLASSIFICATION SYSTEM
Criteria for Assigning Group Symbols and Group Names Using Laboratory TestsA Soil Classification
Group
Symbol
Group NameB
Clean Gravels Cu ! 4 and 1 " Cc " 3E GW Well graded gravelF
Less than 5% finesC Cu
< 4 and/or 1 > Cc > 3E GP Poorly graded gravelF
Fines classify as ML or MH GM Silty gravelF,G, H
Coarse Grained Soils
More than 50% retained
on No. 200 sieve
Gravels
More than 50% of coarse
fraction retained on
No. 4 sieve Gravels with Fines More
than 12% finesC Fines classify as CL or CH GC Clayey gravelF,G,H
Clean Sands Cu ! 6 and 1 " Cc " 3E SW Well graded sandI
Less than 5% finesD Cu
< 6 and/or 1 > Cc > 3E SP Poorly graded sandI
Fines classify as ML or MH SM Silty sandG,H,I
Sands
50% or more of coarse
fraction passes
No. 4 sieve Sands with Fines
More than 12% finesD Fines classify as CL or CH SC Clayey sandG,H,I
Silts and Clays PI > 7 and plots on or above “A” lineJ CL Lean clayK,L,M
Liquid limit less than 50
Inorganic
PI < 4 or plots below “A” lineJ ML SiltK,L,M
Liquid limit - oven
dried
Organic clayK,L,M,N
Fine-Grained Soils
50% or more passes the
No. 200 sieve
Organic
Liquid limit - not
dried
< 0.75 OL
Organic siltK,L,M,O
Inorganic PI plots on or above “A” line CH Fat clayK,L,M
Silts and Clays
Liquid limit 50 or more
PI plots below “A” line MH Elastic siltK,L,M
Organic Liquid limit - oven dried Organic clayK,L,M,P
Liquid limit - not dried
< 0.75 OH
Organic siltK,L,M,Q
Highly organic soils Primarily organic matter, dark in color, and organic odor PT Peat
A Based on the material passing the 3-in. (75-mm) sieve
B If field sample contained cobbles or boulders, or both, add “with cobbles
or boulders, or both” to group name.
C Gravels with 5 to 12% fines require dual symbols: GW-GM well graded
gravel with silt, GW-GC well graded gravel with clay, GP-GM poorly
graded gravel with silt, GP-GC poorly graded gravel with clay.
D Sands with 5 to 12% fines require dual symbols: SW-SM well graded
sand with silt, SW-SC well graded sand with clay, SP-SM poorly graded
sand with silt, SP-SC poorly graded sand with clay
E Cu = D60/D10 Cc =
GENERAL NOTES
DRILLING & SAMPLING SYMBOLS:
SS: Split Spoon - 1⅜" I.D., 2" O.D., unless otherwise noted HS: Hollow Stem Auger
ST: Thin-Walled Tube – 2.5" O.D., unless otherwise noted PA: Power Auger
RS: Ring Sampler - 2.42" I.D., 3" O.D., unless otherwise noted HA: Hand Auger
CS: California Barrel - 1.92" I.D., 2.5" O.D., unless otherwise noted RB: Rock Bit
BS: Bulk Sample or Auger Sample WB: Wash Boring or Mud Rotary
The number of blows required to advance a standard 2-inch O.D. split-spoon sampler (SS) the last 12 inches of the total 18-inch
penetration with a 140-pound hammer falling 30 inches is considered the “Standard Penetration” or “N-value”. For 2.5” O.D.
California Barrel samplers (CB) the penetration value is reported as the number of blows required to advance the sampler 12
inches using a 140-pound hammer falling 30 inches, reported as “blows per inch,” and is not considered equivalent to the
“Standard Penetration” or “N-value”.
WATER LEVEL MEASUREMENT SYMBOLS:
WL: Water Level WS: While Sampling
WCI: Wet Cave in WD: While Drilling
DCI: Dry Cave in BCR: Before Casing Removal
AB: After Boring ACR: After Casing Removal
Water levels indicated on the boring logs are the levels measured in the borings at the times indicated. Groundwater levels at other
times and other locations across the site could vary. In pervious soils, the indicated levels may reflect the location of groundwater.
In low permeability soils, the accurate determination of groundwater levels may not be possible with only short-term observations.
DESCRIPTIVE SOIL CLASSIFICATION: Soil classification is based on the Unified Classification System. Coarse Grained Soils
have more than 50% of their dry weight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand.
Fine Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they
are plastic, and silts if they are slightly plastic or non-plastic. Major constituents may be added as modifiers and minor constituents
may be added according to the relative proportions based on grain size. In addition to gradation, coarse-grained soils are defined
on the basis of their in-place relative density and fine-grained soils on the basis of their consistency.
FINE-GRAINED SOILS COARSE-GRAINED SOILS BEDROCK
(CB)
Blows/Ft.
(SS)
Blows/Ft.
Consistency
(CB)
Blows/Ft.
(SS)
Blows/Ft.
Relative
Density
(CB)
Blows/Ft.
(SS)
Blows/Ft.
Consistency
< 3 0-2 Very Soft 0-5 < 3 Very Loose < 24 < 20 Weathered
3-5 3-4 Soft 6-14 4-9 Loose 24-35 20-29 Firm
6-10 5-8 Medium Stiff 15-46 10-29 Medium Dense 36-60 30-49 Medium Hard
11-18 9-15 Stiff 47-79 30-50 Dense 61-96 50-79 Hard
19-36 16-30 Very Stiff > 79 > 50 Very Dense > 96 > 79 Very Hard
> 36 > 30 Hard
RELATIVE PROPORTIONS OF SAND AND
GRAVEL
GRAIN SIZE TERMINOLOGY
Descriptive Terms of
Other Constituents
Percent of
Dry Weight
Major Component
of Sample
Particle Size
Trace < 15 Boulders Over 12 in. (300mm)
With 15 – 29 Cobbles 12 in. to 3 in. (300mm to 75 mm)
Modifier > 30 Gravel 3 in. to #4 sieve (75mm to 4.75 mm)
Sand
Silt or Clay
#4 to #200 sieve (4.75mm to 0.075mm)
Passing #200 Sieve (0.075mm)
RELATIVE PROPORTIONS OF FINES PLASTICITY DESCRIPTION
Descriptive Terms of
Other Constituents
Percent of
Dry Weight
Term Plasticity Index
Trace
With
Modifiers
< 5
5 – 12
> 12
Non-plastic
Low
Medium
High
0
1-10
11-30
30+
F If soil contains ! 15% sand, add “with sand” to group name.
G If fines classify as CL-ML, use dual symbol GC-GM, or SC-SM.
HIf fines are organic, add “with organic fines” to group name.
I If soil contains ! 15% gravel, add “with gravel” to group name.
J If Atterberg limits plot in shaded area, soil is a CL-ML, silty clay.
K If soil contains 15 to 29% plus No. 200, add “with sand” or “with
gravel,” whichever is predominant.
L If soil contains ! 30% plus No. 200 predominantly sand, add
“sandy” to group name.
M If soil contains ! 30% plus No. 200, predominantly gravel, add
“gravelly” to group name.
N PI ! 4 and plots on or above “A” line.
O PI < 4 or plots below “A” line.
P PI plots on or above “A” line.
Q PI plots below “A” line.
Project # 16-1213
September 2016
Sheet Drilling Rig: Water Depth Information
Start Date 8/24/2016 Auger Type: During Drilling None
Finish Date 8/24/2016 Hammer Type: After Drilling None
Surface Elev. - Field Personnel: 2 Days After Drilling Dci @ 6.0'
USCS
Sampler
Atterberg Limits
Project # 16-1213
September 2016
Sheet Drilling Rig: Water Depth Information
Start Date 8/24/2016 Auger Type: During Drilling None
Finish Date 8/24/2016 Hammer Type: After Drilling None
Surface Elev. - Field Personnel: 2 Days After Drilling B'filled
USCS
Sampler
Atterberg Limits
Project # 16-1213
September 2016
Sheet Drilling Rig: Water Depth Information
Start Date 8/24/2016 Auger Type: During Drilling None
Finish Date 8/24/2016 Hammer Type: After Drilling None
Surface Elev. - Field Personnel: 2 Days After Drilling B'filled
USCS
Sampler
Atterberg Limits
Project # 16-1213
September 2016
Sheet Drilling Rig: Water Depth Information
Start Date 8/24/2016 Auger Type: During Drilling None
Finish Date 8/24/2016 Hammer Type: After Drilling None
Surface Elev. - Field Personnel: 2 Days After Drilling B'filled
USCS
Sampler
Atterberg Limits
Project # 16-1213
September 2016
Sheet Drilling Rig: Water Depth Information
Start Date 8/24/2016 Auger Type: During Drilling 12.0'
Finish Date 8/24/2016 Hammer Type: After Drilling Dci @ 6.0'
Surface Elev. - Field Personnel: 2 Days After Drilling B'filled
USCS
Sampler
Atterberg Limits
Project # 16-1213
September 2016
Sheet Drilling Rig: Water Depth Information
Start Date 8/24/2016 Auger Type: During Drilling 11.0'
Finish Date 8/24/2016 Hammer Type: After Drilling Dci @ 7.5'
Surface Elev. - Field Personnel: 2 Days After Drilling Dci @ 7.0'
USCS
Sampler
Atterberg Limits
Project # 16-1213
September 2016
Sheet Drilling Rig: Water Depth Information
Start Date 8/24/2016 Auger Type: During Drilling 11.0'
Finish Date 8/24/2016 Hammer Type: After Drilling 11.0'
Surface Elev. - Field Personnel: 2 Days After Drilling 10.0'
USCS
Sampler
Atterberg Limits
Project # 16-1213
September 2016
Sheet Drilling Rig: Water Depth Information
Start Date 8/24/2016 Auger Type: During Drilling 12.5'
Finish Date 8/24/2016 Hammer Type: After Drilling 12.5'
Surface Elev. - Field Personnel: 2 Days After Drilling 12.0'
USCS
Sampler
Atterberg Limits
B'filled
During Drilling
After Drilling
Sheet
Start Date
Finish Date
2 Days After Drilling
Water Depth Information
8/24/2016 13.0'
301 E. LINCOLN AVENUE, FORT COLLINS, COLORADO
Project # 16-1213
September 2016
Sampler
USCS
Surface Elev.
Dci @ 10'
Auger Type:
Drilling Rig:
Hammer Type:
Field Personnel:
8/24/2016
-