HomeMy WebLinkAboutCHERRY STREET COTTAGES - PDP - PDP160041 - SUBMITTAL DOCUMENTS - ROUND 2 - PROJECT NARRATIVEProject Development Plan
1
Cherry Street Cottages
Northeast Corner of Cherry and Lyons Streets
Fort Collins, Colorado
Project Development Plan
I. WRITTEN DOCUMENTS
On behalf of Mr. Evan Gilmartin (Applicant), owner of the subject property, Sorensen
Engineering & Construction, LLC (SEC) is pleased to submit these Written Documents in
accordance with the submittal requirements for a Project Development Plan (PDP). The
owner wishes to subdivide the property into six (6) residential lots, with two (2) family
dwelling units on Lots 1, 2, and 3—primary dwelling units on the front with secondary
dwelling units on the back half over the garages—and a single dwelling unit on Lots 4, 5,
and 6. The eastern-most lot (previously identified as “Lot 7”) is now dedicated for a
stormwater detention pond and is referred to as “Tract A.” The access driveway along
the north side of the property is dedicated as “Tract B.” The following information is
submitted in fulfillment of the PDP application submittal guidelines.
A. Application form and Fees
The required PDP application form is attached. The Applicant understands that there
are no additional fees due at this time with this Round 2 submittal.
C. Names and addresses of landowners
As provided by APO Colorado, an excel spreadsheet listing the names and addresses of
all owners of record of real property within 800 feet of the property lines of the subject
property has been delivered to the City. A copy of that excel spreadsheet is attached.
D. Statement of Planning Objectives
The Statement of Planning Objectives was submitted with the Round 1 PDP Application
documents. As indicated on the attached Project Routing Sheet provided by Mr. Ted
Shepard, it is not necessary to resubmit the Statement of Planning Objectives with this
Round 2 submittal.
E. Response Letter addressing issues raised in Round 1 of the PDP Application
As indicated on the attached Project Routing Sheet, 10 copies of the Comment
Response Letter addressing applicable issues raised in the Round 1 review are attached.
F. A complete list of the new street names requested in the proposed development (2
copies)
Not applicable; no new streets are proposed with this project.
Project Development Plan
2
G. Legal description of the site
A tract of land situate in the Northeast ¼ of Section 10, Township 7 North, Range 69
West of the Sixth P.M., City of Fort Collins, County of Larimer, State of Colorado, which,
considering the North line of said Northeast ¼ as bearing North 89°29’09” West, and
that all bearings contained herein relative thereto, is contained within the boundary
lines which begin at a point which bears North 89°29’09” West 1330.64 feet, and again
South 00°13’24” West 1187.69 feet from the Northeast Corner of said Section 10, and
run thence South 00°13’23” West 119.99 feet to the North line of Cherry Street; thence
North 89°13’40” West 367.67 feet; thence along the arc of a 15.00 foot radius curve to
the right a distance of 23.60 feet; the long chord of which bears North 44°09’24” West
21.24 feet; thence North 00°54’52” East 104.91 feet; thence South 89°14’00” East
371,26 feet to the Point of Beginning. (which contains 1.024 acres, more or less)
H. Name and address of each owner of property within the boundaries of the
development plan area.
Evan Gilmartin
Egilmartin, Inc
2519 S Shields St., Ste 1k-194
Fort Collins, CO 80526-1855
I. Names of all general and limited partners (if a partnership), all managers and
directors (if a limited liability company), and/or officers and directors (if a
corporation) involved as either applicants or owners of the project development plan.
Evan Gilmartin
2519 S Shields Street, Ste 1K-194
Fort Collins, CO 80526-1855
J. A development schedule indicating the approximate date when construction of the
project or stages of the same, can be expected to begin and be completed, including
the proposed phasing of construction of public improvements and recreational and
common space areas
A detailed construction schedule will be submitted prior to construction activities, but at
this time, the Applicant expects construction to begin in mid-2017.
II. SITE PLAN DRAWINGS
As required, 10 copies of the Site Plan Drawings are attached.
III. SUBDIVISION PLAT
As required, 10 copies of the Subdivision Plat are attached.
IV. ARCHITECTURAL ELEVATIONS
Project Development Plan
3
The Applicant requests that the submittal of architectural elevations be deferred until
final submittal, or until such time as builders are named and architectural styles and
specific home designs are established.
V. LANDSCAPE PLAN
As required, 10 copies of the Landscape Plan are attached.
VI. TRANSPORTATION IMPACT STUDY
In accordance with conceptual review comments by Martina Wilkenson, Fort Collins
Traffic Operations Department, the requirement for a TIS has been waived.
VII. UTILITY PLANS
As required, 6 copies of the Utility Plan are attached.
VIII. UTILITY PLANS CHECKLIST
One copy of the Utility Plans Checklist is attached.
IX. PRELIMINARY DRAINAGE REPORT AND PLANS
As required, one copy of the Preliminary Drainage Report and Plan is attached.
X. SOILS REPORT
The Applicant requests that the Soils Report requirement be deferred until development
activities begin. With this request, the Applicant understands that the developer is
ultimately responsible for proper soils evaluation and subgrade preparation to prevent
concrete failures in the sidewalks and access alley.
XI. CONCEPTUAL LIGHTING PLAN
Although the “Lighting Plan” is not checked on the attached Project Routing Sheet, the
lighting plan is shown on the Landscape Plan provided with this submittal.
XII. HAZARDOUS MATERIALS IMPACT ANALYSIS
N/A.
XIII. REQUESTS FOR ANY KNOWN ENGINEERING VARIANCES
The Applicant makes no requests for any known engineering variances.
XIV. LETTERS OF INTENT
Project Development Plan
4
N/A. There are no off-site easements or off-site rights-of-way necessary for this project.
XV. ELECTRONIC COPY OF ALL SUBMITTED MATERIALS
As required, one electronic copy of all submitted material is included with this submittal.