Loading...
HomeMy WebLinkAbout2601 CANTON CT. - PDP/FDP - FDP160033 - REPORTS - DRAINAGE REPORTFINAL DRAINAGE AND EROSION CONTROL STUDY 2601 CANTON COURT Prepared for: Dan Bernth Doberstein Lemburg Commerical, Inc 1401 Riverside Avenue Fort Collins, CO 80524 Prepared by: North Star Design, Inc. 700 Automation Drive, Unit I Windsor, Colorado 80550 (970) 686-6939 February 10, 2017 Job Number 347-09 ii February 10, 2017 Heather McDowell City of Fort Collins Stormwater 700 Wood Street Fort Collins, CO 80522-0580 RE: Final Drainage and Erosion Control Study for 2601 Canton Court Dear Heather, I am pleased to submit for your review and approval, this Final Drainage and Erosion Control Study for 2601 Canton Court. I certify that this report for the drainage design was prepared in accordance with the Master Plan and the criteria in the City of Fort Collins Storm Drainage Manual. I appreciate your time and consideration in reviewing this submittal. Please call if you have any questions. Sincerely, Patricia Kroetch, P.E. 700 Automation Drive, Unit I Windsor, CO 80550 Phone: 970-686-6939 Fax: 970-686-1188 iii TABLE OF CONTENTS TABLE OF CONTENTS ............................................................................................................... iii 1. GENERAL LOCATION AND DESCRIPTION 1.1 Location ...................................................................................................................1 1.2 Description of Property ............................................................................................1 2. DRAINAGE BASINS AND SUB-BASINS 2.1 Major Basin Description ..........................................................................................2 2.2 Sub-Basin Description .............................................................................................2 3. DRAINAGE DESIGN CRITERIA 3.1 Regulations ..............................................................................................................2 3.2 Development Criteria Reference and Constraints ...................................................2 3.3 Hydrologic Criteria ..................................................................................................3 3.4 Hydraulic Criteria ....................................................................................................3 3.5 Four Step Four Step Process to Minimize Adverse Impacts of Urbanization .........3 4. DRAINAGE FACILITY DESIGN 4.1 General Concept ......................................................................................................4 4.2 Specific Flow Routing .............................................................................................5 4.3 Drainage Summary ..................................................................................................5 5. CONCLUSIONS 5.1 Compliance with Standards ....................................................................................6 5.2 Drainage Concept ....................................................................................................6 6. REFERENCES ....................................................................................................................7 APPENDICES A Vicinity Map B Hydrologic Computations C Hydraulic Computations D Water Quality Pond Calculations E LID Information, BMP Schedule & Cost Estimate F Erosion & Sediment Control Report 1 | Page 1. GENERAL LOCATION AND DESCRIPTION 1.1 Location The site is located on Lot 11, Prospect Industrial Park located in the Northeast Quarter of Section 20, Township 7 North, Range 68 West of the 9Sixth Principal Meridian, in the City of Fort Collins, Larimer County, Colorado. See the location map in Appendix A. The project is located at the southwest end of Canton Court and is currently an undeveloped parcel. The site bounded on all sides by existing commercial or office developments. 1.2 Description of Property The entire site consists of approximately 1.02 acres of land. The land is currently undeveloped and is lower than the surrounding development and currently does not discharge runoff. The site will be filled and shaped to drain to the southwest, onto the site at 2025 Sharp Point Drive and eventually into Midpoint Drive. Slopes on site range from approximately 0.5% to 12%. This project will include the development of one multi tenant building with man doors on the northwest and overhead doors on the southeast. There will be a private drive, a paved parking lot on the northwest side of the building, a recycled asphalt storage area on the southeast side of the building and landscaping on the remainder of the site. The majority of the site will drain to the south and east into a bio swale (with underdrain) and then into water quality pond on the adjacent lot. This pond will be contained in a drainage easement that will be dedicated to the City with this development proposal. The water will then discharge into Midpoint Drive and be conveyed to the Prospect Ponds where detention for this site will occur. An easement from Natural Areas will be obtained to allow for detention in these ponds. 2 | Page 2. DRAINAGE BASINS AND SUB-BASINS 2.1 Major Basin Description The proposed development lies within the Cache la Poudre Master Drainageway which requires that detention be provided to attenuate runoff to the 2 year historic runoff rate. It is also required that a minimum of fifty percent of the site runoff be treated using the standard water quality treatment as described in the Fort Collins Stormwater Manual and Low Impact Development (LID) treatment methods are required for seventy-five percent of the site runoff. The proposed LID treatment will be a bio swale located on the southeast edge of the site. 2.2 Sub-basin Description This site was most likely included in the original drainage report for Prospect Industrial Park but this report cannot be located. 3. DRAINAGE DESIGN CRITERIA 3.1 Regulations This report was prepared to meet or exceed the “City of Fort Collins Storm Drainage Design Criteria Manual” specifications. Where applicable, the criteria established in the “Urban Storm Drainage Criteria Manual” (UDFCD), developed by the Denver Regional Council of Governments, has been used. 3.2 Development Criteria Reference and Constraints The majority of the runoff from this site has been routed to flow to the proposed bio swale on the southeast side of the site and then routed to a proposed water quality pond on the adjacent property. A small portion of the site will flow to the northeast and into Canton Court without entering the water quality pond. The water quality pond will release runoff into Midpoint Drive which will convey the water southeast to Sharp Point Drive and north into the Prospect Ponds via inlet and storm pipe. The Prospect Ponds will provide detention for this site therefore no onsite detention is being provided for with 3 | Page this design. An easement will be obtained from Natural Areas to allow for detention in the Prospect Ponds. 3.3 Hydrologic Criteria Runoff coefficients calculations were prepared for the 2 and 10-year minor and 100-year major storm frequency utilizing the rational method. 3.4 Hydraulic Criteria The majority of the runoff from the site will flow to the southeast side of the lot and will enter the bio swale. A perforated pipe will collect the runoff and convey it to the water quality pond. The water quality pond will release to Midpoint Drive via an outlet structure and storm pipe and an overflow conveyance is also provided if the system fails or becomes overloaded. A small portion of the runoff from the site will flow to the northeast corner of the site and will be routed through the drive entrance to Canton Court. Detention and water quality extended detention are required for this site. Detention is proposed to be provided in the Prospect Ponds and water quality will be provided in a pond on the adjacent lot. The water quality extended detention volume was calculated to be 0.03 acre feet. The required volume will be accommodated in the proposed pond and will have a maximum water surface of 4895.50. The pond will discharge through a new drainage pipe to the curb in Midpoint Drive. This runoff will then be routed to the existing Prospect Pond on the east side of Sharp Point Drive. 3.5 Four Step Four Step Process to Minimize Adverse Impacts of Urbanization Step 1. Employ Runoff Reduction Practices – reduction of runoff peaks, volumes, and pollutant loads as the site is developed by implementing Low-Impact Development (LID) facilities including:  Increase time of concentration by routing flows around the building and increasing the length of the flow path.  Routing runoff from the proposed site into a bio-swale to promote infiltration and biological uptake.  Routing flows through filter material in the bio swale to increase time of concentration, promote infiltration and provide initial water quality. 4 | Page Step 2. Implement BMPs That Provide a Water Quality Capture Volume with Slow Release - The efforts outlined in Step 1 will facilitate the reduction of runoff; however, this development will also require water quality. Runoff will be routed through the bio- swale and then to a pond that will provide water quality extended detention prior to release into the street to not only reduce the amount of runoff generated from the site through infiltration, but also treat the runoff prior to releasing it from the site. A table showing the Low Impact Development practices being utilized within this project is provided in Appendix E. Step 3. Stabilize Streams - There are no major drainageways in or near this site therefore Step 3 it not directly applicable this project. However, this project will pay stormwater development fees and monthly stormwater utility fees which contribute to the City’s ongoing efforts to attain stream stability where and as needed. Step 4. Implement Site Specific and Other Source Control BMPs - This step applies to covering storage/handling areas and spill containment and control. Vehicle maintenance will be completed off site to prevent potential spills of vehicle fluids. Any handling of chemicals will be completed inside the building and will be handled per the applicable MSDS (material safety data sheet). Spills will be contained immediately and cleaned up using appropriate absorption materials. 4. DRAINAGE FACILITY DESIGN 4.1 General Concept The runoff from this site will flow into the parking lot which will be constructed using conventional materials (asphalt or concrete) or into the storage area which will be recycled asphalt. The runoff from the site will then flow to the southeast and enter the bio swale. The flow will percolated into the subsurface material and enter the perforated pipe. This perforated pipe will convey runoff directly to the water quality pond and, in an overflow situation, a second pipe is provided to convey the runoff to the water quality pond. 5 | Page 4.2 Specific Flow Routing A summary of the drainage patterns within each basin is provided in the following paragraphs. Basin 1 includes a small portion of the paved parking lot and sidewalk. Runoff from this basin will enter Canton Court via the drive entrance. No water quality extended detention or attenuation will be provided for the runoff from this basin. Basin 2 includes the remainder of the lot including the proposed building, a majority of the paved parking lot and sidewalk, the recycled asphalt storage area and the bio swale. The runoff from this basin will flow to the south and east and into the bio swale. A perforated pipe will collect the flow and convey it to the offsite water quality pond. If the perforated pipe becomes clogged or is over capacity, the water will flow in the bio swale to the secondary pipe and be conveyed to the water quality pond. The offsite pond has been sized to accommodate runoff from Lot 11 but may be expanded in the future to also accommodate expansion at 2025 Sharp Point Drive. This pond provides water quality extended detention and will release into a curb opening in Midpoint Drive to the southwest of this site. LID features have been incorporated in the design of the overall site. The site plan currently shows LID measures proposed with the development plan consisting a bio swale. Please see the LID Design Information provided in Appendix D. 4.3 Drainage Summary All runoff from this site will be safely conveyed via surface flow and piping to the water quality pond. The site will generally conform to the Cache la Poudre Master Drainage plan which encompasses this site. The City of Fort Collins will be responsible for maintenance of the existing storm drainage facilities located within the right-of-way. The drainage facilities located outside of the right of way including the bio swale, the water quality pond, the concrete pan in 6 | Page the water quality pond and the pond outlet structure will be maintained by the owner of Lot 11 and any other properties that will contribute runoff to the pond. 5. CONCLUSIONS 5.1 Compliance with Standards All computations that have been completed within this report are in compliance with the City of Fort Collins Storm Drainage Design Criteria Manual and the Cache la Poudre Master Drainage Plan. 5.2 Drainage Concept The proposed drainage concepts presented in this report and on the construction plans adequately provide for conveyance of runoff to the water quality area. Conveyance elements have been designed to pass required flows and to minimize future maintenance. If, at the time of construction, groundwater is encountered, a Colorado Department of Health Construction Dewatering Permit would be required. 7 | Page 6. REFERENCES 1. City of Fort Collins, “Storm Drainage Criteria Manual”, (SDCM), dated March, 1986. 2. Urban Drainage and Flood Control District, “Urban Storm Drainage Criteria Manual”, Volumes 1 and 2, dated March, 1969, and Volume 3 dated September, 1992. A | Page APPENDIX A VICINITY MAP B | Page APPENDIX B HYDROLOGIC COMPUTATIONS North Star Design, Inc. 700 Automation Drive, Unit I Windsor, CO 80550 LOCATION: 2601 Canton Court PROJECT NO: 347-09 COMPUTATIONS BY: ppk DATE: 2/10/2017 Recommended Runoff Coefficients from Table 3-3 of City of Fort Collins Design Criteria Recommended % Impervious from Urban Storm Drainage Criteria Manual % Runoff Impervious coefficient C Streets, parking lots (asphalt): 100% 0.95 Sidewalks: 90% 0.95 Recycled Asphalt: 40% 0.40 Roofs: 90% 0.95 Lawns (flat <2%, heavy soil): 0% 0.20 SUBBASIN TOTAL TOTAL ROOF PAVED SIDEWALK REC. ASPHALT LANDSCAPE % RUNOFF DESIGNATION AREA AREA AREA AREA AREA AREA AREA Impervious COEFF. (ac.) (sq.ft) (sq.ft) (sq.ft) (sq.ft) (sq.ft) (sq.ft) (C) 1 0.02 1,060 0 354 72 0 634 40% 0.50 2 0.99 43,190 9,000 13,202 1,314 11,718 7,956 63% 0.66 TOTAL 1.02 44,250 9,000 13,556 1,386 11,718 8,590 62% 0.66 Historic Lot 11 1.02 44,250 0 0 0 0 44,250 0% 0.20 Equations - Calculated C coefficients & % Impervious are area weighted C =  (Ci Ai) / At Ci = runoff coefficient for specific area, Ai Ai = areas of surface with runoff coefficient of Ci n = number of different surfaces to consider At = total area over which C is applicable; the sum of all Ai's Flow.xls Cval North Star Design, Inc. 700 Automation Drive, Unit I Windsor, CO 80550 LOCATION: 2601 Canton Court PROJECT NO: 347-09 COMPUTATIONS BY: ppk DATE: 2/10/2017 2-yr storm Cf = 1.00 FINAL REMARKS tc DESIGN SUBBASIN(s) Area C Length Slope ti Length Slope n Vel. tt tc = Total L tc=(l/180)+10 POINT (ac) (ft) (%) (min) (ft) (%) Manning (ft/s) (min) ti + tt (ft) (min) (min) (1) (2) (3) (4) (5) (6) (7) (8) rough. (9) (10) (11) (12) (13) (14) 1 1 0.02 0.50 26 1.0 5.5 26 6.5 0.016 5.1 0.08 5.6 52 10.3 5.6 To Canton Ct 2 2 0.99 0.66 46 1.0 5.3 380 0.5 0.016 1.4 4.46 9.8 426 12.4 9.8 To bioswale TOTAL 1.02 0.66 46 1.0 5.4 380 0.5 0.016 1.4 4.46 9.8 426 12.4 9.8 1 Historic Lot 11 1.02 0.20 172 1.6 18.2 131 0.7 0.030 0.9 2.51 20.7 303 11.7 11.7 Historic EQUATIONS: tc = ti + tt ti = [1.87 (1.1 - CCf ) L0.5 ] / S 1/3 tt = L/Vel. Velocity from Manning's Equation with R=0.1 (corresponds to Figure 3-3 of City of Fort Collins Design Manual) final tc = minimum of ti + tt and urbanized basin check min. tc = 5 minutes TIME (ti) TRAVEL TIME / GUTTER OR CHANNEL FLOW (tt) tc CHECK (URBANIZED BASIN) STANDARD FORM SF-2 TIME OF CONCENTRATION - 2 YEAR SUB-BASIN DATA INITIAL /OVERLAND Flow.xls TOC-2 North Star Design, Inc. 700 Automation Drive, Unit I Windsor, CO 80550 LOCATION: 2601 Canton Court PROJECT NO: 347-09 COMPUTATIONS BY: ppk DATE: 2/10/2017 100-yr storm Cf = 1.25 FINAL REMARKS tc DESIGN SUBBASIN(s) Area C C*Cf Length Slope ti Length Slope n Vel. tt tc = Total L tc=(l/180)+10 POINT (ac) (ft) (%) (min) (ft) (%) Manning (ft/s) (min) ti + tt (ft) (min) (min) (1) (2) (3) (4) (5) (6) (7) (8) rough. (9) (10) (11) (12) (13) (14) 1 1 0.02 0.50 0.63 26 1.0 4.3 26 6.5 0.016 5.1 0.08 4.4 52 10.3 5.0 2 2 0.99 0.66 0.83 46 1.0 3.3 380 0.5 0.016 1.4 4.46 7.8 426 12.4 7.8 0 TOTAL 1.02 0.66 0.82 46 1.0 3.4 380 0.5 0.016 1.4 4.46 7.8 426 12.4 7.8 1 Historic Lot 11 1.02 0.20 0.25 172 1.6 17.2 131 0.7 0.030 0.9 2.51 19.7 303 11.7 11.7 EQUATIONS: tc = ti + tt ti = [1.87 (1.1 - CCf ) L 0.5 ] / S 1/3 tt = L/Vel. Velocity from Manning's Equation with R=0.1 (corresponds to Figure 3-3 of City of Fort Collins Design Manual) final tc = minimum of ti + tt and urbanized basin check min. tc = 5 minutes TIME OF CONCENTRATION - 100 YR STANDARD FORM SF-2 SUB-BASIN DATA TIME (ti) INITIAL /OVERLAND TRAVEL TIME / GUTTER OR CHANNEL FLOW (tt) tc CHECK (URBANIZED BASIN) Flow.xls TOC-100 North Star Design, Inc. 700 Automation Drive, Unit I Windsor, CO 80550 RATIONAL METHOD PEAK RUNOFF (2-YEAR) LOCATION: 2601 Canton Court PROJECT NO: 347-09 COMPUTATIONS BY: ppk DATE: 2/10/2017 2-yr storm, Cf = 1.00 TOTAL REMARKS Design Tributary A C*Cf tc i Q (2) from Q (2) Q(2)tot Sub-basin (new) Design Point (ac) (min) (in/hr) (cfs) Point (cfs) (cfs) 1 1 0.02 0.50 5.6 2.69 0.0 0.0 To Canton Ct 2 2 0.99 0.66 9.8 1.99 1.3 1.3 To bioswale 0 TOTAL 1.02 0.66 9.8 2.22 1.5 1.5 1 Historic Lot 11 1.02 0.20 11.7 1.65 0.3 0.33 Historic Q = Cf C iA Q = peak discharge (cfs) C = runoff coefficient Cf = frequency adjustment factor i = rainfall intensity (in/hr) from IDF curve A = drainage area (acres) DIRECT RUNOFF CARRY OVER Flow.xls Q2 North Star Design, Inc. 700 Automation Drive, Unit I Windsor, CO 80550 RATIONAL METHOD PEAK RUNOFF (100-YEAR) LOCATION: 2601 Canton Court PROJECT NO: 347-09 COMPUTATIONS BY: ppk DATE: 2/10/2017 100-yr storm, Cf = 1.25 TOTAL REMARKS Des. Area A C*Cf tc i Q (100) from Q (100) Q(100)tot (new) Design Point Design. (ac) (min) (in/hr) (cfs) Point (cfs) (cfs) 1 1 0.02 0.63 5.0 9.95 0.2 0.15 To Canton Ct 2 2 0.99 0.83 7.8 8.17 6.7 6.71 To bioswale TOTAL 1.02 0.82 7.8 8.39 7.0 7.0 1 Historic Lot 11 1.02 0.25 11.7 5.67 1.4 1.4 Historic Q = C iA Q = peak discharge (cfs) C = runoff coefficient I = rainfall intensity (in/hr) from IDF curve A = drainage area (acres) DIRECT RUNOFF CARRY OVER Flow.xls Q100 C | Page APPENDIX C HYDRAULIC CALCULATIONS Project: Pipe ID: Design Information (Input) Pipe Invert Slope So = 0.0375 ft/ft Pipe Manning's n-value n = 0.0120 Pipe Diameter D = 12.00 inches Design discharge Q = 6.70 cfs Full-flow Capacity (Calculated) Full-flow area Af = 0.79 sq ft Full-flow wetted perimeter Pf = 3.14 ft Half Central Angle Theta = 3.14 radians Full-flow capacity Qf = 7.49 cfs Calculation of Normal Flow Condition Half Central Angle (0<Theta<3.14) Theta = 2.07 radians Flow area An = 0.62 sq ft Top width Tn = 0.88 ft Wetted perimeter Pn = 2.07 ft Flow depth Yn = 0.74 ft Flow velocity Vn = 10.79 fps Discharge Qn = 6.70 cfs Percent Full Flow Flow = 89.45% of full flow Normal Depth Froude Number Frn = 2.26 supercritical Calculation of Critical Flow Condition Half Central Angle (0<Theta-c<3.14) Theta-c = 2.80 radians Critical flow area Ac = 0.78 sq ft Critical top width Tc = 0.34 ft Critical flow depth Yc = 0.97 ft Critical flow velocity Vc = 8.60 fps Critical Depth Froude Number Frc = 1.00 CIRCULAR CONDUIT FLOW (Normal & Critical Depth Computation) 2601 Canton Court Storm pipe between bio swale and water quality pond Culvert.xls, Pipe 2/10/2017, 4:41 PM Project: Pipe ID: Design Information (Input) Pipe Invert Slope So = 0.0100 ft/ft Pipe Manning's n-value n = 0.0120 Pipe Diameter D = 15.00 inches Design discharge Q = 6.70 cfs Full-flow Capacity (Calculated) Full-flow area Af = 1.23 sq ft Full-flow wetted perimeter Pf = 3.93 ft Half Central Angle Theta = 3.14 radians Full-flow capacity Qf = 7.02 cfs Calculation of Normal Flow Condition Half Central Angle (0<Theta<3.14) Theta = 2.17 radians Flow area An = 1.03 sq ft Top width Tn = 1.03 ft Wetted perimeter Pn = 2.71 ft Flow depth Yn = 0.98 ft Flow velocity Vn = 6.51 fps Discharge Qn = 6.70 cfs Percent Full Flow Flow = 95.44% of full flow Normal Depth Froude Number Frn = 1.15 supercritical Calculation of Critical Flow Condition Half Central Angle (0<Theta-c<3.14) Theta-c = 2.30 radians Critical flow area Ac = 1.09 sq ft Critical top width Tc = 0.93 ft Critical flow depth Yc = 1.04 ft Critical flow velocity Vc = 6.14 fps Critical Depth Froude Number Frc = 1.00 CIRCULAR CONDUIT FLOW (Normal & Critical Depth Computation) 2601 Canton Court Water quality pond outlet Culvert.xls, Pipe 2/10/2017, 4:39 PM D | Page APPENDIX D WATER QUALITY POND CALCULATIONS WATER QUALITY POND SIZE LOCATION: 2601 Canton Court PROJECT NO: 347-09 COMPUTATIONS BY: PPK SUBMITTED BY: North Star Design, Inc. DATE: 2/10/2017 From Urban Storm Drainage Criterial Manual Use 40-hour brim-full volume drain time for extended detention basin Required Storage = a * ( 0.91 * I3 - 1.19 * I2 + 0.78 * I ) Water Quality Capture Volume = WQCV = (required storage/12)*(tributary drainage area) Trib. % Imperv. Req. Storage WQCV req. vol DWQ req. area/row area from Fig. EDB-2 WQCV *1.2 from Fig. EDB-3 (ac) (in. of runoff) (ac-ft) (ac-ft) (ft) (in2/row) POND 0.99 63 0.247 0.020 0.024 1.25 0.104 WQ outlet sizing for pond 1 From Figure 5, for 3/8 in. hole diameter Area of hole = 0.110 in2 # of columns = 1 Area provided/row = 0.110 in2 Area Required/row = 0.104 in2 Use 1 columns of 3/8" diam holes STAGE - STORAGE TABLE (100-YEAR) LOCATION: 2601 Canton Court PROJECT NO: 347-09 COMPUTATIONS BY: PPK SUBMITTED BY: North Star Design, Inc. DATE: 6/10/2016 100 yr Detention Volume Required = 0.000 Water Quality Volume Required = 0.024 Total Volume Required= 0.024 Surface Incremental Total Stage Area Storage Storage (ft) (ft2) (ac-ft) (ac-ft) 4893.75 0 4894.0 640 0.001 0.001 4895.0 1,425 0.023 0.024 WQCV 4895.00 1,425 0.000 0.024 4895.50 2,171 0.020 0.045 <==SPILLWAY ELEV 4896 4896.0 2 2,917 0 0.049 0 0.073 4896.5 3,374 0.036 0.109 Emergency Overflow Spillway Sizing LOCATION: 2601 Canton Court PROJECT NO: 347-09 COMPUTATIONS BY: PPK SUBMITTED BY: North Star Design, Inc. DATE: 5/24/2005 Equation for flow over a broad crested weir Q = CLH3/2 where C = weir coefficient = 2.8 H = overflow height L = length of the weir The pond has a spill elevation 0 ft above the maximum water surface elevation in the pond Spillways will be designed with 0.5 ft flow depth, thus H = 0.5 ft Size the spillway assuming that the pond outlet is completely clogged. Q (100) = 6.7 cfs Spill elev = 4895.50 ft 100 yr WSEL = 4895.0 ft Top of berm elev.= 4896.50 Weir length required: L = 7 ft Use L = 10 ft v = 0.96 ft/s E | Page APPENDIX E LID INFORMATION BMP SCHEDULE & COST ESTIMATE 2/10/2017 Calculation for Required LID Treatment New Impervious Area 23942 sq. ft. Required Minimum Impervious Area to be Treated (75%) 17956.5 sq. ft. Impervious Area Treated by LID Treatment Method #1 (bio swale) 37730 sq. ft. Total Impervious Area Treated 37730 sq. ft. Max run on ratio is 10:1, required bio swale area 3773 sq. ft. Area of bio swale 3710 sq. ft. 2601 Canton Court LID Summary Table Project: Disturbed Acres: 1.27 EROSION CONTROL BMPs Units Estimated Quantity Unit Price Total Price L.F. 1150 $3.00 $3,450.00 each 7 $85.00 $595.00 each 1 $220.00 $220.00 each 1 $1,500.00 $1,500.00 each 1 $1,200.00 $1,200.00 each 0 $210.00 $0.00 Sub-Total: $6,965.00 1.5 x Sub-Total: $10,447.50 Amount of security: $10,447.50 Total Acres x Price/acre: $1,524.00 $1,200.00 Sub-Total: $1,524.00 1.5 x Sub-Total: $2,286.00 Amount to Re-seed: $2,286.00 Minimum escrow amount: $3,000.00 Erosion Control Escrow: $10,447.50 Erosion and Sediment Control Escrow/Security Calculation for The City of Fort Collins BMP Amount Silt Fence Concrete Washout Inlet Protection Reseeding Amount Rock Berm Miniumum Escrow Amount 2601 Canton Court Unit Price of Seeding per acre: “The amount of the security must be based on one and one-half times the estimate of the cost to install the approved measures, or one and one-half times the cost to re-vegetate the disturbed land to dry land grasses based upon unit cost determined by the City's Annual Revegetation and Stabilization Bid, whichever is greater. In no instance, will the amount of security be less than one thousand five hundred dollars ($1,500) for residential development or three thousand dollars ($3,000) for commercial development” Rock Sock Vehicle Tracking Control Pad Final Escrow Amount 2/10/2017 3:14 PM \\Nstar\projects\347-09 Canton Court\drainage\ErosionEscrow.xls F | Page APPENDIX F EROSION & SEDIMENT CONTROL REPORT i | Page EROSION & SEDIMENT CONTROLS 1.0 Written Analysis An Erosion and Sediment Control Plan is included herewith. It should be noted, however, that any such Erosion and Sediment Control Plan serves only as a general guide to the Contractor. Staging and/or phasing of the BMPs depicted, and additional or different BMPs from those included may be necessary during construction, or as required by the authorities having jurisdiction. It shall be the responsibility of the Contractor to ensure erosion control measures are properly maintained and followed. The Erosion and Sediment Control Plan is intended to be a living document, constantly adapting to site conditions and needs. The Contractor shall update the location of BMPs as they are installed, removed or modified in conjunction with construction activities. It is imperative to appropriately reflect the current site conditions at all times. The Erosion and Sediment Control Plan shall address both temporary measures to be implemented during construction, as well as permanent erosion control protection. Best Management Practices from the Volume 3, Chapter 7 - Construction BMPs will be utilized. Measures may include, but are not limited to, silt fencing along the disturbed perimeter, gutter protection in the adjacent roadways and inlet protection at proposed storm inlets. Vehicle tracking control pads, spill containment and clean-up procedures, designated concrete washout areas, dumpsters, and job site restrooms shall also be provided by the Contractor. Grading and Erosion Control Notes can be found on Sheet 2 of the Utility Plans. In addition to this report and the plan sheets, the Contractor shall be aware of and adhere to the applicable requirements outlined all Development Agreements pertaining to this property. Also, the Site Contractor for this project will be required to secure a Stormwater Construction General Permit from the Colorado Department of Public Health and Environment (CDPHE), Water Quality Control Division - Stormwater Program, before commencing any earth disturbing activities. The Contractor shall also develop a comprehensive Storm Water Management Plan (SWMP) conforming to applicable ii | Page requirements including descriptions of the ongoing activities, inspections and maintenance of construction BMPs. • The site is approximately 1.02 acres all of which will undergo earthmoving operations. The existing site has existing ground cover (volunteer grasses and weeds) on approximate 45% - 50% of the site as the site has been historically used for storage of materials and vehicles for adjacent properties. Runoff from this site currently does not discharge to the offsite as this site is in a low area with all adjacent sites being raised (filled) upon development. With the proposed development, this site will also be filled and sloped to drain to the southeast. The runoff will then enter Midpoint Drive and be conveyed southeast to Sharp Point Drive, then north to a low point where it will enter the City of Fort Collins Natural Areas ponds (Prospect Ponds) via an inlet and storm pipe. Prospect Ponds discharge into the Cache la Poudre River on the east side of the ponds. The soils on this site are classified by the USGS Soil Survey as Caruso Clay Loam and are classified in the hydrologic group D. The soils are described as having a very slow infiltration rate (high runoff potential) when thoroughly wet. These consist chiefly of clays that have a high shrink-swell potential, soils that have a high water table, soils that have a claypan or clay layer at or near the surface, and soils that are shallow over nearly impervious material. These soils have a very slow rate of water transmission. The rainfall erodibility is deemed to be moderate and the wind erodibility is deemed to be moderate to high. The site is surrounded by developed sites including streets, buildings and paved areas. The construction shall utilize silt fence around the perimeter to control sediment transport from rainfall and from wind. The silt fence that is located in the proposed pavement areas will be removed prior to placing new pavement. Rock socks will be utilized in the existing curb and proposed bio swales to capture sediments that are not fully contained by the silt fence placement. The locations of the rock socks will be in the areas of concentrated flow such as in the existing curb, at the concrete sidewalk chase and on the concrete pans. iii | Page The site will also utilize a vehicle tracking control pad to minimize sediment from being tracked onto adjacent pavements. Sediment that is tracked will be removed and placed within the site or permanently disposed of offsite. A concrete washout will be used on site during the concrete placement. All hardened concrete will be disposed of offsite. These BMP’s have not been located on the site map due to the fact that the site is very small and these BMP’s will need to be placed by the contractor in locations that are most beneficial and will minimize disruption of adjacent traffic. Permanent erosion control consists of covering the soils with a building, concrete walks, concrete pavement, recycled asphalt pavement and sod. No soil will be left exposed to erosion after the construction is complete. Refer to the landscape plan for areas of and instructions for placement of sod and soil amendments required prior to placement of sod. Refer to Appendix E for the timing of the construction phases and the sequential installation of all BMP phasing for this site. Refer to the Appendix E for the Erosion Control Surety calculations. 2.0 SWMP contact information Permit holder: Name: Address: Phone Number: Email Address: Appointed agent: Name: Address: Phone Number: Email Address: iv | Page 3.0 Identification and location of all potential pollution sources Potential Pollutant Source Activity Potential Pollutant Generated Applicable to this project Control Measure Disturbed Areas Sediment X Silt Fence, Rock Socks Soil stockpiles Sediment X Silt Fence, Rock Socks Travel to adjacent public streets Tracked sediment X Tracking Pad, street sweeping Contaminated soils Sediment, chemicals Possible Remove contaminated soils from site ** Loading and unloading chemicals Chemicals Unloading of building materials Trash, debris X Trash dumpsters, Waste Management Firm ** Outdoor storage of chemicals Chemicals On site equipment maintenance Oil, grease On site equipment fueling Diesel, gasoline X Containment berm ** Dust generating activities Particulates, sediment X Water truck Use of fertilizer, pesticides, herbicides Fertilizer, pesticides Use of detergents, solvents, oils Detergents, solvents, oil X If spilled, remove contaminated soils from site ** Waste dumpsters, waste piles Chemicals, trash, debris X Waste Management Firm Concrete washout Concrete, sediment, wash water X Remove hardened concrete, dispose of offsite ** On site equipment washing Detergents, oil On site asphalt batch plant Asphaltic cement, sediment On site concrete batch plant Cement, sediment Portable toilets Domestic sewage X Waste Management Firm ** Refer to Section 1.5.2 for additional Materials Handling & Spill Prevention BMP 4.0 Best Management Practices (BMP’s) for Stormwater Pollution Prevention Structural Practices for Erosion and Sediment Control Structural practices for the site will consist mainly of silt fence and rock sock filters and are described in detail in the following paragraphs. These BMP's are expected to change as the construction progresses and it is the responsibility of the contractor to ensure appropriate BMP's are in place and/or removed at the appropriate time in the construction sequence. All temporary and permanent erosion and sediment control practices must be maintained and repaired as needed to assure continued performance of their intended function. v | Page Silt fence and rock sock filters shall be in place prior to commencement of construction activities. During clearing and grubbing necessary for silt fence installation, all cleared material shall be placed on the uphill side so that if erosion occurs from the cleared material, the sediment will be trapped and not transported downstream. Rock socks shall be implemented in the existing curb line as shown on the Drainage & Erosion Control Plan. All BMP's shall be installed per the details shown on the construction plan set. Temporary & Permanent Structural BMP’s: Structural BMP Approximate location on site Applicable to this Project Silt Fence Site perimeter, refer to site map X Straw bale dams Rock Socks At existing sidewalk culverts, in existing gutters, refer to site map X Earthen diversion dams Vegetated swales Sediment trap/pond Pipe slope drains Geogrid Inlet/outlet protection In the detention Pond X Culverts Refer to site map X Riprap Erosion control mats Inlet protection Vehicle Tracking Control Pad At site entrance, refer to site map X Concrete Washout To be located by Contractor X Non-Structural Practices for Erosion and Sediment Control: Soils exposed during the earthwork phase and landscape prep phase shall be kept in a roughened condition by ripping or disking along land contours until mulch, vegetation, or other permanent erosion control is installed. No large amount of soils (in excess of 15 yards) will be allowed to be stock piled on site. Overburden from the utility pipe trenching will be piled adjacent to trenches upstream of sediment controls and will be replaced in the trenches within 72 hours. vi | Page Excess excavated materials from the demolition and grading phases of the project that cannot be reused on site will be exported as it is excavated. This includes any asphalt pavement from the existing site that is to be removed. A vehicle tracking pad will be installed at a location most beneficial to the site construction as determined by the contractor. Vehicles will not be permitted in the excavated area if soil is muddy. Gravel sub base will be placed and compacted in the areas indicated for pavement following excavation. In the current pre construction state the site enables tracking of silt onto the adjacent streets during wet conditions. During construction activities the street will be monitored for foreign debris tracked out of the site and mechanical sweeping and clean up will be performed as needed. No area shall remain exposed by land disturbing activity for more than thirty (30) days before required temporary or permanent erosion control (e.g. seed/mulch, landscaping, etc.) is installed. Temporary & Permanent non-structural BMP’s: Non-Structural BMP Approximate location on site Applicable to this Project Surface roughening Entire site X Soil stockpile height limit (less than 10’) Perimeter vegetative buffer northwest and southwest boundaries of site X Minimization of site disturbance Mulch Seed & mulch stockpiles after 30 days Stockpile toe protection (silt fence, wattles or ditch) Preservation & protection of existing vegetation & trees northwest and southwest boundaries of site X Good site housekeeping (routine cleanup of trash & constr debris) Entire Site X Sweeping & scraping of hardscape areas On and off site pavements X Heavy equip staged on site, properly maintained & inspected daily (no onsite maintenance) Staging area X vii | Page 5.0 BMP Implementation 5.1 Phased BMP Implementation BMP’s are expected to change as the construction progresses and it is the responsibility of the contractor to ensure appropriate BMP’s are in place and/or removed at the appropriate time in the construction sequence. A construction sequence schedule has been included on the Drainage & Erosion Control Plan and included in the construction plans for this site. All BMP’s shall be inspected and repaired or replaced as required to satisfy the conditions of the Stormwater Discharge Permit. All BMP’s must be maintained and repaired as needed to assure continued performance of their intended function. Refer to Appendix E for the BMP schedule and estimated costs. 5.2 Materials Handling and Spill Prevention: Materials Handling & Spill Prevention BMP Approximate location on site Applicable to this Project Portable toilets, anchored & located away from drainages Contractor to determine X Fuel storage located in bulk tanks with secondary containment & spill kit Mobile fueling performed at least 200 feet away from drainages & fully attended Contractor to determine X Fertilizers, form oil, solvents, cleaners, detergent stored in 55 gal or smaller containers, kept in storage units Contractor to determine X Dumpsters containing used chemicals containers & liquid wastes kept covered Contractor to determine X Equipment cleaning (on site) uses no detergents & flows to onsite retention basin In case of a release of fuel or other chemicals, absorbent booms or earthen berms will be immediately constructed to contain the spill & prevent runoff to adjacent surface waters Location of spill X MSDS sheets for onsite chemicals will be kept at the construction trailer to facilitate spill response & cleanup Contractor to determine X viii | Page 5.3 Dedicated Asphalt or Concrete Batch Plant: Not proposed with this development 5.4 Vehicle Tracking Pad: Vehicle tracking control pad shall be installed wherever construction vehicle access routes intersect paved public roads. Vehicle tracking control pads shall be installed to minimize the transport of sediment (mud) by runoff or vehicles tracking onto the paved surface. Any mud tracked to public roads shall be removed on a daily basis and after any significant storm that causes sediment to be transported. It is unlawful to track sediment/mud onto public streets and may be enforced by the City of Fort Collins, by the State of Colorado or by the EPA. 5.5 Waste Management and Disposal: Portable toilets will be anchored & periodically maintained by waste management company. Dumpsters on site will be covered & periodically emptied by waste management company. Concrete waste will be allowed to harden and then will be removed from site. No washing activities will occur on site. Location of the concrete washout is shown on the site map. The washout will be sufficiently deep to accommodate all anticipated concrete truck wash water. Waste concrete will be allowed to harden and be removed from site periodically as the washout reaches 50% of its capacity. Truck wash water will not be allowed to reach the curb & gutter or any other water course. 5.6 Groundwater and Stormwater Dewatering: No groundwater was encountered during soils exploration therefore ground water is not anticipated to be an issue. If groundwater is encountered a groundwater discharge permit shall be obtained and a detailed report shall be completed describing the location and the route of where pumped groundwater will be conveyed and the measures taken to prevent the transport of any pollutants to downstream waters. ix | Page 5.7 Inspection & Maintenance: It is required that routine site inspections are performed to effectively address maintenance and repair of Best Management Practices (BMP's). The site inspections are to performed by the contractor or an inspector designated by the administrator at a minimum of once every fourteen (14) calendar days on active construction sites and after any significant storm event (an event causing runoff). As part of the site inspections the inspector is required to keep documentation of all inspections and BMP maintenance, including an updated Site Map indicating new BMP's or the removal of BMP's since the previous inspection. Any maintenance, repair, or necessary installation of BMP's that are noted during the inspection must be completed within seven (7) calendar days from the date of the inspection. 6.0 Soil Amendments, Permanent Seeding & Mulching 6.1 Soil Amendments Soil in the bio swale shall be amended per the City of Fort Collins Bioretention Sand Media Specifications found at: http://www.fcgov.com/utilities/img/site_specific/uploads/Bioretention_Sand_Media_Specs.pdf Soil treatment in the water quality area will be to spread imported or stockpiled topsoil to a minimum depth of four inches over areas to be planted. 6.2 Permanent Seeding The following seed mix shall be applied at the rates indicated in the bioswale and in the water quality pond. Other landscaped areas on site shall be treated per the landscape plan. Mulch shall be applied after seeding as the notes indicate below. x | Page Drill seed specified mix in two passes, each at right angles to each other. Drill half of the seed in each pass. If areas are too wet or steep to drill seed, broadcast seed in two opposite directions. Restore fine grade after seeding, and cover seed to depth of 1/4 inch by raking or dragging. Firm seeded areas with a roller weighing maximum of 100 lbs. per foot of width. Ground cover shall be considered established when 70% of the seed has been germinated. At the point that the seed is considered established, the temporary erosion control measures may be removed. 6.3 Mulching All planted areas should be mulched preferably immediately following planting, but in no case later than 14 days from planting. Mulch conserves water and reduces erosion. The most common type of mulch used is hay or grass that is crimped into the soil to hold it. However, crimping may not be practical on slopes steeper than 3:1. The following guidelines should be followed with mulching: • Only weed-free and seed-free straw mulch should be used (grass hay often contains weedy exotic species). Mulch should be applied at 2 tons/acre and adequately secured by crimping, tackifier, netting, or blankets. • Crimping is appropriate on slopes of 3:1 or flatter and must be done so as to tuck mulch fibers into the soil 3 to 4 inches deep. • Tackifier or netting and blankets anchored with staples should be used on slopes steeper than 3:1. xi | Page • Hydraulic mulching may also be used on steep slopes or where access is limited. Wood cellulose fibers mixed with water at 2,000 to 2,500 pounds/acre and organic tackifier at 100 pounds per acre should be applied with a hydraulic mulcher.