HomeMy WebLinkAboutPOUDRE RIVER WHITEWATER PARK (FORMERLY POUDRE RIVER DOWNTOWN PARK) - PDP - PDP160039 - CORRESPONDENCE - REVISIONS1
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
fcgov.com/developmentreview
December 30, 2016
Roger Sherman
BHA DESIGN
1603 OAKRIDGE DRIVE
Fort Collins, CO 80521
RE: Poudre River Whitewater Park (formerly Poudre River Downtown Park), PDP160039, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, you may contact the individual commenter or direct your questions through
the Project Planner, Rebecca Everette, at 970-416-2625 or reverette@fcgov.com.
Comment Summary:
Department: Engineering Development Review
Contact: Marc Ragasa, 970.221.6603, mragasa@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 12/27/2016
12/27/2016: The Utility Plan submittal was incomplete. Please refer to
Appendix E-4 for requirements for Utility Plans. Items highlighted in yellow are
items that are required prior to hearing. Since majority of the crucial items were
missing/inadequate, a full review of the plans was not done. Please resubmit
with required items as well as a Plat.
Response: Please see the revised Utility Plans which have been updated to include the required elements
identified in Appendix E-4 and current design information. A Plat has also been provided
as part of the revised submittal
Department: Environmental Planning
Contact: Rebecca Everette, 970-416-2625, reverette@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 12/28/2016
12/28/2016: Please add the following statement to the notes on all relevant
sheets of the site, landscape, photometric and utility plans: "All undisturbed
areas are intended to be maintained in a native and/or drought-tolerant
2
landscape. Please see Section 3.4.1 of the Land Use Code for allowable uses
and requirements for protecting natural features."
Response: Plans have been updated to include this note.
Comment Number: 2 Comment Originated: 12/28/2016
12/28/2016: Thank you for providing such a thorough Ecological
Characterization Study. This will serve as a good model for future projects along
the Poudre River corridor. Staff concurs with the findings and recommendations
in the ECS.
Response: Thank you.
Topic: Landscape Plans
Comment Number: 3 Comment Originated: 12/28/2016
12/28/2016: Based on discussions at the staff review meeting, it sounds like
the tree mitigation plan may need to be updated due to recent tree
pruning/removal by PRPA. Please coordinate with Forestry and update the
plans accordingly.
Response: The team met with Forestry on site on January 18th
, since then, plans have been updated to
reflect current conditions.
Comment Number: 4 Comment Originated: 12/28/2016
12/28/2016: Staff is comfortable with the approach to tree mitigation outlined
on sheet 1 of the mitigation plan. Please provide the total quantity of mitigation
shrubs that will be used to offset the mitigation trees (~220?).
Response: The total number of mitigation trees is 79, 69 of which are upsized trees and 100 are upsized
shrubs. Exact mitigation quantities will be provided on-site by forester.
Comment Number: 5 Comment Originated: 12/28/2016
12/28/2016: There are some missing mitigation quantities in the tree mitigation
table (sheet 3). Please continue to coordinate with Forestry and update the
table accordingly.
Response: During the meeting with Forestry on January 18th
, the team discussed the missing quantities and
the plans have been updated accordingly.
Comment Number: 6 Comment Originated: 12/28/2016
12/28/2016: It would be helpful to add a table to the landscape plan that
estimates the size (in square feet) of each type of planting area/community (i.e.,
shrub beds, zone 1, zone 2, zone 3, plugs, willow stakes).
Response: Coverage in SF has been added to the landscape plan schedule for each area appropriately.
Comment Number: 7 Comment Originated: 12/28/2016
12/28/2016: Please provide a detailed species list for Seed Mix A1 (High
Plains Meadow Mix). If any seed mixes will be used in Zones 2 and 3, please
provide details for those as well.
Response: Seed Mix A1 was renamed to ‘Comm A1’, Upland Seed (Zone 1). Biohabitats and BHA have been
3
working closely with Rick Bachand (with Natural Areas) to develop an appropriate seed mix for this site. As of
this time, the seed mix is as follows:
High Plains Meadow Mix by Western Native Seed, Coaldale, CO
% Scientific name Common name
3.6 Linum perenne v. lewisii Blue Flax
3.6 Oxytropis sericea Silky Locoweed
3.6 Penstemon angustifolius Pagoda Penstemon
3.6 Rudbeckia hirta Black-eyed Susan
3.6 Helianthus annuus Annual Sunflower
3.0 Penstemon strictus Rocky Mt Penstemon
3.0 Ratibida columnifera Prairie Coneflower
3.0 Ratibida columnifera pulchra Mexican Hat
1.8 Liatris punctata Dotted Gayfeather
0.6 Mirabilis multiflora Wild Four O'Clock
0.3 Penstemon virgatus Wand Beardtongue
0.3 Macheranthera bigelovii Purple Aster
24.5 Bouteloua curtipendula Side Oats Grama
14.0 Pascopyrum smithii Western Wheatgrass
7.0 Elymus trachycaulus Slender Wheatgrass
3.5 Elymus elymoides Bottlebrush Squirreltail
3.5 Bouteloua gracilis Blue Grama
3.5 Oryzopsis hymenoides Indian Ricegrass
3.5 Andropogon gerardii Big Bluestem
3.5 Schizachyrium scoparium Little Bluestem
3.5 Sorghastrum nutans Yellow Indiangrass
3.5 Sporobolus cryptandrus Sand Dropseed
Comment Number: 8 Comment Originated: 12/28/2016
12/28/2016: Please clarify - will the Pollinator Meadow Mix A2 be planted as
seeds or plugs?
Response: The Pollinator Meadow Mix A2 is intended to be installed as plugs. To reduce confusion, the plan
sheet have been modified to label this community as ‘Comm A2’, Upland Seed (Zone 1) & Pollinator Meadow
(Plugs).
Comment Number: 9 Comment Originated: 12/28/2016
12/28/2016: Please clarify what species will be used for the plugs along the
river and wetland area. Are those the herbaceous species listed under Zone 3,
or something else?
Response: The species used for plugs in the lower riparian zone (Zone 3) are the herbaceous species listed
in that section of the plans.
Comment Number: 10 Comment Originated: 12/28/2016
12/28/2016: Planting Note #8 references Zone 4. Which zone is that referring
to, if any?
Response: The mention of Zone 4 is a typographical error. The text should refer to Zone 1. The plans have
been updated.
Comment Number: 11 Comment Originated: 12/28/2016
12/28/2016: When it comes to sourcing plant material, you might consider
contacting the Colorado State Forest Service and High Plains Environmental
4
Center to help with propagation of native species. CSFS has offered to assist
with plant propagation for other City projects.
Response: Acknowledged
Topic: Lighting Plan
Comment Number: 12 Comment Originated: 12/28/2016
12/28/2016: For all proposed light fixtures, please use versions with 3000K
color temperatures or less to minimize impacts to sensitive natural features.
Some fixtures are shown in 4000K and 5000K version on sheet E3.0 of the
lighting plan, which will not meet the environmental protection requirements.
Response: Fixture part numbers called out changed to 3000K.
Comment Number: 13 Comment Originated: 12/28/2016
12/28/2016: Will any motion sensing, dimming, or timing controls be used for
any of the light fixtures. These are all highly recommended to reduce impacts to
the river corridor, wetlands, nesting birds and other wildlife.
Response: The lighting to be installed throughout is dimmable, especially right over and next to the river
corridor. The entire site will photocell on between timer controlled higher traffic times (4am – 11pm).
Occupancy/Motion sensors will be employed in the parking lots and pole lights to provide dimming to 50%
when not occupied to minimize impacts. Side shields will also be employed where needed to further
minimize impact to sensitive areas. Fixture selection and location is also being carefully considered to
minimize impact.
Comment Number: 14 Comment Originated: 12/28/2016
12/28/2016: What will be the mounting height(s) of the light fixtures (particularly
the AA fixture)?
Response: Pole lights (AA) will be 16’. The wall mounted step fixtures are typically mounted at 18”. The
PH1 fixtures will be mounted in the overhead of the pergola structures and at the bottom of the bridge on the
south end and will be governed by the structures. The HR1 along the wall on the south side will be mounted
in the handrail along the wall. The HR1 along the bridge will be mounted close to the walking surface at 6” in
a lower rail.
Comment Number: 15 Comment Originated: 12/28/2016
12/28/2016: The labels on the photometric plan do not match the names and
symbols shown in the Luminaire Schedule on sheet E3.0. Please
update/correct.
Response: Labels have been updated.
Comment Number: 16 Comment Originated: 12/28/2016
12/28/2016: Sheets E3.3, 3.4 and 3.5 all show spillover lighting into the wetland
areas. Please adjust the placement, shielding, or mounting heights of the light
fixtures to eliminate any light trespass into the wetland areas. Please also label
the wetland lines on the photometric plans.
Response: Shielding will be provided on fixtures causing spillage. Fixtures also adjusted to minimize impact
and necessity of shields. Wetland labeling added to photometric plans.
Topic: Site Plan
5
Comment Number: 17 Comment Originated: 12/28/2016
12/28/2016: The future picnic shelter location shown immediately to the east of
the west pond should be moved further from the wetland to avoid any impacts.
Either attach to the trail or move to the opposite side of the trail (or another less
sensitive area).
Response: The future picnic area has been shifted to the other side of the walk.
Comment Number: 18 Comment Originated: 12/28/2016
12/28/2016: Please add a detail to the site plan that compares the existing
(previously approved) Coy Ditch Natural Habitat Buffer to the reconfigured
buffer proposed with this project.
Response: A diagram has been added to the Site Plan.
Department: Light And Power
Contact: Luke Unruh, 9704162724, lunruh@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 12/28/2016
12/28/2016: Please provide a transformer location that is within 10' of a paved
surface. Please show the location on the utility plan.
Response: The transformer location is now shown on the Utility Plan and is located within the
15’ utility easement that will be dedicated by the project, approximately 20’ west of the
emergency access road.
Department: Outside Agencies
Contact: Don Kapperman, Comcast, ,
Topic: General
Comment Number: 1 Comment Originated: 12/27/2016
COMCAST
12/27/2016: Please call in locates to see if Comcast is clear of all work area.
Response: Locates were conducted by a private locating service, under the direction of King Surveyors, as
part of the site survey. Comcast lines were found along the north side of Vine Drive, outside of the project
area. Other communication lines were found in the project area (south side of Vine), but ownership is
currently unknown. Ownership of these lines will be confirmed during final design. Due to the street
widening proposed as part of this project, utilities located on the south side of Vine Drive will likely need to be
relocated prior to widening of the road. Further coordination will be conducted with Comcast as necessary
prior to design completion.
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler@poudre-fire.org
Topic: General
Comment Number: 1 Comment Originated: 12/28/2016
12/28/2016: RIVER ACCESS
Several off-line discussions have occurred regarding this project. What follows
is a summation of those outstanding items currently under consideration:
> 16' fire lanes have been approved by the fire marshal assuming functional fire
6
access remains available.
> The fire lane will require an Emergency Access Alignment. Details should be
labeled on future plans.
> Fire lane signage is needed at the entry point on E Vine to signal emergency
responders this route has been designed for their use.
> End of fire lane, past Xcel site should be posted with, "No large vehicle
access past this point."
> The fire lane connection at E. Vine shall be a rollover curb.
> Removable bollards are approved in this application assuming they are
clearly signed and labeled as to their function and the removal process can be
expediently managed without a loss of time (assuming spring or summer
conditions). Otherwise, a gate is preferred. In either case, PFA will need to
review the bollard or gate design prior to installation.
> Can a small vehicle turn around be provided at the 10' wide walk connection
leading to the parking lot? This may simply require a flared trail intersection at
this location.
> Other details, such as setting of rescue boat anchor points, can be deferred
until a later discussion.
Response: Acknowledged. Please see Site Plan sheets, specifically S3 for additional emergency vehicle
access information. Based on recent discussions, the removable bollards may be replaced with a gate, as
this may be preferred by both PFA and Parks Planning.
Comment Number: 2 Comment Originated: 12/28/2016
12/28/2016: GENERAL FIRE ACCESS
> Ideally, an open pull-off should be provided on E Vine to accommodate
ambulance, PD and fire apparatus on typical day-to-day calls so as not to
obstruct E Vine or create an unsafe environment. This area may overlap with a
drop-off area that was previously proposed. An area near the historic Quonset
was originally discussed.
Response: An open pull-off is provided at the location of the emergency/fire access lane along the west side
of the welding business (Upham Property). Removable bollards (or possible gate) are set back from Vine
Drive to allow for emergency vehicle parking without obstructing the sidewalk along Vine.
Comment Number: 3 Comment Originated: 12/28/2016
12/28/2016: AUTOTURN EXHIBIT
As fire lanes are less than 20' in width, an AutoTurn exhibit will be needed to
verify turning movements.
Response: A turning analysis exhibit was emailed to Jim Lynxwiler on January 30, 2017. The email was sent
from Roger Sherman with BHA Design.
Comment Number: 4 Comment Originated: 12/28/2016
12/28/2016: FIRE LANE - SOFT TRAIL
> Portions of the proposed fire lane are labeled as "soft trail." The design intent
is unclear. The full width of the fire lane needs to support 40 tons. Further details
are needed to determine if this design will meet minimum fire access
specifications and will hold up over time.
Response: The soft portion of the trail has been updated to a Class 6 Roadbase.
7
Comment Number: 5 Comment Originated: 12/28/2016
12/28/2016: SOUTH SIDE RIVER ACCESS
The overall plan should take into account that emergency access is needed on
both sides of the river. The fire marshal would like to see the recreation area
plan to account for and plan for this need.
Response: See site plan sheet 3 for North bank emergency vehicle access. Jim Lynxwiler, Matt Day and
Roger Sherman reviewed the south bank during a site walk on January 26, 2017. Emergency access exists
on the south and east sides of the Power House Institutes property.
Department: Planning Services
Contact: Rebecca Everette, 970-416-2625, reverette@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 12/28/2016
12/28/2016: A standard City signature block needs to be added to the utility
plans.
Response: A standard City signature block has been added to the Utility Plans.
Topic: Site Plan
Comment Number: 2 Comment Originated: 12/28/2016
12/28/2016: Thank you for providing an estimate for the number of parking
spaces needed to support this use. Please provide more information on which
previously designed parks were considered and/or other whitewater park
examples for comparison. How much parking is provided at other whitewater
parks, and how much use is generally observed on normal and peak days? Is
there an average turnover rate for parking spaces, and how does that vary
between weekday, weekend, and event days?
Response: From PDP submittal on December 6, 2017: “Refer to the Site Plan for proposed
parking locations. S2O is the member of the design team that specializes in whitewater parks. Based
on previously designed parks, they estimate some 30 spaces as a requirement during the busy
season and Parks Department estimate an additional 18 spaces would be needed for this sites for
other recreational uses. This equals 48 spaces for the site. The parking lot design currently provides
35 on-site spaces, and 18 on-street parking for overflow. This gives visitors a total of 53 potential
parking spaces. The design team understands that these numbers are only an estimate and have
provided a location for future parking.”
The Poudre River Whitewater Park is different from other regional kayak parks because it only has 2
wave features and it is not being designed to accommodate large events/competitions. Typically
parks of this nature have multiple wave features and host events throughout the kayaking season,
which in Colorado is an average of 45 days due to water levels and typically lasts from May to
June/August. The weekday use of the parking lot will be random/sporadic and modest. It is likely that
weekends will be busier. Due to the equipment required for Kayaking, the majority of parking will be
used by Kayakers. An individual kayak activity would last an average of one hour. Assuming that the
parking lot would turn-over hourly, the highest possible peak hour trip generation would be 35 ingress
and 35 egress vehicles related to the parking lot. This is not likely to occur every day or every daylight
hour of the day. However, these numbers are an estimate. As a precaution, a future parking lot has
been designed as a phase 2 expansion, providing an additional 27 parking spaces. The additional
parking expansion may, or may not, be constructed at some point in the future.
8
Comment Number: 3 Comment Originated: 12/28/2016
12/28/2016: Will there be a shared parking agreement with the Rocky Mountain
Innosphere? Staff expects spillover from the Innosphere into this parking lot
during the week, and vice versa on weekends and event days. A shared parking
agreement that clarifies permission/restrictions for spillover parking or a letter
outlining the adaptive approach to parking management should be provided
prior to hearing.
Response: The City has decided that it will use a “wait and see” approach to determine how the
parking lot will be regulated and if shared parking with Innosphere needs to be investigated further.
Comment Number: 4 Comment Originated: 12/28/2016
12/28/2016: The amount of bike parking provided does not seem adequate to
support the high level of recreational use that is expected. Please arrange a
meeting with FC Bikes staff to discuss the amount of bike parking provided and
rack locations. Perhaps space can be dedicated for potential future/expanded
bike racks to respond to demand once the park is in use.
Response: Bike parking has been expanded from (12) spaces to a total of (20) spaces. A ‘future’ bike
parking location that can hold an additional 8 spaces was also added on the south bank.
Comment Number: 5 Comment Originated: 12/28/2016
12/28/2016: Recycling receptacles should be paired with each trash
receptacle.
Response: The plans have been updated to include recycling receptacles with each trash receptacle.
Comment Number: 6 Comment Originated: 12/28/2016
12/28/2016: On sheet 1 of the Site Plan, please outline the pad sites for the
future picnic shelter and bathroom locations.
Response: Sheet 1 of the site plan has been updated.
Comment Number: 7 Comment Originated: 12/28/2016
12/28/2016: It would be helpful to add a legend to the site plan, given the
number of symbols and line types used on the plans.
Response: The site plan sheets have been updated to include a legend.
Comment Number: 8 Comment Originated: 12/28/2016
12/28/2016: Please add all relevant standard site plan notes, available here:
http://www.fcgov.com/developmentreview/pdf/CFC-Standard-Notes.pdf
Response: All relevant standard site plan notes have been added to the site plan sheets.
Comment Number: 9 Comment Originated: 12/28/2016
12/28/2016: Is the changing room shown on sheet 2 of the Site Plan proposed
with this PDP or for the future? If proposed with the current PDP, please show
as a solid box (rather than dashed lines) on the site plan. Please also provide
an elevation detail for the changing room.
Response: The proposed changing room is part of this current proposed plans. The plans have been updated
to reflect this correctly. Please see the image below, and the additional notes on the site plan.
9
Comment Number: 10 Comment Originated: 12/28/2016
12/28/2016: Please provide color examples for the fence details on sheet 3 of
the Site Plan.
Response: Please see the below images, Type 1, Type 2 and Type 3 respectfully. See site plan for fence type
location.
Comment Number: 11 Comment Originated: 12/28/2016
12/28/2016: Please add color details and/or provide material samples for the
boulders, terraced boulder seating, boulder stairs, concrete seat wall, stone
steps, stone trail, retaining walls, and any other structural or architectural
features.
Response: Additional images that show site character have been added to the site plan as black and white
10
images, below are these same images in color.
Comment Number: 12 Comment Originated: 12/28/2016
12/28/2016: Please add the following note to the site plan: "Items identified as
future improvements will require additional review and approval by the City of
Fort Collins via minor amendment or other appropriate processes."
Response: The note has been added to the site plan.
Department: Stormwater Engineering
Contact: Heidi Hansen, 970-221-6854, hhansen@fcgov.com
Topic: Floodplain
11
Comment Number: 4 Comment Originated: 12/30/2016
All of the proposed improvements in the Poudre River floodway and flood fringe
must go through a CLOMR/LOMR process. Before the PDP can be approved,
the CLOMR and Floodplain Use Permit must be submitted and City staff must
be confident that the proposed design can meet City and FEMA regulations.
The CLOMR must be fully approved by both the City and FEMA before
construction can begin.
Response: A CLOMR application is being prepared and will be submitted soon for City review, followed by
submittal to FEMA.
Comment Number: 5 Comment Originated: 12/30/2016
Please utilize the review checklists for floodplain requirements (50%
development review submittal) available at
http://www.fcgov.com/utilities/what-we-do/stormwater/flooding/forms-documents
. The section under “Drainage and/or Grading Plan” has items required with this
submittal, a separate floodplain sheet can be included if adding all of these
items to the grading plan is too cluttered.
Response: A separate floodplain sheet has been added to the utility plan to display the required items. Per
our discussion and your request, both effective and proposed 100-year and half-foot floodway delineations,
proposed cross section locations, and proposed BFEs will be shown on the floodplain sheet. 500-year
delineations will not be provided on the floodplain sheet since the project does not involve a critical facility
and to reduce the clutter of linework on the sheet. A completed copy of the floodplain review checklist has
also been included with this revised submittal.
Comment Number: 6 Comment Originated: 12/30/2016
Per the submittal checklist, please add to the Drainage Report: a statement that
a FEMA LOMR is required after construction; a discussion of the bathroom
structure relative to the floodplain/floodway; a discussion of the pedestrian
bridge relative to the floodplain/floodway.
Response: The drainage report has been revised and now includes the statement a FEMA LOMR is required
after construction. The report also indicates that the restroom pad will be located above the proposed BFE to
accommodate construction of the restroom out of the regulatory floodplain during the next project phase.
Finally, the report states that the pedestrian bridge is located above the proposed BFE.
Comment Number: 7 Comment Originated: 12/30/2016
No outdoor storage of floatable materials is allowed. Items such as trash cans,
benches, park equipment, dumpsters, etc. must be anchored per an approved
engineered design to prevent them floating downstream as debris. Please call
out these items as being anchored on the site plan.
Response: The notes for site furnishings within the flood plain are labeled as being surface mounted.
Comment Number: 8 Comment Originated: 12/30/2016
As vehicles are considered to be floatable, new parking areas must only allow
daytime parking when owners are on site to remove vehicles if the area begins
to flood. No overnight parking of vehicles is allowed. A plan for how to monitor
the no overnight parking requirement should be included in the Floodplain Use
Permit application.
Response: The Floodplain Use Permit application will specify that signage will be provided stating the
12
overnight parking is not allowed. Parking services will provide enforcement by managing the parking lot as a
City downtown lot.
Contact: Jesse Schlam, 970-218-2932, jschlam@fcgov.com
Topic: Erosion Control
Comment Number: 1 Comment Originated: 12/20/2016
12/20/2016: The site disturbs more than 10,000 sq. ft., therefore Erosion and
Sediment Control Materials need to be submitted for FDP. The erosion control
requirements are in the Stormwater Design Criteria under the Amendments of
Volume 3 Chapter 7 Section 1.3.3. Current Erosion Control Materials
Submitted do not meet requirements. Please submit; an Erosion Control Plan,
an Erosion Control Report, and an Escrow / Security Calculation. If you need
clarification concerning the erosion control section, or if there are any questions
please contact Jesse Schlam 970-218-2932 or email @ jschlam@fcgov.com
Response: An Erosion Control Plan, Erosion Control Report and Escrow/Security calculation will be prepared
and submitted for FDP.
Contact: Shane Boyle, 970-221-6339, sboyle@fcgov.com
Topic: Drainage Report
Comment Number: 2 Comment Originated: 12/30/2016
12/30/2016: Per City Stormwater Criteria, the Drainage Report needs to
address the 4-step process for erosion control. Please revise the report
accordingly.
Response: The 4-step erosion control process is now addressed in the report.
Topic: General
Comment Number: 3 Comment Originated: 12/30/2016
12/30/2016: LID is required for this project. The Conceptual Review comment
response letter is correct in that the 25% pervious paver requirement is no
longer in effect. However, the LID requirement is as follows:
A. 50% of the newly added or modified impervious area must be treated by LID
techniques and 25% of new paved areas must be pervious.
B. 75% of all newly added or modified impervious area must be treated by LID
techniques.
Therefore, if the project is proposing to forego pervious pavers, the site is
required to implement 75% LID treatment for all proposed and future impervious
area. LID is not required for pervious area, but the calculations for any
proposed LID BMPs will need to include all area draining to the BMP. Also,
please note, an LID table will be needed on the Drainage Plan unless a
separate LID exhibit is included as part of the Drainage Report. Please call if
clarification is needed.
Response: Pursuant to our conversations, LID treatment is now addressed by passing runoff (from a
minimum of 75% new impervious area) through enhanced wetland areas of the Coy Ponds and Ditch. This
discussion has been added to the drainage report.
13
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Construction Drawings
Comment Number: 6 Comment Originated: 12/29/2016
12/29/2016: Please change the project title to match the other plan sets.
Response: The project title has been changed in the revised submittal.
Comment Number: 7 Comment Originated: 12/29/2016
12/29/2016: There are line over text issues. See redlines.
Response: The text/line conflicts have been resolved.
Comment Number: 8 Comment Originated: 12/29/2016
12/29/2016: Please add a Benchmark Statement to the plans. The City has
moved to the NAVD88 vertical datum, and as of January 1, 2015, all projects
are required to be on NAVD88 datum. Please provide the following information
for the Benchmark Statement in the EXACT format shown below.
PROJECT DATUM: NAVD88
BENCHMARK # w/ DESCRIPTION
ELEVATION:
BENCHMARK # w/ DESCRIPTION
ELEVATION:
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL
DATUM. SURROUNDING DEVELOPMENTS HAVE USED NGVD29
UNADJUSTED FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE,
THE FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED
= NAVD88 - X.XX’.
Response: The benchmark statement has been added to the cover and survey control sheet.
Comment Number: 9 Comment Originated: 12/29/2016
12/29/2016: Please tie the coordinate values shown for utilities to the project
boundary. We would prefer that this be done by adding property corner values
to each sheet, or showing the property corner values on the horizontal control
plans and adding a note to each sheet with coordinate values.
Response: The property corner values are now shown on the survey control sheet, and a note has been
added to each sheet with coordinate values.
Topic: General
Comment Number: 1 Comment Originated: 12/29/2016
12/29/2016: Please consider changing the sheet numbering on the cover
sheet. We are thinking S1-S3 for the site, L1-L4 for the landscape, M1-M3 for
the mitigation, A1-A2 for the architecture plans.
Response: The sheet numbering system has been updated.
14
Comment Number: 2 Comment Originated: 12/29/2016
12/29/2016: ARCHITECTURE: No comments.
Response: Acknowledged
Topic: Landscape Plans
Comment Number: 4 Comment Originated: 12/29/2016
12/29/2016: MITIGATION: There are line over text issues. See redlines.
Response: The text/line conflicts have been resolved.
Topic: Lighting Plan
Comment Number: 5 Comment Originated: 12/29/2016
12/29/2016: Please change the project title to match the other plan sets.
Response: Title Block updated.
Topic: Site Plan
Comment Number: 3 Comment Originated: 12/29/2016
12/29/2016: There are line over text issues. See redlines.
Response: The text/line conflicts have been resolved.
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 12/27/2016
12/27/2016: Irrigation plans are required no later than at the time of building
permit. The irrigation plans must comply with the provisions outlined in Section
3.2.1(J) of the Land Use Code. Direct questions concerning irrigation
requirements to Eric Olson, at 221-6704 or eolson@fcgov.com
Response: Acknowledged.
Department: Water-Wastewater Engineering
Contact: Shane Boyle, 970-221-6339, sboyle@fcgov.com
Topic: Construction Drawings
Comment Number: 1 Comment Originated: 12/30/2016
12/30/2016: Please add a utility sheet to the construction plans for clarity.
Response: A utility sheet has been added to the construction plans.
Comment Number: 2 Comment Originated: 12/30/2016
12/30/2016: It does not appear that all existing utility services are shown on the
plans. These services will need to be clearly shown and called out and either
reused or abandoned at the main. Conceptual Review comment responses
indicate there will be irrigation service(s) proposed but I could not locate these
on the plans.
Response: The existing water utility services are shown on the utility plan sheets.
The project now intends to repurpose the existing water and sewer service at 101 Vine Drive
15
for the future restroom. Existing water services at 103, 105, 203, and 213 Vine Drive will be
reused for the irrigation system that is currently under design. The irrigation system will be
provided for review as part of FDP process. Sewer and gas services at 103, 105, and 213
Vine Drive will be abandoned during the demolition of the existing buildings on these
properties that will occur prior to the construction of this project.
Topic: General
Comment Number: 3 Comment Originated: 12/30/2016
12/30/2016: More detail will be needed for the proposed utility services and fire
hydrant. This can wait to be addressed until final.
Response: Noted. Details for the proposed utility services and fire hydrant will be provided at final.
Department: Zoning
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 12/20/2016
12/20/2016: The Planning signature block needs to be updated. It should
reflect the Community Development and Neighborhood Services Director.
Response: The plans have been updated.
Comment Number: 2 Comment Originated: 12/20/2016
12/20/2016: At the top of the ramp in the sidewalk west of the handicap parking
spaces there is no landing. This ramp is only visible in the Landscape plan,
please revise all plan sets to match.
Response: The landing at the top of the sidewalk ramp west of the handicap parking spaces is now shown on
the plan sets.