Date: January 11, 2017 Total Acres: 3.17
EROSION CONTROL MEASURE Units
Estimated
Quantity
Unit
Price
Total
Price
L.F. 747 $1.50 $1,120.50
Construction Fence w/Rock Sock L.F. 268 $4.50 $1,206.00
each 34 $75.00 $2,550.00
Wattle Dike Inlet Protection each 0 $100.00 $0.00
each 0 $75.00 $0.00
Wattle Dike Swale Protection each 0 $100.00 $0.00
each 1 $300.00 $300.00
each 0 $150.00 $0.00
each 1 $200.00 $200.00
each 6 $75.00 $450.00
L.F. 358 $1.00 $358.00
per hour 15 $60.00 $900.00
Sub-Total: $7,084.50
1.5 x Sub-Total: $10,626.75
Amount of security: $10,626.75
Total Acres x $1325/acre: $4,200.25
Sub-Total: $4,200.25
1.5 x Sub-Total: $6,300.38
Cost to Re-seed: $6,300.38
Minimum escrow amount: $3,000.00
Erosion Control Escrow: $10,626.75
NOTE: 'Total Acres' represents total disturbed area.
Vehicle Tracking Control Pads
Option 2 | Cost to Re-seed Disturbed acreage
Option 3 | Miniumum Escrow Amount
Final Escrow Amount
Sediment Trap
Concrete Washout Area
Rock Sock
Sawcutting Pollution Prevention
Street Sweeping and Cleaning
Option 1 | BMP Costs
The Park Townhomes at Fossil Ridge
Erosion Control Cost Estimate
Silt Fencing
Inlet Protection
Wattle Dike Curb Side Check Dam