HomeMy WebLinkAboutBANNER HEALTH MEDICAL CAMPUS - FDP - FDP130020 - PLANS - PROJECT SUBMITTAL AND RESUBMITTAL (5)LEVEL 1
0'‐0"
LEVEL 2
15'‐4"
LEVEL 3
32'‐0"
48'‐0"
59'‐8"
T.O. PARAPET
B.O. CANOPY
14'‐0"
T.O. ROOF
LEVEL 1
0'‐0"
LEVEL 2
15'‐4"
LEVEL 3
32'‐0"
48'‐0"
59'‐8"
T.O. PARAPET
B.O. CANOPY
14'‐0"
T.O. ROOF
1. THESE ELEVATIONS ARE REPRESENTATIVE OF THE FULL BUILD
FOR THE BANNER HARMONY MEDICAL CENTER TO ESTABLISH
THE ARCHITECTURAL CHARACTER OF THE BUILDING MASSING
AND MATERIALS.
2. REFER TO SHEETS 7 ‐13 FOR THE PORTION OF THE BUILDING
THAT WILL BE DEVELOPED AS A PART OF PHASE 1.
3. THE CORRESPONDING PHASE 1 ELEVATIONS, WITHIN THE
CONTEXT OF THE FULL BUILD, HAVE BEEN OUTLINED BY DASHED
WHITE LINES ON SHEETS 1 & 2.
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
FINAL PLAN
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
TTLBv.101213
SHEET:
8/8/2013 9:20:30 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
FULL BUILD - ELEVATIONS
1 OF 13
METAL PANEL
MASONRY, TYPE 1
EIFS, COLOR 1
CURTAIN WALL
MASONRY, TYPE 2A
METAL PANEL CANOPY
CURTAIN WALL METAL PANEL
CURTAIN WALL MASONRY, TYPE 1
METAL PANEL
STOREFRONT
AMBULANCE DROP‐OFF
LEVEL 1
0'‐0"
LEVEL 2
15'‐4"
LEVEL 3
32'‐0"
48'‐0"
59'‐8"
T.O. PARAPET
B.O. CANOPY
14'‐0"
T.O. ROOF
LEVEL 1
0'‐0"
LEVEL 2
15'‐4"
LEVEL 3
32'‐0"
48'‐0"
59'‐8"
T.O. PARAPET
B.O. CANOPY
14'‐0"
T.O. ROOF
1. THESE ELEVATIONS ARE REPRESENTATIVE OF THE FULL BUILD
FOR THE BANNER HARMONY MEDICAL CENTER TO ESTABLISH
THE ARCHITECTURAL CHARACTER OF THE BUILDING MASSING
AND MATERIALS.
2. REFER TO SHEETS 7 ‐13 FOR THE PORTION OF THE BUILDING
THAT WILL BE DEVELOPED AS A PART OF PHASE 1.
3. THE CORRESPONDING PHASE 1 ELEVATIONS, WITHIN THE
CONTEXT OF THE FULL BUILD, HAVE BEEN OUTLINED BY DASHED
WHITE LINES ON SHEETS 1 & 2.
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
FINAL PLAN
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
TTLBv.101213
SHEET:
8/8/2013 9:39:23 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
FULL BUILD - ELEVATIONS
2 OF 13
METAL PANEL EIFS, COLOR 1 MASONRY, TYPE 1
STOREFRONT WINDOW METAL PANEL MECHANICAL
SCREEN BEYOND
STONE
CURTAIN WALL
METAL PANEL HORIZONTAL SUNSHADE
MASONRY, TYPE 1
CURTAINWALL
METAL PANEL
EIFS, COLOR 1
STOREFRONT WINDOW
LEVEL 1
0'‐0"
LEVEL 2
14'‐0"
T.O. ROOF
28'‐0"
LEVEL 1
0'‐0"
LEVEL 2
14'‐0"
T.O. ROOF
28'‐0"
1. THESE ELEVATIONS ARE REPRESENTATIVE OF THE FULL BUILD
OUT OF THE BANNER HARMONY MEDICAL CENTER TO
ESTABLISH THE CHARACTER OF THE MASSING AND MATERIALS.
2. REFER TO SHEETS 7 ‐13 FOR THE PORTION OF THE BUILDING
THAT WILL BE DEVELOPED AS A PART OF PHASE 1.
3. THE CORRESPONDING PHASE 1 ELEVATIONS, WITHIN THE
CONTEXT OF THE FULL BUILD, HAVE BEEN OUTLINED BY DASHED
WHITE LINES ON SHEETS 1 & 2.
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
N O R T H
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FINAL PLAN
TTLBv.101213
SHEET:
8/8/2013 8:45:26 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
FULL BUILD - ELEVATIONS
3 OF 13
EIFS, COLOR 1
STOREFRONT WINDOW
WITH HORIZONTAL
SUNSHADE
MASONRY, TYPE 1A METAL PANEL
MASONRY, TYPE 1
SUNSHADE, TYP.
STOREFRONT WINDOW
EIFS, COLOR 1
METAL PANEL MECHANICAL SCREEN
MASONRY, TYPE 1
SUNSHADE
EIFS, COLOR 1
HORIZONTAL
SUNSHADE, TYP. STOREFRONT
WINDOW
MECHANICAL SCREEN
MASONRY, TYPE 1
EIFS, COLOR 1
STOREFRONT WINDOW
SUNSHADE, TYP.
CURTAIN WALL
HORIZONTAL SUNSHADE
LEVEL 1
0'‐0"
LEVEL 2
10'‐0"
T. O. PARAPET
16'‐0"
LEVEL 1
0'‐0"
LEVEL 2
10'‐0"
T. O. PARAPET
16'‐0"
1. THESE ELEVATIONS ARE REPRESENTATIVE OF THE FULL BUILD
OUT OF THE BANNER HARMONY MEDICAL CENTER TO
ESTABLISH THE CHARACTER OF THE MASSING AND MATERIALS.
2. REFER TO SHEETS 7 ‐13 FOR THE PORTION OF THE BUILDING
THAT WILL BE DEVELOPED AS A PART OF PHASE 1.
3. THE CORRESPONDING PHASE 1 ELEVATIONS, WITHIN THE
CONTEXT OF THE FULL BUILD, HAVE BEEN OUTLINED BY DASHED
WHITE LINES ON SHEETS 1 & 2.
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
N O R T H
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FINAL PLAN
TTLBv.101213
SHEET:
8/8/2013 8:45:37 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
FULL BUILD - ELEVATIONS
4 OF 13
MASONRY, TYPE 1 MASONRY, TYPE 1A PRECAST CONCRETE, COLOR TO MATCH EIFS MASONRY, TYPE 1
MASONRY, TYPE 1A
MASONRY, TYPE 1 METAL PANEL MASONRY, TYPE 1A PRECAST CONCRETE, COLOR TO MATCH EIFS MASONRY, TYPE 1
MASONRY, TYPE 1A
METAL PANEL CANOPY PRECAST CONCRETE, COLOR TO MATCH EIFS
METAL PANEL
PRECAST CONCRETE,
COLOR TO MATCH EIFS
METAL PANEL MASONRY, TYPE 1A PRECAST CONCRETE, COLOR TO MATCH EIFS METAL PANEL
MASONRY, TYPE 1
MASONRY PARAPET CAP MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP MASONRY PARAPET CAP
FINAL PLAN NOTES
4. SIGNAGE IS NOT APPROVED THROUGH THE FINAL PLAN. ALL SIGNAGE
WILL RECEIVE A SEPARATE SIGN PERMIT FOR APPROVAL
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
FINAL PLAN
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
TTLBv.101213
SHEET:
8/8/2013 9:40:58 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
FULL BUILD - SHADOW ANALYSIS
5 OF 13
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
FINAL PLAN
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
TTLBv.101213
SHEET:
8/8/2013 9:41:20 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
FULL BUILD - SHADOW ANALYSIS
6 OF 13
FLOOR 1 (4910.25')
100' ‐ 0"
FLOOR 2
115' ‐ 4"
PARAPET (D&T 2)
134' ‐ 8"
7 6 4 3.3 3 2.9 1.7 1.5
LOW CANOPY ROOF
112' ‐ 0"
4.7 4.3 2.8
ST
MP2
SF‐1 ST
MP1
SF‐1 SF‐1
BL‐1
BL‐1
ST
SS3
EXTERIOR WALL
EXPANSION JOINT
MP1
BL‐1
MP1 SF‐1
SF‐1
BL‐1
MP1
PC
EIFS‐2 ST
MP1
SIGNAGE, BY
OWNER, SEE
ELECTRICAL FOR
POWER
MP1
MC
PC PC
MC MC
PC
PC
MP1
MP1
SIGNAGE, BY
OWNER, SEE
ELECTRICAL FOR
POWER
PC
MC
GS GV
GS
GS
GV
GV
GS
GV
GS
GV
14' ‐ 0"
MP1
MP1
FLOOR 1 (4910.25')
100' ‐ 0"
ZA.6 ZB ZB.9 ZC.4 ZD ZE ZF
MP1
MP1
SF‐1
MP1
EIFS‐2 EIFS‐2
EIFS‐1
MP1
EIFS‐1
EIFS‐2
EIFS‐1
EIFS‐2 EIFS‐2
EIFS‐1
SF‐1
BL‐1 BL‐1
PC MC MC
MC
BL‐1
MC
PC MP2
MP1
MC
GV
GV
GV
GS GS
I J.2
PARAPET (ENTRY)
128' ‐ 0"
T.O. ROOF SCREEN
(CLINIC)
123' ‐ 6"
PARAPET (FLR 1 LOW)
116' ‐ 8"
T.O. ROOF SCREEN
(BED TOWER 1)
146' ‐ 1 1/2"
T.O. ROOF SCREEN
(BED TOWER 2)
139' ‐ 9 1/2"
FLOOR 1 (4910.25')
100' ‐ 0"
1.5
Z1 Z2 Z3
PARAPET(FLOOR 1)
117' ‐ 8"
Z4
Z7
Z4.6 Z5 Z6
EIFS‐2
BL‐1
EIFS‐1 EIFS‐1
EIFS‐2
MP1
MP2
SF‐1
PC MC
MC
FLOOR 1 (4910.25')
100' ‐ 0"
FLOOR 2
115' ‐ 4"
Z7 1.7 2.5 3.5 4.5 5.5 6.5 6.7
MP1
MP2
SS2 SS2
SS2 SS2
SS2
EIFS‐2
MC
CJ CJ CJ CJ CJ
GV GS
GV GS
MP1
EIFS‐1
EIFS‐1
EIFS‐2
GV
BL‐1
SF‐1
SS2
SS2
CJ
CJ CJ
CJ
MC
PC
MC
CJ CJ
CJ CJ CJ
CJ
PARAPET ( BED TOWER
3)
133' ‐ 0"
T.O. ROOF SCREEN
(BED TOWER 1)
146' ‐ 1 1/2"
T.O. ROOF SCREEN
(BED TOWER 2)
139' ‐ 9 1/2"
STONE VENEER (COLOR AND FINISH TBD)
CMU BLOCK VENEER (DARK COLOR AND FINISH TBD)
(SEE SHEET 8 FOR COURSING DETAIL)
CMU BLOCK VENEER (LIGHT COLOR AND FINISH TBD)
(SEE SHEET 8 FOR COURSING DETAIL)
SPLIT FACE VENEER ( DARK COLOR AND FINISH TBD )
(SEE SHEET 9 FOR COURSING DETAIL)
SPLIT FACE VENEER ( LIGHT COLOR AND FINISH TBD )
(SEE SHEET 9 FOR COURSING DETAIL)
ZINC METAL PANEL (WALL)
PREFINISHED METAL PANEL (SCREEN)
EIFS (LIGHT COLOR AND FINISH TBD)
EIFS (DARK COLOR AND FINISH TBD)
METAL PARAPET CAP
PRECAST CONCRETE PARAPET CAP (COLOR AND FINISH TBD)
ROOF MEMBRANE
METAL PANEL CANOPY ROOF FASCIA
VERTICAL SUN SHADE
FLOOR 1 (4910.25')
100' ‐ 0"
FLOOR 2
115' ‐ 4"
ZD M L ZC.4 K.5 K J H G.5 G F
EIFS‐2
EIFS‐1
GV
CJ
CJ CJ CJ CJ CJ
CJ
J.2 I
MP1
BL‐1
SF‐1
MP2
PC MC
INTERIOR
CORRIDOR
GS
GV
GV
PARAPET (D&T 3)
133' ‐ 8"
T.O. ROOF SCREEN
(D&T)
146' ‐ 7 1/2"
FLOOR 1 (4910.25')
100' ‐ 0"
FLOOR 2
115' ‐ 4"
F E D C B A 0.4A 0.A
EIFS‐2 EIFS‐2
EIFS‐1
EIFS‐1
MP2
MC
MC
MP1
SIGNAGE, BY
OWNER, SEE
ELECTRICAL FOR
POWER
BL‐2
CJ CJ CJ CJ
CJ CJ CJ CJ CJ CJ
GV
GV
PARAPET (D&T 3)
133' ‐ 8"
T.O. ROOF SCREEN
(D&T)
146' ‐ 7 1/2"
14' ‐ 0"
STONE VENEER (COLOR AND FINISH TBD)
CMU BLOCK VENEER (DARK COLOR AND FINISH TBD)
(SEE SHEET 12 FOR COURSING DETAIL)
CMU BLOCK VENEER (LIGHT COLOR AND FINISH TBD)
(SEE SHEET 12 FOR COURSING DETAIL)
SPLIT FACE VENEER ( DARK COLOR AND FINISH TBD )
FLOOR 1 (4910.25')
100' ‐ 0"
XG XF XE XC XB
MP2
SF‐2
EIFS‐2 EIFS‐2
SF‐2
EIFS‐2
SF‐2 SF‐2
SF‐2
MP2
BL‐2
EIFS‐1 BL‐2
EIFS‐1 BL‐2
EIFS‐1 EIFS‐1
TRANSFORMER
PC
MC
PC MC
PC
PC
MP2
PC
5' ‐ 0"
8' ‐ 0"
MC
EXHAUST VENTS,
SEE MECHANICAL
J.2 XH X6.5
PAINTED METAL STAIR
SF‐2
T.O. ROOF SCREEN
(CLINIC)
123' ‐ 6"
PARAPET (FLR 1 LOW)
116' ‐ 8"
FLOOR 1 (4910.25')
100' ‐ 0"
XA XD XF XG
MP2
SF‐2
MP2
BL‐2
MC
PAINTED METAL FENCE
X6.5 XH J.2
EIFS‐1 EIFS‐1
EIFS‐2
INTERIOR CORRIDOR
PAINTED METAL CANOPY
T.O. ROOF SCREEN
(CLINIC)
123' ‐ 6"
PARAPET (FLR 1 LOW)
116' ‐ 8"
FLOOR 1 (4910.25')
100' ‐ 0"
X1 X3
GV
MP2
FLOOR 1 (4910.25')
100' ‐ 0"
FLOOR 2
115' ‐ 4"
X3 X2.5 X2 X1.3 X1 10.0 9.7 7.9 7
14' ‐ 0"
SF‐2
EIFS‐1
EIFS‐2
MP2
EIFS‐1
GV EIFS‐2
SF‐1
BL‐1 MP1
BL‐1
MP1
MP2
FUEL TANK SCREEN SECURITY GATE PAINTED METAL FENCE
MP2
BL‐2
STONE VENEER (COLOR AND FINISH TBD)
CMU BLOCK VENEER (DARK COLOR AND FINISH TBD)
(SEE SHEET 12 FOR COURSING DETAIL)
CMU BLOCK VENEER (LIGHT COLOR AND FINISH TBD)
(SEE SHEET 12 FOR COURSING DETAIL)
SPLIT FACE VENEER ( DARK COLOR AND FINISH TBD )
(SEE SHEET 13 FOR COURSING DETAIL)
SPLIT FACE VENEER ( LIGHT COLOR AND FINISH TBD )
(SEE SHEET 13 FOR COURSING DETAIL)
ZINC METAL PANEL (WALL)
PREFINISHED METAL PANEL (SCREEN)
EIFS (LIGHT COLOR AND FINISH TBD)
EIFS (DARK COLOR AND FINISH TBD)
METAL PARAPET CAP
PRECAST CONCRETE PARAPET CAP (COLOR AND FINISH TBD)
ROOF MEMBRANE
METAL PANEL CANOPY ROOF FASCIA
VERTICAL SUN SHADE
HORIZONTAL SUN SHADE
VERTICAL GLASS SHADE
ST
BL1
BL2
MP1
MP2
EIFS‐1
MC
SS1
SS2
SS3
RM
PC
SF1
SF2
EIFS‐2
SS
CJ
HORIZONTAL CONTROL JOINT
PROVIDE CUSTOM SEALANT COLOR TO
MATCH VENEER. SEE DETAILS:
SANDBLASTED (COLOR A: TBD)
GROUNDFACE (COLOR A: TBD)
GROUNDFACE (COLOR B: TBD)
SANDBLASTED (COLOR B: TBD)
GROUNDFACE (COLOR C: TBD)
SANDBLASTED (COLOR C: TBD)
GROUNDFACE (COLOR D: TBD)
HORIZONTAL WORK POINT A HORIZONTAL WORK POINT B
VERTICAL WORK POINT A
VERTICAL WORK POINT B
30' ‐ 0"
12"
12"
12"
12"
12"
12"
12"
12"
12"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
4"
4"
4"
4"
4"
4"
4"
4" 4"
4" 4"
4"
4"
4"
4"
SANDBLASTED (COLOR E: TBD)
GROUNDFACE (COLOR E: TBD)
GROUNDFACE (COLOR F: TBD)
SANDBLASTED (COLOR F: TBD)
GROUNDFACE (COLOR G: TBD)
SANDBLASTED (COLOR G: TBD)
GROUNDFACE (COLOR H: TBD)
HORIZONTAL WORK POINT A HORIZONTAL WORK POINT B
VERTICAL WORK POINT A
VERTICAL WORK POINT B
30' ‐ 0"
12"
12"
12"
12"
12"
12"
12"
12"
12"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
4"
4"
4"
4"
4"
4"
4"
4" 4"
4" 4"
4"
4"
4"
4"
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
N O R T H
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FINAL PLAN
TTLBv.101213
SHEET:
8/8/2013 8:54:59 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
PHASE 1 - ELEVATIONS
13 OF 13
1/4" = 1'‐0"
COURSING ELEVATION CMU BLOCK 1 (BL1)
1/4" = 1'‐0"
COURSING ELEVATION CMU BLOCK 2 (BL2)
BLOCK:
EIFS:
VERTICAL CONTROL JOINT
PROVIDE CUSTOM SEALANT COLOR TO
MATCH VENNER. SEE DETAILS:
BLOCK:
EIFS:
CJ
VISION GLAZING
SPANDREL GLAZING
GV
GS
SPLITFACE (COLOR A: TBD)
SPLITFACE (COLOR B: TBD)
HORIZONTAL WORK POINT A HORIZONTAL WORK POINT B
VERTICAL WORK POINT A
VERTICAL WORK POINT B
30' ‐ 0"
16' ‐ 0"
12"
12"
12"
12"
12"
12"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
4"
4"
4" 4"
4" 4"
4"
4"
4"
4"
SPLITFACE (COLOR E: TBD)
SPLITFACE (COLOR F: TBD)
HORIZONTAL WORK POINT A HORIZONTAL WORK POINT B
VERTICAL WORK POINT A
VERTICAL WORK POINT B
30' ‐ 0"
16' ‐ 0"
12"
12"
12"
12"
12"
12"
8"
8"
8"
8"
8"
8"
8"
8"
8"
8"
4"
4"
4" 4"
4" 4"
4"
4"
4"
4"
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
FINAL PLAN
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
TTLBv.101213
SHEET:
8/8/2013 10:03:45 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
PHASE 1 - ELEVATIONS
12 OF 13
12 OF 13 1/8" = 1'‐0"
1 NORTH ELEVATION ‐ EAST END
EXTERIOR ELEVATIONS ‐ MATERIAL LEGEND
PROJECT
NORTH
PHASE 1
ELEVATION
KEY PLAN
PHASE 1
FULL
BUILD
FULL
BUILD
FULL
BUILD
COURSING LEGEND SPLIT FACE ‐ 1 (SF1)
COURSING LEGEND SPLIT FACE ‐ 2 (SF2)
NOTE:
SIGNAGE IS NOT APPROVED THROUGH THE FINAL
PLAN. ALL SIGNAGE WILL RECEIVE A SEPARATE
SIGN PERMIT FOR APPROVAL
MP2
10.0
CJ CJ
CJ
CJ CJ CJ CJ CJ CJ
EIFS‐1
T.O. ROOF SCREEN
(CLINIC)
123' ‐ 6"
PARAPET (FLR 1 LOW)
116' ‐ 8"
EIFS‐2
STONE VENEER (COLOR AND FINISH TBD)
CMU BLOCK VENEER (DARK COLOR AND FINISH TBD)
(SEE SHEET 8 FOR COURSING DETAIL)
CMU BLOCK VENEER (LIGHT COLOR AND FINISH TBD)
(SEE SHEET 8 FOR COURSING DETAIL)
SPLIT FACE VENEER ( DARK COLOR AND FINISH TBD )
(SEE SHEET 9 FOR COURSING DETAIL)
SPLIT FACE VENEER ( LIGHT COLOR AND FINISH TBD )
(SEE SHEET 9 FOR COURSING DETAIL)
ZINC METAL PANEL (WALL)
PREFINISHED METAL PANEL (SCREEN)
EIFS (LIGHT COLOR AND FINISH TBD)
EIFS (DARK COLOR AND FINISH TBD)
METAL PARAPET CAP
PRECAST CONCRETE PARAPET CAP (COLOR AND FINISH TBD)
ROOF MEMBRANE
METAL PANEL CANOPY ROOF FASCIA
VERTICAL SUN SHADE
HORIZONTAL SUN SHADE
VERTICAL GLASS SHADE
GLAZING ‐ VISION
GLAZING ‐ SPANDREL
ST
BL1
BL2
MP1
MP2
EIFS‐1
MC
SS1
SS2
SS3
RM
PC
SF1
SF2
EIFS‐2
SS
CJ
HORIZONTAL CONTROL JOINT
PROVIDE CUSTOM SEALANT COLOR TO
MATCH VENEER. SEE DETAILS:
BLOCK:
EIFS:
VERTICAL CONTROL JOINT
PROVIDE CUSTOM SEALANT COLOR TO
MATCH VENNER. SEE DETAILS:
BLOCK:
EIFS:
CJ
GV
GS
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
FINAL PLAN
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
TTLBv.101213
SHEET:
8/8/2013 9:59:36 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
PHASE 1 - ELEVATIONS
11 OF 13
11 OF 13 1/8" = 1'‐0"
1 CUP EAST ELEVATION
11 OF 13 1/8" = 1'‐0"
2 CUP WEST ELEVATION
11 OF 13 1/8" = 1'‐0"
3 CUP SOUTH ELEVATION
PROJECT
NORTH
PHASE 1
ELEVATION
KEY PLAN
PHASE 1
FULL
BUILD
FULL
BUILD
FULL
BUILD
EXTERIOR ELEVATIONS ‐ MATERIAL LEGEND
1
2
3
NOTE:
SIGNAGE IS NOT APPROVED THROUGH THE FINAL
PLAN. ALL SIGNAGE WILL RECEIVE A SEPARATE
SIGN PERMIT FOR APPROVAL
(SEE SHEET 13 FOR COURSING DETAIL)
SPLIT FACE VENEER ( LIGHT COLOR AND FINISH TBD )
(SEE SHEET 13 FOR COURSING DETAIL)
ZINC METAL PANEL (WALL)
PREFINISHED METAL PANEL (SCREEN)
EIFS (LIGHT COLOR AND FINISH TBD)
EIFS (DARK COLOR AND FINISH TBD)
METAL PARAPET CAP
PRECAST CONCRETE PARAPET CAP (COLOR AND FINISH TBD)
ROOF MEMBRANE
METAL PANEL CANOPY ROOF FASCIA
VERTICAL SUN SHADE
HORIZONTAL SUN SHADE
VERTICAL GLASS SHADE
ST
BL1
BL2
MP1
MP2
EIFS‐1
MC
SS1
SS2
SS3
RM
PC
SF1
SF2
EIFS‐2
SS
CJ
HORIZONTAL CONTROL JOINT
PROVIDE CUSTOM SEALANT COLOR TO
MATCH VENEER. SEE DETAILS:
BLOCK:
EIFS:
VERTICAL CONTROL JOINT
PROVIDE CUSTOM SEALANT COLOR TO
MATCH VENNER. SEE DETAILS:
BLOCK:
EIFS:
CJ
VISION GLAZING
SPANDREL GLAZING
GV
GS
FLOOR 1 (4910.25')
100' ‐ 0"
FLOOR 2
115' ‐ 4"
Q P N M K
LOW CANOPY ROOF
112' ‐ 0"
Q.5
EIFS‐2 EIFS‐2
EIFS‐2
EIFS‐1 EIFS‐1
EIFS‐1
MC
MC MC MC
MC
MP1
MP1 EIFS‐1
EIFS‐2
MP2
GS
GV
GV
GS
CJ CJ
CJ
CJ
CJ
CJ
CJ
CJ CJ CJ CJ
MC
PARAPET ( BED TOWER
3)
133' ‐ 0"
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
FINAL PLAN
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
TTLBv.101213
SHEET:
8/8/2013 9:50:39 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
PHASE 1 - ELEVATIONS
10 OF 13
10 OF 13 1/8" = 1'‐0"
1 EAST ELEVATION ‐ SOUTH D&T
10 OF 13 1/8" = 1'‐0"
2 EAST ELEVATION ‐ NORTH D&T
EXTERIOR ELEVATIONS ‐ MATERIAL LEGEND
PROJECT
NORTH
PHASE 1
ELEVATION
KEY PLAN
PHASE 1
FULL
BUILD
FULL
BUILD
FULL
BUILD
10 OF 13 1/8" = 1'‐0"
3 EAST ELEVATION ‐ BED TOWER
3
1
2
NOTE:
SIGNAGE IS NOT APPROVED THROUGH THE FINAL
PLAN. ALL SIGNAGE WILL RECEIVE A SEPARATE
SIGN PERMIT FOR APPROVAL
HORIZONTAL SUN SHADE
VERTICAL GLASS SHADE
GLAZING ‐ VISION
GLAZING ‐ SPANDREL
ST
BL1
BL2
MP1
MP2
EIFS‐1
MC
SS1
SS2
SS3
RM
PC
SF1
SF2
EIFS‐2
SS
CJ
HORIZONTAL CONTROL JOINT
PROVIDE CUSTOM SEALANT COLOR TO
MATCH VENEER. SEE DETAILS:
BLOCK:
EIFS:
VERTICAL CONTROL JOINT
PROVIDE CUSTOM SEALANT COLOR TO
MATCH VENNER. SEE DETAILS:
BLOCK:
EIFS:
CJ
GV
GS
FLOOR 1 (4910.25')
100' ‐ 0"
FLOOR 2
115' ‐ 4"
6.7 7.9 8.0 9.0 9.7 10.0
MP2
MP1
EIFS‐1
EIFS‐2
GV GV
GS GV GS GV
MP1
MC
MC
SS2
SS2
SS2
SS2
SS2 SS2
PARAPET ( BED TOWER
3)
133' ‐ 0"
FLOOR 1 (4910.25')
100' ‐ 0"
FLOOR 2
115' ‐ 4"
PARAPET (TOWER 1)
144' ‐ 8"
J K L M N P Q
LOW CANOPY ROOF
112' ‐ 0"
PARAPET (BED TOWER
2)
134' ‐ 0"
K.5
SS3
SS3
SS3
SS3
SF‐1 SF‐1
MP2
BL‐1
BL‐1
PC
MC
LOBBY
PC
GV
GS
GS
I J.2 Q.5
SS1 SS1
SS1
BL‐1
SF‐1 GV
GV
MP1
PC
GV
GS
GV
GS
T.O. ROOF SCREEN
(BED TOWER 1)
146' ‐ 1 1/2"
T.O. ROOF SCREEN
(BED TOWER 2)
139' ‐ 9 1/2"
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
N O R T H
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FINAL PLAN
TTLBv.101213
SHEET:
8/8/2013 8:52:26 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
PHASE 1 - ELEVATIONS
9 OF 13
9 OF 13 1/8" = 1'‐0"
2 SOUTH ELEVATION ‐ WEST BED TOWER
PROJECT
NORTH
PHASE 1
ELEVATION
KEY PLAN
PHASE 1
FULL
BUILD
FULL
BUILD
FULL
BUILD
EXTERIOR ELEVATIONS ‐ MATERIAL LEGEND
9 OF 13 1/8" = 1'‐0"
3 SOUTH ELEVATION ‐ EAST BED TOWER
9 OF 13 1/8" = 1'‐0"
1 WEST ELEVATION
1
23
NOTE:
SIGNAGE IS NOT APPROVED THROUGH THE FINAL
PLAN. ALL SIGNAGE WILL RECEIVE A SEPARATE
SIGN PERMIT FOR APPROVAL
GV
GV
GS
GV
MP1 GS ST
BL‐1
SF‐1
MP1
MP1
MC PC
GV
PARAPET (ENTRY)
128' ‐ 0"
PARAPET (LOW
CANOPY ROOF)
113' ‐ 6"
T.O. ROOF SCREEN
(CLINIC)
123' ‐ 6"
FLOOR 1 (4910.25')
100' ‐ 0"
PARAPET(FLOOR 1)
117' ‐ 8"
ZF ZE ZD ZC.4
9' ‐ 0"
EIFS‐2 EIFS‐2
MP2
MC
EIFS‐1
GV
T.O. ROOF SCREEN
(CLINIC)
123' ‐ 6"
STONE VENEER (COLOR AND FINISH TBD)
CMU BLOCK VENEER (DARK COLOR AND FINISH TBD)
(SEE SHEET 12 FOR COURSING DETAIL)
CMU BLOCK VENEER (LIGHT COLOR AND FINISH TBD)
(SEE SHEET 12 FOR COURSING DETAIL)
SPLIT FACE VENEER ( DARK COLOR AND FINISH TBD )
(SEE SHEET 13 FOR COURSING DETAIL)
SPLIT FACE VENEER ( LIGHT COLOR AND FINISH TBD )
(SEE SHEET 13 FOR COURSING DETAIL)
ZINC METAL PANEL (WALL)
PREFINISHED METAL PANEL (SCREEN)
EIFS (LIGHT COLOR AND FINISH TBD)
EIFS (DARK COLOR AND FINISH TBD)
METAL PARAPET CAP
PRECAST CONCRETE PARAPET CAP (COLOR AND FINISH TBD)
ROOF MEMBRANE
METAL PANEL CANOPY ROOF FASCIA
VERTICAL SUN SHADE
HORIZONTAL SUN SHADE
VERTICAL GLASS SHADE
ST
BL1
BL2
MP1
MP2
EIFS‐1
MC
SS1
SS2
SS3
RM
PC
SF1
SF2
EIFS‐2
SS
CJ
HORIZONTAL CONTROL JOINT
PROVIDE CUSTOM SEALANT COLOR TO
MATCH VENEER. SEE DETAILS:
BLOCK:
EIFS:
VERTICAL CONTROL JOINT
PROVIDE CUSTOM SEALANT COLOR TO
MATCH VENNER. SEE DETAILS:
BLOCK:
EIFS:
CJ
VISION GLAZING
SPANDREL GLAZING
GV
GS
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
N O R T H
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FINAL PLAN
TTLBv.101213
SHEET:
8/8/2013 8:48:14 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
PHASE 1 - ELEVATIONS
8 OF 13
8 OF 13 1/8" = 1'‐0"
1 WEST ELEVATION ‐ CLINIC
8 OF 13 1/8" = 1'‐0"
2 SOUTH ELEVATION ‐ CLINIC & LOBBY
8 OF 13 1/8" = 1'‐0"
3 EAST ELEVATION ‐ CLINIC
PROJECT
NORTH
PHASE 1
ELEVATION
KEY PLAN
PHASE 1
FULL
BUILD
FULL
BUILD
FULL
BUILD
EXTERIOR ELEVATIONS ‐ MATERIAL LEGEND
1
2
3
2
NOTE:
SIGNAGE IS NOT APPROVED THROUGH THE FINAL
PLAN. ALL SIGNAGE WILL RECEIVE A SEPARATE
SIGN PERMIT FOR APPROVAL
EIFS‐1
T.O. ROOF SCREEN
(D&T)
146' ‐ 7 1/2"
PARAPET (TOWER 2)
143' ‐ 8"
PARAPET (ENTRY)
128' ‐ 0"
BL‐2
FLOOR 1 (4910.25')
100' ‐ 0"
FLOOR 2
115' ‐ 4"
PARAPET (D&T 2)
134' ‐ 8"
A A.2 B C D E F G G.5 H
MP1
SF‐1
BL‐1
MP1
ST
ST
MP2
SS3
BL‐2
ST
MP1
MP1
MC MC
ST
MP1
SF‐1 SF‐2
BL‐1
SF‐1
BL‐1
BL‐1
SF‐1
EIFS‐2
EIFS‐1
PC
PC
PC
12' ‐ 0"
SIGNAGE, BY
OWNER, SEE
ELECTRICAL FOR
POWER
MP1
PC PC
GS GV
GS GV
GV
GS
GS
GS GV
GS GV
GS
GV
GS
GS
14' ‐ 0"
T.O. ROOF SCREEN
(D&T)
146' ‐ 7 1/2"
PARAPET (ENTRY)
128' ‐ 0"
PARAPET (LOW
CANOPY ROOF)
113' ‐ 6"
MP1
FLOOR 1 (4910.25')
100' ‐ 0"
Z3 Z2 Z1
PARAPET(FLOOR 1)
117' ‐ 8"
Z7 Z6 Z5 Z4
ST
ST
SF‐1
SF‐1
SF‐1
BL‐1
MP1
BL‐1 BL‐1
SS3
MP1 MP1
MP1
ST
BL‐1
MP1
ST ST
SF‐1 SF‐1
MC
ST
MP2
MP1
PC
MC PC MC
PC PC
PC
GV
GS
GV
GS GS
GV GV
14' ‐ 0"
PARAPET (ENTRY)
128' ‐ 0"
T.O. ROOF SCREEN
(CLINIC)
123' ‐ 6"
BOULDER ASSOCIATES ARCHITECTS 1426 PEARL ST., SUITE 300 BOULDER, CO 303.499.7795
FORT COLLINS, COLORADO
BANNER HEALTH MEDICAL CAMPUS
HARMONY RD. & LADY MOON DR.
FINAL PLAN
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, Colorado 80525
voice: 970.223.7577
fax: 970.223.1827
TTLBv.101213
SHEET:
8/8/2013 9:45:08 AM C:\Revit Local Files\122114 A12-Central_mfiore.rvt
REV. AUG. 9, 2013
PHASE 1 - ELEVATIONS
7 OF 13
7 OF 13 1/8" = 1'‐0"
1 NORTH ELEVATION ‐ EAST END
7 OF 13 1/8" = 1'‐0"
2 WEST ELEVATION ‐ NORTH END
PROJECT
NORTH
PHASE 1
ELEVATION
KEY PLAN
PHASE 1
FULL
BUILD
FULL
BUILD
FULL
BUILD
7 OF 13 1/8" = 1'‐0"
3 NORTH ELEVATION ‐ WEST END
1
2
3
NOTE:
SIGNAGE IS NOT APPROVED THROUGH THE FINAL
PLAN. ALL SIGNAGE WILL RECEIVE A SEPARATE
SIGN PERMIT FOR APPROVAL
METAL PANEL MECHANICAL SCREEN
MECHANICAL SCREEN
STOREFRONT WINDOW
EIFS, COLOR 2
MASONRY, TYPE 1
MASONRY, TYPE 1
MASONRY, TYPE 1A
EIFS, COLOR 1
EIFS, COLOR 2
MASONRY, TYPE 1A
CURTAIN WALL
MASONRY, TYPE 1
MASONRY, TYPE 1A
METAL PANEL
TRASH ENCLOSURE
WALK‐IN DOOR
MASONRY, TYPE 1A
CURTAIN WALL
WALK‐IN DOOR
TRASH ENCLOSURE ACCESS,
METAL DOOR
EIFS, COLOR 2
MASONRY, TYPE 1
MASONRY,
TYPE 1A
MASONRY, TYPE 1A
CURTAIN WALL
EIFS, COLOR 2
MASONRY, TYPE 1
MASONRY, TYPE 1A
MASONRY, TYPE 1
MASONRY, TYPE 1A
MASONRY PARAPET CAP MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
BIKE PARKING UNDER METAL
PANEL OVERHANG
MASONRY PARAPET CAP
MASONRY PARAPET CAP
FINAL PLAN NOTES
4. SIGNAGE IS NOT APPROVED THROUGH THE FINAL
PLAN. ALL SIGNAGE WILL RECEIVE A SEPARATE SIGN
PERMIT FOR APPROVAL
HORIZONTAL SUNSHADE, TYP. AT
ALL SOUTH FACING PATIENT ROOMS
METAL PANEL
EIFS, COLOR 1
STOREFRONT WINDOW
HORIZONTAL SUNSHADE, TYP. AT
ALL SOUTH FACING PATIENT ROOMS
METAL PANEL
HORIZONTAL
SUNSHADE
MASONRY, TYPE 1
CURTAIN WALL
METAL PANEL
MASONRY, TYPE 1
SUNSHADE, TYPICAL AT ALL EAST
FACING PATIENT ROOMS.
STOREFRONT WINDOW METAL PANEL
METAL PANEL MECHANICAL
SCREEN (TYP.)
MASONRY, TYPE 2
METAL PANEL
CURTAIN WALL
MASONRY, TYPE 1
CURTAIN WALL
METAL PANEL
MECHANICAL SCREEN
EIFS, COLOR 1
MASONRY, TYPE 2
STOREFRONT WINDOW
MASONRY, TYPE 1A
METAL PANEL
MASONRY, TYPE 1A
MASONRY, TYPE 2A
MASONRY, TYPE 1A
MASONRY, TYPE 2A
MASONRY, TYPE 1A
MASONRY, TYPE 2A
SUNSHADES PROJECT 3'
FROM FACE OF WALL (TYP.)
METAL PANEL
EIFS, COLOR 1
EIFS, COLOR 2
EIFS, COLOR 2 EIFS, COLOR 2
MASONRY, TYPE 1A
EIFS, COLOR 2
EIFS, COLOR 1
EIFS, COLOR 2 EIFS, COLOR 2
METAL PANEL MECHANICAL SCREEN
EIFS, COLOR 1
EIFS, COLOR 2
MASONRY, TYPE 1A
METAL PANEL
MECHANICAL SCREEN
SUNSHADE FIN
DIAGNOSTICS AND TREATMENT WALL SITS
APPROXIMATELY 80' BEYOND THE FACE OF THE
CENTRAL UTILITY PLAN. SEE NORTH ELEVATION FOR
OFFSET
MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
FINAL PLAN NOTES
THIS AREA REPRESENTS THE PORTION OF THE
BUILDING THAT WILL BE BUILT AS A PART OF PHASE 1.
REFER TO SHEET 8 FOR MORE DETAILED PHASE 1
ELEVATIONS FOR THIS AREA.
THIS AREA REPRESENTS THE PORTION OF THE
BUILDING THAT WILL BE BUILT AS A PART OF PHASE 1.
REFER TO SHEET 9 FOR MORE DETAILED PHASE 1
ELEVATIONS FOR THIS AREA.
THIS AREA REPRESENTS THE PORTION OF THE
BUILDING THAT WILL BE BUILT AS A PART OF PHASE 1.
REFER TO SHEET 11 FOR MORE DETAILED PHASE 1
ELEVATIONS FOR THIS AREA.
4. SIGNAGE IS NOT APPROVED THROUGH THE FINAL
PLAN. ALL SIGNAGE WILL RECEIVE A SEPARATE SIGN
PERMIT FOR APPROVAL
CANOPY
MASONRY, TYPE 1
MASONRY , TYPE 2
MASONRY, TYPE 1
CURTAIN WALL
CURTAIN WALL EIFS, COLOR 1
MECHANICAL
SCREEN
METAL PANEL
STONE
METAL PANEL
CURTAIN WALL STONE METAL PANEL
METAL PANEL CANOPY METAL PANEL
STOREFRONT
STOREFRONT WINDOW
CURTAIN WALL
STOREFRONT WINDOW
METAL PANEL
STOREFRONT WINDOW
BUILDING MOUNTED SIGNAGE
METAL PANEL MECHANICAL SCREEN
ROOF TOP MECHANICAL SCREEN
CANOPY MOUNTED
SIGNAGE
BUILDING MOUNTED SIGNAGE
ROOF TOP MECHANICAL SCREEN
SUNSHADE, TYPICAL AT ALL
WEST FACING PATIENT ROOMS
MASONRY, TYPE 1
BUILDING MOUNTED
SIGNAGE
MASONRY, TYPE 1A
MASONRY, TYPE 1A
MASONRY, TYPE 1A
MASONRY , TYPE 2A
METAL FENCE AND
SECURITY GATE
MASONRY, TYPE 1A
MASONRY, TYPE 2
MASONRY, TYPE 1A
MASONRY, TYPE 1
EIFS, COLOR 2
EIFS, COLOR 2
MASONRY, TYPE 1A
METAL PANEL MECHANICAL
SCREEN BEYOND (TYP.)
MASONRY, TYPE 1
METAL PANEL METAL PANEL
METAL PANEL CANOPY FOR STAFF
ENTRANCE AND BIKE PARKING
SUNSHADE FIN
MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
MASONRY PARAPET CAP
THIS AREA REPRESENTS THE PORTION OF THE
BUILDING THAT WILL BE BUILT AS A PART OF PHASE 1.
REFER TO SHEET 7 FOR MORE DETAILED PHASE 1
ELEVATIONS FOR THIS AREA.
THIS AREA REPRESENTS THE PORTION OF THE
BUILDING THAT WILL BE BUILT AS A PART OF PHASE 1.
REFER TO SHEET 7, 8 & 9 FOR MORE DETAILED PHASE 1
ELEVATIONS FOR THIS AREA.
FINAL PLAN NOTES
4. SIGNAGE IS NOT APPROVED THROUGH THE FINAL
PLAN. ALL SIGNAGE WILL RECEIVE A SEPARATE SIGN
PERMIT FOR APPROVAL