The Standard at Fort Collins
Approximate Construction Schedule
Start End
Closing 05/29/17 05/29/17
Off-site Public Improvements 05/30/17 08/1/17
Demo & Abatement 06/26/17 08/18/17
Site Grading 08/21/17 09/29/17
Foundation Work 10/02/17 02/16/18
Vertical Construction, Interior
Work, and Site Improvements
11/6/17 06/30/19
Construction Complete 06/30/19 06/30/19
The project is proposed to be completed in one phase.
Dates shown are approximate and may be updated as
the project approaches the start of construction.