Loading...
HomeMy WebLinkAboutTHE STANDARD AT FORT COLLINS - PDP - PDP160035 - SUBMITTAL DOCUMENTS - ROUND 1 - SUPPORTING DOCUMENTATION (2)October 19, 2016 The Standard at Fort Collins Approximate Construction Schedule Start End Closing 05/29/17 05/29/17 Off-site Public Improvements 05/30/17 08/1/17 Demo & Abatement 06/26/17 08/18/17 Site Grading 08/21/17 09/29/17 Foundation Work 10/02/17 02/16/18 Vertical Construction, Interior Work, and Site Improvements 11/6/17 06/30/19 Construction Complete 06/30/19 06/30/19 The project is proposed to be completed in one phase. Dates shown are approximate and may be updated as the project approaches the start of construction.