HomeMy WebLinkAboutSTADIUM APARTMENTS (FORMERLY LAKE STREET APARTMENTS) - FDP - FDP160037 - SUBMITTAL DOCUMENTS - ROUND 1 - DRAINAGE REPORTFINAL DRAINAGE REPORT Stadium Apartments Fort Collins, Colorado September 19, 2016 Prepared for: Student Housing CSU LLC 2607 Monroe Street Madison, WI 53711 Prepared by: 301 North Howes Street, Suite 100 Fort Collins, Colorado 80521 Phone: 970.221.4158 Fax: 970.221.4159 www.northernengineering.com Project Number: 1232-001 P This Drainage Report is consciously provided as a PDF. Please consider the environment before printing this document in its entirety. When a hard copy is absolutely necessary, we recommend double-sided printing. September 19, 2016 City of Fort Collins Stormwater Utility 700 Wood Street Fort Collins, Colorado 80521 RE: Final Drainage Report for Stadium Apartments Dear Staff: Northern Engineering is pleased to submit this Preliminary Drainage and Erosion Control Report for your review. This report accompanies the Preliminary Development Review submittal for the proposed Stadium Apartments. Comments from the Preliminary Development Review Letter dated April 15, 2016 have been addressed. Written responses thereto can be found in the comprehensive response to comments letter on file with Current Planning. This report has been prepared in accordance to Fort Collins Stormwater Criteria Manual (FCSCM), and serves to document the stormwater impacts associated with the proposed Stadium Apartments project. We understand that review by the City is to assure general compliance with standardized criteria contained in the FCSCM. If you should have any questions as you review this report, please feel free to contact us. Sincerely, NORTHERN ENGINEERING SERVICES, INC. Nicholas W. Haws, PE Cody Snowdon Project Manager Project Engineer Stadium Apartments Final Drainage Report TABLE OF CONTENTS I. GENERAL LOCATION AND DESCRIPTION ................................................................... 1 A. Location ....................................................................................................................................... 1 B. Description of Property ................................................................................................................ 2 C. Floodplain .................................................................................................................................... 3 II. DRAINAGE BASINS AND SUB-BASINS ....................................................................... 5 A. Major Basin Description ............................................................................................................... 5 B. Sub-Basin Description .................................................................................................................. 5 III. DRAINAGE DESIGN CRITERIA ................................................................................... 5 A. Regulations .................................................................................................................................. 5 B. Four Step Process ........................................................................................................................ 5 C. Development Criteria Reference and Constraints ......................................................................... 6 D. Hydrological Criteria .................................................................................................................... 7 E. Hydraulic Criteria ......................................................................................................................... 7 F. Floodplain Regulations Compliance .............................................................................................. 7 G. Modifications of Criteria .............................................................................................................. 7 IV. DRAINAGE FACILITY DESIGN .................................................................................... 7 A. General Concept .......................................................................................................................... 7 B. Specific Details ............................................................................................................................. 9 V. CONCLUSIONS ...................................................................................................... 12 A. Compliance with Standards ........................................................................................................ 12 B. Drainage Concept ...................................................................................................................... 12 References ....................................................................................................................... 13 APPENDICES: APPENDIX A – Hydrologic Computations APPENDIX B – Hydraulic Computations B.1 – Storm Sewers (For Future Use) B.2 – Inlets (For Future Use) B.3 – Detention Facilities (For Future Use) APPENDIX C – Water Quality Design Computations APPENDIX D – Erosion Control Report Stadium Apartments Final Drainage Report LIST OF TABLES AND FIGURES: Figure 1 – Aerial Photograph ................................................................................................ 2 Figure 2 – Proposed Site Plan ............................................................................................... 3 Figure 3 – Existing FEMA Floodplains .................................................................................... 4 Figure 4 – Existing City Floodplains ....................................................................................... 4 MAP POCKET: C8.00 - Drainage Exhibit C8.01 – Historic Drainage Exhibit Stadium Apartments Final Drainage Report 1 I. GENERAL LOCATION AND DESCRIPTION A. Location 1. Vicinity Map 2. Stadium Apartments project is located in the southwest quarter of Section 14, Township 7 North, Range 69 West of the 6th Principal Meridian, City of Fort Collins, County of Larimer, State of Colorado. 3. The project site is located south of Lake Street and is composed of two properties, 821 and 801 West Lake Street. 4. Currently the existing lots does not have any stormwater or water quality facilities. The western property consisted of Beebe Christian School and is composed of an existing building, parking lot and associated walks. The eastern property consist of a single family residence with a gravel drive and associated walks and accessory buildings. The project site is composed of 26% imperviousness. The existing site all drains from the southwest corner of the property to the northeast corner and into West Lake Street. 5. The project is currently bordered to the south by single family residences, west by Plymouth Congregational Church, north by West Lake Street and east by Blue Ridge Apartments. Stadium Apartments Final Drainage Report 2 B. Description of Property 1. Stadium Apartments is approximately 2.45 net acres. Figure 1 – Aerial Photograph 2. Stadium Apartments consists of two properties with two existing structures and multiple out buildings. The western lot consist of Beebe Christian School with a parking lot and associated sidewalks. The eastern lot consist of a single family residence with a gravel driveway, multiple accessory buildings and associated sidewalks. There is not off-site drainage entering the existing properties. All runoff generated from the project drains from the southwest corner of the site to the northeast corner and is discharged into West Lake Street. 3. According to the United States Department of Agriculture (USDA) Natural Resources Conservation Service (NRCS) Soil Survey, 100 percent of the site consists of Altvan- Satanta loam, which falls into Hydrologic Soil Groups B. 4. The proposed development will include the demolition of the existing structures, parking lot, gravel drive and associated sidewalks. The proposed project will include one large multi-family building, an exterior parking lots and associated drive aisle and sidewalks. The exterior parking lot is planned to be composed of StormTech chambers underneath the paving. The section of drive constructed on top of the StormTech Chambers will act as a portion of the project’s water quality and detention facility. Surrounding green space will act as the remaining water quality and detention facility. Stadium Apartments Final Drainage Report 3 Figure 2– Proposed Site Plan 5. No irrigation facilities or major drainageways are within the property limits. 6. The project site is within the High Density Mixed-Use Neighborhood District (H-M-N) Zoning District. The proposed use is permitted within the zone district. C. Floodplain 1. The subject property is not located in a FEMA or City regulatory floodplain. 2. The FEMA Panel 0801010979H illustrates the proximity of the project site to the nearest FEMA delineated regulatory floodplain. It is noted that the vertical datum utilized for site survey work is the City of Fort Collins Benchmark #29-92 Elevation = 5025.67 (NAVD 88) Stadium Apartments Final Drainage Report 4 Figure 3 – Existing FEMA Floodplains Figure 4 – Existing City Floodplains Stadium Apartments Final Drainage Report 5 II. DRAINAGE BASINS AND SUB-BASINS A. Major Basin Description 1. Stadium Apartments is located within the Old Town Basin, which is located primarily in Old Town Fort Collins. B. Sub-Basin Description 1. The property historically drains from the southwest corner of the western lot to the northeast corner of the eastern lot. Stormwater is routed via overland flow across the existing lots. The project only consists of one basin; Basin H1. Stormwater is historically discharged directly into West Lake Street (1.75 cfs for the 2-year storm and 8.15 cfs for the 100-year event). A more detailed description of the projects proposed drainage patterns follows in Section IV.A.4., below. 2. No drainage is routed onto the property from the surrounding properties. A full-size copy of the Historic and Proposed Drainage Exhibit can be found in the Map Pocket at the end of this report. III. DRAINAGE DESIGN CRITERIA A. Regulations There are no optional provisions outside of the FCSCM proposed with the Stadium Apartments project. B. Four Step Process The overall stormwater management strategy employed with the Stadium Apartments project utilizes the “Four Step Process” to minimize adverse impacts of urbanization on receiving waters. The following is a description of how the proposed development has incorporated each step. Step 1 – Employ Runoff Reduction Practices Several techniques have been utilized with the proposed development to facilitate the reduction of runoff peaks, volumes, and pollutant loads as the site is developed from the current use by implementing multiple Low-Impact Development (LID) strategies including: Selecting a site that has been previously developed and currently consist of a School building and single family residence, an asphalt parking lot, gravel access drive and associated sidewalks. Providing vegetated open areas along the north, south and east portion of the site to reduce the overall impervious area and to minimize directly connected impervious areas (MDCIA). Routing flows, to the extent feasible, through drain rock both within the underground detention section to increase time of concentration, promote infiltration and provide initial water quality. Routing runoff through the drain rock within the underground detention area to increase time of concentration, promote infiltration and provide water quality. Stadium Apartments Final Drainage Report 6 Step 2 – Implement BMPs That Provide a Water Quality Capture Volume (WQCV) with Slow Release The efforts taken in Step 1 will facilitate the reduction of runoff; however, this development will still generate stormwater runoff that will require additional BMPs and water quality. Stormwater generated from the southeast corner of property and the courtyard located within the center area of the building will be routed through an extended detention pond for water quality. Stormwater generated from the roof is routed directly into isolator rows located in the underground detention sections and drains through the drain rock surrounding the chambers. Stormwater generated from the majority of the parking area will be routed via overland flow to an area inlet located south of the parking area. The stormwater will then be routed directly into isolator rows located in the underground detention sections and drains through the drain rock surrounding the chambers. Stormwater generated from the area to the north of the building will be routed through an extended detention pond for water quality. The areas running off-site to the west and the east only consist of landscape area and will be routed across landscape before leaving the site. Step 3 – Stabilize Drainageways As stated in Section I.B.5, above, there are no major drainageways in or near the subject site. While this step may not seem applicable to Stadium Apartments, the proposed project indirectly helps achieve stabilized drainageways nonetheless. Once again, site selection has a positive effect on stream stabilization. By repurposing an already developed, under-utilized site with existing stormwater infrastructure, combined with LID, the likelihood of bed and bank erosion is greatly reduced. Furthermore, this project will pay one-time stormwater development fees, as well as ongoing monthly stormwater utility fees, both of which help achieve Citywide drainageway stability. Step 4 – Implement Site Specific and Other Source Control BMPs. This step typically applies to industrial and commercial developments and is not applicable for this project. C. Development Criteria Reference and Constraints 1. There are no known drainage studies for the existing properties. 2. There are no known drainage studies for any adjacent properties that will have any effect on the Stadium Apartments project. 3. The subject property is essentially an "in-fill" development project as the property is surrounded by currently developed properties. As such, several constraints have been identified during the course of this analysis that will impact the proposed drainage system including: Existing elevations along the north property lines adjacent to the West Lake Street will be maintained. Existing elevations along the south and west will also be maintained. Areas along the eastern property line will be raised through use of a landscape wall. Existing vegetation along a portion of the east and west sides of the subject property will be preserved. As previously mentioned, overall drainage patterns of the existing site will be maintained. Stadium Apartments Final Drainage Report 7 D. Hydrological Criteria 1. The City of Fort Collins Rainfall Intensity-Duration-Frequency Curves, as depicted in Figure RA-16 of the FCSCM, serve as the source for all hydrologic computations associated with this development. Tabulated data contained in Table RA-7 has been utilized for Rational Method runoff calculations. 2. The Rational Method has been employed to compute stormwater runoff utilizing coefficients contained in Tables RO-11 and RO-12 of the FCSCM. 3. The Rational Formula-based Modified Federal Aviation Administration (FAA) procedure has been utilized for detention storage calculations. 4. Three separate design storms have been utilized to address distinct drainage scenarios. A fourth design storm has also been computed for comparison purposes. The first design storm considered is the 80th percentile rain event, which has been employed to design the project’s water quality features. The second event analyzed is the “Minor,” or “Initial” Storm, which has a 2-year recurrence interval. The third event considered is the “Major Storm,” which has a 100-year recurrence interval. The fourth storm computed, for comparison purposes only, is the 10-year event. 5. No other assumptions or calculation methods have been used with this development that are not referenced by current City of Fort Collins criteria. E. Hydraulic Criteria 1. As previously noted, the subject property historically drains into West Lake Street. The majority of the site drains stormwater via overland flow. 2. All drainage facilities proposed with the Stadium Apartments project are designed in accordance with criteria outlined in the FCSCM and/or the Urban Drainage and Flood Control District’s (UDFCD) Urban Storm Drainage Criteria Manual. 3. As stated in Section I.C.1, above, the subject property is not located within any regulatory floodplain. 4. The Stadium Apartments project does not propose to modify any natural drainageways. F. Floodplain Regulations Compliance 1. As previously mentioned, all structures are located outside of any FEMA 100-year or City floodplain, and thus are not subject to any floodplain regulations. G. Modifications of Criteria 1. The proposed Stadium Apartments development is not requesting any modification at this time. IV. DRAINAGE FACILITY DESIGN A. General Concept 1. The main objectives of the Stadium Apartments drainage design are to maintain existing drainage patterns and ensure no adverse impacts to any adjacent properties. 2. As previously mentioned, there are no off-site flows draining onto the existing property. Stadium Apartments Final Drainage Report 8 3. A list of tables and figures used within this report can be found in the Table of Contents at the front of the document. The tables and figures are located within the sections to which the content best applies. 4. The Stadium Apartments project is composed of five major drainage basins, designated as Basins A, B, C, D and OS. The drainage patterns for each major basin are further described below. Basin A Basin A is further subdivided into two (2) sub-basins, designated as Basins A1 and A2. Sub-basin A1 is composed primarily of the area located southeast of the building and consists of landscape surfacing. Stormwater generated from this sub-basin is routed via overland and swale flow and discharges directly into Pond A. Sub-basin A2 is composed entirely of the courtyard internal to the building and consists of some landscape surfacing, but predominantly hardscape. Stormwater generated from this sub-basin is routed via overland flow within the courtyard and discharge through a pipe internal to the building and into Pond A. Basin B Basin B is further subdivided into four (4) sub-basins, designated as Basins B1, B2, B3 and B4. Sub-basin B1 is composed primarily of the parking area located south of the building and consists of some landscape surfacing. Stormwater generated from this sub-basin is routed via overland and gutter flow and discharges through curb cuts before being intercepted by an area inlet and routed into Underground Detention Pond B. Sub-basin B2 consists entirely of roof surface. Stormwater generated from this sub-basin is routed internal to the building through pipe flow and discharged directly into an isolator row within Underground Pond B. Sub-basin B3 is composed primarily of the parking area located southwest of the building and consists of some landscape surfacing, but predominantly hardscape. Stormwater generated from this sub-basin is routed via overland and gutter flow and discharges through sumped inlet directly into Underground Pond B. Sub-basin B4 consists entirely of roof surface. Stormwater generated from this sub-basin is routed internal to the building through pipe flow and discharged directly into an isolator row within Underground Pond B. Basin C Basin C is further subdivided into two (2) sub-basins, designated as Basins C1 and C2. Sub-basin C1 is composed primarily of the area located north of the building and consists primarily of landscape surfacing with some hardscape surfaces. Stormwater generated from this sub-basin is routed via overland and swale flow and discharges directly into the Underground Pond C. Sub-basin C2 is composed of a small drive area located towards the northwest corner of the building and consists primarily of hardscape. Stormwater generated from this sub-basin is routed via overland flow and is intercepted by a sidewalk culvert and discharged directly into Pond C. Basin D Basin D1 is composed of the drive area located northwest of the building and consists primarily of hardscape. Stormwater generated from this sub-basin is routed via overland flow and is intercepted by a sumped inlet and discharged directly into Underground Pond D. Stadium Apartments Final Drainage Report 9 Basin OS Basin OS is further subdivided into three (3) sub-basins, designated as Basins OS1, OS2 and OS3. Sub-basin OS1 is composed primarily of the area located northeast of the building and consists of landscape surfacing. Stormwater generated from this sub- basin is routed via overland flow and discharges undetained into West Lake Street. Sub-basin OS2 is composed of a small portion of the drive entrance and consists primarily of hardscape. Stormwater generated from this sub-basin is routed via overland flow and discharges undetained into West Lake Street. Sub-basin OS3 is composed primarily of the area west of the western parking area and consists of landscape surfacing. Stormwater generated from this sub-basin is routed via overland flow and discharges undetained into the Plymouth Congregational Church’s parking lot and ultimately discharging into West Lake Street. A full-size copy of the Drainage Exhibit can be found in the Map Pocket at the end of this report. B. Specific Details 1. The main drainage problem associated with this project site is the deficiency of water quality present within the existing site. Currently the entire site drains overland and discharges directly into the West Lake Street without water quality. The proposed site will mitigate this issue by instituting the following water quality devices: All of the runoff generated from the proposed building roof (Basin B3) will be routed into the drain rock surrounding the underground detention. The runoff generated from the majority of the proposed drive aisle and parking (Basins B and D) will be routed through an isolator row within the underground detention area. The remaining runoff (Basins A & C) will be routed to extended detention ponds. 2. The release rate for the undeveloped land (pre-development) was established by calculating the 2-year peak runoff rate for the entire project area and excluding all portions of the proposed project that release undetained (Sub-basins OS1, OS2 and OS3). The overall 2-year peak runoff rate was calculated at 1.75 cfs, resulting in a maximum release rate of 1.06 cfs from Basin A, B, C and D. This release rate was utilized in the FAA procedure detention storage computations (Refer to Appendix B for these calculations). 3. Detention Pond Calculations Pond A The FAA method was used to size the on-site ponds for quantity detention. Calculations for Pond A, based on the characteristics of Basin A and an adjusted release rate of 0.36 cfs, indicate a detention volume of 2,015 cu. ft. This does not included any Water Quality Capture Volume (WQCV) of 255 cu. ft., resulting in an overall detention volume of 2,270 cu. ft. Water quality will be treated through extended detention. Pond B Calculations for Pond B, based on the characteristics of Basin B and an adjusted release rate of 0.30 cfs, indicate a detention volume of 20,281 cu. ft. This volume includes the 12-hour release Water Quality Capture Volume (WQCV) calculated for Stadium Apartments Final Drainage Report 10 this basin (1,548 cu. ft.). During a Water Quality storm event, the Water Quality Capture Volume will be routed directly into an isolator row. The isolator rows were sized to capture either the 12-hour release Water Quality Capture Volume (WQCV) within the chambers and the surrounding aggregate or the volume required to detain the Water Quality storm event only within the chambers, whichever is greater. Pond C Calculations for Pond C, based on the characteristics of Basin C and an adjusted release rate of 0.20 cfs, indicate a detention volume of 697 cu. ft. This does not included any Water Quality Capture Volume (WQCV) of 147 cu. ft., resulting in an overall detention volume of 824 cu. ft. Pond D Calculations for Pond D, based on the characteristics of Basin D and an adjusted release rate of 0.20 cfs, indicate a detention volume of 991 cu. ft. This volume includes the 12-hour release Water Quality Capture Volume (WQCV) calculated for this basin (121 cu. ft.). During a Water Quality storm event, the Water Quality Capture Volume will be routed directly into an isolator row. The isolator rows were sized to capture either the 12-hour release Water Quality Capture Volume (WQCV) within the chambers and the surrounding aggregate or the volume required to detain the Water Quality storm event only within the chambers, whichever is greater. 4. Detention Pond Results Pond A The total storage available within Pond A is 2,486 cu. ft at a top of pond elevation of 5028.8 feet. The WQCV is achieved at a water surface elevation of 5027.6 feet, the 100-year detention volume is achieved at a water surface elevation of 5028.63 feet and the overall detention volume is achieved at a high water surface elevation of 5028.72 feet. There is a proposed landscape wall with a top of wall elevation of 5029.34 located along the eastern property line to allow for additional freeboard. Pond B The storage volume available within StormTech Vault Structure within Pond B is 20,297 cu. ft. This includes the volume stored in the aggregate surround the chambers. The achieve water quality, a total of 24 chambers are proposed to be wrapped and installed as isolator rows. The water quality volume achieved within isolator rows (aggregate included) is 1,598 cu. ft., while the volume achieved within only the chambers of the isolator row is 1,102 cu. ft. Pond C The total storage available within Pond C is 984 cu. ft at a top of pond elevation of 5026.4 feet. The WQCV is achieved at a water surface elevation of 5025.78 feet, the 100-year detention volume is achieved at a water surface elevation of 5026.25 feet and the overall detention volume is achieved at a high water surface elevation of 5026.32 feet. Stadium Apartments Final Drainage Report 11 Pond D The storage volume available within StormTech Vault Structure within Pond D is 992 cu. ft. This includes the volume stored in the aggregate surround the chambers. The achieve water quality, a total of 5 chambers are proposed to be wrapped and installed as isolator rows. The water quality volume achieved within isolator rows (aggregate included) is 147 cu. ft., while the volume achieved within only the chambers of the isolator row is 44 cu. ft. 5. Pond A was designed to overtop the pond in the northeast corner. In the case that the outlet structure should clog, stormwater would overtop and be routed north along the existing concrete wall/fence bordering the project site to the east. This stormwater will ultimately be routed and discharged into W. Lake Street. In the case that the area inlet within Sub-basin B4 should clog or backwatering should occur, stormwater would overtop from Sub-basin B1 into Sub-basin B2. The excess stormwater from this basin would continue to overtop and pass through Sub-Basins B2, D1, C2, and OS2 before it discharges directly into W. Lake Street. In the case that the curb inlet within Sub-basin B2 should clog or backwatering should occur, stormwater would overtop from Sub-basin B2 into Sub-basin D1. The excess stormwater from this basin would continue to overtop and pass through Sub-Basins C2, and OS2 before it discharges directly into W. Lake Street. Pond C was designed to overtop the pond in the northeast corner. In the case that the outlet structure should clog, stormwater would overtop and discharged directly into W. Lake Street. In the case that the curb inlet within Sub-basin D1 should clog, stormwater would overtop from Sub-basin D1 into Sub-basin C2. The excess stormwater from this basin would continue to overtop and pass through Sub-Basins OS2 before it discharges directly into W. Lake Street. Stadium Apartments Final Drainage Report 12 V. CONCLUSIONS A. Compliance with Standards 1. The drainage design proposed with the Stadium Apartments project complies with the City of Fort Collins’ Stormwater Criteria Manual. 2. The drainage design proposed with the Stadium Apartments project complies with the City of Fort Collins’ Master Drainage Plan for the Old Town Basin. 3. There are no regulatory floodplains associated with the Stadium Apartments development. 4. The drainage plan and stormwater management measures proposed with the Stadium Apartments development are compliant with all applicable State and Federal regulations governing stormwater discharge. B. Drainage Concept 1. The drainage design proposed with this project will effectively limit potential damage associated with its stormwater runoff. Stadium Apartments will detain for the pervious area converted to impervious areas by releasing at the 2-year existing rate during the developed100-year storm. 2. The proposed Stadium Apartments development will not impact the Master Drainage Plan recommendations for the Old Town major drainage basin. Stadium Apartments Final Drainage Report 13 References 1. City of Fort Collins Landscape Design Guidelines for Stormwater and Detention Facilities, November 5, 2009, BHA Design, Inc. with City of Fort Collins Utility Services. 2. Fort Collins Stormwater Criteria Manual, City of Fort Collins, Colorado, as adopted by Ordinance No. 174, 2011, and referenced in Section 26-500 (c) of the City of Fort Collins Municipal Code. 3. Larimer County Urban Area Street Standards, Adopted January 2, 2001, Repealed and Reenacted, Effective October 1, 2002, Repealed and Reenacted, Effective April 1, 2007. 4. Soils Resource Report for Larimer County Area, Colorado, Natural Resources Conservation Service, United States Department of Agriculture. 5. Urban Storm Drainage Criteria Manual, Volumes 1-3, Urban Drainage and Flood Control District, Wright-McLaughlin Engineers, Denver, Colorado, Revised April 2008. APPENDIX A HYDROLOGIC COMPUTATIONS CHARACTER OF SURFACE: Runoff Coefficient Percentage Impervious Project: Lake Street Apartments Streets, Parking Lots, Roofs, Alleys, and Drives: Calculations By: C. Snowdon Asphalt ……....……………...……….....…...……………….………………………………….. 0.95 100% Date: Concrete …….......……………….….……….………………..….………………………………… 0.95 90% Gravel ……….…………………….….…………………………..……………………………….. 0.50 40% Roofs …….…….………………..……………….…………………………………………….. 0.95 90% Pavers…………………………...………………..…………………………………………….. 0.40 22% Lawns and Landscaping Sandy Soil ……..……………..……………….…………………………………………….. 0.15 0% Clayey Soil ….….………….…….…………..………………………………………………. 0.25 0% 2-year Cf = 1.00 100-year Cf = 1.25 Basin ID Basin Area (s.f.) Basin Area (ac) Area of Asphalt (ac) Area of Concrete (ac) Area of Roofs (ac) Area of Gravel (ac) Area of Lawns and Landscaping (ac) 2-year Composite Runoff Coefficient 10-year Composite Runoff Coefficient 100-year Composite Runoff Coefficient Composite % Imperv. H1 106750 2.45 0.21 0.12 0.34 0.06 1.72 0.38 0.38 0.47 26% HISTORIC COMPOSITE % IMPERVIOUSNESS AND RUNOFF COEFFICIENT CALCULATIONS Notes September 19, 2016 10-year Cf = 1.00 **Soil Classification of site is Sandy Loam** Runoff Coefficients are taken from the City of Fort Collins Storm Drainage Design Criteria and Construction Standards, Table 3-3. % Impervious taken from UDFCD USDCM, Volume I. Page 1 of 10 D:\Projects\1232-001\Drainage\Hydrology\1232-001_Rational-Calcs.xlsx\Hist-C-Values Overland Flow, Time of Concentration: Project: Lake Street Apartments Calculations By: Date: Gutter/Swale Flow, Time of Concentration: Tt = L / 60V Tc = Ti + Tt (Equation RO-2) Velocity (Gutter Flow), V = 20·S½ Velocity (Swale Flow), V = 15·S½ NOTE: C-value for overland flows over grassy surfaces; C = 0.25 Is Length >500' ? C*Cf (2-yr Cf=1.00) C*Cf (10-yr Cf=1.00) C*Cf (100-yr Cf=1.25) Length, L (ft) Slope, S (%) Ti 2-yr (min) Ti 10-yr (min) Ti 100-yr (min) Length, L (ft) Slope, S (%) Velocity, V (ft/s) Tt (min) Length, L (ft) Slope, S (%) Velocity, V (ft/s) Tt (min) 2-yr Tc Rational Method Equation: Project: Lake Street Apartments Calculations By: Date: From Section 3.2.1 of the CFCSDDC Rainfall Intensity: h1 H1 2.45 15 15 13 0.38 0.38 0.47 1.90 3.24 7.04 1.75 3.00 8.15 HISTORIC RUNOFF COMPUTATIONS Intensity, i2 (in/hr) Intensity, i10 (in/hr) Intensity, i100 (in/hr) Notes C. Snowdon September 19, 2016 Rainfall Intensity taken from the City of Fort Collins Storm Drainage Design Criteria (CFCSDDC), Figure 3.1 Design Point Basin(s) Area, A (acres) 2-yr Tc (min) 10-yr Tc (min) 100-yr Tc (min) Flow, Q2 (cfs) Flow, Q10 (cfs) Flow, Q100 (cfs) C2 C 10 C100 Q = C f ( C )( i )( A ) Page 3 of 10 D:\Projects\1232-001\Drainage\Hydrology\1232-001_Rational-Calcs.xlsx\Hist-Direct-Runoff CHARACTER OF SURFACE: Runoff Coefficient Percentage Impervious Project: Lake Street Apartments Streets, Parking Lots, Roofs, Alleys, and Drives: Calculations By: Asphalt ……....……………...……….....…...……………….………………………………….0.. 95 100% Date: Concrete …….......……………….….……….………………..….………………………………… 0.95 90% Gravel ……….…………………….….…………………………..……………………………….0.. 50 40% Roofs …….…….………………..……………….…………………………………………….. 0.95 90% Pavers…………………………...………………..…………………………………………….. 0.40 22% Lawns and Landscaping Sandy Soil ……..……………..……………….…………………………………………….. 0.15 0% Clayey Soil ….….………….…….…………..………………………………………………. 0.25 0% 2-year Cf = 1.00 100-year Cf = 1.25 Basin ID Basin Area (s.f.) Basin Area (ac) Area of Asphalt (ac) Area of Concrete (ac) Area of Roofs (ac) Area of Gravel (ac) Area of Pavers (ac) Area of Lawns and Landscaping (ac) 2-year Composite Runoff Coefficient 10-year Composite Runoff Coefficient 100-year Composite Runoff Coefficient Composite % Imperv. A1 6337 0.145 0.000 0.017 0.000 0.000 0.000 0.129 0.24 0.24 0.30 10% A2 7708 0.177 0.000 0.177 0.000 0.000 0.000 0.000 0.95 0.95 1.00 90% B1 19564 0.449 0.220 0.037 0.000 0.000 0.000 0.192 0.61 0.61 0.76 56% B2 18374 0.422 0.000 0.000 0.422 0.000 0.000 0.000 0.95 0.95 1.00 90% B3 8193 0.188 0.132 0.021 0.000 0.000 0.000 0.036 0.80 0.80 1.00 80% B4 24252 0.557 0.000 0.000 0.557 0.000 0.000 0.000 0.95 0.95 1.00 90% C1 4730 0.109 0.000 0.023 0.000 0.000 0.000 0.086 0.32 0.32 0.40 19% Overland Flow, Time of Concentration: Project: Lake Street Apartments Calculations By: Date: Gutter/Swale Flow, Time of Concentration: Tt = L / 60V Tc = T i + Tt (Equation RO-2) Velocity (Gutter Flow), V = 20·S ½ Velocity (Swale Flow), V = 15·S ½ NOTE: C-value for overland flows over grassy surfaces; C = 0.25 Is Length >500' ? C*Cf (2-yr Cf=1.00) C*Cf (10-yr Cf=1.00) C*Cf (100-yr Cf=1.25) Length, L (ft) Slope, S (%) Ti 2-yr (min) Ti 10-yr (min) Ti 100-yr (min) Length, L (ft) Slope, S (%) Velocity, V (ft/s) Tt (min) Length, L (ft) Slope, S (%) Velocity, V (ft/s) Rational Method Equation: Project: Lake Street Apartments Calculations By: Date: From Section 3.2.1 of the CFCSDDC Rainfall Intensity: a1 A1 0.15 6 6 6 0.24 0.24 0.30 2.76 4.72 9.63 0.10 0.17 0.43 a2 A2 0.18 5 5 5 0.95 0.95 1.00 2.85 4.87 9.95 0.48 0.82 1.76 b1 B1 0.45 5 5 5 0.61 0.61 0.76 2.85 4.87 9.95 0.78 1.33 3.39 b2 B2 0.42 5 5 5 0.95 0.95 1.00 2.85 4.87 9.95 1.14 1.95 4.20 b3 B3 0.19 5 5 5 0.80 0.80 1.00 2.85 4.87 9.95 0.43 0.73 1.87 b4 B4 0.56 5 5 5 0.95 0.95 1.00 2.85 4.87 9.95 1.51 2.58 5.54 c1 C1 0.11 5 5 5 0.32 0.32 0.40 2.85 4.87 9.95 0.10 0.17 0.43 c2 C2 0.05 5 5 5 0.88 0.88 1.00 2.85 4.87 9.95 0.13 0.22 0.51 d1 D1 0.14 5 5 5 0.76 0.76 0.96 2.85 4.87 9.95 0.30 0.51 1.29 os1 OS1 0.15 5 5 5 0.24 0.24 0.29 2.85 4.87 9.95 0.10 0.18 0.45 os2 OS2 0.02 5 5 5 0.58 0.58 0.73 2.85 4.87 9.95 0.04 0.07 0.17 os3 OS3 0.04 5 5 5 0.15 0.15 0.19 2.85 4.87 9.95 0.02 0.03 0.07 DEVELOPED RUNOFF COMPUTATIONS C100 Notes Design Point Flow, Q100 (cfs) Flow, Q2 (cfs) 10-yr Tc (min) 2-yr Tc (min) C2 Flow, Q10 (cfs) Intensity, i100 (in/hr) Basin(s) C. Snowdon September 19, 2016 Intensity, i10 (in/hr) Rainfall Intensity taken from the City of Fort Collins Storm Drainage Design Criteria (CFCSDDC), Figure 3.1 C10 Area, A (acres) Intensity, i2 (in/hr) 100-yr Tc (min) Q = C f ( C )( i )( A ) Page 6 of 10 D:\Projects\1232-001\Drainage\Hydrology\1232-001_Rational-Calcs.xlsx\Direct-Runoff CHARACTER OF SURFACE: Runoff Coefficient Percentage Impervious Project: Lake Street Apartments Streets, Parking Lots, Roofs, Alleys, and Drives: Calculations By: Asphalt ……....……………...……….....…...……………….………………………………….. 0.95 100% Date: Concrete …….......……………….….……….………………..….………………………………… 0.95 90% Gravel ……….…………………….….…………………………..……………………………….. 0.50 40% Roofs …….…….………………..……………….…………………………………………….. 0.95 90% Pavers…………………………...………………..…………………………………………….. 0.40 22% Lawns and Landscaping Sandy Soil ……..……………..……………….…………………………………………….. 0.15 0% Clayey Soil ….….………….…….…………..………………………………………………. 0.25 0% 2-year Cf = 1.00 100-year Cf = 1.25 Design Point Basin IDs Basin Area (s.f.) Basin Area (ac) Area of Asphalt (ac) Area of Concrete (ac) Area of Roofs (ac) Area of Gravel (ac) Area of Pavers (ac) Area of Lawns and Landscaping (ac) 2-year Composite Runoff Coefficient 10-year Composite Runoff Coefficient 100-year Composite Runoff Coefficient Composite % Imperv. a1 A1-A2 14045 0.322 0.000 0.194 0.000 0.000 0.000 0.129 0.63 0.63 0.79 54% b1 B1-B2 37938 0.871 0.220 0.037 0.422 0.000 0.000 0.192 0.77 0.77 0.97 73% b3 B3-B4 32445 0.745 0.132 0.021 0.557 0.000 0.000 0.192 0.94 0.94 1.00 87% b1 B1-B4 70383 1.616 0.352 0.058 0.979 0.000 0.000 0.228 0.84 0.84 1.00 79% c1 C1 & C2 6947 0.159 0.029 0.040 0.000 0.000 0.000 0.121 0.53 0.53 0.66 41% COMBINED DEVELOPED COMPOSITE % IMPERVIOUSNESS AND RUNOFF COEFFICIENT CALCULATIONS September 19, 2016 Overland Flow, Time of Concentration: Project: Lake Street Apartments Calculations By: Date: Gutter/Swale Flow, Time of Concentration: Tt = L / 60V Tc = T i + Tt (Equation RO-2) Velocity (Gutter Flow), V = 20·S ½ Velocity (Swale Flow), V = 15·S ½ NOTE: C-value for overland flows over grassy surfaces; C = 0.25 Is Length >500' ? C*Cf (2-yr Cf=1.00) C*Cf (10-yr Cf=1.00) C*Cf (100-yr Cf=1.25) Length, L (ft) Slope, S (%) Ti 2-yr (min) Ti 10-yr (min) Ti 100-yr (min) Length, L (ft) Slope, S (%) Velocity, V (ft/s) Tt (min) Length, L (ft) Slope, S (%) Velocity, V (ft/s) Rational Method Equation: Project: Lake Street Apartments Calculations By: Date: From Section 3.2.1 of the CFCSDDC Rainfall Intensity: a1 A1-A2 0.32 6 6 6 0.63 0.63 0.79 2.76 4.72 9.63 0.6 1.0 2.4 b1 B1-B2 0.87 5 5 5 0.77 0.77 0.97 2.85 4.87 9.95 1.9 3.3 8.4 b3 B3-B4 0.74 5 5 5 0.94 0.94 1.00 2.85 4.87 9.95 2.0 3.4 7.4 b1 B1-B4 1.62 5 5 5 0.84 0.84 1.00 2.85 4.87 9.95 3.9 6.6 16.1 c1 C1 & C2 0.16 5 5 5 0.53 0.53 0.66 2.85 4.87 9.95 0.2 0.4 1.0 COMBINED DEVELOPED RUNOFF COMPUTATIONS C. Snowdon September 19, 2016 Rainfall Intensity taken from the City of Fort Collins Storm Drainage Design Criteria (CFCSDDC), Figure 3.1 Design Point Basin(s) Area, A (acres) 2-yr Tc (min) 10-yr Tc (min) 100-yr Tc (min) Flow, Q2 (cfs) Flow, Q10 (cfs) Flow, Q100 (cfs) C2 C10 C100 Intensity, i2 (in/hr) Intensity, i10 (in/hr) Intensity, i100 (in/hr) Q = C f ( C )( i )( A ) Page 9 of 10 D:\Projects\1232-001\Drainage\Hydrology\1232-001_Rational-Calcs.xlsx\Comb-Direct-Runoff DESIGN POINT BASIN ID TOTAL AREA (acres) C2 C100 2-yr Tc (min) 100-yr Tc (min) Q2 (cfs) Q100 (cfs) a1 A1 0.145 0.24 0.30 6.0 5.6 0.10 0.43 a2 A2 0.177 0.95 1.00 5.0 5.0 0.48 1.76 b1 B1 0.449 0.61 0.76 5.2 5.0 0.78 3.39 b2 B2 0.422 0.95 1.00 5.0 5.0 1.14 4.20 b3 B3 0.188 0.80 1.00 5.0 5.0 0.43 1.87 b4 B4 0.557 0.95 1.00 5.0 5.0 1.51 5.54 c1 C1 0.109 0.32 0.40 5.0 5.0 0.10 0.43 c2 C2 0.051 0.88 1.00 5.0 5.0 0.13 0.51 d1 D1 0.136 0.76 0.96 5.0 5.0 0.30 1.29 os1 OS1 0.154 0.24 0.29 5.0 5.0 0.10 0.45 os2 OS2 0.024 0.58 0.73 5.0 5.0 0.04 0.17 os3 OS3 0.039 0.15 0.19 5.0 5.0 0.02 0.07 DESIGN POINT BASIN ID TOTAL AREA (acres) C2 C100 2-yr Tc (min) 100-yr Tc (min) Q2 (cfs) Q100 (cfs) h1 H1 2.451 0.38 0.47 14.5 13.0 1.75 8.15 Page 10 of 10 D:\Projects\1232-001\Drainage\Hydrology\1232-001_Rational-Calcs.xlsx\SUMMARY-TABLE APPENDIX B HYDRAULIC COMPUTATIONS B.1 – Storm Sewers B.2 – Inlets B.3 – Detention Facilities APPENDIX B.1 STORM SEWERS (FOR FUTURE USE) APPENDIX B.2 INLETS (FOR FUTURE USE) APPENDIX B.3 DETENTION FACILITIES Pond No : a1 100-yr 0.79 6.00 min 2015 ft3 0.32 acres 0.046 ac-ft Max Release Rate = 0.36 cfs Time (min) Ft Collins 100-yr Intensity (in/hr) Inflow Volume (ft3) Outflow Adjustment Factor Qav (cfs) Outflow Volume (ft3) Storage Volume (ft3) 5 9.950 760 1.00 0.36 108 652 10 7.720 1180 0.80 0.29 173 1007 15 6.520 1495 0.70 0.25 227 1268 20 5.600 1712 0.65 0.23 281 1431 25 4.980 1903 0.62 0.22 335 1568 30 4.520 2072 0.60 0.22 389 1684 35 4.080 2182 0.59 0.21 443 1740 40 3.740 2286 0.58 0.21 497 1790 45 3.460 2380 0.57 0.20 551 1829 50 3.230 2468 0.56 0.20 605 1863 55 3.030 2547 0.55 0.20 659 1888 60 2.860 2623 0.55 0.20 713 1910 65 2.720 2702 0.55 0.20 767 1935 70 2.590 2771 0.54 0.20 821 1950 75 2.480 2843 0.54 0.19 875 1968 80 2.380 2910 0.54 0.19 929 1981 85 2.290 2975 0.54 0.19 983 1992 90 2.210 3040 0.53 0.19 1037 2003 95 2.130 3093 0.53 0.19 1091 2002 100 2.060 3148 0.53 0.19 1145 2004 105 2.000 3209 0.53 0.19 1199 2011 110 1.940 3261 0.53 0.19 1253 2009 115 1.890 3322 0.53 0.19 1307 2015 120 1.840 3375 0.53 0.19 1361 2014 *Note: Using the method described in Urban Storm Drainage Criteria Manual Volume 2. A = Tc = Project Location : Design Point C = Design Storm DETENTION POND CALCULATION; MODIFIED FAA METHOD w/ Ft Collins IDF Input Variables Results Required Detention Volume Fort Collins, Colorado Project Title Date: Project Number Calcs By: Client Pond Designation Invert Elevation Water Quality Volume 100-yr Detention Volume Total Pond Volume Min Sc D = Depth between contours (ft.) A1 = Surface Area lower contour (ft2) t A2 = Surface Area upper contour (ft2) Area/Row No. of Rows 5026.80 0.18 0.00 0.00 0.00 0.0000 5027.00 76.37 0.20 5.35 5.35 0.0001 5027.20 238.22 0.20 29.96 35.32 0.0008 5027.40 439.08 0.20 66.71 102.03 0.0023 5027.80 1128.04 0.40 302.79 404.82 0.0093 WQCV 5028.00 1558.80 0.20 267.53 672.34 0.0154 5028.20 1943.94 0.20 349.57 1021.91 0.0235 5028.40 2290.48 0.20 422.97 1444.88 0.0332 5028.60 2606.17 0.20 489.33 1934.20 0.0444 5028.80 2911.56 0.20 551.49 2485.69 0.0571 Total Vol Elevation Depth Volume WQCV 5027.60 0.80 0.0058 100-yr Detention 5028.63 1.83 0.0463 Overall Detention 5028.72 1.92 0.0521 Total Outlet Area 0.10 sq. in. Detention Pond A Volume Elevation (ft) Surface Area (ft2) Incremental Depth (ft) Incremental Vol. (ft3) Total Vol. (ft3) Total Vol. (ac-ft) n 1/4 0.05 Required Area Per Row 0.031 sq-in 2 Detention Pond A 5026.80 ft 0.0058 ac-ft 0.0463 ac-ft Circular Perforation Sizing 1 0.0521 ac-ft Dia (in.) Student Housing CSU, LLC Lake Street Apartments September 19, 2016 1232-001 C. Snowdon ( ) 3 V D * A 1 A 2 A 1 * A 2 Project Title Date: Project Number Calcs By: Client Pond Designation Q = 0.34 cfs C = 0.65 Q = Release Rate (cfs) Eh = 5028.72 ft C = Discharge Coefficients (unitless) Ei = 5026.80 ft Aa = Area Allowed of Opening (ft2) Ec = 5026.92 ft Circular g = Gravity (32.2 ft/s2) Ec = 5026.89 ft Rectangular Eh = High Water Surface Elevation (ft) Ei = Elevation of Outlet Invert (ft) 0.047020725 ft2 Ec = Elevation of Outlet Centroid (ft) 6.770984 in2 Orifice Size (in.) 2 -15/16 in. Area (in2) 6.72 sq-in Q 0.33 cfs Orifice Height (in.) 2 - 1/4 in. Orifice Width (in.) 3 in. Area (in2) 6.72 sq-in Q 0.33 cfs September 19, 2016 1232-001 C. Snowdon Student Housing CSU, LLC Detention Pond A Aa = Circular Orifice 100-Year Orifice Rectangular Orifice 100-Year Orifice Lake Street Apartments Detention Pond A 0.006 5027.60 0.0463 0.0521 5028.72 5028.80 Required Water Quality Storage (ac- ft) Water Quality Surface Pond ID Elevation (ft) High Water Surface Elevation (ft) Top of Pond Elevation (ft) Total Detention Volume (ac-ft) Required 100-year Detention Volume (ac-ft) Pond No : b1 100-yr 1.00 5.00 min 20281 ft3 1.62 acres 0.466 ac-ft Max Release Rate = 0.30 cfs Time (min) Ft Collins 100-yr Intensity (in/hr) Inflow Volume (ft3) Outflow Adjustment Factor Qav (cfs) Outflow Volume (ft3) Storage Volume (ft3) 5 9.950 4823 1.00 0.30 90 4733 10 7.720 7484 0.75 0.23 135 7349 15 6.520 9481 0.67 0.20 180 9301 20 5.600 10858 0.63 0.19 225 10633 25 4.980 12070 0.60 0.18 270 11800 30 4.520 13146 0.58 0.18 315 12831 35 4.080 13844 0.57 0.17 360 13484 40 3.740 14503 0.56 0.17 405 14098 45 3.460 15095 0.56 0.17 450 14645 50 3.230 15657 0.55 0.17 495 15162 55 3.030 16156 0.55 0.16 540 15616 60 2.860 16636 0.54 0.16 585 16051 65 2.720 17140 0.54 0.16 630 16510 70 2.590 17576 0.54 0.16 675 16901 75 2.480 18032 0.53 0.16 720 17312 80 2.380 18459 0.53 0.16 765 17694 85 2.290 18871 0.53 0.16 810 18061 90 2.210 19283 0.53 0.16 855 18428 95 2.130 19617 0.53 0.16 900 18717 100 2.060 19971 0.53 0.16 945 19026 105 2.000 20359 0.52 0.16 990 19369 110 1.940 20688 0.52 0.16 1035 19653 115 1.890 21071 0.52 0.16 1080 19991 120 1.840 21406 0.52 0.16 1125 20281 *Note: Using the method described in Urban Storm Drainage Criteria Manual Volume 2. DETENTION POND CALCULATION; MODIFIED FAA METHOD w/ Ft Collins IDF Input Variables Results Required Detention Volume Fort Collins, Colorado 1232-001 Lake Street Apartments Project Number : Project Name : Pond B A = Project Title Date: Project Number Calcs By: Client Pond Designation Q = 0.30 cfs C = 0.65 Q = Release Rate (cfs) Eh = 5028.99 ft C = Discharge Coefficients (unitless) Ei = 5025.49 ft Aa = Area Allowed of Opening (ft2) Ec = 5025.59 ft Circular g = Gravity (32.2 ft/s2) Ec = 5025.62 ft Rectangular Eh = High Water Surface Elevation (ft) Ei = Elevation of Outlet Invert (ft) 0.030741917 ft2 Ec = Elevation of Outlet Centroid (ft) 4.426836 in2 Orifice Size (in.) 2 - 3/8 in. Area (in2) 4.43 sq-in Q 0.30 cfs Orifice Height (in.) 3 in. Orifice Width (in.) 1 - 4/8 in. Area (in2) 4.43 sq-in Q 0.29 cfs September 19, 2016 Lake Street Apartments C. Snowdon Student Housing CSU, LLC Pond B - Outlet Structure Aa = Circular Orifice 100-Year Orifice Rectangular Orifice 100-Year Orifice 1232-001 Project: By: Units: Imperial Point of Contact Date: Required Storage Volume 20,281 CF Select Stormtech Chamber System SC-740 Stone Porosity (Industry Standard = 40%) 40% Stone Foundation Depth 6 Inches Storage Volume Per Chamber 74.90 CF Avg Cover over Chambers (18 in min. & 96 in max.) 18 Inches 30 in (762 mm) Number of Chambers Required - 271 6 in (150 mm) Approximate Bed Size Required 9,656 SF Tons of Stone Required 1,107 Tons Volume of Excavation 1,609 CY Area of Filter Fabric 2,708 SY # of End Caps Required 18 Each Length of ISOLATOR ROW 220.72 FT ISOLATOR FABRIC 123 SY Is the limiting dimension for the bed the width or length? width Width 45 FT Length 45 FT # of Chambers Long 31 EA # of Chambers long - EA # of Rows 9 EA # of Rows - EA Actual Length 224.32 FT Actual Length - FT Actual Width 44.25 FT Actual Width - FT 8 of the chambers rows will contain only 30 chambers Please call StormTech @ 888-892-2694 for conceptual cost estimates. To use this sheet: Please enter data into the blue and green cells. If switching between Imperial and Metric units please check the correct units and data is input in the green cells. System Requirements Lake Street Apartments - Detention Pond B Northern Engineering C. Snowdon 9.19.16 Material Estimate Controlled by Width (Rows) Controlled by Length 6" (150 mm) MIN. 6" MIN. 12" MIN. TYP. PAVEMENT 18" (460 mm) MIN. 96" (2440 mm) MAX. FOR UNPAVED INSTALLATION WHERE RUTTING FROM VEHICLES MAY OCCUR, INCREAST COVER TO 24" MINIMUM. www.stormtech.com│20 Beaver Road│Suite 104│Wethersfield│Connecticut│06109│888.892.2694│fax 866.328.8401 Project: Chamber Model - SC-740 Units - Imperial 100 Number of chambers - 271 Voids in the stone (porosity) - 40 % Base of STONE Elevation - 5025.49 ft Amount of Stone Above Chambers - 6 in Amount of Stone Below Chambers - 6 in Height of System Incremental Single Chamber Incremental Total Chamber Incremental Stone Incremental Ch & St Cumulative Chamber Elevation (inches) (cubic feet) (cubic feet) (cubic feet) (cubic feet) (cubic feet) (feet) 42 0.00 0.00 305.36 305.36 20296.91 5028.99 41 0.00 0.00 305.36 305.36 19991.54 5028.91 40 0.00 0.00 305.36 305.36 19686.18 5028.82 39 0.00 0.00 305.36 305.36 19380.81 5028.74 38 0.00 0.00 305.36 305.36 19075.45 5028.66 37 0.00 0.00 305.36 305.36 18770.09 5028.57 36 0.05 14.90 299.40 314.31 18464.72 5028.49 35 0.16 44.15 287.70 331.86 18150.42 5028.41 34 0.28 76.41 274.80 351.21 17818.56 5028.32 33 0.60 163.67 239.89 403.57 17467.35 5028.24 32 0.80 217.26 218.46 435.72 17063.78 5028.16 31 0.95 257.63 202.31 459.94 16628.06 5028.07 30 1.07 291.19 188.89 480.08 16168.12 5027.99 29 1.18 319.91 177.40 497.31 15688.04 5027.91 28 1.27 342.99 168.17 511.16 15190.72 5027.82 27 1.36 367.21 158.48 525.69 14679.56 5027.74 26 1.45 394.06 147.74 541.80 14153.88 5027.66 25 1.52 413.20 140.08 553.28 13612.07 5027.57 24 1.58 428.81 133.84 562.65 13058.79 5027.49 23 1.64 445.06 127.34 572.40 12496.14 5027.41 22 1.70 460.57 121.14 581.71 11923.74 5027.32 21 1.75 475.04 115.35 590.39 11342.03 5027.24 20 1.80 488.56 109.94 598.50 10751.64 5027.16 19 1.85 502.70 104.28 606.99 10153.14 5027.07 18 1.89 513.03 100.15 613.18 9546.16 5026.99 17 1.93 524.12 95.72 619.83 8932.97 5026.91 16 1.97 535.22 91.27 626.50 8313.14 5026.82 15 2.01 544.69 87.49 632.18 7686.64 5026.74 14 2.04 554.19 83.69 637.88 7054.46 5026.66 13 2.07 562.31 80.44 642.75 6416.58 5026.57 12 2.10 570.43 77.19 647.62 5773.83 5026.49 11 2.13 577.72 74.28 651.99 5126.21 5026.41 10 2.15 583.69 71.89 655.58 4474.21 5026.32 9 2.18 589.98 69.37 659.35 3818.63 5026.24 8 2.20 595.75 67.06 662.82 3159.28 5026.16 7 2.21 598.19 66.09 664.28 2496.46 5026.07 6 0.00 0.00 305.36 305.36 1832.19 5025.99 5 0.00 0.00 305.36 305.36 1526.82 5025.91 Pond No : c1 100-yr 0.66 5.00 min 697 ft3 0.16 acres 0.016 ac-ft Max Release Rate = 0.20 cfs Time (min) Ft Collins 100-yr Intensity (in/hr) Inflow Volume (ft3) Outflow Adjustment Factor Qav (cfs) Outflow Volume (ft3) Storage Volume (ft3) 5 9.950 314 1.00 0.20 60 254 10 7.720 488 0.75 0.15 90 398 15 6.520 618 0.67 0.13 120 498 20 5.600 707 0.63 0.13 150 557 25 4.980 786 0.60 0.12 180 606 30 4.520 856 0.58 0.12 210 646 35 4.080 902 0.57 0.11 240 662 40 3.740 945 0.56 0.11 270 675 45 3.460 983 0.56 0.11 300 683 50 3.230 1020 0.55 0.11 330 690 55 3.030 1052 0.55 0.11 360 692 60 2.860 1084 0.54 0.11 390 694 65 2.720 1117 0.54 0.11 420 697 70 2.590 1145 0.54 0.11 450 695 75 2.480 1175 0.53 0.11 480 695 80 2.380 1202 0.53 0.11 510 692 85 2.290 1229 0.53 0.11 540 689 90 2.210 1256 0.53 0.11 570 686 95 2.130 1278 0.53 0.11 600 678 100 2.060 1301 0.53 0.11 630 671 105 2.000 1326 0.52 0.10 660 666 110 1.940 1348 0.52 0.10 690 658 115 1.890 1373 0.52 0.10 720 653 120 1.840 1394 0.52 0.10 750 644 *Note: Using the method described in Urban Storm Drainage Criteria Manual Volume 2. A = Tc = Project Location : Design Point C = Design Storm DETENTION POND CALCULATION; MODIFIED FAA METHOD w/ Ft Collins IDF Input Variables Results Required Detention Volume Fort Collins, Colorado Project Title Date: Project Number Calcs By: Client Pond Designation Invert Elevation Water Quality Volume 100-yr Detention Volume Total Pond Volume Min Sc D = Depth between contours (ft.) A1 = Surface Area lower contour (ft2) t A2 = Surface Area upper contour (ft2) Area/Row No. of Rows 5025.40 27.16 0.00 0.00 0.00 0.0000 5025.60 373.07 0.20 33.39 33.39 0.0008 5025.80 663.64 0.20 102.29 135.68 0.0031 WQCV 5026.00 1113.21 0.20 175.76 311.44 0.0071 5026.20 1744.81 0.20 283.45 594.88 0.0137 5026.40 2151.73 0.20 388.94 983.83 0.0226 Total Vol WQCV Elevation Depth Volume WQCV 5025.78 0.38 0.0029 100-yr Detention 5026.25 0.85 0.0160 Overall Detention 5026.32 0.92 0.0189 Total Outlet Area 0.05 sq. in. Pond C Volume Elevation (ft) Surface Area (ft2) Incremental Depth (ft) Incremental Vol. (ft3) Total Vol. (ft3) Total Vol. (ac-ft) n 1/4 0.05 Required Area Per Row 0.021 sq-in 1 Pond C 5025.40 ft 0.0029 ac-ft 0.0160 ac-ft Circular Perforation Sizing 1 0.0189 ac-ft Dia (in.) Student Housing CSU, LLC Lake Street Apartments September 19, 2016 1232-001 C. Snowdon ( ) 3 V D * A 1 A 2 A 1 * A 2 = + + Project Title Date: Project Number Calcs By: Client Pond Designation Q = 0.20 cfs C = 0.65 Q = Release Rate (cfs) Eh = 5026.34 ft C = Discharge Coefficients (unitless) Ei = 5025.40 ft Aa = Area Allowed of Opening (ft2) Ec = 5025.51 ft Circular g = Gravity (32.2 ft/s2) Ec = 5025.52 ft Rectangular Eh = High Water Surface Elevation (ft) Ei = Elevation of Outlet Invert (ft) 0.039535711 ft2 Ec = Elevation of Outlet Centroid (ft) 5.693142 in2 Orifice Size (in.) 2 -11/16 in. Area (in2) 5.69 sq-in Q 0.19 cfs Orifice Height (in.) 2 - 7/8 in. Orifice Width (in.) 2 in. Area (in2) 5.69 sq-in Q 0.19 cfs Circular Orifice 100-Year Orifice Rectangular Orifice 100-Year Orifice Lake Street Apartments September 19, 2016 1232-001 C. Snowdon Student Housing CSU, LLC Pond C Aa = Pond C 0.00291 5025.83 0.0160 0.0189 5026.34 5026.40 Required Water Quality Storage (ac-ft) Water Quality Surface Pond ID Elevation (ft) High Water Surface Elevation (ft) Top of Pond Elevation (ft) Total Detention Volume (ac-ft) Required 100-year Detention Volume (ac-ft) Pond No : d1 100-yr 0.96 5.00 min 991 ft3 0.14 acres 0.023 ac-ft Max Release Rate = 0.20 cfs Time (min) Ft Collins 100-yr Intensity (in/hr) Inflow Volume (ft3) Outflow Adjustment Factor Qav (cfs) Outflow Volume (ft3) Storage Volume (ft3) 5 9.950 390 1.00 0.20 60 330 10 7.720 606 0.75 0.15 90 516 15 6.520 768 0.67 0.13 120 648 20 5.600 879 0.63 0.13 150 729 25 4.980 977 0.60 0.12 180 797 30 4.520 1064 0.58 0.12 210 854 35 4.080 1121 0.57 0.11 240 881 40 3.740 1174 0.56 0.11 270 904 45 3.460 1222 0.56 0.11 300 922 50 3.230 1267 0.55 0.11 330 937 55 3.030 1308 0.55 0.11 360 948 60 2.860 1347 0.54 0.11 390 957 65 2.720 1388 0.54 0.11 420 968 70 2.590 1423 0.54 0.11 450 973 75 2.480 1460 0.53 0.11 480 980 80 2.380 1494 0.53 0.11 510 984 85 2.290 1528 0.53 0.11 540 988 90 2.210 1561 0.53 0.11 570 991 95 2.130 1588 0.53 0.11 600 988 100 2.060 1617 0.53 0.11 630 987 105 2.000 1648 0.52 0.10 660 988 110 1.940 1675 0.52 0.10 690 985 115 1.890 1706 0.52 0.10 720 986 120 1.840 1733 0.52 0.10 750 983 *Note: Using the method described in Urban Storm Drainage Criteria Manual Volume 2. DETENTION POND CALCULATION; MODIFIED FAA METHOD w/ Ft Collins IDF Input Variables Results Required Detention Volume Fort Collins, Colorado 1232-001 Lake Street Apartments Project Number : Project Name : Pond D A = Project Title Date: Project Number Calcs By: Client Pond Designation Q = 0.20 cfs C = 0.65 Q = Release Rate (cfs) Eh = 5028.04 ft C = Discharge Coefficients (unitless) Ei = 5025.71 ft Aa = Area Allowed of Opening (ft2) Ec = 5025.80 ft Circular g = Gravity (32.2 ft/s2) Ec = 5025.84 ft Rectangular Eh = High Water Surface Elevation (ft) Ei = Elevation of Outlet Invert (ft) 0.025118618 ft2 Ec = Elevation of Outlet Centroid (ft) 3.617081 in2 Orifice Size (in.) 2 - 1/8 in. Area (in2) 3.62 sq-in Q 0.20 cfs Orifice Height (in.) 3 in. Orifice Width (in.) 1 - 1/4 in. Area (in2) 3.62 sq-in Q 0.19 cfs September 19, 2016 Lake Street Apartments C. Snowdon Student Housing CSU, LLC Pond D Aa = Circular Orifice 100-Year Orifice Rectangular Orifice 100-Year Orifice 1232-001 Project: By: Units: Imperial Point of Contact Date: Required Storage Volume 991 CF Select Stormtech Chamber System SC-310 Stone Porosity (Industry Standard = 40%) 40% Stone Foundation Depth 6 Inches Storage Volume Per Chamber 31.00 CF Avg Cover over Chambers (18 in min. & 96 in max.) 18 Inches 16 in (406 mm) Number of Chambers Required - 32 6 in (150 mm) Approximate Bed Size Required 952 SF Tons of Stone Required 91 Tons Volume of Excavation 118 CY Area of Filter Fabric 285 SY # of End Caps Required 26 Each Length of ISOLATOR ROW 21.36 FT ISOLATOR FABRIC 9 SY Is the limiting dimension for the bed the width or length? width Width 45 FT Length 45 FT # of Chambers Long 3 EA # of Chambers long - EA # of Rows 13 EA # of Rows - EA Actual Length 24.96 FT Actual Length - FT Actual Width 44.79 FT Actual Width - FT 7 of the chambers rows will contain only 2 chambers Please call StormTech @ 888-892-2694 for conceptual cost estimates. To use this sheet: Please enter data into the blue and green cells. If switching between Imperial and Metric units please check the correct units and data is input in the green cells. System Requirements Lake Street Apartments - Detention Pond D Northern Engineering C. Snowdon 9.19.16 Material Estimate Controlled by Width (Rows) Controlled by Length 6" (150 mm) MIN. 6" MIN. 12" MIN. TYP. PAVEMENT 18" (460 mm) MIN. 96" (2440 mm) MAX. FOR UNPAVED INSTALLATION WHERE RUTTING FROM VEHICLES MAY OCCUR, INCREAST COVER TO 24" MINIMUM. www.stormtech.com│20 Beaver Road│Suite 104│Wethersfield│Connecticut│06109│888.892.2694│fax 866.328.8401 Project: Chamber Model - SC-310 Units - Imperial 100 Number of chambers - 32 Voids in the stone (porosity) - 40 % Base of STONE Elevation - 5025.71 ft Amount of Stone Above Chambers - 6 in Amount of Stone Below Chambers - 6 in Height of System Incremental Single Chamber Incremental Total Chamber Incremental Stone Incremental Ch & St Cumulative Chamber Elevation (inches) (cubic feet) (cubic feet) (cubic feet) (cubic feet) (cubic feet) (feet) 28 0.00 0.00 25.30 25.30 991.90 5028.04 27 0.00 0.00 25.30 25.30 966.59 5027.96 26 0.00 0.00 25.30 25.30 941.29 5027.88 25 0.00 0.00 25.30 25.30 915.99 5027.79 24 0.00 0.00 25.30 25.30 890.68 5027.71 23 0.00 0.00 25.30 25.30 865.38 5027.63 22 0.06 1.88 24.55 26.43 840.08 5027.54 21 0.15 4.95 23.32 28.27 813.64 5027.46 20 0.27 8.51 21.90 30.41 785.37 5027.38 19 0.54 17.43 18.33 35.76 754.96 5027.29 18 0.70 22.53 16.29 38.82 719.20 5027.21 17 0.82 26.38 14.75 41.13 680.38 5027.13 16 0.92 29.59 13.47 43.06 639.24 5027.04 15 1.01 32.48 12.31 44.79 596.19 5026.96 14 1.09 35.03 11.29 46.32 551.39 5026.88 13 1.15 36.94 10.53 47.47 505.07 5026.79 12 1.21 38.88 9.75 48.63 457.61 5026.71 11 1.27 40.80 8.99 49.78 408.98 5026.63 10 1.32 42.39 8.35 50.74 359.20 5026.54 9 1.36 43.68 7.83 51.51 308.46 5026.46 8 1.40 44.96 7.32 52.28 256.95 5026.38 7 1.43 45.91 6.94 52.85 204.67 5026.29 6 0.00 0.00 25.30 25.30 151.82 5026.21 5 0.00 0.00 25.30 25.30 126.52 5026.13 4 0.00 0.00 25.30 25.30 101.21 5026.04 3 0.00 0.00 25.30 25.30 75.91 5025.96 2 0.00 0.00 25.30 25.30 50.61 5025.88 1 0.00 0.00 25.30 25.30 25.30 5025.79 StormTech SC-310 Cumulative Storage Volumes Lake Street Apartments - Pond D Include Perimeter Stone in Calculations Click Here for Metric Pond ID Required Water Quality Volume (ac-ft) Water Quality Surface Elevation (ft) Required 100-year Detention Volume (ac-ft) Total Detention Volume (ac-ft) High Water Surface Elevation (ft) Top of Pond Elevation (ft) Pond A (EDB) 0.006 5027.60 0.0480 0.0538 5028.75 5028.80 Pond B (UG) 0.0355 N/A 0.4656 0.4656 5028.99 N/A Pond C (EDB) 0.0029 5025.83 0.0160 0.0189 5026.34 5026.40 Pond D (UG) 0.0029 N/A 0.0160 0.0160 5028.04 N/A APPENDIX C WATER QUALITY DESIGN COMPUTATIONS Project Title Date: Project Number Calcs By: Client Pond Designation 1 WQCV = Watershed inches of Runoff (inches) 54.00% a = Runoff Volume Reduction (constant) i = Total imperviousness Ratio (i = Iwq/100) 0.217 in A = 0.32 ac V = 0.0058 ac-ft V = Water Quality Design Volume (ac-ft) WQCV = Water Quality Capture Volume (inches) A = Watershed Area (acres) 255 cu. ft. Drain Time a = i = WQCV = Figure EDB-2 - Water Quality Capture Volume (WQCV), 80th Percentile Runoff Event Lake Street Apartments September 19, 2016 1232-001 C. Snowdon Student Housing CSU, LLC Detention Pond A 0.217 0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 WQCV (watershed inches) Total Imperviousness Ratio (i = Iwq/100) Water Quality Capture Volume 6 hr 12 hr 24 hr 40 hr WQCV = a ( 0.91 i 3 - 1 . 19 i 2 + 0 . 78 i ) WQCV = a ( 0.91 i 3 - 1 . 19 i 2 + 0 . 78 i ) V * A 12 WQCV ÷ ø 1008 Project Title Date: Project Number Calcs By: Client Basins 0.8 WQCV = Watershed inches of Runoff (inches) 73.00% a = Runoff Volume Reduction (constant) i = Total imperviousness Ratio (i = Iwq/100) 0.231 in A = 0.87 ac V = 0.0168 ac-ft V = Water Quality Design Volume (ac-ft) WQCV = Water Quality Capture Volume (inches) A = Watershed Area (acres) 1232-001 September 19, 2016 Lake Street Apartments C. Snowdon Student Housing CSU, LLC WQ Basins B1 & B2 732 cu. ft. Drain Time a = i = WQCV = Figure EDB-2 - Water Quality Capture Volume (WQCV), 80th Percentile Runoff Event 0.231 0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 WQCV (watershed inches) Total Imperviousness Ratio (i = Iwq/100) Water Quality Capture Volume 6 hr 12 hr 24 hr 40 hr WQCV = a ( 0.91 i 3 - 1 . 19 i 2 + 0 . 78 i ) WQCV = a ( 0.91 i 3 - 1 . 19 i 2 + 0 . 78 i ) V * A 12 WQCV ÷ WQ 0.77 5.00 min 543 ft3 0.87 acres 0.01 ac-ft Max Release Rate = 0.24 cfs Time (min) Ft Collins WQ Intensity (in/hr) Inflow Volume (ft3) Outflow Adjustment Factor Qav (cfs) Outflow Volume (ft3) Storage Volume (ft3) 5 1.425 287 1.00 0.24 71 216 10 1.105 445 1.00 0.24 142 303 15 0.935 564 0.67 0.16 142 423 20 0.805 648 0.63 0.15 177 471 25 0.715 719 0.60 0.14 212 507 30 0.650 785 0.58 0.14 248 537 35 0.585 824 0.57 0.13 283 541 40 0.535 861 0.56 0.13 318 543 45 0.495 896 0.56 0.13 354 542 50 0.460 925 0.55 0.13 389 536 55 0.435 963 0.55 0.13 425 538 60 0.410 990 0.54 0.13 460 530 65 0.385 1007 0.54 0.13 495 512 70 0.365 1028 0.54 0.13 531 497 75 0.345 1041 0.53 0.13 566 475 80 0.330 1062 0.53 0.13 601 461 85 0.315 1077 0.53 0.12 637 441 90 0.305 1105 0.53 0.12 672 432 95 0.290 1109 0.53 0.12 708 401 100 0.280 1127 0.53 0.12 743 384 105 0.270 1141 0.52 0.12 778 362 110 0.260 1151 0.52 0.12 814 337 115 0.255 1180 0.52 0.12 849 331 120 0.245 1183 0.52 0.12 884 299 *Note: Using the method described in Urban Storm Drainage Criteria Manual Volume 2. Lake Street Apartments 1232-001 DETENTION POND CALCULATION; MODIFIED FAA METHOD w/ Ft Collins IDF Input Variables Results Required Detention Volume Client Basins Project Number Project Title WQ Basins B1 & B2 Student Housing CSU, LLC 1008 Project Title Date: Project Number Calcs By: Client Basins 0.8 WQCV = Watershed inches of Runoff (inches) 87.00% a = Runoff Volume Reduction (constant) i = Total imperviousness Ratio (i = Iwq/100) 0.302 in A = 0.74 ac V = 0.0187 ac-ft V = Water Quality Design Volume (ac-ft) WQCV = Water Quality Capture Volume (inches) A = Watershed Area (acres) Figure EDB-2 - Water Quality Capture Volume (WQCV), 80th Percentile Runoff Event 816 cu. ft. Drain Time a = i = WQCV = 1232-001 September 19, 2016 Lake Street Apartments C. Snowdon Student Housing CSU, LLC WQ Basins B3 & B4 0.231 0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 WQCV (watershed inches) Total Imperviousness Ratio (i = Iwq/100) Water Quality Capture Volume 6 hr 12 hr 24 hr 40 hr WQCV = a ( 0.91 i 3 - 1 . 19 i 2 + 0 . 78 i ) WQCV = a ( 0.91 i 3 - 1 . 19 i 2 + 0 . 78 i ) V * A 12 WQCV ÷ WQ 0.94 5.00 min 549 ft3 0.74 acres 0.01 ac-ft Max Release Rate = 0.26 cfs Time (min) Ft Collins WQ Intensity (in/hr) Inflow Volume (ft3) Outflow Adjustment Factor Qav (cfs) Outflow Volume (ft3) Storage Volume (ft3) 5 1.425 299 1.00 0.26 78 221 10 1.105 464 1.00 0.26 156 309 15 0.935 589 0.67 0.17 156 434 20 0.805 676 0.63 0.16 195 482 25 0.715 751 0.60 0.16 233 517 30 0.650 819 0.58 0.15 272 547 35 0.585 860 0.57 0.15 311 549 40 0.535 899 0.56 0.15 350 549 45 0.495 936 0.56 0.14 389 547 50 0.460 966 0.55 0.14 428 538 55 0.435 1005 0.55 0.14 467 538 60 0.410 1033 0.54 0.14 506 527 65 0.385 1051 0.54 0.14 545 506 70 0.365 1073 0.54 0.14 584 490 75 0.345 1087 0.53 0.14 623 464 80 0.330 1109 0.53 0.14 662 447 85 0.315 1125 0.53 0.14 700 424 90 0.305 1153 0.53 0.14 739 414 95 0.290 1157 0.53 0.14 778 379 100 0.280 1176 0.53 0.14 817 359 105 0.270 1191 0.52 0.14 856 335 110 0.260 1201 0.52 0.14 895 306 115 0.255 1232 0.52 0.14 934 298 120 0.245 1235 0.52 0.14 973 262 *Note: Using the method described in Urban Storm Drainage Criteria Manual Volume 2. C = Tc = A = Basins WQ Basins B1 & B2 Input Variables Results Design Point Design Storm Required Detention Volume WQ Basins B3 & B4 DETENTION POND CALCULATION; MODIFIED FAA METHOD w/ Ft Collins IDF Project Title 1232-001 Project Number Lake Street Apartments Vault ID Total Required WQ Volume (cf) Flow, WQ (cfs) Chamber Type Chamber Release Ratea (cfs) Chamber Volumeb (cf) Installed Camber w/ Aggregatec (cf) Mimimum No. of Chambersd Total Release Ratee (cfs) Required Storage Volume by FAA Method (cf) Mimimum No. of Chambersf Storage Provided within the Chambersg (cf) Total Installed System Volumeh (cf) WQ Basins B1 & B2 732 0.95 SC-740 0.024 45.90 74.90 10 0.24 543 12 551 899 WQ Basins B3 & B4 816 1.00 SC-740 0.024 45.90 74.90 11 0.26 549 12 551 899 SC-740 a. Release rate per chamber, limited by flow through geotextile with accumulated sediment. b. Volume within chamber only, not accounting for void spaces in surrounding aggregate. c. Volume includes chamber and void spaces (40%) in surrounding aggregate, per chamber unit. d. Number of chambers required to provide full WQCV within total installed system, including aggregate. e. Release rate per chamber times number of chambers. f. Number of chambers required to provide required FAA storage volume stored within the chamber only (no aggregate storage). g. Volume provided in chambers only (no aggregate storage). This number must meet or exceed the required FAA storage volume. e. System volume includes total number of chambers, plus surrounding aggregate. This number must meet or exceed the required WQCV. Chamber Configuration Summary D:\Projects\1232-001\Drainage\Detention\1232-002 Pond B Pond_Orifice Calc.xls Chamber Dimensions SC-160 SC-310 SC-740 Width (in) 25.0 34.0 51.0 Length (in) 84.4 85.4 85.4 Height (in) 12.0 16.0 30.0 Floor Area (sf) 14.7 20.2 30.2 Chamber Volume (cf) 6.9 14.7 45.9 Chamber/Aggregate Volume (cf) 15.0 29.3 74.9 Flow Rate* 0.35 gpm/sf 1 cf = 7.48052 gal 1 gallon = 0.133681 cf 1 GPM = 0.002228 cfs *Flow rate based on 1/2 of Nov 07 QMAX in Figure 17 of UNH Testing Report SC-160 SC-310 SC-740 Flow Rate/chamber (cfs) 0.011426 0.015724 0.023586 StormTech Chamber Data Chamber Flow Rate Chamber Flow Rate Conversion (gpm/sf to cfs) D:\Projects\1232-001\Drainage\Detention\1232-002 Pond B Pond_Orifice Calc.xls Project Title Date: Project Number Calcs By: Client Pond Designation 1 WQCV = Watershed inches of Runoff (inches) 41.00% a = Runoff Volume Reduction (constant) i = Total imperviousness Ratio (i = Iwq/100) 0.182 in A = 0.16 ac V = 0.0029 ac-ft V = Water Quality Design Volume (ac-ft) WQCV = Water Quality Capture Volume (inches) A = Watershed Area (acres) 1.2 = 20% Additional Volume (Sediment Accumulation) 127 cu. ft. Lake Street Apartments September 19, 2016 1232-001 C. Snowdon Student Housing CSU, LLC Pond C Drain Time a = i = WQCV = Figure EDB-2 - Water Quality Capture Volume (WQCV), 80th Percentile Runoff Event 0.182 0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 WQCV (watershed inches) Total Imperviousness Ratio (i = Iwq/100) Water Quality Capture Volume 6 hr 12 hr 24 hr 40 hr WQCV = a ( 0.91 i 3 - 1 . 19 i 2 + 0 . 78 i ) WQCV = a ( 0.91 i 3 - 1 . 19 i 2 + 0 . 78 i ) * * 1 . 2 12 V WQCV A ÷ 1008 Project Title Date: Project Number Calcs By: Client Basins 0.8 WQCV = Watershed inches of Runoff (inches) 76.00% a = Runoff Volume Reduction (constant) i = Total imperviousness Ratio (i = Iwq/100) 0.244 in A = 0.14 ac V = 0.0028 ac-ft V = Water Quality Design Volume (ac-ft) WQCV = Water Quality Capture Volume (inches) A = Watershed Area (acres) 121 cu. ft. Drain Time a = i = WQCV = Figure EDB-2 - Water Quality Capture Volume (WQCV), 80th Percentile Runoff Event 1232-001 September 19, 2016 Lake Street Apartments C. Snowdon Student Housing CSU, LLC Pond D 0.231 0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 WQCV (watershed inches) Total Imperviousness Ratio (i = Iwq/100) Water Quality Capture Volume 6 hr 12 hr 24 hr 40 hr WQCV = a ( 0.91 i 3 - 1 . 19 i 2 + 0 . 78 i ) WQCV = a ( 0.91 i 3 - 1 . 19 i 2 + 0 . 78 i ) V * A 12 WQCV ÷ Pond D WQ 0.76 5.00 min 41 ft3 0.14 acres 0.00 ac-ft Max Release Rate = 0.08 cfs Time (min) Ft Collins WQ Intensity (in/hr) Inflow Volume (ft3) Outflow Adjustment Factor Qav (cfs) Outflow Volume (ft3) Storage Volume (ft3) 5 1.425 44 1.00 0.08 24 21 10 1.105 69 1.00 0.08 47 21 15 0.935 87 0.67 0.05 47 40 20 0.805 100 0.63 0.05 59 41 25 0.715 111 0.60 0.05 71 40 30 0.650 121 0.58 0.05 83 39 35 0.585 127 0.57 0.04 94 33 40 0.535 133 0.56 0.04 106 27 45 0.495 138 0.56 0.04 118 20 50 0.460 143 0.55 0.04 130 13 55 0.435 149 0.55 0.04 142 7 60 0.410 153 0.54 0.04 153 0 65 0.385 155 0.54 0.04 165 -10 70 0.365 159 0.54 0.04 177 -18 75 0.345 161 0.53 0.04 189 -28 80 0.330 164 0.53 0.04 200 -36 85 0.315 166 0.53 0.04 212 -46 90 0.305 171 0.53 0.04 224 -54 95 0.290 171 0.53 0.04 236 -65 100 0.280 174 0.53 0.04 248 -74 105 0.270 176 0.52 0.04 259 -83 110 0.260 178 0.52 0.04 271 -94 115 0.255 182 0.52 0.04 283 -101 120 0.245 183 0.52 0.04 295 -112 *Note: Using the method described in Urban Storm Drainage Criteria Manual Volume 2. Pond D Student Housing CSU, LLC A = Tc = Design Point C = Design Storm Lake Street Apartments 1232-001 DETENTION POND CALCULATION; MODIFIED FAA METHOD w/ Ft Collins IDF Vault ID Total Required WQ Volume (cf) Flow, WQ (cfs) Chamber Type Chamber Release Ratea (cfs) Chamber Volumeb (cf) Installed Camber w/ Aggregatec (cf) Mimimum No. of Chambersd Total Release Ratee (cfs) Required Storage Volume by FAA Method (cf) Mimimum No. of Chambersf Storage Provided within the Chambersg (cf) Total Installed System Volumeh (cf) Pond D 121 0.13 SC-310 0.016 14.70 29.30 5 0.08 41 3 44 147 SC-740 a. Release rate per chamber, limited by flow through geotextile with accumulated sediment. b. Volume within chamber only, not accounting for void spaces in surrounding aggregate. c. Volume includes chamber and void spaces (40%) in surrounding aggregate, per chamber unit. d. Number of chambers required to provide full WQCV within total installed system, including aggregate. e. Release rate per chamber times number of chambers. f. Number of chambers required to provide required FAA storage volume stored within the chamber only (no aggregate storage). g. Volume provided in chambers only (no aggregate storage). This number must meet or exceed the required FAA storage volume. e. System volume includes total number of chambers, plus surrounding aggregate. This number must meet or exceed the required WQCV. Chamber Configuration Summary D:\Projects\1232-001\Drainage\Detention\1232-002 Pond D Pond_Orifice Calc.xls Chamber Dimensions SC-160 SC-310 SC-740 Width (in) 25.0 34.0 51.0 Length (in) 84.4 85.4 85.4 Height (in) 12.0 16.0 30.0 Floor Area (sf) 14.7 20.2 30.2 Chamber Volume (cf) 6.9 14.7 45.9 Chamber/Aggregate Volume (cf) 15.0 29.3 74.9 Flow Rate* 0.35 gpm/sf 1 cf = 7.48052 gal 1 gallon = 0.133681 cf 1 GPM = 0.002228 cfs *Flow rate based on 1/2 of Nov 07 QMAX in Figure 17 of UNH Testing Report SC-160 SC-310 SC-740 Flow Rate/chamber (cfs) 0.011426 0.015724 0.023586 StormTech Chamber Data Chamber Flow Rate Chamber Flow Rate Conversion (gpm/sf to cfs) D:\Projects\1232-001\Drainage\Detention\1232-002 Pond D Pond_Orifice Calc.xls APPENDIX D EROSION CONTROL REPORT Lake Avenue Apartments Final Erosion Control Report A comprehensive Erosion and Sediment Control Plan (along with associated details) will be included with the final construction drawings. It should be noted, however, that any such Erosion and Sediment Control Plan serves only as a general guide to the Contractor. Staging and/or phasing of the BMPs depicted, and additional or different BMPs from those included may be necessary during construction, or as required by the authorities having jurisdiction. It shall be the responsibility of the Contractor to ensure erosion control measures are properly maintained and followed. The Erosion and Sediment Control Plan is intended to be a living document, constantly adapting to site conditions and needs. The Contractor shall update the location of BMPs as they are installed, removed or modified in conjunction with construction activities. It is imperative to appropriately reflect the current site conditions at all times. The Erosion and Sediment Control Plan shall address both temporary measures to be implemented during construction, as well as permanent erosion control protection. Best Management Practices from the Volume 3, Chapter 7 – Construction BMPs will be utilized. Measures may include, but are not limited to, silt fencing along the disturbed perimeter, gutter protection in the adjacent roadways and inlet protection at proposed storm inlets. Vehicle tracking control pads, spill containment and clean-up procedures, designated concrete washout areas, dumpsters, and job site restrooms shall also be provided by the Contractor. Grading and Erosion Control Notes can be found on Sheet CS2 of the Utility Plans. The Utility Plans at final design will also contain a full-size Erosion Control Plan as well as a separate sheet dedicated to Erosion Control Details. In addition to this report and the referenced plan sheets, the Contractor shall be aware of, and adhere to, the applicable requirements outlined in any existing Development Agreement(s) of record, as well as the Development Agreement, to be recorded prior to issuance of the Development Construction Permit. Also, the Site Contractor for this project will be required to secure a Stormwater Construction General Permit from the Colorado Department of Public Health and Environment (CDPHE), Water Quality Control Division – Stormwater Program, before commencing any earth disturbing activities. Prior to securing said permit, the Site Contractor shall develop a comprehensive StormWater Management Plan (SWMP) pursuant to CDPHE requirements and guidelines. The SWMP will further describe and document the ongoing activities, inspections, and maintenance of construction BMPs. MAP POCKET DR1 – OVERALL DRAINAGE EXHIBIT Input Variables Results Required Detention Volume Client Basins Project Number Project Title Page 2 of 5 1232-002 Pond D Pond_Orifice Calc.xls ø ö ç è = æ 12 hr ø ö ç è = æ 40 hr Client Student Housing CSU, LLC Page 4 of 7 1232-002 Pond B Pond_Orifice Calc.xls ø ö ç è = æ 12 hr A = Tc = Design Point C = Design Storm WQ Basins B1 & B2 Page 2 of 7 1232-002 Pond B Pond_Orifice Calc.xls ø ö ç è = æ 12 hr ö ç è = æ 40 hr Tc = Project Location : Design Point C = Design Storm Page 1 of 1 1232-001_Pond D_DetentionVolume_FAAModified Method.xls 1232-001 Lake Street Apartments Project Number : Project Name : Pond C Page 1 of 1 1232-001_Pond C_DetentionVolume_FAAModified Method.xls 4 0.00 0.00 305.36 305.36 1221.46 5025.82 3 0.00 0.00 305.36 305.36 916.09 5025.74 2 0.00 0.00 305.36 305.36 610.73 5025.66 1 0.00 0.00 305.36 305.36 305.36 5025.57 StormTech SC-740 Cumulative Storage Volumes Lake Street Apartments - Pond B Include Perimeter Stone in Calculations Click Here for Metric Tc = Project Location : Design Point C = Design Storm Page 1 of 1 1232-001_Pond B_DetentionVolume_FAAModified Method.xls = + + 1232-001 Lake Street Apartments Project Number : Project Name : Pond A Page 1 of 1 1232-001_Pond A_DetentionVolume_FAAModified Method.xls Tt (min) 2-yr Tc (min) 10-yr Tc (min) 100-yr Tc (min) a1 A1-A2 No 0.24 0.24 0.30 20 2.00 5.69 5.69 5.29 N/A N/A N/A 187 0.5 10.61 0.3 6 6 6 b1 B1-B2 No 0.95 0.95 1.00 N/A N/A N/A N/A 100 1.00% 2.00 0.8 N/A N/A N/A 5 5 5 b3 B3-B4 No 0.61 0.61 0.76 N/A N/A N/A N/A 325 1.00% 2.00 2.7 N/A N/A N/A 5 5 5 b1 B1-B4 No 0.61 0.61 0.76 N/A N/A N/A N/A 165 1.00% 2.00 1.4 N/A N/A N/A 5 5 5 c1 C1 & C2 No 0.95 0.95 1.00 20 14.40% 0.5 0.5 0.3 N/A N/A N/A N/A N/A N/A 5 5 5 COMBINED DEVELOPED TIME OF CONCENTRATION COMPUTATIONS C. Snowdon September 19, 2016 Design Point Basin IDs Overland Flow Pipe/Internal Building Flow Swale Flow Time of Concentration (Equation RO-4) ( ) 3 1 1 . 87 1 . 1 * S Ti C Cf L - = Page 8 of 10 D:\Projects\1232-001\Drainage\Hydrology\1232-001_Rational-Calcs.xlsx\Comb-Tc-10-yr_&_100-yr **Soil Classification of site is Sandy Loam** 10-year Cf = 1.00 Runoff Coefficients are taken from the City of Fort Collins Storm Drainage Design Criteria and Construction Standards, Table 3-3. % Impervious taken from UDFCD USDCM, Volume I. C. Snowdon Page 7 of 10 D:\Projects\1232-001\Drainage\Hydrology\1232-001_Rational-Calcs.xlsx\Comb-C-Values Tt (min) 2-yr Tc (min) 10-yr Tc (min) 100-yr Tc (min) a1 A1 No 0.24 0.24 0.30 20 2.00% 5.7 5.7 5.3 N/A N/A N/A 187 0.5 10.61 0.3 6 6 6 a2 A2 No 0.95 0.95 1.00 N/A N/A N/A N/A 100 1.00% 2.00 0.8 N/A N/A N/A 5 5 5 b1 B1 No 0.61 0.61 0.76 25 3.00% 3.2 3.2 2.2 235 1.00% 2.00 2.0 N/A N/A N/A 5 5 5 b2 B2 No 0.95 0.95 1.00 N/A N/A N/A N/A 100 1.00% 2.00 0.8 N/A N/A N/A 5 5 5 b3 B3 No 0.80 0.80 1.00 74 3.11% 3.3 3.3 1.1 64 0.50% 1.41 0.8 N/A N/A N/A 5 5 5 b4 B4 No 0.95 0.95 1.00 N/A N/A N/A N/A 293 1.00% 2.00 2.4 N/A N/A N/A 5 5 5 c1 C1 No 0.32 0.32 0.40 20 14.40% 2.7 2.7 2.4 N/A N/A N/A 165 0.5 10.61 0.3 5 5 5 c2 C2 No 0.88 0.88 1.00 N/A N/A N/A N/A 67 0.54% 1.47 0.8 N/A N/A N/A 5 5 5 d1 D1 No 0.76 0.76 0.96 13 5.00% 1.3 1.3 0.6 156 0.87% 1.87 1.4 N/A N/A N/A 5 5 5 os1 OS1 No 0.24 0.24 0.29 35 15.00% 3.9 3.9 3.6 0 N/A N/A N/A N/A N/A N/A 5 5 5 os2 OS2 No 0.58 0.58 0.73 10 2.00% 2.4 2.4 1.7 52 4.50% 4.24 0.2 N/A N/A N/A 5 5 5 os3 OS3 No 0.15 0.15 0.19 21 25.00% 2.8 2.8 2.7 N/A N/A N/A N/A N/A N/A 5 5 5 DEVELOPED TIME OF CONCENTRATION COMPUTATIONS Gutter/Internal Building Flow Swale Flow Design Point Basin Overland Flow C. Snowdon September 19, 2016 Time of Concentration (Equation RO-4) ( ) 3 1 1 . 87 1 . 1 * S Ti C Cf L - = Page 5 of 10 D:\Projects\1232-001\Drainage\Hydrology\1232-001_Rational-Calcs.xlsx\Tc-10-yr_&_100-yr C2 2217 0.051 0.029 0.017 0.000 0.000 0.000 0.004 0.88 0.88 1.00 88% D1 5935 0.136 0.091 0.014 0.000 0.000 0.000 0.032 0.76 0.76 0.96 76% OS1 6696 0.154 0.000 0.016 0.000 0.000 0.000 0.137 0.24 0.24 0.29 10% OS2 1052 0.024 0.009 0.004 0.000 0.000 0.000 0.011 0.58 0.58 0.73 52% OS3 1691 0.039 0.000 0.000 0.000 0.000 0.000 0.039 0.15 0.15 0.19 0% TOTAL 106749 2.45 0.481 0.326 0.979 0.000 0.000 0.665 0.73 0.73 0.92 68% DEVELOPED COMPOSITE % IMPERVIOUSNESS AND RUNOFF COEFFICIENT CALCULATIONS Runoff Coefficients are taken from the City of Fort Collins Storm Drainage Design Criteria and Construction Standards, Table 3-3. % Impervious taken from UDFCD USDCM, Volume I. 10-year Cf = 1.00 September 19, 2016 **Soil Classification of site is Sandy Loam** C. Snowdon Page 4 of 10 D:\Projects\1232-001\Drainage\Hydrology\1232-001_Rational-Calcs.xlsx\C-Values (min) 10-yr Tc (min) 100-yr Tc (min) h1 H1 No 0.38 0.38 0.47 146 2.74% 11.7 11.7 10.1 N/A N/A N/A 241 0.88% 1.41 2.9 15 15 13 HISTORIC TIME OF CONCENTRATION COMPUTATIONS C. Snowdon September 19, 2016 Design Point Basin Overland Flow Gutter Flow Swale Flow Time of Concentration (Equation RO-4) ( ) 3 1 1 . 87 1 . 1 * S Ti C Cf L - = Page 2 of 10 D:\Projects\1232-001\Drainage\Hydrology\1232-001_Rational-Calcs.xlsx\Hist-Tc-10-yr_&_100-yr