CITY OF FORT COLLINS
TYPE 1 ADMINISTRATIVE HEARING
FINDINGS AND DECISION
HEARING DATE: June 6, 2016
PROJECT NAME: Angie Lee Periodontics
CASE NUMBER: PDP #160012
APPLICANT: Russell Lee
Ripley Design, Inc.
419 Canyon Avenue, Suite 200
Fort Collins, CO 80521
Chris Aronson, Architect
VAUGHT FRYE LARSON ARCHITECTS
419 Canyon Avenue, Suite 200
Fort Collins, CO 80521
OWNER: Jesus Martin
Aspen Summit LLC
1223 Red Oak Court
Fort Collins, CO 80525
HEARING OFFICER: Marcus A. McAskin
PROJECT DESCRIPTION: The Angie Lee Periodontics PDP (PDP #160012) is a request for
approval of a Project Development Plan (PDP) to construct a one-story 7,300 square foot building
composed of a 4,400 square foot dental office for Angie Lee Periodontics and a 2,900 square foot
building expansion area.
The PDP proposes 23 off-street parking spaces, a six foot (6’) wide attached sidewalk to the north,
street trees and other landscaping. The subject property is legally described as Lot 2, Miramont Self
Storage P.U.D. (the “Property”). The Property is located southwest of the Oakridge Drive and
Boardwalk Drive intersection and is zoned Harmony Corridor District (H-C).
The proposed building is subject to Administrative (Type 1) review in the H-C Zone District,
pursuant to Section 4.26(B)(2)(c)(1) of the Land Use Code (offices, financial services and clinics).
2
BACKGROUND: The surrounding zoning and land uses are set forth below:
Direction Zone District Existing Land Uses
North Harmony Corridor District (H-C) Miramont Office Park – Learning Experience
child care
South Harmony Corridor District (H-C) Miramont Self Storage PUD
East Medium Density Mixed-Use
Neighborhood District (M-M-N)
Oak Hill Apartments PUD
West Harmony Corridor District (H-C) Miramont Self Storage PUD
SUMMARY OF DECISION: Approved.
ZONE DISTRICT: Harmony Corridor (H-C) Zone District
HEARING: The Hearing Officer opened the hearing on Monday, June 6, 2016, in Conference
Rooms A-D, 281 North College Avenue, Fort Collins, Colorado, at approximately 5:30 PM. No
members of the public were present at the hearing. In addition to Messrs. Martin, Lee and Aronson
identified on page one above, the following consultant representing the Owner was also in
attendance:
Kevin Brazleton
United Civil Design Group, Inc.
1501 Academy Ct., Suite 203
Fort Collins, CO 80524
EVIDENCE: Prior to or at the hearing, the Hearing Officer accepted the following documents as
part of the record of this proceeding:
1. Property Vicinity Map.
2. Planning Department Staff Report prepared for Angie Lee Periodontics (PDP
#160012). A copy of the Staff Report is attached to this decision as
ATTACHMENT A and is incorporated herein by reference.
3. PDP for Angie Lee Periodontics, consisting of the following seven (7) sheets:
a. Cover Sheet
b. Site Plan
c. Landscape Plan
d. Landscape Notes and Details
e. Lighting Plan
3
f. Architectural Elevations (A-1)
g. Architectural Elevations (A-2)
4. Planning Objectives dated March 30, 2016 from Ripley Design, Inc. (2 pages).
5. Letter dated February 25, 2016 from Christine Wess, Operations Manager of
SecurCare Self Storage (“SecurCare”), indicating SecurCare’s willingness to
cooperate with the Applicant and Owner with respect to granting a temporary
construction easement for future grading activities associated with the project
proposed for development on the Property (1 page).
6. Utility Plans for Angie Lee Periodontics (7 Sheets).
7. Plat of Miramont Office Park (1 Sheet).
8. Plat of Miramont Self Storage P.U.D. (1 Sheet).
9. Miramont Self Storage P.U.D. Final Site Plan (3 Sheets).
10. Affidavit of Publication dated May 27, 2016, evidencing proof of publication of
Notice of Hearing in the Fort Collins Coloradan on May 27, 2016.
11. Notice of Public Hearing.
12. The City’s Comprehensive Plan, Code, and the formally promulgated polices of the
City are all considered part of the record considered by the Hearing Officer.
TESTIMONY: The following persons testified at the hearing:
From the City: Jason Holland, City Planner
From the Applicant: Russell Lee
Ripley Design, Inc.
419 Canyon Avenue, Suite 200
Fort Collins, CO 80521
Chris Aronson, Architect
VAUGHT FRYE LARSON ARCHITECTS
419 Canyon Avenue, Suite 200
Fort Collins, CO 80521
From the Owner: Jesus Martin
Aspen Summit LLC
1223 Red Oak Court
Fort Collins, CO 80525
From the Public: None.
The hearing on this matter was closed at approximately 5:47 p.m.
4
FINDINGS
1. Evidence presented to the Hearing Officer established the fact that notice of the public
hearing was properly posted, mailed and published.
2. Based on testimony provided at the public hearing and a review of the materials in the record
of this case, the Hearing Officer concludes as follows:
A. the Application complies with the applicable procedural and administrative
requirements of Article 2 of the Land Use Code;
B. the Application complies with the applicable General Development Standards
contained in Article 3 of the Land Use Code; and
C. the Application complies with the applicable Harmony Corridor (H-C) Zone District
standards contained in Article 4, Division 4.26 of the Land Use Code, including
4.26(D)(3)(a) which establishes a maximum height of six (6) stories for all non-
residential buildings, and Section 4.26(E)(1), which requires that all development in
the H-C District comply with the applicable Harmony Corridor design standards.
3. The Application’s satisfaction of the applicable Article 2, 3 and 4 requirements of the Land
Use Code is sufficiently detailed in the Staff Report, a copy of which is attached as
ATTACHMENT A and is incorporated herein by reference.
DECISION
Based on the findings set forth above, the Hearing Officer hereby enters the following ruling:
A. The Angie Lee Periodontics Project Development Plan (PDP #160012) is approved
for the Property as submitted.
B. The Applicant shall submit a final plan for the Property within three (3) years of the
date of this decision. If Applicant fails to submit a final plan to the City within said
three (3) year period, this PDP approval shall automatically lapse and become null
and void in accordance with Section 2.2.11(C) of the Code.
C. In accordance with Section 2.2.11(C) of the Code, the Angie Lee Periodontics PDP
shall not be considered a site specific development plan and no vested rights shall
attach to the PDP.
Nothing in this decision shall abrogate the Director’s authority to grant one (1) extension of the
Angie Lee Periodontics PDP. As set forth in Section 2.2.11(C) of the Land Use Code, the extension
may not exceed six (6) months in length.
5
DATED this 10
th
day of June, 2016.
___________________________________
Marcus A. McAskin
Hearing Officer
6
ATTACHMENT A
Staff Report
Angie Lee Periodontics Project Development Plan
(PDP# 160012)
Item 2
Item # 2 Page 1
STAFF REPORT June 6, 2016
Hearing Officer
PROJECT NAME
ANGIE LEE PERIODONTICS, PDP160012
STAFF
Jason Holland, City Planner
PROJECT INFORMATION
PROJECT DESCRIPTION: This is a proposal for a one-story 7,300 square foot building composed of
a 4,400 square foot dental office for Angie Lee Periodontics and a 2,900
square foot building expansion area. The plan also proposes 23 off-street
parking spaces, a 6-foot wide sidewalk to the north, street trees and other
landscaping. The property is located on Lot 2 of the Miramont Self
Storage P.U.D (southwest of the Oakridge Drive and Boardwalk Drive
intersection) and is zoned Harmony Corridor District (H-C).This project is
subject to approval by a Hearing Officer (Type 1 review).
APPLICANT: Russ Lee
Ripley Design, Inc.
419 Canyon Avenue, Suite 200
Fort Collins, CO 80521
OWNER: Aspen Summit LLC
1223 Red Oak Ct.
Fort Collins, CO 80525
RECOMMENDATION: Approval
EXECUTIVE SUMMARY
The approval of the Angie Lee PDP complies with the applicable requirements of the City of Fort Collins
Land Use Code (LUC), more specifically:
• The Angie Lee PDP complies with process located in Division 2.2 - Common Development
Review Procedures for Development Applications of Article 2 – Administration.
• The Angie Lee PDP complies with the relevant Harmony Corridor District standards in
Division 4.26 of the Land Use Code.
• The Angie Lee PDP complies with the relevant standards located in Article 3.
Item 2
Item # 2 Page 2
VICINITY MAP:
Item 2
Item # 2 Page 3
COMMENTS:
1. Background:
The surrounding zoning and land uses are as follows:
Direction Zone District Existing Land Uses
North Harmony Corridor District (H-C) Miramont Office Park – Learning Experience
child care
South Harmony Corridor District (H-C) Miramont Self Storage PUD
East Medium Density Mixed-Use
Neighborhood District (M-M-N)
Oak Hill Apartments PUD
West Harmony Corridor District (H-C) Miramont Self Storage PUD
• The property and surrounding area was annexed in August 1980 as part of the Keenland
Annexation.
• The subject property was originally planned in 2001 as Lot 2 of the Miramont Self Storage PUD
(see attached plan). At that time, Lot 2 was planned as a 7,500 “Office Building” with a similar
site layout as what is proposed with the Angie Lee Periodontics PDP.
2. Compliance with Applicable Harmony Corridor District Standards:
The project complies with all applicable Harmony Corridor standards with the following relevant
comments provided:
A. Section 4.26(A) - Purpose
The proposed land uses and site configuration are consistent with the purpose of the Harmony
Corridor District, by contributing to an attractive and complete mixed-use area with a major
employment base.
B. Section 4.26(B) - Permitted Uses
The proposed land uses are consistent with the permitted uses in the Harmony Corridor
District, subject to a Type 1 administrative review. The development uses specifically
proposed with the P.D.P. are Offices, Financial Services and Clinics. All of these proposed
uses are considered Primary Commercial Uses and no Secondary Uses are proposed.
Examples of Primary Uses in the H-C District are research and testing facilities, hospitals,
industrial, regional and international headquarters, private schools and universities, and
professional offices.
Examples of Secondary Uses in the H-C District are child care centers, lodging, convenience
shopping centers, standard restaurants, and residential uses. Secondary Uses are limited to
not more than 25% of the total gross area of development plans in the H-C zone district.
Item 2
Item # 2 Page 4
C. Section 4.26(D) - Land Use Standards
Section 4.26(D)(3)(a) designates a maximum building height of 6 stories for all nonresidential
buildings. A maximum building height of 1 story is proposed in conformance with this
standard.
D. Section 4.26(E) - Development Standards
Section 4.26(E)(1) requires that all development in the H-C Harmony Corridor District shall also
comply with the applicable Harmony Corridor design standards. A copy of the Harmony Corridor
standards that are referenced in the Land Use Code can be viewed here:
http://www.fcgov.com/planning/pdf/harmony-corridor-standards-doc.pdf
Typically these standards are more relevant for larger scale projects that include multiple
parcels, buildings, and uses. Also, additional standards apply to development proposals with
frontage on Harmony Road. The project is in compliance with all applicable design standards as
follows:
• The landscape pattern, plant section, and sidewalk alignment are consistent with the
Harmony standards.
• The building design provides an overall high quality, attractive architectural design,
consistent with the Harmony Corridor Standards.
• All parking is fully screened from public streets by plant material and building
placement.
3. Compliance with Article 3 of the Land Use Code - General Development Standards
The project complies with all applicable General Development Standards with the following
relevant comments provided:
A. Section 3.2.1 - Landscaping
• Street trees and “Full Tree Stocking” are provided along all high use and high visibility
areas of the development in accordance with the standards of this section.
• Ground cover areas in parking lots and at the building foundation are also planted in
accordance with the minimum requirements, with deciduous and evergreen shrubs,
perennials and ornamental grasses used extensively. Trees are planted in the parking
lot interior and perimeter in conformance with the minimum requirements and in
conformance with the standards recommended with the Harmony Corridor design
guidelines.
• Ornamental Street trees are proposed along East Boardwalk Drive. Tree spacing is
required to be between 20 and 40 foot intervals when ornamental trees are used. The
project has approximately 145 feet of frontage and six ornamental trees are proposed,
which is an average spacing of 24 feet, in compliance with this standard.
Item 2
Item # 2 Page 5
• Native and low-water-use landscaping is provided along the building foundation, in
compliance with Section 3.2.1(E)(2)(d) which requires that planting beds at least five
feet in depth are provided along at least 50% of the building walls.
• Section 3.2.1(E)(5) Parking Lot Interior Landscaping requires a minimum of 6%
interior landscape space. The parking lot area perimeter is approximately 7,740
square feet, with 464 square feet of interior landscape area required. The project
provides approximately 630 square feet of interior landscape area, in compliance with
this standard.
• This section also requires that requires that landscaped islands with canopy shade
trees be evenly distributed through the project:
o 3.2.1(E)(5)(b) Maximized Area of Shading. Landscaped islands shall be
evenly distributed to the maximum extent feasible. At a minimum, trees shall
be planted at a ratio of at least one (1) canopy shade tree per one hundred
fifty (150) square feet of internal landscaped area with a landscaped surface of
turf, ground cover perennials or mulched shrub plantings.
o 3.2.1(E)(5)(b) (c) Landscaped Islands. In addition to any pedestrian refuge
areas, each landscaped island shall include one (1) or more canopy shade
trees, be of length greater than eight (8) feet in its smallest dimension, include
at least eighty (80) square feet of ground area per tree to allow for root
aeration, and have raised concrete curbs.
o The project provides a total of four canopy shade trees within the parking area
in conformance with this standard.
B. Section 3.2.2 - Access, Circulation and Parking
A total of 23 off-street parking spaces are provided in accordance with the minimum and
maximum quantity permitted in this section. The building is 7,300 square feet total. For the uses
proposed, the following minimum and maximum parking is calculated as follows per LUC Section
3.2.2(K)(1)(a):
• Minimum: 2/1000; 15 spaces required;
• Maximum: 3.5/1000 (average); 25 spaces permitted.
The parking spaces and drive isles provided meet the minimum dimensional requirements in this
section. In conformance with the Purpose, General Standard and Development Standards
described in this section, the parking and circulation system provided with the project is well
designed with regard to safety, efficiency and convenience for vehicles, bicycles, pedestrians
and transit.
C. Section 3.5.3 - Mixed-Use, Institutional and Commercial Buildings
• The overall building design provides a reasonable level of quality that satisfies the
commercial building requirements of this section. Variations in massing, juxtaposed
materials and forms with varied patterns of recesses and projections provide vertical
and horizontal interest, breaking down the overall scale of the building.
Item 2
Item # 2 Page 6
• All building elevations provide a recognizable base and top treatment in accordance
with Section 3.5.3(D)(6). Entrance canopies and vertically projecting roof elements
are used to further articulate the building and provide material emphasis.
• The building is oriented towards the street in conformance with the “build-to” line
requirement;
• Entrances are clearly identified and articulated with a prominent steel entrance
canopy as a sheltering element;
• All facades are subdivided and proportioned using features such as windows,
changes in roofline, architectural columns, masonry panels, and changes in texture
and material.
4. Neighborhood Meeting
Due to the uses proposed, a City neighborhood meeting was not required and the applicant did not elect
to hold a neighborhood meeting for the project.
5. Findings of Fact
When considering the Angie Lee Periodontics Project Development Plan, PDP160012, staff makes the
following findings of fact:
A. The Angie Lee Periodontics PDP complies with the process located in Division 2.2 -
Common Development Review Procedures for Development Applications of Article 2 -
Administration.
B. The Angie Lee Periodontics PDP complies with the relevant Harmony Corridor District
standards in Division 4.26 of the Land Use Code.
C. The Major Amendment complies with the relevant standards located in Article 3 - General
Development Standards.
RECOMMENDATION:
Staff recommends Angie Lee Periodontics Project Development Plan, PDP160012 based on the
Findings of Fact.
Item 2
Item # 2 Page 7
ATTACHMENTS
1. Site, Landscape and Lighting Plan (PDF)
2. Building Elevations (PDF)
3. Utility Plan (PDF)
4. Statement of Planning Objectives (PDF)
5. Existing Miramont Plat (PDF)
6. Existing Miramont Office Park Plat (PDF)
7. Original Miramont PUD plan (PDF)
8. Easement Letter (PDF)