HomeMy WebLinkAbout221 E. MOUNTAIN AVENUE - BASIC DEVELOPMENT REVIEW - BDR160011 - SUBMITTAL DOCUMENTS - ROUND 1 - GEOTECHNICAL (SOILS) REPORTGeotechnical Engineering Report
221 East Mountain Office Building
221 East Mountain Avenue
Fort Collins, Colorado
April 20, 2016
Terracon Project No. 20165029
Prepared for:
MAV Development Co
Ann Arbor, Michigan
Prepared by:
Terracon Consultants, Inc.
Fort Collins, Colorado
TABLE OF CONTENTS
EXECUTIVE SUMMARY ............................................................................................................ i
1.0 INTRODUCTION ............................................................................................................ 1
2.0 PROJECT INFORMATION ............................................................................................ 1
2.1 Project Description .............................................................................................. 1
2.2 Site Location and Description ............................................................................. 2
3.0 SUBSURFACE CONDITIONS ....................................................................................... 2
3.1 Geology .............................................................................................................. 2
3.2 Typical Subsurface Profile .................................................................................. 2
3.3 Laboratory Testing .............................................................................................. 3
3.4 Corrosion Protection (Water-Soluble Sulfates) .................................................... 3
3.5 Groundwater ....................................................................................................... 3
3.6 Pressuremeter Testing ........................................................................................ 4
4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION ..................................... 4
4.1 Geotechnical Considerations .............................................................................. 4
4.1.1 Groundwater and Caving Soils ................................................................ 4
4.1.2 Foundation and Floor System Recommendations ................................... 5
4.2 Earthwork ........................................................................................................... 5
4.2.1 Site Preparation........................................................................................ 5
4.2.2 Demolition ............................................................................................... 5
4.2.3 Excavation ............................................................................................... 6
4.2.4 Subgrade Preparation .............................................................................. 6
4.2.5 Fill Materials and Placement ..................................................................... 7
4.2.6 Compaction Requirements ....................................................................... 8
4.2.7 Utility Trench Backfill ............................................................................... 8
4.2.8 Grading and Drainage .............................................................................. 9
4.3 Foundations .......................................................................................................10
4.3.1 Drilled Piers Bottomed in Bedrock - Design Recommendations ..............10
4.3.2 Drilled Piers Bottomed in Bedrock - Construction Considerations ...........11
4.3.3 Spread Footings - Design Recommendations .........................................11
4.3.4 Spread Footings - Construction Considerations ......................................12
4.4 Seismic Considerations......................................................................................13
4.5 Floor Systems ....................................................................................................13
4.5.1 Floor System - Design Recommendations ..............................................13
4.5.2 Floor Systems - Construction Considerations .........................................14
4.6 Elevator Pit ........................................................................................................14
4.6.1 Elevator Pit Design Recommendations ...................................................14
4.6.2 Elevator Pit Construction Considerations ................................................15
4.7 Pavements .........................................................................................................15
4.7.1 Pavements – Subgrade Preparation .......................................................15
4.7.2 Pavements – Design Recommendations ................................................16
4.7.3 Pavements – Construction Considerations .............................................18
4.7.4 Pavements – Maintenance .....................................................................18
5.0 GENERAL COMMENTS ...............................................................................................18
TABLE OF CONTENTS (continued)
Appendix A – FIELD EXPLORATION
Exhibit A-1 Site Location Map
Exhibit A-2 Exploration Plan
Exhibit A-3 Field Exploration Description
Exhibits A-4 to A-7 Boring Logs
Exhibits A-8 to A-10 Pressuremeter Test Results
Appendix B – LABORATORY TESTING
Exhibit B-1 Laboratory Testing Description
Exhibit B-2 Atterberg Limits Test Results
Exhibit B-3 Grain-size Distribution Test Results
Exhibit B-4 Water-soluble Sulfate Test Results
Appendix C – SUPPORTING DOCUMENTS
Exhibit C-1 General Notes
Exhibit C-2 Unified Soil Classification System
Exhibit C-3 Description of Rock Properties
Exhibit C-4 Laboratory Test Significance and Purpose
Exhibits C-5 and C-6 Report Terminology
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable i
EXECUTIVE SUMMARY
A geotechnical investigation has been performed for the proposed office building to be constructed
at 221 East Mountain Avenue in Fort Collins, Colorado. Four (4) borings, presented as Exhibits
A-4 through A-7 and designated as Boring No. 1 through Boring No. 4, were performed to depths of
approximately 15.3 to 35 feet below existing site grades. This report specifically addresses the
recommendations for the proposed office building. Borings performed in these areas are for
informational purposes and will be utilized by others.
Based on the information obtained from our subsurface exploration, the site can be developed for
the proposed project. However, the following geotechnical considerations were identified and will
need to be considered:
Borings completed as part of our geotechnical study at this site were performed in the existing
parking lot and pavement areas surrounding the existing structure currently occupying the
site. Existing pavement materials encountered in our borings generally consisted of 3 to 8
inches of asphalt, concrete or asphalt overlying concrete.
Subsurface conditions encountered below the existing pavement materials generally consist
of about 2 to 3 feet of sand with varying amounts of clay over about 10 feet of well graded
sand with varying amounts of gravel and cobbles. Sandstone bedrock was encountered
below the sands with gravels and cobbles at depths ranging from about 13 to 14 feet below
existing site grades and extended to the maximum depths explored.
Groundwater was encountered in two of the borings at depths of about 12 to 13 feet below
existing ground surface during drilling and approximately one day after drilling. Groundwater
levels can and should be expected to fluctuate with varying seasonal and weather conditions,
irrigation on or adjacent to the site and with fluctuations in nearby water features.
Demolition of the existing building currently occupying the site should include complete
removal of all foundation systems, pavements, floor slabs, and exterior flatwork within the
proposed construction area. Discussions regarding re-use of the asphalt and concrete as
recycled materials during the new construction are presented in the report.
The proposed building may be supported on either a drilled pier foundation system
bottomed in bedrock or a shallow footing foundations bearing on the dense native soil or
on newly placed engineered fill. Drilled piers will require temporary casing for proper
construction. Heavy-duty pier drilling equipment will also likely be required to penetrate
the very hard sandstone identified below the site.
A slab-on-grade floor system is recommended for the proposed building.
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable ii
The amount of movement of foundations, floor slabs, pavements, etc. will be related to the
wetting of underlying supporting soils. Therefore, it is imperative the recommendations
discussed in the 4.2.8 Grading and Drainage section of this report be followed to reduce
potential movement.
The 2012 International Building Code, Table 1613.5.2 IBC seismic site classification for this
site is C.
Close monitoring of the construction operations discussed herein will be critical in achieving
the design subgrade support. We therefore recommend that Terracon be retained to
monitor this portion of the work.
This summary should be used in conjunction with the entire report for design purposes. It should
be recognized that details were not included or fully developed in this section, and the report must
be read in its entirety for a comprehensive understanding of the items contained herein. The section
titled GENERAL COMMENTS should be read for an understanding of the report limitations.
Responsive ■ Resourceful ■ Reliable 1
GEOTECHNICAL ENGINEERING REPORT
221 East Mountain Office Building
221 East Mountain Avenue
Fort Collins, Colorado
Terracon Project No. 20165029
April 20, 2016
1.0 INTRODUCTION
This report presents the results of our geotechnical engineering services performed for the
proposed office building to be located at 221 East Mountain Avenue in Fort Collins, Colorado
(Exhibit A-1). The purpose of these services is to provide information and geotechnical
engineering recommendations relative to:
subsurface soil and bedrock conditions foundation design and construction
groundwater conditions floor slab design and construction
grading and drainage pavement construction
lateral earth pressures earthwork
seismic considerations
Our geotechnical engineering scope of work for this project included the initial site visit, the
advancement of four test borings to depths ranging from approximately 15.3 to 35 feet below
existing site grades, laboratory testing for soil engineering properties and engineering analyses
to provide foundation, floor system and pavement design and construction recommendations.
Logs of the borings along with an Exploration Plan (Exhibit A-2) are included in Appendix A. The
results of the laboratory testing performed on soil and bedrock samples obtained from the site
during the field exploration are included in Appendix B.
2.0 PROJECT INFORMATION
2.1 Project Description
Item Description
Site layout Refer to the Exploration Plan (Exhibit A-2 in Appendix A)
Structures
We understand the new retail/office building will be a four-story
approximately 70,000 gross square foot building.
Building construction
We understand the building will be steel-framed with a slab-on-metal
deck and a slab-on-grade main level.
Maximum loads Column loads: 150 – 500 kips (provided)
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 2
Item Description
Below-grade areas
We understand that no below-grade areas are planned. However,
the proposed elevator pit will likely extend several feet below grade.
Traffic loading
NAPA Traffic Class: (assumed)
Automobile Parking Areas: Class I
Truck traffic and main drives Class II
2.2 Site Location and Description
Item Description
Location
The project site is located at 221 East Mountain Avenue in Fort
Collins, Colorado.
Existing site features
The site is partially covered by an existing building and parking lot
with some landscaped vegetation around the perimeter.
Surrounding developments
To the west and south of the site are commercial buildings, to the
north of the site is East Mountain Avenue and to the east of the site
is Mathews Street.
Current ground cover
The ground cover outside the existing building envelope is mostly
asphaltic concrete with some concrete pavement and flatwork.
Existing topography The site is relatively flat.
3.0 SUBSURFACE CONDITIONS
3.1 Geology
The Pleistocene Age Slocum Alluvium comprises the site surficial geologic materials (Colton,
19781). These materials generally consist of cobbles and gravels up to 20 feet thick. Materials
are typically well-rounded and of igneous and metamorphic origin, although some are
sedimentary (Colton, 19781).
The underlying bedrock consists of the Hygiene Sandstone Member of the Upper Cretaceous
Age Pierre Shale. A hard, glauconitic, ridge-forming sandstone makes up the upper portions of
this member and has been reported to range in thickness between 600 and 800 feet (Colton,
19781).
3.2 Typical Subsurface Profile
Specific conditions encountered at each boring location are indicated on the individual boring logs
included in Appendix A. Stratification boundaries on the boring logs represent the approximate
1 Colton, Roger B., 1978, Geologic Map of the Boulder-Fort Collins-Greeley Area, Colorado, United
States Geologic Survey, Map I-855-G.
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 3
location of changes in soil types; in-situ, the transition between materials may be gradual. Based
on the results of the borings, subsurface conditions on the project site can be generalized as
follows:
Material Description
Approximate Depth to
Bottom of Stratum (feet)
Consistency/Density/Hardness
Asphalt and concrete
About 3 to 8 inches below
existing site grades.
--
Sand with varying amount of clay
About 2 to 4 feet below existing
site grades.
Loose to dense
Well graded sand with varying
amounts of gravel and cobbles
About 13 feet below existing
site grades. Only found in
Boring Nos. 1, 2 and 3.
Medium dense to very dense
Silty clayey sand with gravel and
cobbles
About 14 feet below existing
site grades. Only found in
Boring No. 4.
Very dense
Sandstone bedrock
To the maximum depth of
exploration of about 35 feet.
Very hard
3.3 Laboratory Testing
Samples of on-site soils selected for plasticity testing exhibited low to moderate plasticity with
liquid limits ranging from 23 to 28 and plasticity indices ranging from 6 to 9. Laboratory test results
are presented in Appendix B.
3.4 Corrosion Protection (Water-Soluble Sulfates)
Results of water-soluble sulfate testing indicate that ASTM Type I or II portland cement should be
specified for all project concrete on and below grade. Foundation concrete should be designed
for low sulfate exposure in accordance with the provisions of the ACI Design Manual, Section
318, Chapter 4.
3.5 Groundwater
The boreholes were observed while drilling and after completion for the presence and level of
groundwater. In addition, delayed water levels were also obtained in some borings. The water levels
observed in the boreholes are noted on the attached boring logs, and are summarized below
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 4
Boring Number
Depth to groundwater
while drilling, ft.
Depth to groundwater
1 day after drilling, ft.
Elevation of
groundwater 1 day after
drilling, ft.
1 13 12.6 4962.1
2 Not encountered -- --
3 Not encountered -- --
4 12 Caving in borehole --
These observations represent groundwater conditions at the time of and shortly after the field
exploration, and may not be indicative of other times or at other locations. Groundwater levels
can be expected to fluctuate with varying seasonal and weather conditions, and other factors.
3.6 Pressuremeter Testing
Pressuremeter testing was performed within the sandstone bedrock at two (2) of the boring
locations (PMT 1 and PMT 2, as shown on Exhibit A-2). Two (2) tests were performed at PMT 1
and one (1) test was performed at PMT 2 at varying depths within the bedrock strata.
Pressuremeter testing was performed using a cylindrical probe with an inner rubber membrane
and an outer protective sheath that were inflated using fluid pressurized against the sidewalls of
the borings at depths determined in the field during completion of the borings. The deformation
of the bearing strata was measured periodically while increasing pressures until the bedrock failed
in shear. Pressuremeter test results are presented on Exhibits A-8 through A-10 in Appendix A.
Using the data collected during pressuremeter testing, in-situ strength parameters were
calculated including Young’s Moduli, limit pressures, and Menard deformation moduli. Using
these values, the bedrock was modeled more accurately than conventional methods, and values
for deep foundation design and construction criteria were calculated.
4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION
4.1 Geotechnical Considerations
Based on subsurface conditions encountered in the borings, the site appears suitable for the
proposed construction from a geotechnical point of view provided certain precautions and design
and construction recommendations described in this report are followed. We have identified
geotechnical conditions that could impact design and construction of the proposed structures,
pavements, and other site improvements.
4.1.1 Groundwater and Caving Soils
As previously stated, groundwater was measured at depths ranging from about 12 to 13 feet
below existing site grades. Although no below-grade areas are planned for the proposed building
other than anticipated elevator pit(s), groundwater may impact installation of deep utilities. Caving
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 5
soils and groundwater will impact construction of drilled pier foundations requiring the use of
temporary casing and placement of concrete using tremie or other similar methods.
4.1.2 Foundation and Floor System Recommendations
The proposed building may be supported on either a drilled pier foundation system bottomed in
bedrock or a spread footing foundation system bearing on properly prepared on-site soils or
properly placed imported fill. We recommend a slab-on-grade for the interior floor system of the
proposed building. Even when bearing on properly prepared soils, movement of the slab-on-
grade floor system is possible should the subgrade soils undergo an increase in moisture content.
We estimate movement of about 1 inch is possible. If the owner cannot accept the risk of slab
movement, a structural floor should be used.
4.2 Earthwork
The following presents recommendations for site preparation, demolition, excavation, subgrade
preparation and placement of engineered fills on the project. All earthwork on the project should
be observed and evaluated by Terracon on a full-time basis. The evaluation of earthwork should
include observation of removal and recompaction of existing fill materials likely to be encountered
during demolition, observation of over-excavation operations, testing of engineered fills, subgrade
preparation, subgrade stabilization, and other geotechnical conditions exposed during the
construction of the project.
4.2.1 Site Preparation
Prior to placing any fill, strip and remove existing asphalt, concrete or vegetation and any other
deleterious materials from the proposed construction area. Stripped organic materials should be
wasted from the site or used to re-vegetate landscaped areas or exposed slopes after completion
of grading operations. Prior to the placement of fills, the site should be graded to create a relatively
level surface to receive fill, and to provide for a relatively uniform thickness of fill beneath proposed
structures.
4.2.2 Demolition
Demolition of the existing on-site building should include complete removal of all foundation
systems, below-grade structural elements, pavements, and exterior flat work within the proposed
construction area. This should include removal of any utilities to be abandoned along with any loose
utility trench backfill or loose backfill found adjacent to existing foundations. All materials derived
from the demolition of existing structures and pavements should be removed from the site. The
types of foundation systems supporting the existing on-site building are not known. If some or all of
the existing buildings are supported by drilled piers, the existing piers should be truncated a
minimum depth of 3 feet below areas of planned new construction.
Consideration could be given to re-using the asphalt and concrete provided the materials are
processed and uniformly blended with the on-site soils. Asphalt and/or concrete materials should
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 6
be processed to a maximum size of 2-inches and blended at a ratio of 30 percent asphalt/concrete
to 70 percent of on-site soils.
4.2.3 Excavation
It is anticipated that excavations for the proposed construction can be accomplished with
conventional earthmoving equipment. Excavations into the on-site soils will encounter weak and/or
saturated soil conditions with possible caving conditions. Excavation penetrating the bedrock (if
required) may require the use of specialized heavy-duty equipment to advance the excavation and
facilitate rock break-up and removal. Consideration should be given to obtaining a unit price for
difficult excavation in the contract documents for the project.
The soils to be excavated can vary significantly across the site as their classifications are based
solely on the materials encountered in widely-spaced exploratory test borings. The contractor
should verify that similar conditions exist throughout the proposed area of excavation. If different
subsurface conditions are encountered at the time of construction, the actual conditions should be
evaluated to determine any excavation modifications necessary to maintain safe conditions.
Although evidence of fills or underground facilities such as septic tanks, vaults, basements, and
utilities was not observed during the site reconnaissance, such features could be encountered
during construction. If unexpected fills or underground facilities are encountered, such features
should be removed and the excavation thoroughly cleaned prior to backfill placement and/or
construction.
Depending upon depth of excavation and seasonal conditions, surface water infiltration and/or
groundwater may be encountered in excavations on the site. It is anticipated that pumping from
sumps may be utilized to control water within excavations.
The subgrade soil conditions should be evaluated during the excavation process and the stability
of the soils determined at that time by the contractors’ Competent Person. Slope inclinations flatter
than the OSHA maximum values may have to be used. The individual contractor(s) should be
made responsible for designing and constructing stable, temporary excavations as required to
maintain stability of both the excavation sides and bottom. All excavations should be sloped or
shored in the interest of safety following local, and federal regulations, including current OSHA
excavation and trench safety standards.
As a safety measure, it is recommended that all vehicles and soil piles be kept a minimum lateral
distance from the crest of the slope equal to the slope height. The exposed slope face should be
protected against the elements
4.2.4 Subgrade Preparation
After completion of site preparation, the top 8 inches of the exposed ground surface should be
scarified, moisture conditioned, and recompacted to at least 95 percent of the maximum dry unit
weight as determined by ASTM D698 before any new fill, foundation or pavement is placed.
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 7
In addition, large cobbles may be encountered beneath floor slabs or foundation areas if footings
are selected as the foundation type for the proposed building. Such conditions could create point
loads on the bottom of floor slabs and foundations, increasing the risk potential for differential
movement and cracking. If such conditions are encountered in the excavations, the cobbles
should be removed and be replaced with engineered fill, conditioned to near optimum moisture
content and compacted.
After the bottom of the excavation has been compacted, engineered fill can be placed to bring the
building pad and pavement subgrade to the desired grade. Engineered fill should be placed in
accordance with the recommendations presented in subsequent sections of this report.
The stability of the subgrade may be affected by precipitation, repetitive construction traffic or
other factors. If unstable conditions develop, workability may be improved by scarifying and
drying. Alternatively, over-excavation of wet zones and replacement with granular materials may
be used, or crushed gravel and/or rock can be tracked or “crowded” into the unstable surface soil
until a stable working surface is attained. Use of geotextile or cement could also be considered
as a stabilization technique. Laboratory evaluation is recommended to determine the effect of
chemical stabilization on subgrade soils prior to construction. Lightweight excavation equipment
may also be used to reduce subgrade pumping.
4.2.5 Fill Materials and Placement
The on-site soils or approved granular and low plasticity cohesive imported materials may be used
as fill material. The soil removed from this site that is free of organic or objectionable materials,
as defined by a field technician who is qualified in soil material identification and compaction
procedures, can be re-used as fill for the building pad and pavement subgrade. It should be noted
that clayey sand will require reworking to adjust the moisture content to meet the compaction
criteria.
Imported soils (if required) should meet the following material property requirements:
Gradation Percent finer by weight (ASTM C136)
4” 100
3” 70-100
No. 4 Sieve 50-100
No. 200 Sieve 50 (max.)
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 8
Soil Properties Values
Liquid Limit 35 (max.)
Plastic Limit 6 (max.)
Maximum Expansive Potential (%) Non-expansive1
1. Measured on a sample compacted to approximately 95 percent of the maximum dry unit weight as
determined by ASTM D698 at optimum moisture content. The sample is confined under a 100 psf
surcharge and submerged.
4.2.6 Compaction Requirements
Engineered fill should be placed and compacted in horizontal lifts, using equipment and
procedures that will produce recommended moisture contents and densities throughout the lift.
Item Description
Fill lift Thickness
9 inches or less in loose thickness when heavy, self-
propelled compaction equipment is used
4 to 6 inches in loose thickness when hand-guided
equipment (i.e. jumping jack or plate compactor) is used
Minimum compaction requirements
95 percent of the maximum dry unit weight as determined
by AASHTO T180
Moisture content -3 to +3 % of the optimum moisture content
1. We recommend engineered fill be tested for moisture content and compaction during placement.
Should the results of the in-place density tests indicate the specified moisture or compaction limits
have not been met, the area represented by the test should be reworked and retested as required
until the specified moisture and compaction requirements are achieved.
2. Specifically, moisture levels should be maintained low enough to allow for satisfactory compaction to
be achieved without the fill material pumping when proofrolled.
4.2.7 Utility Trench Backfill
All trench excavations should be made with sufficient working space to permit construction including
backfill placement and compaction.
All underground piping within or near the proposed structure should be designed with flexible
couplings, so minor deviations in alignment do not result in breakage or distress. Utility knockouts
in foundation walls should be oversized to accommodate differential movements. It is imperative
that utility trenches be properly backfilled with relatively clean materials. If utility trenches are
backfilled with relatively clean granular material, they should be capped with at least 18 inches of
cohesive fill in non-pavement areas to reduce the infiltration and conveyance of surface water
through the trench backfill.
Utility trenches are a common source of water infiltration and migration. All utility trenches that
penetrate beneath the building should be effectively sealed to restrict water intrusion and flow
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 9
through the trenches that could migrate below the building. We recommend constructing an
effective clay “trench plug” that extends at least 5 feet out from the face of the building exterior. The
plug material should consist of clay compacted at a water content at or above the soil’s optimum
water content. The clay fill should be placed to completely surround the utility line and be compacted
in accordance with recommendations in this report.
It is strongly recommended that a representative of Terracon provide full-time observation and
compaction testing of trench backfill within building and pavement areas.
4.2.8 Grading and Drainage
All grades must be adjusted to provide effective drainage away from the proposed building and
existing buildings surrounding the site during construction and maintained throughout the life of
the proposed project. Infiltration of water into foundation excavations must be prevented during
construction. Landscape irrigation adjacent to foundations should be minimized or eliminated.
Water permitted to pond near or adjacent to the perimeter of the structure (either during or post-
construction) can result in significantly higher soil movements than those discussed in this report.
As a result, any estimations of potential movement described in this report cannot be relied upon
if positive drainage is not obtained and maintained, and water is allowed to infiltrate the fill and/or
subgrade.
Exposed ground (if any) should be sloped at a minimum of 10 percent grade for at least 10 feet
beyond the perimeter of the proposed building, where possible. The use of swales, chases and/or
area drains may be required to facilitate drainage in unpaved areas around the perimeter of the
building. Backfill against foundations and exterior walls should be properly compacted and free of
all construction debris to reduce the possibility of moisture infiltration. After construction of the
proposed building and prior to project completion, we recommend verification of final grading be
performed to document positive drainage, as described above, has been achieved.
Flatwork and pavements will be subject to post-construction movement. Maximum grades
practical should be used for paving and flatwork to prevent areas where water can pond. In
addition, allowances in final grades should take into consideration post-construction movement
of flatwork, particularly if such movement would be critical. Where paving or flatwork abuts the
structure, care should be taken that joints are properly sealed and maintained to prevent the
infiltration of surface water.
Planters located adjacent to structure should preferably be self-contained. Sprinkler mains and
spray heads should be located a minimum of 5 feet away from the building line(s). Low-volume,
drip style landscaped irrigation should not be used near the building. Roof drains should
discharge on to pavements or be extended away from the structure a minimum of 10 feet through
the use of splash blocks or downspout extensions. A preferred alternative is to have the roof
drains discharge by solid pipe to storm sewers or to a detention pond or other appropriate outfall.
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 10
4.3 Foundations
The proposed building can be supported by either a drilled pier foundation system bottomed in
bedrock or a shallow, spread footing foundation system. Design recommendations for
foundations for the proposed structure and related structural elements are presented in the
following paragraphs.
4.3.1 Drilled Piers Bottomed in Bedrock - Design Recommendations
Description Value
Estimated pier length 16 to 20 feet
Minimum pier diameter 18 inches
Minimum bedrock embedment 1 6 feet
Maximum allowable end-bearing pressure 80,000 psf
Allowable skin friction (for portion of pier embedded into bedrock 3,500 psf
1. Drilled piers should be embedded into hard or very hard bedrock materials. Actual structural
loads and pier diameters may dictate embedment deeper than the recommended minimum
penetration.
Piers should be considered to work in group action if the horizontal spacing is less than three pier
diameters. A minimum practical horizontal clear spacing between piers of at least three diameters
should be maintained, and adjacent piers should bear at the same elevation. The capacity of
individual piers must be reduced when considering the effects of group action. Capacity reduction
is a function of pier spacing and the number of piers within a group. If group action analyses are
necessary, capacity reduction factors can be provided for the analyses.
To satisfy forces in the horizontal direction using LPILE, piers may be designed for the following
lateral load criteria:
Parameters Sand
Sandstone
Bedrock
LPILE soil type Sand (Reese) Sand (Reese)
Effective unit weight (pcf) above groundwater 120 125
Effective unit weight (pcf) below groundwater 60 125 (perched)
Average angle of internal friction, (degrees) 35 40
Coefficient of subgrade reaction, k (pci)* 90 225
1. For purposes of LPILE analysis, assume a groundwater depth of about 12 feet below existing
ground surface (approximately Elev. 4963 feet).
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 11
4.3.2 Drilled Piers Bottomed in Bedrock - Construction Considerations
Very hard sandstone bedrock was encountered below the entire site. It is possible drilling to design
depth may require specialized drilling equipment for completion of pier holes into the very hard
bedrock layers.
Groundwater/caving soil conditions indicate that temporary steel casing may be required to properly
drill and clean piers prior to concrete placement. Groundwater should be removed from each pier
hole prior to concrete placement. Pier concrete should be placed immediately after completion of
drilling and cleaning. If pier concrete cannot be placed in dry conditions, a tremie should be used
for concrete placement. Free-fall concrete placement in piers will only be acceptable if provisions
are taken to avoid striking the concrete on the sides of the hole or reinforcing steel. The use of a
bottom-dump hopper, or an elephant's trunk discharging near the bottom of the hole where concrete
segregation will be minimized, is recommended. Due to potential sloughing and raveling, foundation
concrete quantities may exceed calculated geometric volumes.
Casing should be withdrawn in a slow continuous manner maintaining a sufficient head of
concrete to prevent infiltration of water or caving soils or the creation of voids in pier concrete.
Pier concrete should have a relatively high fluidity when placed in cased pier holes or through a
tremie. Pier concrete with slump in the range of 5 to 7 inches is recommended.
We recommend the sides of each pier should be mechanically roughened in the sandstone
bearing strata. This should be accomplished by a roughening tooth placed on the auger. Shaft
bearing surfaces must be cleaned prior to concrete placement. A representative of Terracon
should observe the bearing surface and shaft configuration.
4.3.3 Spread Footings - Design Recommendations
As an alternative, we believe the proposed building can be constructed on spread footing
foundations bearing on properly prepared on-site soils or newly placed engineered fill. We
understand column loads may be as large as 500 kips which could result in very large footing pad
sizes. However, subsurface conditions below this site are conducive to support of spread footing
foundations and we believe they are a viable foundation alternative.
Description Values
Bearing material
Properly prepared on-site soil or new, properly
placed engineered fill.
Maximum allowable bearing pressure 1 3,500 psf
Lateral earth pressure coefficients 2
Active, Ka = 0.27
Passive, Kp = 3.69
At-rest, Ko = 0.43
Sliding coefficient 2 µ = 0.56
Moist soil unit weight ɣ = 120 pcf
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 12
Description Values
Minimum embedment depth below finished
grade 3
30 inches
Estimated total movement About 1 inch
Estimated differential movement About ½ to ¾ of total movement
1. The recommended maximum allowable bearing pressure assumes any unsuitable fill or loose soils,
if encountered, will be over-excavated and replaced with properly compacted engineered fill. The
design bearing pressure applies to a dead load plus design live load condition. The design bearing
pressure may be increased by one-third when considering total loads that include wind or seismic
conditions.
2. The lateral earth pressure coefficients and sliding coefficients are ultimate values and do not include
a factor of safety. The foundation designer should include the appropriate factors of safety.
3. For frost protection and to reduce the effects of seasonal moisture variations in the subgrade soils.
The minimum embedment depth is for perimeter footings beneath unheated areas and is relative to
lowest adjacent finished grade, typically exterior grade.
Footings should be proportioned to reduce differential foundation movement. As discussed, total
movement resulting from the assumed structural loads is estimated to be on the order of about 1
inch. Additional foundation movements could occur if water from any source infiltrates the
foundation soils; therefore, proper drainage should be provided in the final design and during
construction and throughout the life of the structure. Failure to maintain the proper drainage as
recommended in the 4.2.8 Grading and Drainage section of this report will nullify the movement
estimates provided above.
4.3.4 Spread Footings - Construction Considerations
Spread footing construction should only be considered if the estimated foundation movement can
be tolerated. Subgrade soils beneath footings should be moisture conditioned and compacted as
described in the 4.2 Earthwork section of this report. The moisture content and compaction of
subgrade soils should be maintained until foundation construction.
Footings and foundation walls should be reinforced as necessary to reduce the potential for distress
caused by differential foundation movement.
Unstable subgrade conditions should be observed by Terracon to assess the subgrade and
provide suitable alternatives for stabilization. Stabilized areas should be proof-rolled prior to
continuing construction to assess the stability of the subgrade.
Foundation excavations and confirmation of appropriate demolition and reworking below the
building pad should be observed by Terracon. If the soil conditions encountered differ significantly
from those presented in this report, supplemental recommendations will be required.
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 13
4.4 Seismic Considerations
Code Used Site Classification
2012 International Building Code (IBC) 1 C 2
1. In general accordance with the 2012 International Building Code, Table 1613.5.2.
2. The 2012 International Building Code (IBC) requires a site soil profile determination extending a
depth of 100 feet for seismic site classification. The current scope requested does not include the
required 100 foot soil profile determination. The borings completed for this project extended to a
maximum depth of about 35 feet and this seismic site class definition considers that similar soil and
bedrock conditions exist below the maximum depth of the subsurface exploration. Additional
exploration to deeper depths could be performed to confirm the conditions below the current depth of
exploration. Alternatively, a geophysical exploration could be utilized in order to attempt to justify a
more favorable seismic site class. However, we believe a higher seismic site class for this site is
unlikely.
4.5 Floor Systems
A slab-on-grade may be utilized for the interior floor system for the proposed building. All existing
fill and construction debris associated with demolition of the existing structure should be
completely removed and replaced with properly compacted fill prior to construction of the
proposed floor slab. If the estimated movement cannot be tolerated, a structurally-supported floor
system, supported independent of the subgrade materials, is recommended.
Subgrade soils beneath interior and exterior slabs should be scarified to a depth of at least 8
inches, moisture conditioned and compacted. The moisture content and compaction of subgrade
soils should be maintained until slab construction.
4.5.1 Floor System - Design Recommendations
Even when bearing on properly prepared soils, movement of the slab-on-grade floor system is
possible should the subgrade soils undergo an increase in moisture content. We estimate
movement of about 1 inch is possible. If the owner cannot accept the risk of slab movement, a
structural floor should be used. If conventional slab-on-grade is utilized, the subgrade soils should
be prepared as presented in the 4.2 Earthwork section of this report.
For structural design of concrete slabs-on-grade subjected to point loadings, a modulus of
subgrade reaction of 150 pounds per cubic inch (pci) may be used for floors supported on re-
compacted existing soils at the site.
Additional floor slab design and construction recommendations are as follows:
Positive separations and/or isolation joints should be provided between slabs and all
foundations, columns, or utility lines to allow independent movement.
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 14
Control joints should be saw-cut in slabs in accordance with ACI Design Manual, Section
302.1R-37 8.3.12 (tooled control joints are not recommended) to control the location and
extent of cracking.
Interior utility trench backfill placed beneath slabs should be compacted in accordance
with the recommendations presented in the 4.2 Earthwork section of this report.
Floor slabs should not be constructed on frozen subgrade.
The use of a vapor retarder should be considered beneath concrete slabs that will be
covered with wood, tile, carpet or other moisture sensitive or impervious floor coverings,
or when the slab will support equipment sensitive to moisture. When conditions warrant
the use of a vapor retarder, the slab designer and slab contractor should refer to ACI
302 for procedures and cautions regarding the use and placement of a vapor retarder.
Other design and construction considerations, as outlined in the ACI Design Manual,
Section 302.1R are recommended.
4.5.2 Floor Systems - Construction Considerations
Movements of slabs-on-grade using the recommendations discussed in previous sections of this
report will likely be reduced and tend to be more uniform. The estimates discussed above assume
that the other recommendations in this report are followed. Additional movement could occur
should the subsurface soils become wetted to significant depths, which could result in potential
excessive movement causing uneven floor slabs and severe cracking. This could be due to over
watering of landscaping, poor drainage, improperly functioning drain systems, and/or broken utility
lines. Therefore, it is imperative that the recommendations presented in this report be followed.
4.6 Elevator Pit
We anticipate an elevator pit will be included in the interior of the building. The elevator pit will
likely consist of reinforced concrete walls with a concrete base slab. Based on our experience
with this type of structure, we anticipate the base slabs will be about 5 feet below the level of the
finished floor slab.
4.6.1 Elevator Pit Design Recommendations
Subsurface conditions in elevator pit excavations are generally anticipated to consist of sands with
varying amounts of clay, gravel and possible cobbles. Groundwater was encountered at depths of
about 12 to 13 feet below existing site grades at the time of our field exploration. However,
groundwater levels can and should be expected to fluctuate over time. We do not anticipate
groundwater will significantly impact the elevator pit construction at this site.
The elevator pit walls should be designed for the lateral earth pressures imposed by the soil
backfill. Earth pressures will primarily be influenced by structural design of the walls, conditions
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 15
of wall restraint and type, compaction and drainage of the backfill. For purposes of design, we
have assumed approximately 5 feet of fill will be retained by the pit walls and backfill will consist of
the on-site clayey sands. If taller walls are planned, or if different type of backfill is used, we should
be contacted to review our data and confirm or modify the design criteria presented below.
Active earth pressure is commonly used for design of walls (such as free-standing cantilever
retaining walls) and assumes some wall rotation and deflection. For walls that can deflect and
rotate about the base, with top lateral movements of about ¼ to ½ percent or more of the wall
height, lower “active” earth pressures could be considered for design. Use of the “active” condition
assumes deflection and thus cracking of walls could occur. For rigid walls where negligible or very
little rotation and deflection will occur, "at-rest" lateral earth pressures should be used in the
design.
Reinforced concrete pit walls should be designed for lateral earth pressures at least equal to those
indicated in the following table.
Earth Pressure
Conditions
Backfill Soil Type
Equivalent Fluid Density
(pcf)
Active (Ka) On-site sands 32
At-Rest (Ko) On-site sands 52
The lateral earth pressures presented above do not include a factor of safety. As such, appropriate
factors of safety should be applied to these values. Furthermore, the lateral earth pressures do
not include the influence of surcharge, equipment or floor loading, which should be added.
4.6.2 Elevator Pit Construction Considerations
The elevator pit excavations should be observed by the geotechnical engineer to confirm that the
subsurface conditions are consistent with those encountered in our test borings. If the soil
conditions encountered differ from those presented in this report, supplemental recommendations
will be required. Where loose or unsuitable bearing materials are encountered in the excavation,
these materials should be over-excavated to the minimum depth determined by the geotechnical
engineer and replaced with approved engineered fill. Terracon should be contacted to evaluate
bearing conditions in the elevator pit excavations well in advance of forming foundations.
4.7 Pavements
4.7.1 Pavements – Subgrade Preparation
On most project sites, the site grading is accomplished relatively early in the construction phase.
Fills are typically placed and compacted in a uniform manner. However as construction proceeds,
the subgrade may be disturbed due to utility excavations, construction traffic, desiccation, or
rainfall/snow melt. As a result, the pavement subgrade may not be suitable for pavement
construction and corrective action will be required. The subgrade should be carefully evaluated
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 16
at the time of pavement construction for signs of disturbance or instability. We recommend the
pavement subgrade be thoroughly proofrolled with a loaded tandem-axle dump truck prior to final
grading and paving. All pavement areas should be moisture conditioned and properly compacted
to the recommendations in this report immediately prior to paving.
4.7.2 Pavements – Design Recommendations
Design of new privately-maintained pavements for the project has been based on the procedures
described by the National Asphalt Pavement Associations (NAPA) and the American Concrete
Institute (ACI).
We assumed the following design parameters for NAPA flexible pavement thickness design:
Automobile Parking Areas
Class I - Parking stalls and parking lots for cars and pick-up trucks, with
Equivalent Single Axle Load (ESAL) up to 7,000 over 20 years
Main Traffic Corridors
Class II – Parking lots with a maximum of 10 trucks per day with Equivalent
Single Axle Load (ESAL) up to 27,000 over 20 years (Including trash trucks)
Subgrade Soil Characteristics
USCS Classification – SC to SW, classified by NAPA as Medium to Good
We assumed the following design parameters for ACI rigid pavement thickness design based
upon the average daily truck traffic (ADTT):
Automobile Parking Areas
ACI Category A: Automobile parking with an ADTT of 1 over 20 years
Main Traffic Corridors
ACI Category A: Automobile parking area and service lanes with an ADTT of
up to 10 over 20 years
Subgrade Soil Characteristics
USCS Classification – SC to SW
Concrete modulus of rupture value of 600 psi
We should be contacted to confirm and/or modify the recommendations contained herein if actual
traffic volumes differ from the assumed values shown above.
Recommended alternatives for flexible and rigid pavements are summarized for each traffic area
as follows:
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 17
Traffic Area
Alternative
Recommended Pavement Thicknesses (Inches)
Asphaltic
Concrete
Surface
Aggregate
Base Course1
Portland
Cement
Concrete
Total
Automobile Parking Areas
(NAPA Class I and ACI Category A)
A 3½ 6 -- 9½
B - - 5 5
Main Traffic Corridors
(NAPA Class II and ACI Category A)
A 4½ 6 - 10½
B - - 6 6
Aggregate base course (if used on the site) should consist of a blend of sand and gravel which
meets strict specifications for quality and gradation. Use of materials meeting Colorado
Department of Transportation (CDOT) Class 5 or 6 specifications is recommended for aggregate
base course. Aggregate base course should be placed in lifts not exceeding 6 inches and
compacted to a minimum of 95 percent of the maximum dry unit weight as determined by ASTM
D698.
Asphaltic concrete should be composed of a mixture of aggregate, filler and additives (if required)
and approved bituminous material. The asphalt concrete should conform to approved mix
designs stating the Superpave properties, optimum asphalt content, job mix formula and
recommended mixing and placing temperatures. Aggregate used in asphalt concrete should
meet particular gradations. Material meeting CDOT Grading S or SX specifications or equivalent
is recommended for asphalt concrete. Mix designs should be submitted prior to construction to
verify their adequacy. Asphalt material should be placed in maximum 3-inch lifts and compacted
within a range of 92 to 96 percent of the theoretical maximum (Rice) density (ASTM D2041).
Where rigid pavements are used, the concrete should be produced from an approved mix design
with the following minimum properties:
Properties Value
Compressive strength 4,000 psi
Cement type Type I or II portland cement
Entrained air content (%) 5 to 8
Concrete aggregate ASTM C33 and CDOT section 703
Concrete should be deposited by truck mixers or agitators and placed a maximum of 90 minutes
from the time the water is added to the mix. Longitudinal and transverse joints should be provided
as needed in concrete pavements for expansion/contraction and isolation per ACI 325. The
location and extent of joints should be based upon the final pavement geometry.
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 18
For areas subject to concentrated and repetitive loading conditions (if any) such as dumpster
pads, truck delivery docks and ingress/egress aprons, we recommend using a portland cement
concrete pavement with a thickness of at least 6 inches underlain by at least 4 inches of granular
base. Prior to placement of the granular base, the areas should be thoroughly proofrolled. For
dumpster pads, the concrete pavement area should be large enough to support the container and
tipping axle of the refuse truck.
Pavement performance is affected by its surroundings. In addition to providing preventive
maintenance, the civil engineer should consider the following recommendations in the design and
layout of pavements:
Site grades should slope a minimum of 2 percent away from the pavements;
The subgrade and the pavement surface have a minimum 2 percent slope to promote proper
surface drainage;
Consider appropriate edge drainage and pavement under drain systems;
Install pavement drainage surrounding areas anticipated for frequent wetting;
Install joint sealant and seal cracks immediately;
Seal all landscaped areas in, or adjacent to pavements to reduce moisture migration to
subgrade soils; and
Placing compacted, low permeability backfill against the exterior side of curb and gutter.
4.7.3 Pavements – Construction Considerations
Openings in pavement, such as landscape islands, are sources for water infiltration into
surrounding pavements. Water collects in the islands and migrates into the surrounding subgrade
soils thereby degrading support of the pavement. This is especially applicable for islands with
raised concrete curbs, irrigated foliage, and low permeability near-surface soils. The civil design
for the pavements with these conditions should include features to restrict or to collect and
discharge excess water from the islands. Examples of features are edge drains connected to the
storm water collection system or other suitable outlet and impermeable barriers preventing lateral
migration of water such as a cutoff wall installed to a depth below the pavement structure.
4.7.4 Pavements – Maintenance
Preventative maintenance should be planned and provided for an ongoing pavement
management program in order to enhance future pavement performance. Preventive
maintenance consists of both localized maintenance (e.g. crack and joint sealing and patching)
and global maintenance (e.g. surface sealing). Preventative maintenance is usually the first
priority when implementing a planned pavement maintenance program and provides the highest
return on investment for pavements.
5.0 GENERAL COMMENTS
Terracon should be retained to review the final design plans and specifications so comments can
be made regarding interpretation and implementation of our geotechnical recommendations in
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable 19
the design and specifications. Terracon also should be retained to provide observation and testing
services during grading, excavation, foundation construction and other earth-related construction
phases of the project.
The analysis and recommendations presented in this report are based upon the data obtained
from the borings performed at the indicated locations and from other information discussed in this
report. This report does not reflect variations that may occur between borings, across the site, or
due to the modifying effects of construction or weather. The nature and extent of such variations
may not become evident until during or after construction. If variations appear, we should be
immediately notified so that further evaluation and supplemental recommendations can be
provided.
The scope of services for this project does not include either specifically or by implication any
environmental or biological (e.g., mold, fungi, and bacteria) assessment of the site or identification
or prevention of pollutants, hazardous materials or conditions. If the owner is concerned about
the potential for such contamination or pollution, other studies should be undertaken.
This report has been prepared for the exclusive use of our client for specific application to the
project discussed and has been prepared in accordance with generally accepted geotechnical
engineering practices. No warranties, either express or implied, are intended or made. Site
safety, excavation support, and dewatering requirements are the responsibility of others. In the
event that changes in the nature, design, or location of the project as described in this report are
planned, the conclusions and recommendations contained in this report shall not be considered
valid unless Terracon reviews the changes and either verifies or modifies the conclusions of this
report in writing.
APPENDIX A
FIELD EXPLORATION
TOPOGRAPHIC MAP IMAGE COURTESY OF
THE U.S. GEOLOGICAL SURVEY
QUADRANGLES INCLUDE: FORT COLLINS,
CO (1984).
1901 Sharp Point Dr Ste C
SITE LOCATION MAP
Fort Collins, CO 80525-4429
221 East Mountain Office Building
221 East Mountain Avenue
Fort Collins, CO
20165029
DIAGRAM IS FOR GENERAL LOCATION ONLY,
AND IS NOT INTENDED FOR CONSTRUCTION
PURPOSES
Project Manager:
MGH
Drawn by:
EDB
EDB
Checked by:
EDB
Approved by:
4/18/2016
A-1
Project No. Exhibit
File Name:
Date:
Scale: 1”=2,000’
221 East Mountain Office Building
221 East Mountain Avenue
Fort Collins, CO
MGH
EDB
EDB
EDB
4/18/2016
20165029 EXPLORATION PLAN
AERIAL PHOTOGRAPHY PROVIDED BY
MICROSOFT BING MAPS
1901 Sharp Point Dr Ste C
Fort Collins, CO 80525-4429
LEGEND
DIAGRAM IS FOR GENERAL LOCATION ONLY,
AND IS NOT INTENDED FOR CONSTRUCTION
PURPOSES
Approximate Boring Location
Project Manager:
Drawn by:
Checked by:
Approved by:
1
Scale:
Project No.
File Name:
Date:
PMT 1
AS SHOWN
A-2
Exhibit
PMT 2
PMT 1
Approximate
Pressuremeter Testing
Location
Approximate Location of
Temporary Benchmark (Top of
Manhole Rim – Elevation
4973.5’)
MATHEWS STREET
EAST MOUNTAIN AVENUE
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable Exhibit A-3
Field Exploration Description
The locations of borings were based upon the proposed development shown on the provided site
plan and areas of the site reasonably accessible for a drill rig. The borings were located in the
field by measuring from existing site features. The ground surface elevation was surveyed at
each boring location referencing the temporary benchmark shown on Exhibit A-2 using an
engineer’s level.
The borings were drilled with a CME-550X ATV drill rig with solid-stem and hollow-stem augers
as well wireline coring. During the drilling operations, lithologic logs of the borings were recorded
by the field engineer. Disturbed samples were obtained at selected intervals utilizing a 2-inch
outside diameter split-spoon sampler and a 3-inch outside diameter ring-barrel sampler.
Penetration resistance values were recorded in a manner similar to the standard penetration test
(SPT). This test consists of driving the sampler into the ground with a 140-pound hammer free-
falling through a distance of 30 inches. The number of blows required to advance the ring-barrel
sampler 12 inches (18 inches for standard split-spoon samplers, final 12 inches are recorded) or
the interval indicated, is recorded as a standard penetration resistance value (N-value). The blow
count values are indicated on the boring logs at the respective sample depths. Ring-barrel sample
blow counts are not considered N-values.
A CME automatic SPT hammer was used to advance the samplers in the borings performed on this
site. A greater efficiency is typically achieved with the automatic hammer compared to the
conventional safety hammer operated with a cathead and rope. Published correlations between the
SPT values and soil properties are based on the lower efficiency cathead and rope method. This
higher efficiency affects the standard penetration resistance blow count value by increasing the
penetration per hammer blow over what would be obtained using the cathead and rope method. The
effect of the automatic hammer's efficiency has been considered in the interpretation and analysis of
the subsurface information for this report.
The standard penetration test provides a reasonable indication of the in-place density of sandy
type materials, but only provides an indication of the relative stiffness of cohesive materials since
the blow count in these soils may be affected by the moisture content of the soil. In addition,
considerable care should be exercised in interpreting the N-values in gravelly soils, particularly
where the size of the gravel particle exceeds the inside diameter of the sampler.
Pressuremeter testing was performed at various depths within the sandstone bedrock
encountered below the site. Rock coring was also performed in the very hard bedrock layers to
provide access for pressuremeter testing.
Groundwater measurements were obtained in the borings at the time of site exploration and one
day after drilling. After subsequent groundwater measurements were obtained, the borings were
backfilled with auger cuttings and sand (if needed) and patched (if needed). Some settlement of
the backfill and/or patch may occur and should be repaired as soon as possible.
13
4
16
2
16
18
4974.5
4972.5
4968.5
4961.5
4950.5
4-8-10
N=18
12-12-7
N=19
18-31-25
N=56
50/4"
50/3"
50/3"
0.4
2.0
6.0
13.0
24.3
CONCRETE PAVEMENT - 5 inches
CLAYEY SAND, with gravel, dark brown, medium dense
WELL GRADED SAND, fine to coarse grained, light brown,
medium dense
WELL GRADED SAND, with gravels and cobbles, light brown,
very dense
SEDIMENTARY BEDROCK - SANDSTONE, fine to medium
grained, light brown, very hard
Boring Terminated at 24.3 Feet
Stratification lines are approximate. In-situ, the transition may be gradual. Hammer Type: Automatic
GRAPHIC LOG
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT. GEO SMART LOG-NO WELL 20165029.GPJ TERRACON2015.GDT 4/21/16
221 East Mountain Avenue
Fort Collins, Colorado
SITE:
Page 1 of 1
Advancement Method:
Continuous Flight Auger
Abandonment Method:
Borings backfilled with soil cuttings after delayed groundwater
measurement.
1901 Sharp Point Dr Ste C
Fort Collins, CO
Notes:
Project No.: 20165029
Drill Rig: CME-550x
Boring Started: 4/4/2016
BORING LOG NO. 1
CLIENT: MAV Development Company
South State Commons I
Driller: J. Cothron
Boring Completed: 4/4/2016
Exhibit:
2723 South State Street, Suite 250
Ann Arbor, MI 48104
8 27
3
2
15
23-14-9
4973.5
4971
4969
4961
4939
0
84
96
100
88
0
76
96
100
88
4-4-6
N=10
5-2-9
N=11
50/5"
50/5"
0.7
3.0
5.0
13.0
35.0
PAVEMENT SECTION - Asphalt pavement (3 inches) over
Concrete (4 inches)
CLAYEY SAND WITH GRAVEL (SC), brown, medium dense
WELL GRADED SAND WITH GRAVEL, light brown, medium
dense
WELL GRADED SAND WITH GRAVEL, with cobbles and
gravels, light brown, medium dense to very dense
SEDIMENTARY BEDROCK - SANDSTONE, gray to dark gray,
very hard
Boring Terminated at 35 Feet
Stratification lines are approximate. In-situ, the transition may be gradual. Hammer Type: Automatic
GRAPHIC LOG
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT. GEO SMART LOG-NO WELL 20165029.GPJ TERRACON2015.GDT 4/21/16
221 East Mountain Avenue
Fort Collins, Colorado
SITE:
Page 1 of 1
Advancement Method:
Hollow-stem auger (0-14.4); NQ Wireline core (14.4-35)
Abandonment Method:
Borings backfilled with soil cuttings and patched upon
completion.
1901 Sharp Point Dr Ste C
Fort Collins, CO
Notes:
Project No.: 20165029
Drill Rig: CME-550x
Boring Started: 4/4/2016
BORING LOG NO. 2
38
2
13
3
3
12
23-15-8
4974.5
4974
4972
4962
4944
70
100
84
100
70
96
72
70
3-3-2
N=5
7-11-35
N=46
37-45-43
N=88
50/5"
0.5
1.0
3.0
13.0
31.0
CONCRETE PAVEMENT - 6 inches
BASE COARSE- Sand and Gravel
CLAYEY SAND (SC), dark brown, loose
WELL GRADED SAND WITH GRAVEL, with clay and some
gravel and cobbles, very dense
SEDIMENTARY BEDROCK - SANDSTONE, gray, very hard
Boring Terminated at 31 Feet
Stratification lines are approximate. In-situ, the transition may be gradual. Hammer Type: Automatic
GRAPHIC LOG
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT. GEO SMART LOG-NO WELL 20165029.GPJ TERRACON2015.GDT 4/21/16
221 East Mountain Avenue
Fort Collins, Colorado
SITE:
Page 1 of 1
Advancement Method:
Hollow-stem auger (0-14.4); NQ Wireline core (14.4-31)
Abandonment Method:
Borings backfilled with soil cuttings and patched upon
completion.
1901 Sharp Point Dr Ste C
Fort Collins, CO
Notes:
Project No.: 20165029
Drill Rig: CME-550x
Boring Started: 4/5/2016
BORING LOG NO. 3
CLIENT: MAV Development Company
South State Commons I
49
15
3
5
2
7
28-22-6
4974
4970.5
4960.5
4959.5
4959
2-4-10
N=14
12-23-18
N=41
28-34-14
N=48
20/4"
50/3"
50/3"
0.5
4.0
14.0
15.0
15.3
PAVEMENT SECTION - Asphalt pavement (2.4 inches) over
Concrete (3 inches)
CLAYEY SAND, dark brown, medium dense to dense
SILTY CLAYEY SAND (SC-SM), with gravel and cobbles, light
gray to red-brown, very dense
WEATHERED BEDROCK - SANDSTONE, fine grained, olive
to gray, weathered
SEDIMENTARY BEDROCK - SANDSTONE, light brown to
gray, very hard
Boring Terminated at 15.3 Feet
Stratification lines are approximate. In-situ, the transition may be gradual. Hammer Type: Automatic
GRAPHIC LOG
THIS BORING LOG IS NOT VALID IF SEPARATED FROM ORIGINAL REPORT. GEO SMART LOG-NO WELL 20165029.GPJ TERRACON2015.GDT 4/21/16
221 East Mountain Avenue
Fort Collins, Colorado
SITE:
Page 1 of 1
Advancement Method:
Hollow-stem auger
Abandonment Method:
Borings backfilled with soil cuttings and patched upon
completion.
1901 Sharp Point Dr Ste C
Fort Collins, CO
Notes:
Project No.: 20165029
Drill Rig: CME-550x
Boring Started: 4/4/2016
BORING LOG NO. 4
CLIENT: MAV Development Company
South State Commons I
Driller: J. Cothron
Boring Completed: 4/4/2016
Exhibit:
No
24.00 ft
3.28 ft
0.33
Probe size: 1.000
Pressure Volume Pressure Volume DR/R0
psi in³ psi in³ %
0 0.0 12 0.0 0.00 51,038 psi
73 44.1 80 43.7 18.53
145 46.2 152 45.5 19.23 ◄ 1,166 psi
218 47.2 225 46.2 19.50
290 48.0 297 46.7 19.68 ◄ 43.78
363 48.7 370 47.0 19.81
435 49.8 442 47.8 20.10 297 psi
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A 3.92
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
Raw Readings
Project name:
Borehole name:
Test number:
Test date: (mm/dd/yyyy)
TEXAM Pressuremeter Test
Test depth:
Manometer height above ground:
221 East Mountain Office Building
B-2
4/4/2016
Use of a slotted casing:
PRESSIO COMPANION V.15
Ratio E / PL
:
Yield pressure PF
:
Ratio PL
/ PF
:
Pressuremeter probe was unable to maintain pressure after
reaching a maximum pressure of 30 bar.
Calibration Sheet Reference
2
Remarks
Ultimate pressure PL
:
2
No
33.00 ft
3.28 ft
0.33
Probe size: 1.000
Pressure Volume Pressure Volume DR/R0
psi in³ psi in³ %
0 0.0 16 0.0 0.00 51,676 psi
73 19.2 85 18.8 8.37
145 20.7 158 20.1 8.90 ◄ 1,680 psi
218 21.7 230 20.7 9.15
290 22.5 302 21.2 9.37 30.75
363 23.2 375 21.5 9.51 ◄
435 24.2 447 22.2 9.78 375 psi
508 25.6 520 23.3 10.26
580 27.5 592 24.9 10.91 4.48
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
Ultimate pressure PL
:
1
N Fluid density:
Corrected Readings
Poisson's coefficient:
Pressiometric modulus E:
Test Results
PRESSIO COMPANION V.15
Ratio E / PL
:
Yield pressure PF
:
Ratio PL
/ PF
:
Pressuremeter probe was unable to maintain pressure after
reaching a maximum pressure of 40 bar.
Calibration Sheet Reference
2
Remarks
TEXAM Pressuremeter Test
Test depth:
Manometer height above ground:
221 East Mountain Office Building
B-2
4/4/2016
Use of a slotted casing:
No
28.50 ft
3.28 ft
0.33
Probe size: 1.000
Pressure Volume Pressure Volume DR/R0
psi in³ psi in³ %
0 0.0 14 0.0 0.00 121,495 psi
73 29.5 83 29.1 12.67
145 30.9 155 30.0 13.05 ◄ 2,028 psi
218 31.9 227 30.6 13.27
290 32.6 300 30.9 13.43 59.90
363 33.3 372 31.1 13.50
435 33.9 445 31.3 13.58 662 psi
508 34.4 517 31.4 13.60
580 34.9 590 31.5 13.65 3.06
653 35.4 662 31.6 13.68 ◄
725 35.8 735 31.6 13.68
798 36.7 807 32.0 13.85
870 37.3 880 32.2 13.93
943 38.1 952 32.6 14.08
1015 39.1 1025 33.1 14.30
1088 40.3 1097 33.9 14.62
1160 41.8 1170 35.0 15.07
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A
Ultimate pressure PL
:
3
N Fluid density:
Corrected Readings
Poisson's coefficient:
Pressiometric modulus E:
Test Results
PRESSIO COMPANION V.15
Ratio E / PL
:
Yield pressure PF
:
Ratio PL
/ PF
:
Calibration Sheet Reference
3
Remarks
TEXAM Pressuremeter Test
Test depth:
Manometer height above ground:
221 East Mountain Office Building
B-3
4/5/2016
Use of a slotted casing:
Raw Readings
Project name:
APPENDIX B
LABORATORY TESTING
Geotechnical Engineering Report
221 East Mountain Office Building ■ Fort Collins, Colorado
April 20, 2016 ■ Terracon Project No. 20165029
Responsive ■ Resourceful ■ Reliable Exhibit B-1
Laboratory Testing Description
The soil and bedrock samples retrieved during the field exploration were returned to the laboratory
for observation by the project geotechnical engineer. At that time, the field descriptions were
reviewed and an applicable laboratory testing program was formulated to determine engineering
properties of the subsurface materials.
Laboratory tests were conducted on selected soil and bedrock samples. The results of these
tests are presented on the boring logs and in this appendix. The test results were used for the
geotechnical engineering analyses, and the development of foundation and earthwork
recommendations. The laboratory tests were performed in general accordance with applicable
locally accepted standards. Soil samples were classified in general accordance with the Unified
Soil Classification System described in Appendix C. Rock samples were visually classified in
general accordance with the description of rock properties presented in Appendix C. Procedural
standards noted in this report are for reference to methodology in general. In some cases variations
to methods are applied as a result of local practice or professional judgment.
Water content Plasticity index
Grain-size distribution
Water-soluble sulfate content
Dry density
0
10
20
30
40
50
60
0 20 40 60 80 100
CL or OL CH or OH
ML or OL
MH or OH
Boring ID Depth PL PI Description
CLAYEY SAND with GRAVEL
CLAYEY SAND
SILTY, CLAYEY SAND
SC
SC
SC-SM
Fines
P
L
A
S
T
I
C
I
T
Y
I
N
D
E
X
LIQUID LIMIT
"U" Line
"A" Line
23
23
28
14
15
22
9
8
6
27
38
49
LL USCS
2
3
4
ATTERBERG LIMITS RESULTS
ASTM D4318
2 - 3.5
2 - 3.5
14 - 14.3
PROJECT NUMBER: 20165029
PROJECT: 221 East Mountain Office Building
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
100 10 1 0.1 0.01 0.001
1
2
3
3
4
23
23
28
0.354
0.091
0.599
2.168
1.187
0.221
2.991
0.104
25
25
19
25
19
6 16
20 30
40 50
1.5 6 200
810
26.9
29.0
10.1
30.7
8.7
0.162
14
13.0
26.9
38.0
1.5
49.2
TASK NO: 160411020
Analytical Results
Terracon, Inc. - Fort Collins
Eric D. Bernhardt
Company:
Report To:
Company:
Bill To:
1901 Sharp Point Drive
Suite C
Fort Collins CO 80525
Accounts Payable
Terracon, Inc. - Lenexa
13910 W. 96th Terrace
Lenexa KS 66215
20165029
Date Reported: 4/18/16
Task No.: 160411020
Matrix: Soil - Geotech
Date Received: 4/11/16
Client Project:
Client PO:
Customer Sample ID 20165029 B1 @ 2 Ft.
Test Method
Lab Number: 160411020-01
Result
Sulfate - Water Soluble 0.007 % AASHTO T290-91/ ASTM D4327
240 South Main Street / Brighton, CO 80601-0507 / 303-659-2313
Mailing Address: P.O. Box 507 / Brighton, CO 80601-0507 / Fax: 303-659-2315
DATA APPROVED FOR RELEASE BY
Abbreviations/ References:
160411020
AASHTO - American Association of State Highway and Transportation Officials.
ASTM - American Society for Testing and Materials.
ASA - American Society of Agronomy.
DIPRA - Ductile Iron Pipe Research Association Handbook of Ductile Iron Pipe.
APPENDIX C
SUPPORTING DOCUMENTS
Exhibit: C-1
Unconfined Compressive Strength
Qu, (psf)
500 to 1,000
2,000 to 4,000
4,000 to 8,000
1,000 to 2,000
less than 500
> 8,000
Non-plastic
Low
Medium
High
DESCRIPTION OF SYMBOLS AND ABBREVIATIONS
SAMPLING
WATER LEVEL
FIELD TESTS
GENERAL NOTES
Over 12 in. (300 mm)
12 in. to 3 in. (300mm to 75mm)
3 in. to #4 sieve (75mm to 4.75 mm)
#4 to #200 sieve (4.75mm to 0.075mm
Passing #200 sieve (0.075mm)
Particle Size
< 5
5 - 12
> 12
Percent of
Dry Weight
Descriptive Term(s)
of other constituents
RELATIVE PROPORTIONS OF FINES
0
1 - 10
11 - 30
> 30
Plasticity Index
Soil classification is based on the Unified Soil Classification System. Coarse Grained Soils have more than 50% of their dry
weight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand. Fine Grained Soils have
less than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they are plastic, and
silts if they are slightly plastic or non-plastic. Major constituents may be added as modifiers and minor constituents may be
added according to the relative proportions based on grain size. In addition to gradation, coarse-grained soils are defined
on the basis of their in-place relative density and fine-grained soils on the basis of their consistency.
LOCATION AND ELEVATION NOTES
Percent of
Dry Weight
Major Component
of Sample
Trace
With
Modifier
RELATIVE PROPORTIONS OF SAND AND GRAVEL GRAIN SIZE TERMINOLOGY
Trace
With
Modifier
DESCRIPTIVE SOIL CLASSIFICATION
Boulders
Cobbles
Gravel
Sand
UNIFIED SOIL CLASSIFICATION SYSTEM
Exhibit C-2
Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests A
Soil Classification
Group
Symbol Group Name B
Coarse Grained Soils:
More than 50% retained
on No. 200 sieve
Gravels:
More than 50% of
coarse fraction retained
on No. 4 sieve
Clean Gravels:
Less than 5% fines C
Cu 4 and 1 Cc 3 E GW Well-graded gravel F
Cu 4 and/or 1 Cc 3 E GP Poorly graded gravel F
Gravels with Fines:
More than 12% fines C
Fines classify as ML or MH GM Silty gravel F,G,H
Fines classify as CL or CH GC Clayey gravel F,G,H
Sands:
50% or more of coarse
fraction passes No. 4
sieve
Clean Sands:
Less than 5% fines D
Cu 6 and 1 Cc 3 E SW Well-graded sand I
Cu 6 and/or 1 Cc 3 E SP Poorly graded sand I
Sands with Fines:
More than 12% fines D
Fines classify as ML or MH SM Silty sand G,H,I
Fines classify as CL or CH SC Clayey sand G,H,I
Fine-Grained Soils:
50% or more passes the
No. 200 sieve
Silts and Clays:
Liquid limit less than 50
Inorganic:
PI 7 and plots on or above “A” line J CL Lean clay K,L,M
PI 4 or plots below “A” line J ML Silt K,L,M
Organic:
Liquid limit - oven dried
0.75 OL
Organic clay K,L,M,N
Liquid limit - not dried Organic silt K,L,M,O
Silts and Clays:
Liquid limit 50 or more
Inorganic:
PI plots on or above “A” line CH Fat clay K,L,M
PI plots below “A” line MH Elastic Silt K,L,M
Organic:
Liquid limit - oven dried
0.75 OH
Organic clay K,L,M,P
Liquid limit - not dried Organic silt K,L,M,Q
Highly organic soils: Primarily organic matter, dark in color, and organic odor PT Peat
A Based on the material passing the 3-inch (75-mm) sieve
B If field sample contained cobbles or boulders, or both, add “with cobbles
or boulders, or both” to group name.
DESCRIPTION OF ROCK PROPERTIES
Exhibit C-3
WEATHERING
Fresh Rock fresh, crystals bright, few joints may show slight staining. Rock rings under hammer if crystalline.
Very slight Rock generally fresh, joints stained, some joints may show thin clay coatings, crystals in broken face show
bright. Rock rings under hammer if crystalline.
Slight Rock generally fresh, joints stained, and discoloration extends into rock up to 1 in. Joints may contain clay. In
granitoid rocks some occasional feldspar crystals are dull and discolored. Crystalline rocks ring under hammer.
Moderate Significant portions of rock show discoloration and weathering effects. In granitoid rocks, most feldspars are dull
and discolored; some show clayey. Rock has dull sound under hammer and shows significant loss of strength
as compared with fresh rock.
Moderately severe All rock except quartz discolored or stained. In granitoid rocks, all feldspars dull and discolored and majority
show kaolinization. Rock shows severe loss of strength and can be excavated with geologist’s pick.
Severe All rock except quartz discolored or stained. Rock “fabric” clear and evident, but reduced in strength to strong
soil. In granitoid rocks, all feldspars kaolinized to some extent. Some fragments of strong rock usually left.
Very severe All rock except quartz discolored or stained. Rock “fabric” discernible, but mass effectively reduced to “soil” with
only fragments of strong rock remaining.
Complete Rock reduced to ”soil”. Rock “fabric” not discernible or discernible only in small, scattered locations. Quartz may
be present as dikes or stringers.
HARDNESS (for engineering description of rock – not to be confused with Moh’s scale for minerals)
Very hard Cannot be scratched with knife or sharp pick. Breaking of hand specimens requires several hard blows of
geologist’s pick.
Hard Can be scratched with knife or pick only with difficulty. Hard blow of hammer required to detach hand specimen.
Moderately hard Can be scratched with knife or pick. Gouges or grooves to ¼ in. deep can be excavated by hard blow of point of
a geologist’s pick. Hand specimens can be detached by moderate blow.
Medium Can be grooved or gouged 1/16 in. deep by firm pressure on knife or pick point. Can be excavated in small
chips to pieces about 1-in. maximum size by hard blows of the point of a geologist’s pick.
Soft Can be gouged or grooved readily with knife or pick point. Can be excavated in chips to pieces several inches in
size by moderate blows of a pick point. Small thin pieces can be broken by finger pressure.
Very soft Can be carved with knife. Can be excavated readily with point of pick. Pieces 1-in. or more in thickness can be
broken with finger pressure. Can be scratched readily by fingernail.
Joint, Bedding, and Foliation Spacing in Rock
a
Spacing Joints Bedding/Foliation
Less than 2 in. Very close Very thin
2 in. – 1 ft. Close Thin
1 ft. – 3 ft. Moderately close Medium
3 ft. – 10 ft. Wide Thick
More than 10 ft. Very wide Very thick
a. Spacing refers to the distance normal to the planes, of the described feature, which are parallel to each other or nearly so.
Rock Quality Designator (RQD) a Joint Openness Descriptors
RQD, as a percentage Diagnostic description Openness Descriptor
Exceeding 90 Excellent No Visible Separation Tight
90 – 75 Good Less than 1/32 in. Slightly Open
75 – 50 Fair 1/32 to 1/8 in. Moderately Open
50 – 25 Poor 1/8 to 3/8 in. Open
Less than 25 Very poor 3/8 in. to 0.1 ft. Moderately Wide
a. RQD (given as a percentage) = length of core in pieces Greater than 0.1 ft. Wide
4 in. and longer/length of run.
References: American Society of Civil Engineers. Manuals and Reports on Engineering Practice - No. 56. Subsurface Investigation for
Design and Construction of Foundations of Buildings. New York: American Society of Civil Engineers, 1976. U.S.
Department of the Interior, Bureau of Reclamation, Engineering Geology Field Manual.
Exhibit C-4
LABORATORY TEST
SIGNIFICANCE AND PURPOSE
Test Significance Purpose
California Bearing
Ratio
Used to evaluate the potential strength of subgrade soil,
subbase, and base course material, including recycled
materials for use in road and airfield pavements.
Pavement Thickness
Design
Consolidation
Used to develop an estimate of both the rate and amount of
both differential and total settlement of a structure.
Foundation Design
Direct Shear
Used to determine the consolidated drained shear strength
of soil or rock.
Bearing Capacity,
Foundation Design,
and Slope Stability
Dry Density
Used to determine the in-place density of natural, inorganic,
fine-grained soils.
Index Property Soil
Behavior
Expansion
Used to measure the expansive potential of fine-grained
soil and to provide a basis for swell potential classification.
Foundation and Slab
Design
Gradation
Used for the quantitative determination of the distribution of
particle sizes in soil.
Soil Classification
Liquid & Plastic Limit,
Plasticity Index
Used as an integral part of engineering classification
systems to characterize the fine-grained fraction of soils,
and to specify the fine-grained fraction of construction
materials.
Soil Classification
Permeability
Used to determine the capacity of soil or rock to conduct a
liquid or gas.
Groundwater Flow
Analysis
pH
Used to determine the degree of acidity or alkalinity of a
soil.
Corrosion Potential
Resistivity
Used to indicate the relative ability of a soil medium to carry
electrical currents.
Corrosion Potential
R-Value
Used to evaluate the potential strength of subgrade soil,
subbase, and base course material, including recycled
materials for use in road and airfield pavements.
Pavement Thickness
Exhibit C-5
REPORT TERMINOLOGY
(Based on ASTM D653)
Allowable Soil
Bearing Capacity
The recommended maximum contact stress developed at the interface of the foundation
element and the supporting material.
Alluvium
Soil, the constituents of which have been transported in suspension by flowing water and
subsequently deposited by sedimentation.
Aggregate Base
Course
A layer of specified material placed on a subgrade or subbase usually beneath slabs or
pavements.
Backfill A specified material placed and compacted in a confined area.
Bedrock
A natural aggregate of mineral grains connected by strong and permanent cohesive forces.
Usually requires drilling, wedging, blasting or other methods of extraordinary force for
excavation.
Bench A horizontal surface in a sloped deposit.
Caisson (Drilled
Pier or Shaft)
A concrete foundation element cast in a circular excavation which may have an enlarged
base. Sometimes referred to as a cast-in-place pier or drilled shaft.
Coefficient of
Friction
A constant proportionality factor relating normal stress and the corresponding shear stress
at which sliding starts between the two surfaces.
Colluvium
Soil, the constituents of which have been deposited chiefly by gravity such as at the foot of a
slope or cliff.
Compaction The densification of a soil by means of mechanical manipulation
Concrete Slab-on-
Grade
A concrete surface layer cast directly upon a base, subbase or subgrade, and typically used
as a floor system.
Differential
Movement
Unequal settlement or heave between, or within foundation elements of structure.
Earth Pressure The pressure exerted by soil on any boundary such as a foundation wall.
ESAL
Equivalent Single Axle Load, a criteria used to convert traffic to a uniform standard, (18,000
pound axle loads).
Engineered Fill
Specified material placed and compacted to specified density and/or moisture conditions
under observations of a representative of a geotechnical engineer.
Equivalent Fluid
A hypothetical fluid having a unit weight such that it will produce a pressure against a lateral
support presumed to be equivalent to that produced by the actual soil. This simplified
approach is valid only when deformation conditions are such that the pressure increases
linearly with depth and the wall friction is neglected.
Existing Fill (or
Man-Made Fill)
Materials deposited throughout the action of man prior to exploration of the site.
Existing Grade The ground surface at the time of field exploration.
Exhibit C-6
REPORT TERMINOLOGY
(Based on ASTM D653)
Expansive Potential The potential of a soil to expand (increase in volume) due to absorption of moisture.
Finished Grade The final grade created as a part of the project.
Footing A portion of the foundation of a structure that transmits loads directly to the soil.
Foundation The lower part of a structure that transmits the loads to the soil or bedrock.
Frost Depth The depth at which the ground becomes frozen during the winter season.
Grade Beam
A foundation element or wall, typically constructed of reinforced concrete, used to span
between other foundation elements such as drilled piers.
Groundwater Subsurface water found in the zone of saturation of soils or within fractures in bedrock.
Heave Upward movement.
Lithologic
The characteristics which describe the composition and texture of soil and rock by
observation.
Native Grade The naturally occurring ground surface.
Native Soil Naturally occurring on-site soil, sometimes referred to as natural soil.
Optimum Moisture
Content
The water content at which a soil can be compacted to a maximum dry unit weight by a given
compactive effort.
Perched Water
Groundwater, usually of limited area maintained above a normal water elevation by the
presence of an intervening relatively impervious continuous stratum.
Scarify To mechanically loosen soil or break down existing soil structure.
Settlement Downward movement.
Skin Friction (Side
Shear)
The frictional resistance developed between soil and an element of the structure such as a
drilled pier.
Soil (Earth)
Sediments or other unconsolidated accumulations of solid particles produced by the physical
and chemical disintegration of rocks, and which may or may not contain organic matter.
Strain The change in length per unit of length in a given direction.
Stress The force per unit area acting within a soil mass.
Strip To remove from present location.
Subbase A layer of specified material in a pavement system between the subgrade and base course.
Subgrade The soil prepared and compacted to support a structure, slab or pavement system.
Design
Soluble Sulfate
Used to determine the quantitative amount of soluble
sulfates within a soil mass.
Corrosion Potential
Unconfined
Compression
To obtain the approximate compressive strength of soils
that possess sufficient cohesion to permit testing in the
unconfined state.
Bearing Capacity
Analysis for
Foundations
Water Content
Used to determine the quantitative amount of water in a soil
mass.
Index Property Soil
Behavior
C Gravels with 5 to 12% fines require dual symbols: GW-GM well-graded
gravel with silt, GW-GC well-graded gravel with clay, GP-GM poorly
graded gravel with silt, GP-GC poorly graded gravel with clay.
D Sands with 5 to 12% fines require dual symbols: SW-SM well-graded
sand with silt, SW-SC well-graded sand with clay, SP-SM poorly graded
sand with silt, SP-SC poorly graded sand with clay
E Cu = D60/D10 Cc =
10 60
2
30
D x D
(D )
F If soil contains 15% sand, add “with sand” to group name.
G If fines classify as CL-ML, use dual symbol GC-GM, or SC-SM.
H If fines are organic, add “with organic fines” to group name.
I If soil contains 15% gravel, add “with gravel” to group name.
J If Atterberg limits plot in shaded area, soil is a CL-ML, silty clay.
K If soil contains 15 to 29% plus No. 200, add “with sand” or “with gravel,”
whichever is predominant.
L If soil contains 30% plus No. 200 predominantly sand, add “sandy” to
group name.
M If soil contains 30% plus No. 200, predominantly gravel, add
“gravelly” to group name.
N PI 4 and plots on or above “A” line.
O PI 4 or plots below “A” line.
P PI plots on or above “A” line.
Q PI plots below “A” line.
Silt or Clay
Descriptive Term(s)
of other constituents
N
(HP)
(T)
(DCP)
(PID)
(OVA)
< 15
15 - 29
> 30
Term
PLASTICITY DESCRIPTION
Water levels indicated on the soil boring
logs are the levels measured in the
borehole at the times indicated.
Groundwater level variations will occur
over time. In low permeability soils,
accurate determination of groundwater
levels is not possible with short term water
level observations.
Water Level After
a Specified Period of Time
Water Level After a
Specified Period of Time
Water Initially
Encountered
Standard
Penetration
Test
Unless otherwise noted, Latitude and Longitude are approximately determined using a hand-held GPS device. The accuracy
of such devices is variable. Surface elevation data annotated with +/- indicates that no actual topographical survey was
conducted to confirm the surface elevation. Instead, the surface elevation was approximately determined from topographic
maps of the area.
Standard Penetration Test
Resistance (Blows/Ft.)
Hand Penetrometer
Torvane
Dynamic Cone Penetrometer
Photo-Ionization Detector
Organic Vapor Analyzer
STRENGTH TERMS
Standard Penetration or
N-Value
Blows/Ft.
Descriptive Term
(Consistency)
Descriptive Term
(Density)
CONSISTENCY OF FINE-GRAINED SOILS
(50% or more passing the No. 200 sieve.)
Consistency determined by laboratory shear strength testing, field
visual-manual procedures or standard penetration resistance
Standard Penetration or
N-Value
Blows/Ft.
(More than 50% retained on No. 200 sieve.)
Density determined by Standard Penetration Resistance
RELATIVE DENSITY OF COARSE-GRAINED SOILS
Hard > 30
> 50 Very Stiff 15 - 30
Stiff
Medium Stiff
Very Soft 0 - 1
Medium Dense
Loose Soft
Very Dense
Dense 30 - 50 8 - 15
10 - 29 4 - 8
4 - 9 2 - 4
Very Loose 0 - 3
%Fines
LL PL PI
1 4
3/4 1/2
60
fine
1
2
3
3
4
18.42
GRAIN SIZE IN MILLIMETERS
PERCENT FINER BY WEIGHT
coarse fine
U.HYDROMETERS. SIEVE OPENING IN INCHES U.S. SIEVE NUMBERS
14
15
22
9
8
6
0.74
D100
Cc Cu
SILT OR CLAY
4
D30 D10 %Gravel %Sand
9 - 10.5
2 - 3.5
2 - 3.5
9 - 10.5
14 - 14.3
3/8 3 100
3 2 140
COBBLES GRAVEL SAND
USCS Classification
60.1
44.1
51.8
67.8
42.1
D60
coarse medium
Boring ID Depth
Boring ID Depth
GRAIN SIZE DISTRIBUTION
9 - 10.5
2 - 3.5
2 - 3.5
9 - 10.5
14 - 14.3
()
CLAYEY SAND with GRAVEL (SC)
CLAYEY SAND (SC)
POORLY GRADED SAND with GRAVEL (SP)
SILTY, CLAYEY SAND (SC-SM)
ASTM D422 / ASTM C136
PROJECT NUMBER: 20165029
PROJECT: 221 East Mountain Office Building
SITE: 221 East Mountain Avenue
Fort Collins, Colorado
CLIENT: MAV Development Company
South State Commons I
EXHIBIT: B-3
1901 Sharp Point Dr Ste C
Fort Collins, CO
LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. GRAIN SIZE: USCS-2 20165029.GPJ 35159097 - ATTERBERG ISSUE.GPJ 4/18/16
SITE: 221 East Mountain Avenue
Fort Collins, Colorado
CLIENT: MAV Development Company
South State Commons I
EXHIBIT: B-2
1901 Sharp Point Dr Ste C
Fort Collins, CO
LABORATORY TESTS ARE NOT VALID IF SEPARATED FROM ORIGINAL REPORT. ATTERBERG LIMITS 20165029.GPJ TERRACON2015.GDT 4/18/16
CL-ML
Borehole name:
Test number:
Test date: (mm/dd/yyyy)
0
20
40
60
80
100
120
140
160
180
0 500 1000 1500 2000 2500
Volume (in³)
Pressure (psi)
Pressuremeter Test - Corrected Curve
Raw Readings
Project name:
Borehole name:
Test number:
Test date: (mm/dd/yyyy)
0
20
40
60
80
100
120
140
160
0 200 400 600 800 1000 1200 1400 1600 1800
Volume (in³)
Pressure (psi)
Pressuremeter Test - Corrected Curve
N Fluid density:
Corrected Readings
Poisson's coefficient:
Pressiometric modulus E:
Test Results
0
50
100
150
200
250
0 200 400 600 800 1000 1200 1400
Volume (in³)
Pressure (psi)
Pressuremeter Test - Corrected Curve
2723 South State Street, Suite 250
Ann Arbor, MI 48104
A-7
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratory
procedures and additional data (if any).
See Appendix C for explanation of symbols and
abbreviations.
PROJECT: 221 East Mountain Office Building
PERCENT FINES
WATER
CONTENT (%)
ATTERBERG
LIMITS
LL-PL-PI
Surface Elev.: 4974.3 (Ft.)
ELEVATION (Ft.)
SAMPLE TYPE
WATER LEVEL
OBSERVATIONS
DEPTH (Ft.)
5
10
15
RECOVERY (%)
RQD (%)
FIELD TEST
RESULTS
DEPTH
LOCATION See Exhibit A-2
Latitude: 40.58654401° Longitude: -105.074265°
Boring collapsed upon removal of augers
12' while drilling
Boring collapsed upon removal of augers
WATER LEVEL OBSERVATIONS
12' while drilling
Driller: J. Cothron
Boring Completed: 4/5/2016
Exhibit:
2723 South State Street, Suite 250
Ann Arbor, MI 48104
A-6
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratory
procedures and additional data (if any).
See Appendix C for explanation of symbols and
abbreviations.
PROJECT: 221 East Mountain Office Building
PERCENT FINES
WATER
CONTENT (%)
ATTERBERG
LIMITS
LL-PL-PI
Surface Elev.: 4975.1 (Ft.)
ELEVATION (Ft.)
SAMPLE TYPE
WATER LEVEL
OBSERVATIONS
DEPTH (Ft.)
5
10
15
20
25
30
RECOVERY (%)
RQD (%)
FIELD TEST
RESULTS
DEPTH
LOCATION See Exhibit A-2
Latitude: 40.58655096° Longitude: -105.074586°
No free water observed
WATER LEVEL OBSERVATIONS
CLIENT: MAV Development Company
South State Commons I
Driller: J. Cothron
Boring Completed: 4/4/2016
Exhibit:
2723 South State Street, Suite 250
Ann Arbor, MI 48104
A-5
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratory
procedures and additional data (if any).
See Appendix C for explanation of symbols and
abbreviations.
PROJECT: 221 East Mountain Office Building
PERCENT FINES
WATER
CONTENT (%)
ATTERBERG
LIMITS
LL-PL-PI
Surface Elev.: 4974.1 (Ft.)
ELEVATION (Ft.)
SAMPLE TYPE
WATER LEVEL
OBSERVATIONS
DEPTH (Ft.)
5
10
15
20
25
30
35
RECOVERY (%)
RQD (%)
FIELD TEST
RESULTS
DEPTH
LOCATION See Exhibit A-2
Latitude: 40.58679001° Longitude: -105.074287°
No free water observed
WATER LEVEL OBSERVATIONS
A-4
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratory
procedures and additional data (if any).
See Appendix C for explanation of symbols and
abbreviations.
PROJECT: 221 East Mountain Office Building
PERCENT FINES
WATER
CONTENT (%)
ATTERBERG
LIMITS
LL-PL-PI
Surface Elev.: 4974.7 (Ft.)
ELEVATION (Ft.)
SAMPLE TYPE
WATER LEVEL
OBSERVATIONS
DEPTH (Ft.)
5
10
15
20
RECOVERY (%)
RQD (%)
FIELD TEST
RESULTS
DEPTH
LOCATION See Exhibit A-2
Latitude: 40.586816° Longitude: -105.07463°
13' while drilling
12.6' on 4/5/2016
WATER LEVEL OBSERVATIONS