May 20, 2016
Cathy Mathis
TB GROUP
444 MOUNTAIN AVENUE
Berthoud, CO 80525
RE: 2590 Midpoint Drive, PDP160010, Round Number 2
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, you may contact the individual commenter or direct your questions through
the Project Planner, Meaghan Overton, at 970-416-2283 or moverton@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Meaghan Overton, 970-416-2283, moverton@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 04/12/2016
05/20/2016: Because the applicant isn't sure exactly what will be stored in the
storage area yet, the screening as it’s shown now will be sufficient. Just be sure
the existing fencing is shown on the site plan along with the landscaping. Any
materials stored in the storage area must be completely screened from view. In
the future, should there be any complaints or issues, the owner may need to add
more screening.
05/16/2016: Please see comment from zoning regarding the required
screening of the storage area.
04/12/2016: What is the intended use of the asphalt area at the back of the
site? Additional screening may be required.
Comment Number: 6 Comment Originated: 05/20/2016
05/20/2016: After discussion at staff review, departments with outstanding
comments agreed that the project is close to being ready for hearing. I will
coordinate a final round of electronic review to address any outstanding
comments/issues prior to hearing.
2
Topic: Landscape Plans
Comment Number: 2 Comment Originated: 04/12/2016
05/16/2016: Thank you for including the interior landscaping calculation on the
landscape plan. Because the landscape islands near the overhead door
entrances have been removed, the landscape plan does not meet the interior
parking lot requirements. Have you considered removing one of the 20 parking
spaces to satisfy the interior landscaping requirement? If the site can not meet
the code requirement, a request for a modification of standard will be required.
04/12/2016: The response letter indicated that there is a calculation showing
that 6% of the parking lot interior is devoted to landscaping. I don't see that on
the landscape plan. Please include this calculation.
Department: Engineering Development Review
Contact: Katie Sexton, 970-221-6501, ksexton@fcgov.com
Topic: General
Comment Number: 9 Comment Originated: 05/17/2016
05/17/2016: Please include LCUASS driveway detail 707.1
Department: Internal Services
Contact: Sarah Carter, 970-416-2748, scarter@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 1 Comment Originated: 05/17/2016
05/17/2016: Please schedule a pre-submittal meeting for this project.
Pre-Submittal meetings assist the designer/builder by assuring, early on in the
design, that the new projects are on track to complying with all of the adopted
City codes and Standards listed below. The proposed project should be in the
early to mid-design stage for this meeting to be effective. Applicants of new
projects should email scarter@fcgov.com to schedule a pre-submittal meeting.
Applicants should be prepared to present site plans, floor plans, and elevations
and be able to discuss code issues of occupancy, square footage and type of
construction being proposed.
Comment Number: 2 Comment Originated: 05/17/2016
05/17/2016: Construction shall comply with adopted codes as amended.
Current adopted codes are:
2012 International Building Code (IBC)
2012 International Residential Code (IRC)
2012 International Energy Conservation Code (IECC)
2012 International Mechanical Code (IMC)
2012 International Fuel Gas Code (IFGC)
2012 International Plumbing Code (IPC) as amended by the State of Colorado
2014 National Electrical Code (NEC) as amended by the State of Colorado
Fort Collins has amendments to most of the codes listed above. See the
fcgov.com/building web page to view them.
Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2009.
Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF.
Frost Depth: 30 inches.
3
Wind Load: 100- MPH 3 Second Gust Exposure B.
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code Use Commercial: 2012 IECC commercial chapter.
Comment Number: 3 Comment Originated: 05/17/2016
05/17/2016: Prescriptive energy compliance with increased insulation values is
required for buildings using electric heat.
Department: Stormwater Engineering
Contact: Dan Mogen, 970-224-6192, dmogen@fcgov.com
Topic: General
Comment Number: 3 Comment Originated: 04/12/2016
05/18/2016: Please expand report narrative to explain the proposed scenario
with the northern detention pond. Will the outlet structure need to be modified?
If so, provide detail. Please also show proposed grading in this area.
04/12/2016: It is noted that Basin 1 will be sharing a detention basin with the
adjacent property. It doesn't appear that easement will be required as the
properties are owned by the same party. Please document the required volume
for the adjacent property or include in the basin sizing calculations.
Comment Number: 5 Comment Originated: 04/12/2016
05/18/2016: Comment still applies. Slight discrepancies are seen, likely due to
the equation used (see redlines).
04/12/2016: Please review the time of concentration and associated rainfall
intensities using in the runoff calculations.
Comment Number: 6 Comment Originated: 04/12/2016
05/18/2016: Please provide historic basin calculations to support the proposed
release rate.
04/12/2016: What is sub-basin P1? It is seen in the calculations, but other
references remain unseen.
Comment Number: 9 Comment Originated: 04/12/2016
05/18/2016: Comment still applies.
04/12/2016: How was the designed outfall rate of 0.14 cfs/acre determined?
Please show calculation for 2-year historic runoff rate.
Comment Number: 10 Comment Originated: 04/12/2016
05/18/2016: Comment still applies.
04/12/2016: Please expand the drainage report narrative overall to give a
better understanding of the proposed development. A number of things are
currently unclear with the project including how the LID requirements are being
met and what is ultimately being proposed for the 2 detention basins. Are both
water quality and LID being proposed for the detention basin bottoms? Please
expand to help clarify the overall design.
Comment Number: 11 Comment Originated: 04/12/2016
05/18/2016: Please see redlined table.
04/12/2016: Please discuss and document how LID requirements are being
met. A table would be helpful for this and a sample table can be downloaded at:
http://tinyurl.com/SampleLIDTable.
Comment Number: 13 Comment Originated: 04/12/2016
4
05/18/2016: Please see updated redlined plans and drainage report. Please
return with resubmittal.
04/12/2016: Please see redlined plans and drainage report. Please return with
resubmittal.
Comment Number: 14 Comment Originated: 04/12/2016
05/18/2016: Comment still applies.
04/12/2016: Please note that additional comments may be forthcoming upon
future submittals as additional details are discovered.
Comment Number: 15 Comment Originated: 05/18/2016
05/18/2016: Are any plantings proposed within the proposed rain gardens? It
appears that sod is proposed for the southern rain garden, please note that sod
cannot be used in this location and will need to be seeded if grass is desired.
Please also remove the weed barrier from the northern rain garden.
Comment Number: 16 Comment Originated: 05/18/2016
05/18/2016: Please provide a drainage easement for the proposed rain
gardens and detention basins at least up to the 100-year water surface
elevation.
Comment Number: 17 Comment Originated: 05/18/2016
05/18/2016: Overall, it appears that the proposed design is acceptable;
however, expanded narrative in the report and additional detail in the plans are
needed in order to better understand the proposed conditions and how the
system overall will function.
Contact: Jesse Schlam, 970-218-2932, jschlam@fcgov.com
Topic: Erosion Control
Comment Number: 1 Comment Originated: 03/29/2016
05/16/2016: Erosion Control Plan had a minor redline on the details page.
Erosion Control Report was not found in the supplied documents. Erosion
control escrow Calculation was not found in the supplied document as well. If
you need clarification concerning the erosion control section, or if there are any
questions please contact Jesse Schlam 970-218-2932 or email @
jschlam@fcgov.com
03/29/2016: Current Erosion Control Materials Submitted do not meet
requirements. Please submit; Erosion Control Plan (based upon redlines),
Erosion Control Report (Based upon comments returned to the planner on
3/29/2016) , and an Escrow / Security Calculation (with the correct method for
calculating an escrow see redline comments in the report). If you need
clarification concerning the erosion control section, or if there are any questions
please contact Jesse Schlam 970-218-2932 or email @ jschlam@fcgov.com
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Construction Drawings
Comment Number: 9 Comment Originated: 04/13/2016
05/17/2016: Please correct the equation as marked. See redlines.
04/13/2016: Please provide the following information for the Benchmark
Statement in the EXACT format shown below.
5
PROJECT DATUM: NAVD88
BENCHMARK # w/ DESCRIPTION
ELEVATION:
BENCHMARK # w/ DESCRIPTION
ELEVATION:
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL
DATUM. SURROUNDING DEVELOPMENTS HAVE USED NGVD29
UNADJUSTED FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE,
THE FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED
= NAVD88 - X.XX¿.
Comment Number: 10 Comment Originated: 04/13/2016
05/17/2016: This has not been completely corrected.
04/13/2016: Some of the sheet titles in the sheet index do not match the sheet
titles on the noted sheets. See redlines.
Comment Number: 11 Comment Originated: 04/13/2016
05/17/2016: This has not been corrected.
04/13/2016: All benchmark statements must match on all sheets.
Comment Number: 12 Comment Originated: 04/13/2016
05/17/2016: There are line over text issues. See redlines.
04/13/2016: There are line over text issues. See redlines.
Comment Number: 18 Comment Originated: 05/17/2016
05/17/2016: Some of the easement descriptions shown are incorrect. If they
are going to stay on the plan, they should match what is shown on the
Subdivision Plat, or documentation needs to be provided for easements
recorded after the Subdivision Plat was recorded.
Topic: Landscape Plans
Comment Number: 5 Comment Originated: 04/13/2016
05/17/2016: Please change to Lot 18 on all sheets.
04/13/2016: Please add Lot 18, Prospect Industrial Park" to the title block.
Topic: Site Plan
Comment Number: 2 Comment Originated: 04/13/2016
05/17/2016: There is no change, and no response was received.
04/13/2016: Please provide information documenting a 9' Utility Easement
along Midpoint Drive. The Plat shows a 6' Utility Easement.
Comment Number: 3 Comment Originated: 04/13/2016
05/17/2016: Please change to Lot 18 on all sheets.
04/13/2016: Please add Lot 18, Prospect Industrial Park" to the title block.
Comment Number: 17 Comment Originated: 05/17/2016
05/17/2016: Some of the easement descriptions shown are incorrect. If they
are going to stay on the plan, they should match what is shown on the
6
Subdivision Plat, or documentation needs to be provided for easements
recorded after the Subdivision Plat was recorded.
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 04/11/2016
04/11/2016: Irrigation plans are required no later than at the time of building
permit. The irrigation plans must comply with the provisions outlined in Section
3.2.1(J) of the Land Use Code. Direct questions concerning irrigation
requirements to Eric Olson, at 221-6704 or eolson@fcgov.com
Department: Water-Wastewater Engineering
Contact: Dan Mogen, 970-224-6192, dmogen@fcgov.com
Topic: General
Comment Number: 2 Comment Originated: 04/12/2016
05/18/2016: I've noted that the service has been changed to 4" and can
connect to the main via wye. This requires a minimum slope of 2% (1% is
proposed).
04/12/2016: A 6" sanitary service connection into an 8" main requires either
connecting at a manhole or cutting in a tee.
Comment Number: 6 Comment Originated: 04/12/2016
05/18/2016: Please see updated redlined report and plans and return with
resubmittal.
04/12/2016: Please see redlines and return with resubmittal.
Comment Number: 7 Comment Originated: 04/12/2016
05/18/2016: Comment still applies.
04/12/2016: Please note that additional comments may be forthcoming upon
future submittals as additional details are discovered.
Department: Zoning
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
Topic: General
Comment Number: 3 Comment Originated: 04/12/2016
05/10/2016: The area labeled as recycle asphalt appears to be storage area.
Please include screening around this entire area.
04/12/2016: Please identify the fence material of the existing fence? Will it
provide screening? Is it more than chain link?