HomeMy WebLinkAboutALTA VISTA WTF (903 BUCKINGHAM ST.) - PDP - PDP160004 - CORRESPONDENCE - REVISIONSApril 7, 2016
Attn: Clay Frickey
Planning Department
Fort Collins Planning Services
281 North College Avenue
Fort Collins, CO 80524
RE: Alta Vista Comment Response Letter
Department: Planning Services
Comment Number 1
Color samples have been submitted with this application for review by Planning
Services.
Department: Engineering Development Review
Comment Number 1
Page C-3 of the drawings has calculations for the total impermeable area added by the
site. The total impermeable area added is less than 200 sq. ft. and therefore no
detention ponds or drainage plans are necessary. The tower will be located on a flat
portion of the property, so no grading will be necessary. Construction details have been
included in the updated drawings submitted with this application.
Comment Number 2
The Colorado Iron and Metal FDP will be amended and resubmitted with the required
public improvements.
Comment Number 3
The access and utility easements will be dedicated by separate documents with this
submission.
Department: Light and Power
Comment Number 1
Sheet C-3 shows location of the proposed pad-mounted transformer and service rack
with meter bank. The transformer location meets the clearance and location
requirements.
Comment Number 2
Atlas accepts to this comment.
Comment Number 3
A utility easement between Atlas Tower and Landowner that includes primary lines and
transformer has been included with this application.
Comment Number 4
A complete C-1 and one-line diagram have been provided to Light and Power.
Comment Number 5
The Verizon transformer has been removed from the drawings submitted with this
applicatoin.
Department: PFA
Comment Number 1
A fire lane is delineated on sheet C-1 of the drawings set included with this submission.
Atlas believes that the proposed fire lane meets the city’s fire land specifications.
Comment Number 2
The proposed tower will be addressed separately as required by this comment after
zoning approval.
Storm Water Engineering
Comment Number 1
The approved plans for Colorado Iron and metal are to be amended and resubmitted
with the telecommunications facility incorporated into the plans.
Comment Number 2
Our plans have been modified so that the impervious area is less than 1000 sq. ft, as
detailed on sheet C-3. Because of this, it is Atlas’s understanding that no drainage
report or construction drawings related to drainage are required with this application.
Comment Number 3
Our plans have been modified so that the impervious area is less than 1000 sq. ft, as
detailed on sheet C-3. Because of this, it is Atlas’s understanding that no drainage
report or construction drawings related to drainage are required with this application.
Comment Number 4
Our plans have been modified so that the impervious area is less than 1000 sq. ft, as
detailed on sheet C-3. Because of this, it is Atlas’s understanding that no drainage
report or construction drawings related to drainage are required with this application.
Comment Number 5
Our plans have been modified so that the impervious area is less than 1000 sq. ft, as
detailed on sheet C-3. Because of this, it is Atlas’s understanding that no drainage
report or construction drawings related to drainage are required with this application.
Comment Number 6
Our plans have been modified so that the impervious area is less than 1000 sq. ft, as
detailed on sheet C-3. Because of this, it is Atlas’s understanding that no drainage
report or construction drawings related to drainage are required with this application.
Department: Technical Services
Comment Number 1
Atlas made the requested changes.
Comment Number 2
Atlas made the requested changes.
Best Regards,
Caleb Crossland
Atlas Tower Companies
4450 Arapahoe Ave., Suite 100
Boulder, CO 80303