HomeMy WebLinkAboutTHE OVERLOOK - PDP - PDP160011 - SUBMITTAL DOCUMENTS - ROUND 1 - DRAINAGE REPORTPRELIMINARY DRAINAGE AND EROSION CONTROL REPORT March 30, 2016 The Overlook Fort Collins, Colorado Prepared for: Stockover Investments, LLC 1806 Westview Road Fort Collins, CO 80524 970-556-8132 Prepared by: 301 N. Howes Street, Suite 100 Fort Collins, Colorado 80521 Phone: 970.221.4158 www.northernengineering.com Project Number: 1174-001  This Drainage Report is consciously provided as a PDF. Please consider the environment before printing this document in its entirety. When a hard copy is absolutely necessary, we recommend double-sided printing. RE: Preliminary Drainage and Erosion Control Report for The Overlook Dear Staff: Northern Engineering is pleased to submit this Preliminary Drainage and Erosion Control Report for your review. This report accompanies Project Development Plan submittal for the proposed The Overlook development. This report has been prepared in accordance to Fort Collins Stormwater Criteria Manual (FCSCM), and serves to document the stormwater impacts associated with the proposed project. We understand that review by the City is to assure general compliance with standardized criteria contained in the FCSCM. If you should have any questions as you review this report, please feel free to contact us. Sincerely, NORTHERN ENGINEERING SERVICES, INC. Stephanie Thomas, PE Project Engineer The Overlook Preliminary Drainage Report TABLE OF CONTENTS I. GENERAL LOCATION AND DESCRIPTION ................................................................... 1 A. Location ....................................................................................................................................... 1 B. Description of Property ................................................................................................................ 2 C. Floodplain .................................................................................................................................... 3 II. DRAINAGE BASINS AND SUB-BASINS ....................................................................... 4 A. Major Basin Description ............................................................................................................... 4 B. Sub-Basin Description .................................................................................................................. 4 III. DRAINAGE DESIGN CRITERIA ................................................................................... 4 A. Regulations .................................................................................................................................. 4 B. Four Step Process ........................................................................................................................ 4 C. Development Criteria Reference and Constraints ......................................................................... 5 D. Hydrological Criteria .................................................................................................................... 5 E. Hydraulic Criteria ......................................................................................................................... 5 F. Floodplain Regulations Compliance .............................................................................................. 6 G. Modifications of Criteria .............................................................................................................. 6 IV. DRAINAGE FACILITY DESIGN .................................................................................... 6 A. General Concept .......................................................................................................................... 6 B. Specific Details ............................................................................................................................. 8 V. CONCLUSIONS ........................................................................................................ 8 A. Compliance with Standards .......................................................................................................... 8 B. Drainage Concept ........................................................................................................................ 8 References ......................................................................................................................... 9 APPENDICES: APPENDIX A – Hydrologic Computations APPENDIX B – Hydraulic Computations (NOT INCLUDED WITH PDP) B.1 – Detention Ponds and Water Quality B.2 – Storm Sewers (NOT INCLUDED WITH PDP) B.3 – Inlets (NOT INCLUDED WITH PDP) APPENDIX C – SWMM Modeling APPENDIX D – Erosion Control Report APPENDIX E – LID Exhibit The Overlook Preliminary Drainage Report LIST OF TABLES AND FIGURES: Figure 1 – Aerial Photograph ................................................................................................ 2 Figure 2– Proposed Site Plan ................................................................................................ 3 Figure 3 – Existing Floodplains ............................................................................................. 3 MAP POCKET: DR1 - Drainage Exhibit The Overlook Preliminary Drainage Report 1 I. GENERAL LOCATION AND DESCRIPTION A. Location 1. Vicinity Map 2. Located in the western half of Section 36, Township 7 North, Range 69 West of the 6th Prime Meridian, City of Fort Collins, County of Larimer, State of Colorado. The site is a part of Lots 3 and 4, Observatory Heights. 3. Bounded to the north by First National Bank 1st PUD, to the west by John F. Kennedy Parkway, to the south by Larimer County Canal, and to the east by a Private Drive and Wharf at the Landings PUD Phase 2 Replat. 4. No significant offsite flows are directed into the site. The majority of off-site flows are are prevented from entering the site by curb and gutter. 5. The Overlook was originally included in the Revised Master Plan and Supplemental Drainage Report for Fort Collins National Bank PUD, prepared by Cornell Consulting Company, Revised April 4, 1980. The Overlook Preliminary Drainage Report 2 B. Description of Property 1. The site is approximately 3.29 acres. Approximately 0.23 acres of the 3.29 acres is a parcel of land already developed by the First National Bank PUD; hence this area is included in the original drainage report and accounted for in the existing detention pond. Figure 1 – Aerial Photograph 2. The existing site is comprised of vacant land with natural grasses and vegetation. In the northeast corner of the site exists an existing parking lot. This existing parking lot will be demolished with this project and reconfigured in another location. 3. The majority of the site slopes to the north, while an eastern portion slopes to the east. 4. A report by Earth Engineering Consultants dated December 14, 2015 lists the soils for the area as consisting of lean clay with varying amounts of silt and sand, and sandstone/siltstone bedrock ranging from 2 to 7 feet below the ground surface. These soils are classified as Hydrologic Soil Group C and have a low infiltration rate. 5. The proposed project site plan is composed of 2 buildings connected by a walkway. These buildings are classified as mixed-use with commercial on the first floor and residential above. This site will employ many water quality features and runoff reduction facilities including rain gardens, landscape buffers, and extended detention basins. The Overlook Preliminary Drainage Report 3 Figure 2– Proposed Site Plan 6. No existing irrigation facilities are known at this time. 7. The project site is within the First National Bank 1st PUD Master Plan. The proposed project is not requesting a change in the land use. C. Floodplain 1. The subject property is not located in a FEMA or City regulatory floodplain. Figure 3 – Existing Floodplains The Overlook Preliminary Drainage Report 4 II. DRAINAGE BASINS AND SUB-BASINS A. Major Basin Description 1. The Overlook project is located within the Foothills Drainage Basin, which is located between Prospect Road and Larimer #2 Canal from north to south and approximately between Shields Street and Zeigler Road from west to east. B. Sub-Basin Description 1. The western half of the property generally drains to the center of the property. From there, flows are conveyed north in a swale to the access road bordering the north side of the property. Flows within the access road are collected in an inlet at Horsetooth Road. From there, flows are detained and released to Warren Reservoir. 2. The eastern half of the site generally sheet flows to the eastern boundary. From there, flows sheet flow to backlot swales and drain pans routing flows around the existing residential buildings. These flows are also collected in downstream inlets and detained prior to be released to Warren Reservoir. 3. The proposed plan will generally detain developed flows and release to the detention ponds north of the site, on the First National Bank property. These ponds have been sized and included in the previous drainage report. III. DRAINAGE DESIGN CRITERIA A. Regulations There are no optional provisions outside of the FCSCM proposed with The Overlook project. B. Four Step Process The overall stormwater management strategy employed with The Overlook project utilizes the “Four Step Process” to minimize adverse impacts of urbanization on receiving waters. The following is a description of how the proposed development has incorporated each step. Step 1 – Employ Runoff Reduction Practices Several techniques have been utilized with the proposed development to facilitate the reduction of runoff peaks, volumes, and pollutant loads as the site is developed from the current use by implementing multiple Low Impact Development (LID) strategies including: Providing rain gardens throughout the site to reduce the overall impervious area and to minimize directly connected impervious areas (MDCIA). Providing planter boxes with a rain garden filter section at downspout locations from the building to reduce runoff from the rooftops. Step 2 – Implement BMPs That Provide a Water Quality Capture Volume (WQCV) with Slow Release The efforts taken in Step 1 will facilitate the reduction of runoff; however, this development will still generate stormwater runoff that will require additional BMPs and water quality. The majority of stormwater runoff from the site will ultimately be intercepted and treated in proposed water quality ponds. The Overlook Preliminary Drainage Report 5 Step 3 – Stabilize Drainageways There are no major drainageways within the subject property. This property discharges to existing detention ponds that have been designed to accommodate runoff from this project as a part of the First National Bank 1st PUD Master Plan. Step 4 – Implement Site Specific and Other Source Control BMPs. The proposed project will improve upon site specific source controls compared to historic conditions: Localized trash enclosures within the development will allow for the disposal of solid waste. Rain gardens and planter boxes for water treatment prior to flows entering the extended detention basins. Water Quality measures to protect and prolong the design life of the BMPs delineated in Step 1. C. Development Criteria Reference and Constraints 1. The proposed site is a part of the Revised Master Plan and Supplemental Drainage Report for Fort Collins National Bank PUD, prepared by Cornell Consulting Company, Revised April 4, 1980. This report states a release rate of 75% of the 2-year release. This is less than the typical 2-year release requirement. 2. This site is subject to the LID requirements per the City of Fort Collins. Please see the LID Exhibit located in the Appendix for calculations concerning LID treatment. The site must either have the following: 75% of total new impervious areas must be treated through an LID (Low Impact Development) treatment BMP, or 50% of total new impervious areas must be treated through an LID (Low Impact Development) treatment BMP and 25% of new pavement shall be pervious. D. Hydrological Criteria 1. The City of Fort Collins Rainfall Intensity-Duration-Frequency Curves, as depicted in Figure RA-16 of the FCSCM, serve as the source for all hydrologic computations associated with the development. Tabulated data contained in Table RA-7 has been utilized for Rational Method runoff calculations. 2. The Rational Method has been employed to compute stormwater runoff utilizing coefficients contained in Tables RO-11 and RO-12 of the FCSCM. 3. EPA SWMM modeling was utilized for detention storage calculations. 4. Three separate design storms have been utilized to address distinct drainage scenarios. The first event analyzed is the “Minor,” or “Initial” Storm, which has a 2- year recurrence interval. The second event considered is the “Major Storm,” which has a 100-year recurrence interval. The third storm computed, for comparison purposes only, is the 10-year event. 5. No other assumptions or calculation methods have been used with this development that are not referenced by current City of Fort Collins criteria. E. Hydraulic Criteria 1. As previously noted, the subject property historically drains to the north and east. The north flows are collected in an existing inlet on the private access drive at Horsetooth Road then conveyed to an existing detention pond that releases to Warren The Overlook Preliminary Drainage Report 6 Reservoir. 2. All drainage facilities proposed with The Overlook project are designed in accordance with criteria outlined in the FCSCM and/or the Urban Drainage and Flood Control District’s (UDFCD) Urban Storm Drainage Criteria Manual. 3. As stated previously, the subject property is not located within a FEMA regulatory floodplain. 4. The Overlook project does not propose to modify any natural drainageways. F. Floodplain Regulations Compliance 1. As previously mentioned, all structures are located outside of any FEMA 100-year floodplain, and thus are not subject to any floodplain regulations. G. Modifications of Criteria 1. The proposed development is not requesting any modifications to criteria at this time. IV. DRAINAGE FACILITY DESIGN A. General Concept 1. The main objectives of The Overlook drainage design are to maintain the allowable storm runoffs as outlined within the Revised Master Plan and Supplemental Drainage Report for Fort Collins National Bank PUD. 2. A list of tables and figures used within this report can be found in the Table of Contents at the front of the document. The tables and figures are located within the sections to which the content best applies. 3. Historic runoff from The Overlook project site was evaluated. This evaluation provided the historic 2-yr and 100-yr peak runoff rates for the existing site. Basin H1 Basin H1 has an area of 0.23 acres. This basin contains a portion of the existing private access road and an existing parking lot. The 2-yr and 100-yr peak runoff rates from Basin H1 are 0.56 cfs and 2.27 cfs, respectively. Basin H1 has been accounted for in previous subdivision drainage designs. Therefore, detention of this area is not proposed. Basin H2 Basin H2 has an area of 3.04 acres. This basin contains the majority of The Overlook site. This existing basin contains vacant land. The 2-yr and 100-yr peak runoff rates from Basin H2 are 1.05 cfs and 4.78 cfs, respectively. 4. The Overlook project divided the site into three (3) major drainage basins, designated as Basins A, B, and UD. The project further subdivided Basin A in to seven (7) sub- basins, Basin B into five (5) sub-basins, and Basin UD into five (5) sub-bains. The drainage patterns anticipated for each basin and sub-basin are further described below. Basin A Basin A is a total of 1.79 acres. Basin A consists of proposed building, parking lot, sidewalk, landscape areas and rain gardens. Runoff from Basins A1, A2, A3 and A4 The Overlook Preliminary Drainage Report 7 flow via overland flow and gutter to proposed rain gardens. Runoff from Basin A5 is collected in trench drains and conveyed to Detention Pond A. Runoff from Basin A7 is collected in a curb inlet and conveyed to Detention Pond A. Basin A7 contains Detention Pond A. Total flow during a 100-yr storm from Basin A is calculated at a routed 12.0 cfs. Basin B Basin B is a total of 1.04 acres. Basin B consists of proposed building, parking lot, sidewalk, landscape areas and rain gardens. Runoff from Basins B1 and B2 are collected in a storm pipe and curb inlet and are conveyed to a rain garden. Runoff from Basins B3 and B4 are collected by curb inlets and are conveyed to Detention Pond B. Basin B5 contains Detention Pond B. Total flow during a 100-yr storm from Basin B is calculated at a routed 5.97 cfs. Basin UD Basin UD is a total of 0.47 acres. This basin is not detained and runoff will continues to flow to historic capture points. Basin UD1 and UD5 will continue, as historically, to overland flow to the adjacent The Wharf Subdivision. Basins UD1 and UD5 have a percent impervious of 1% and 0%, respectively. Runoff from these basins is considered negligible and similar to historic. Basins UD2, UD3, and UD4 combine for a developed 54% impervious and total combined area of 0.41 acres. These basins overland flow to either JFK Parkway or the Private Access Road. Flows are conveyed along gutters to an inlet located at the intersection of the Private Access Drive and Horsetooth Road. Total flows during a 100-yr storm from Basins UD2, UD3, and UD4 are a combined routed flow of 2.53 cfs. Historical 100-yr runoff from the existing parking lot (demolished with this project), was calculated at 2.27 cfs. The proposed undetained runoff is 0.26 cfs more than historic from the parking lot. Due to the increased runoff, the release rate from the proposed detention ponds has been restricted to below 75% of 2-year historic runoff rate. 5. Two (2) detention ponds are proposed with The Overlook development. Detention Pond A is located within Basin A and Detention Pond B is located within Basin B. Detention Pond B is routed through Detention Pond A. Release from Detention Pond A is then conveyed to the existing detention pond on the Bank Property. Detention Pond A Detention Pond A has a total of 0.50 ac-ft storage available. 0.48 ac-ft of storage is required with this project. Water quality control volume for Basin A is included in the pond volume. Emergency Overflow from the pond is directed north to the existing access road. Release rate from Pond A is proposed at 0.56 cfs. Detention Pond B Detention Pond B has a total of 0.33 ac-ft storage available. 0.25 ac-ft of storage is required with this project. Water quality control volume for Basin B is included in the pond volume. Emergency Overflow from the pond is directed east to The Wharf development. 0.80 ft of freeboard is provided to prevent emergency overflow. The existing The Wharf development should be able to accommodate any emergency overflow from the site through a network of drainage pans. Release rate from Pond B is proposed at 0.19 cfs. The Overlook Preliminary Drainage Report 8 Total developed 100-yr runoff from the site is a combination of the undetained flows from Basins UD2, UD3, and UD4 plus the 0.56 cfs release from Pond A for a total 3.12 cfs. A combination of the Historic 100-yr runoff from Basin H1 plus the 75% of the 2-yr runoff from Basin H2 totals 3.06 cfs. The proposed developed site is expected to release 0.06 cfs more than the historic. The additional 0.06 cfs is considered negligible. This additional flow does not account for the different peaking times for the release rate from the pond and peak runoff from the undetained basins. When peaking times are accounted for, this additional flow is expected to disappear. A full-size copy of the Drainage Exhibit can be found in the Map Pocket at the end of this report. B. Specific Details 1. Additional details to be provided with the FDP submittal. V. CONCLUSIONS A. Compliance with Standards 1. The drainage design proposed with The Overlook project complies with the City of Fort Collins’ Stormwater Criteria Manual. 2. The drainage design proposed with The Overlook project complies with the City of Fort Collins’ Master Drainage Plan for the Foothills Drainage Basin. 3. There are no regulatory floodplains associated with the development. 4. The drainage plan and stormwater management measures proposed with the development are compliant with all applicable State and Federal regulations governing stormwater discharge. 5. The site achieves the requirements set forth by the City of Fort Collins for Low Impact Development (LID) by providing 76% total impervious areas as being treated through an LID treatment. Please see LID Exhibit located in the Appendix. B. Drainage Concept 1. The drainage design proposed with this project will effectively comply with previous studies and will limit any potential damage or erosion associated with its stormwater runoff. All existing downstream drainage facilities are expected to not be impacted negatively by this development 2. The drainage design is anticipated to be very conservative. We have omitted any runoff reduction that will manifest due to infiltration from rain gardens. This is currently unable to be calculated with available soils data. The Overlook Preliminary Drainage Report 9 References 1. Fort Collins Stormwater Criteria Manual, City of Fort Collins, Colorado, as adopted by Ordinance No. 174, 2011, and referenced in Section 26-500 (c) of the City of Fort Collins Municipal Code. 2. Subsurface Exploration Report, JFK Luxury Apartments Fort Collins, Colorado, December 14, 2015, Earth Engineering Consultants, Inc.(EEC Project No. 1152119). 3. Larimer County Urban Area Street Standards, Adopted January 2, 2001, Repealed and Reenacted, Effective October 1, 2002, Repealed and Reenacted, Effective April 1, 2007. 4. Soils Resource Report for Larimer County Area, Colorado, Natural Resources Conservation Service, United States Department of Agriculture. 5. Urban Storm Drainage Criteria Manual, Volumes 1-3, Urban Drainage and Flood Control District, Wright-McLaughlin Engineers, Denver, Colorado, Revised April 2008. APPENDIX A HYDROLOGIC COMPUTATIONS The Overlook CHARACTER OF SURFACE 1 : Runoff Coefficient Percentage Impervious Project: The Overlook Streets, Parking Lots, Roofs, Alleys, and Drives: Calculations By: S. Thomas Asphalt ……....……………...……….....…...……………….………………………………………………………….0.95 . 100% Date: March 29, 2016 Concrete …….......……………….….……….………………..….…………………………………………………….0.95 . 90% Gravel (packed) ……….…………………….….…………………………..………………………………………….0.50 . 40% Roofs …….…….………………..……………….……………………………………………………………………… 0.95 90% Pavers…………………………...………………..……………………………………………………………………… 0.40 22% Lawns and Landscaping Sandy Soil Flat <2% ……………………………………………………………………………………………………………… 0.10 0% Average 2% to 7% ………………………………………………………………………………………………….0.15 . 0% Steep >7% …………………………………………………………………………………………………………… 0.20 0% Clayey Soil Flat <2% ……………………………………………………………………………………………………………… 0.20 0% Average 2% to 7% ………………………………………………………………………………………………….0.25 . 0% Steep >7% …………………………………………………………………………………………………………… 0.35 0% 2-year Cf = 1.00 10-year Cf = 1.00 100-year Cf = 1.25 Runoff Coefficients are taken from the Fort Collins Stormwater Criteria Manual, Table RO-11 Sub-Basin ID Sub- BasinBasin Area (ac) Area of Asphalt (ac) Area of Concrete (ac) Area of Pavers (ac) Area of Roofs (ac) Soil Type and Average Slope Area of Lawns and Landscaping (ac) 2-year Composite Runoff Coefficient 10-year Composite Runoff Coefficient 100-year Composite Runoff Coefficient Composite % Imperv. H1 0.23 0.17 0.03 0.00 0.00 Clayey | Average 2% to 7% 0.029 0.86 0.86 1.00 86% The Overlook Overland Flow, Time of Concentration: The Overlook Gutter/Swale Flow, Time of Concentration: Tt = L / 60V Tc = Ti + Tt (Equation RO-2) Velocity (Gutter Flow), V = 20·S½ Velocity (Swale Flow), V = 15·S½ NOTE: C-value for overland flows over grassy surfaces; C = 0.25 Is Length >500' ? C*Cf (2-yr Cf=1.00) C*Cf (10-yr Cf=1.00) C*Cf (100-yr Cf=1.25) Length, L (ft) Slope, S (%) Ti 2-yr (min) Ti 10-yr (min) Ti 100-yr (min) Length, L (ft) Slope, S (%) Velocity, V (ft/s) Tt (min) 2-yr Tc (min) 10-yr Tc (min) 100-yr Tc (min) 1 H1 No 0.86 0.86 1.00 104 2.40% 3.4 3.4 1.4 267 1.69% 2.60 1.7 5.1 5.1 5.0 2 H2 Yes 0.25 0.25 0.31 526 2.47% 27.0 27.0 25.0 0 N/A N/A N/A 27.0 27.0 25.0 * Time of Concentrations are calculated for the entire basin and used for both the Impervious and Pervious portions of the basins. EXISTING TIME OF CONCENTRATION COMPUTATIONS S. Thomas The Overlook Rational Method Equation: Project: The Overlook Calculations By: Date: Rainfall Intensity: 1 H1 0.23 5 5 5 0.86 0.86 1.00 2.85 4.87 9.95 0.56 0.96 2.27 2 H2 3.04 27 27 25 0.25 0.25 0.31 1.39 2.37 5.04 1.05 1.80 4.78 EXISTING RUNOFF COMPUTATIONS C100 Design Point Flow, Q100 (cfs) Flow, Q2 (cfs) 10-yr Tc (min) 2-yr Tc (min) C2 Flow, Q10 (cfs) Intensity, i100 (in/hr) Sub-Basin(s) S. Thomas Rainfall Intensity taken from the Fort Collins Stormwater Criteria Manual (FCSCM), Tables RA-7 and RA-8 March 29, 2016 Intensity, i10 (in/hr) C10 Area, A (acres) Intensity, i2 (in/hr) 100-yr Tc (min) Q = C f ( C )( i )( A ) 3/29/2016 12:08 PM D:\Projects\1174-001\Drainage\Hydrology\1174-001_Existing_Rational_Calcs.xlsx\Runoff The Overlook CHARACTER OF SURFACE 1 : Runoff Coefficient Percentage Impervious Project: The Overlook Streets, Parking Lots, Roofs, Alleys, and Drives: Calculations By: S. Thomas Asphalt ……....……………...……….....…...……………….………………………………………………………….0.95 . 100% Date: March 29, 2016 Concrete …….......……………….….……….………………..….…………………………………………………….0.95 . 90% Gravel (packed) ……….…………………….….…………………………..………………………………………….0.50 . 40% Roofs …….…….………………..……………….……………………………………………………………………… 0.95 90% Pavers…………………………...………………..……………………………………………………………………… 0.40 22% Lawns and Landscaping Sandy Soil Flat <2% ……………………………………………………………………………………………………………… 0.10 0% Average 2% to 7% ………………………………………………………………………………………………….0.15 . 0% Steep >7% …………………………………………………………………………………………………………… 0.20 0% Clayey Soil Flat <2% ……………………………………………………………………………………………………………… 0.20 0% Average 2% to 7% ………………………………………………………………………………………………….0.25 . 0% Steep >7% …………………………………………………………………………………………………………… 0.35 0% 2-year Cf = 1.00 10-year Cf = 1.00 100-year Cf = 1.25 Runoff Coefficients are taken from the Fort Collins Stormwater Criteria Manual, Table RO-11 Sub-Basin ID Sub- BasinBasin Area (ac) Area of Asphalt (ac) Area of Concrete (ac) Area of Pavers (ac) Area of Roofs (ac) Soil Type and Average Slope Area of Lawns and Landscaping (ac) 2-year Composite Runoff Coefficient 10-year Composite Runoff Coefficient 100-year Composite Runoff Coefficient Composite % Imperv. A1 0.55 0.00 0.01 0.00 0.54 Clayey | Average 2% to 7% 0.000 0.95 0.95 1.00 90% The Overlook Overland Flow, Time of Concentration: The Overlook Gutter/Swale Flow, Time of Concentration: Tt = L / 60V Tc = Ti + Tt (Equation RO-2) Velocity (Gutter Flow), V = 20·S½ Velocity (Swale Flow), V = 15·S½ NOTE: C-value for overland flows over grassy surfaces; C = 0.25 Is Length >500' ? C*Cf (2-yr Cf=1.00) C*Cf (10-yr Cf=1.00) C*Cf (100-yr Cf=1.25) Length, L (ft) Slope, S (%) Ti 2-yr (min) Ti 10-yr (min) Ti 100-yr (min) Length, L (ft) Slope, S (%) Velocity, V (ft/s) Tt (min) 2-yr Tc (min) 10-yr Tc (min) 100-yr Tc (min) 1 A1 No 0.95 0.95 1.00 91 12.42% 1.2 1.2 0.8 N/A N/A N/A 5.0 5.0 5.0 1 A2 No 0.31 0.31 0.39 97 0.82% 15.5 15.5 14.0 N/A N/A N/A 15.5 15.5 14.0 2 A3 No 0.91 0.91 1.00 157 5.57% 2.5 2.5 1.3 161 0.78% 1.76 1.5 5.0 5.0 5.0 3 A4 No 0.84 0.84 1.00 58 4.14% 2.3 2.3 0.9 170 0.35% 1.19 2.4 5.0 5.0 5.0 4 A5 No 0.88 0.88 1.00 33 0.91% 2.4 2.4 1.1 N/A N/A N/A 5.0 5.0 5.0 The Overlook Rational Method Equation: Project: The Overlook Calculations By: Date: Rainfall Intensity: 1 A1 0.55 5 5 5 0.95 0.95 1.00 2.85 4.87 9.95 1.49 2.54 5.46 1 A2 0.10 16 16 14 0.31 0.31 0.39 1.84 3.14 6.71 0.06 0.10 0.26 2 A3 0.47 5 5 5 0.91 0.91 1.00 2.85 4.87 9.95 1.23 2.10 4.71 3 A4 0.25 5 5 5 0.84 0.84 1.00 2.85 4.87 9.95 0.59 1.01 2.45 4 A5 0.10 5 5 5 0.88 0.88 1.00 2.85 4.87 9.95 0.26 0.45 1.03 5 A6 0.18 5 5 5 0.85 0.85 1.00 2.85 4.87 9.95 0.43 0.73 1.77 6 A7 0.14 5 5 5 0.25 0.25 0.31 2.85 4.87 9.95 0.10 0.17 0.43 TOTAL BASIN A TOTAL BASIN A 1.79 16 16 14 0.82 0.82 1.00 1.84 3.14 6.71 2.70 4.60 12.00 7 B1 0.32 7 7 5 0.63 0.63 0.79 2.60 4.44 9.95 0.53 0.90 2.53 8 B2 0.27 5 5 5 0.95 0.95 1.00 2.85 4.87 9.95 0.73 1.24 2.67 9 B3 0.12 5 5 5 0.88 0.88 1.00 2.85 4.87 9.95 0.30 0.51 1.18 10 B4 0.11 5 5 5 0.88 0.88 1.00 2.85 4.87 9.95 0.28 0.47 1.10 11 B5 0.22 16 16 15 0.29 0.29 0.36 1.84 3.14 6.62 0.11 0.19 0.51 TOTAL BASIN B TOTAL BASIN B 1.04 16 16 15 0.70 0.70 0.87 1.84 3.14 6.62 1.33 2.26 5.97 13 UD2 0.04 11 11 10 0.42 0.42 0.53 2.17 3.71 7.72 0.04 0.06 0.17 13 UD3 0.10 11 11 10 0.31 0.31 0.39 2.13 3.63 7.72 0.06 0.11 0.29 13 UD4 0.27 5 5 5 0.79 0.79 0.99 2.85 4.87 9.95 0.61 1.04 2.67 TOTAL BASIN UD2-UD4 TOTAL BASIN UD2-UD4 0.41 11 11 10 0.64 0.64 0.80 2.13 3.63 7.72 0.56 0.95 2.53 12 UD1 0.03 5 5 5 0.26 0.26 0.32 2.85 4.87 9.95 0.02 0.03 0.08 12 UD5 0.03 5 5 5 0.25 0.25 0.31 2.85 4.87 9.95 0.02 0.03 0.09 TOTAL SITE TOTAL SITE 3.29 16 16 15 0.75 0.75 0.94 1.84 3.14 6.62 4.53 7.73 20.38 Area, A (acres) Intensity, i2 (in/hr) 100-yr Tc (min) PROPOSED RUNOFF COMPUTATIONS C100 Design Point Flow, Q100 (cfs) Flow, Q2 (cfs) 10-yr Tc (min) 2-yr Tc (min) C2 Flow, Q10 (cfs) Intensity, i100 (in/hr) APPENDIX B HYDRAULIC COMPUTATIONS B.1 DETENTION POND SIZING B.2 STORM SEWER (NOT INCLUDED) B.3 INLET (NOT INCLUDED) APPENDIX B.1 DETENTION PONDS AND WATER QUALITY The Overlook 1174-001 Fort Collins, Colorado S. Thomas Date: 3/29/2016 Pond No.: Detention Pond A A 100-yr 1.00 Approx. WQCV 2144 ft3 Area (A)= 1.79 acres Quantity Detention 18632 ft3 (per SWMM) Max Release Rate = 0.56 cfs Total Volume 20776 ft3 Total Volume 0.48 ac-ft Detention Pond Calculation | SWMM Method Project Number: Project Location: Calculations By: Input Variables Results Design Point Design Storm Required Detention Volume Developed "C" = 3/29/2016 12:04 PM D:\Projects\1174-001\Drainage\Detention\1174-001__Detention Pond A.xlsm\FAA_CoFC idf_Pond 1 1174-001 Fort Collins, CO S. Thomas Date: 3/29/2016 Pond No.: A A7 100-yr 0.48 acft 5020.23 ft. Design Storm WQCV Required Volume= 2144 ft3 5014.87 ft. Contour Elevation (Y- values) Contour Area Depth Column Not Used Incremental Volume Total Volume Total Volume ft2 ft. ft3 ft3 ft3 acre-feet 5,013.20 7.7 0.00 0 0 0 0 5,013.40 244.02 0.20 20 20 0.00 5,013.60 803.69 0.20 99 119 0.00 5,013.80 1,333.72 0.20 211 330 0.01 5,014.00 1,511.37 0.20 284 614 0.01 5,014.20 1,628.45 0.20 314 928 0.02 5,014.40 1,749.36 0.20 337 1265 0.03 5,014.60 1,875.79 0.20 362 1627 0.04 5,014.80 2,009.54 0.20 388 2015 0.05 5,015.00 2,154.87 0.20 416 2431 0.06 5,015.20 2,237.34 0.20 439 2870 0.07 5,015.40 2,321.15 0.20 455 3325 0.08 5,015.60 2,423.05 0.20 474 3799 0.09 5,015.80 2,538.12 0.20 496 4295 0.10 5,016.00 2,662.90 0.20 520 4814 0.11 5,016.20 2,768.83 0.20 543 5357 0.12 5,016.40 2,883.13 0.20 565 5922 0.14 5,016.60 3,008.11 0.20 588 6510 0.15 5,016.80 3,136.88 0.20 614 7124 0.16 5,017.00 3,270.11 0.20 640 7764 0.18 5,017.20 3,388.00 0.20 665 8429 0.19 5,017.40 3,479.57 0.20 686 9115 0.21 5,017.60 3,564.42 0.20 704 9819 0.23 5,017.80 3,643.25 0.20 720 10539 0.24 5,018.00 3,719.24 0.20 735 11274 0.26 5,018.20 3,801.90 0.20 751 12026 0.28 5,018.40 3,885.54 0.20 768 12794 0.29 5,018.60 3,970.30 0.20 785 13578 0.31 5,018.80 4,059.01 0.20 802 14381 0.33 5,019.00 4,150.05 0.20 820 15201 0.35 5,019.20 4,261.66 0.20 840 16041 0.37 5,019.40 4,375.21 0.20 863 16904 0.39 5,019.60 4,495.27 0.20 886 17790 0.41 5,019.80 4,653.89 0.20 914 18704 0.43 5,020.00 4,838.55 0.20 948 19652 0.45 5,020.20 5,038.34 0.20 987 20639 0.47 5,020.40 5,254.04 0.20 1028 21667 0.50 Design Point Design Storm Require Volume= Stage - Storage Calculation The Overlook 1174-001 Fort Collins, Colorado S. Thomas Date: 3/29/2016 Pond No.: Detention Pond B B 100-yr 0.87 Approx. WQCV 906 ft3 Area (A)= 1.04 acres Quantity Detention 9892 ft3 (per SWMM) Max Release Rate = 0.19 cfs Total Volume 10798 ft3 Total Volume 0.25 ac-ft Detention Pond Calculation | SWMM Method Project Number: Project Location: Calculations By: Input Variables Results Design Point Design Storm Required Detention Volume Developed "C" = 3/29/2016 12:06 PM D:\Projects\1174-001\Drainage\Detention\1174-001__Detention Pond B.xlsm\SWMM_CoFC idf_Pond 1 1174-001 Fort Collins, CO S. Thomas Date: 3/29/2016 Pond No.: B B 100-yr 0.25 acft 5021.19 ft. Design Storm WQCV Required Volume= 906 ft 3 5018.28 ft. Contour Elevation (Y- values) Contour Area Depth Column Not Used Incremental Volume Total Volume Total Volume ft 2 ft. ft 3 ft 3 ft 3 acre-feet 5,016.60 0.45 0.00 0 0 0 0 5,016.80 41.52 0.20 3 3 0.00 5,017.00 149.92 0.20 18 21 0.00 5,017.20 304.11 0.20 44 66 0.00 5,017.40 469.78 0.20 77 142 0.00 5,017.60 647.54 0.20 111 253 0.01 5,017.80 837.28 0.20 148 401 0.01 5,018.00 1,039.65 0.20 187 588 0.01 5,018.20 1,255.23 0.20 229 817 0.02 5,018.40 1,483.68 0.20 273 1091 0.03 5,018.60 1,726.73 0.20 320 1411 0.03 5,018.80 1,982.69 0.20 370 1781 0.04 5,019.00 2,249.92 0.20 423 2204 0.05 5,019.20 2,531.35 0.20 477 2681 0.06 5,019.40 2,830.40 0.20 535 3217 0.07 5,019.60 3,115.85 0.20 594 3810 0.09 5,019.80 3,393.85 0.20 650 4461 0.10 5,020.00 3,668.01 0.20 705 5166 0.12 5,020.20 3,958.49 0.20 762 5928 0.14 5,020.40 4,328.60 0.20 828 6755 0.16 5,020.60 4,729.31 0.20 905 7660 0.18 5,020.80 5,118.92 0.20 984 8643 0.20 5,021.00 5,472.22 0.20 1058 9701 0.22 5,021.20 5,791.41 0.20 1125 10826 0.25 5,021.40 6,080.43 0.20 1186 12012 0.28 5,021.60 6,351.35 0.20 1242 13254 0.30 5,021.80 6,595.94 0.20 1293 14547 0.33 Design Point Design Storm Require Volume= Stage - Storage Calculation Project Number: APPENDIX B.2 STORM SEWERS APPENDIX B.3 INLETS APPENDIX C SWMM MODELING SUBB SUBA OUTLETB OUTLETA OUT1 PONDB PONDA GAGE1 02/26/2016 00:15:00 SWMM 5.1 Page 1 Time Series FC100-YR Elapsed Time (hours) 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 10 9 8 7 6 5 4 3 2 1 0 SWMM 5.1 Page 1 System Precipitation (in/hr) Elapsed Time (hours) 0 1 2 3 4 5 6 7 Precipitation (in/hr) 6.0 5.0 4.0 3.0 2.0 1.0 0.0 SWMM 5.1 Page 1 Subcatchment SUBB Runoff (CFS) Subcatchment SUBA Runoff (CFS) Elapsed Time (hours) 0 1 2 3 4 5 6 7 Runoff (CFS) 9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0 SWMM 5.1 Page 1 Node PONDA Volume (ft3) Node PONDB Volume (ft3) Elapsed Time (hours) 0 1 2 3 4 5 6 7 Volume (ft3) 20000.0 18000.0 16000.0 14000.0 12000.0 10000.0 8000.0 6000.0 4000.0 2000.0 0.0 SWMM 5.1 Page 1 S U M M A R Y S T A T I S T I C S =================================== Object .............. Node PONDA Variable ............. Volume (ft3) Event Period ......... Variable Event Statistic ...... Peak (ft3) Event Threshold ...... Volume > 0.0000 (ft3) Event Threshold ...... Separation Time >= 6.0 (hr) Period of Record ..... 02/26/2016 to 02/26/2016 Number of Events ..... 1 Event Frequency*...... 1.000 Minimum Value ........ 18621.891 Maximum Value ........ 18621.891 Mean Value ........... 18621.891 Std. Deviation ....... 0.000 Skewness Coeff. ...... 0.000 *Fraction of all reporting periods belonging to an event. SWMM 5.1 Page 1 S U M M A R Y S T A T I S T I C S =================================== Object .............. Node PONDB Variable ............. Volume (ft3) Event Period ......... Variable Event Statistic ...... Peak (ft3) Event Threshold ...... Volume > 0.0000 (ft3) Event Threshold ...... Separation Time >= 6.0 (hr) Period of Record ..... 02/26/2016 to 02/26/2016 Number of Events ..... 1 Event Frequency*...... 1.000 Minimum Value ........ 9858.642 Maximum Value ........ 9858.642 Mean Value ........... 9858.642 Std. Deviation ....... 0.000 Skewness Coeff. ...... 0.000 *Fraction of all reporting periods belonging to an event. SWMM 5.1 Page 1 Link OUTLETA Flow (CFS) Link OUTLETB Flow (CFS) Elapsed Time (hours) 0 1 2 3 4 5 6 7 Flow (CFS) 0.6 0.4 0.2 0.0 SWMM 5.1 Page 1 Table - Node OUT1 Depth Total Inflow Days Hours (ft) (CFS) 0 00:15:00 0.00 0.02 0 00:30:00 0.00 0.12 0 00:45:00 0.00 0.40 0 01:00:00 0.00 0.48 0 01:15:00 0.00 0.51 0 01:30:00 0.00 0.53 0 01:45:00 0.00 0.54 0 02:00:00 0.00 0.56 0 02:15:00 0.00 0.56 0 02:30:00 0.00 0.56 0 02:45:00 0.00 0.55 0 03:00:00 0.00 0.55 0 03:15:00 0.00 0.54 0 03:30:00 0.00 0.54 0 03:45:00 0.00 0.53 0 04:00:00 0.00 0.52 0 04:15:00 0.00 0.52 0 04:30:00 0.00 0.51 0 04:45:00 0.00 0.51 0 05:00:00 0.00 0.50 0 05:15:00 0.00 0.49 0 05:30:00 0.00 0.49 0 05:45:00 0.00 0.48 0 06:00:00 0.00 0.48 SWMM 5.1 Page 1 APPENDIX D EROSION CONTROL REPORT The Overlook Preliminary Erosion Control Report A comprehensive Erosion and Sediment Control Plan (along with associated details) will be included with the final construction drawings. It should be noted, however, that any such Erosion and Sediment Control Plan serves only as a general guide to the Contractor. Staging and/or phasing of the BMPs depicted, and additional or different BMPs from those included may be necessary during construction, or as required by the authorities having jurisdiction. It shall be the responsibility of the Contractor to ensure erosion control measures are properly maintained and followed. The Erosion and Sediment Control Plan is intended to be a living document, constantly adapting to site conditions and needs. The Contractor shall update the location of BMPs as they are installed, removed or modified in conjunction with construction activities. It is imperative to appropriately reflect the current site conditions at all times. The Erosion and Sediment Control Plan shall address both temporary measures to be implemented during construction, as well as permanent erosion control protection. Best Management Practices from the Volume 3, Chapter 7 – Construction BMPs will be utilized. Measures may include, but are not limited to, silt fencing along the disturbed perimeter, gutter protection in the adjacent roadways and inlet protection at existing and proposed storm inlets. Vehicle tracking control pads, spill containment and clean-up procedures, designated concrete washout areas, dumpsters, and job site restrooms shall also be provided by the Contractor. Grading and Erosion Control Notes can be found on Sheet CS2 of the Utility Plans. The Utility Plans at final design will also contain a full-size Erosion Control Plan as well as a separate sheet dedicated to Erosion Control Details. In addition to this report and the referenced plan sheets, the Contractor shall be aware of, and adhere to, the applicable requirements outlined in any existing Development Agreement(s) of record, as well as the Development Agreement, to be recorded prior to issuance of the Development Construction Permit. Also, the Site Contractor for this project will be required to secure a Stormwater Construction General Permit from the Colorado Department of Public Health and Environment (CDPHE), Water Quality Control Division – Stormwater Program, before commencing any earth disturbing activities. Prior to securing said permit, the Site Contractor shall develop a comprehensive StormWater Management Plan (SWMP) pursuant to CDPHE requirements and guidelines. The SWMP will further describe and document the ongoing activities, inspections, and maintenance of construction BMPs. APPENDIX E LID EXHIBIT LID CALL UTILITY NOTIFICATION CENTER OF COLORADO Know what's R These drawings are instruments of service provided by Northern Engineering Services, Inc. and are not to be used for any type of construction unless signed and sealed by a Professional Engineer in the employ of Northern Engineering Services, Inc. NOT FOR CONSTRUCTION 200 South College Avenue, Suite 010 Fort Collins, Colorado 80524 N O R T H E RN PHONE: 970.221.4158 FAX: 970.221.4159 www.northernengineering.com ( IN FEET ) 0 1 INCH = 30 FEET 30 30 60 90 KEYMAP TOTAL SITE IMPERVIOUS AREA: 93,519 SF (2.15 AC) NOT INCLUDING EXISTING IMPERVIOUS AREA TOTAL RAIN GARDEN AREA: 1,593 SF TOTAL RAIN GARDEN RUN-ON AREA (IMPERVIOUS ONLY): 71,487SF (1.64 AC) OVERALL RAIN GARDEN TO RUN-ON RATIO: 45:1 TOTAL IMPERVIOUS AREA TREATED: 71,487 SF (1.64 AC) PERCENT OF TOTAL IMPERVIOUS AREA TREATED: 76.4% MAP POCKET DR1 – OVERALL DRAINAGE EXHIBIT HDR1 CALL UTILITY NOTIFICATION CENTER OF COLORADO Know what's R These drawings are instruments of service provided by Northern Engineering Services, Inc. and are not to be used for any type of construction unless signed and sealed by a Professional Engineer in the employ of Northern Engineering Services, Inc. NOT FOR CONSTRUCTION 200 South College Avenue, Suite 010 Fort Collins, Colorado 80524 N O R T H E RN PHONE: 970.221.4158 FAX: 970.221.4159 www.northernengineering.com ( IN FEET ) 0 1 INCH = 30 FEET 30 30 60 90 KEYMAP LEGEND: 5013 PROPOSED CONTOUR 93 EXISTING CONTOUR PROPERTY BOUNDARY EXISTING STORM SEWER 1. THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE COMMENCING NEW CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE FOR FOR ALL UNKNOWN UNDERGROUND UTILITIES. 2. REFER TO THE "PRELIMINARY DRAINAGE AND EROSION CONTROL REPORT FOR THE OVERLOOK BY NORTHERN ENGINEERING, DATED MARCH 30, 2016 FOR ADDITIONAL INFORMATION. NOTES: FLOW PATH DRAINAGE BASIN BUBBLE A DESIGN POINT A BASIN BOUNDARY PROPOSED STORM SEWER FOR DRAINAGE REVIEW ONLY NOT FOR CONSTRUCTION DRAINAGE SUMMARY TABLE DESIGN POINT BASIN ID TOTAL AREA (acres) C2 C100 2-yr DR1 CALL UTILITY NOTIFICATION CENTER OF COLORADO Know what's R CityDate Engineer Date Date Date Date Stormwater Utility Parks & Recreation Traffic Engineer Date Water & Wastewater Utility City of Fort Collins, Colorado UTILITY PLAN APPROVAL Environmental Planner These drawings are instruments of service provided by Northern Engineering Services, Inc. and are not to be used for any type of construction unless signed and sealed by a Professional Engineer in the employ of Northern Engineering Services, Inc. NOT FOR CONSTRUCTION 200 South College Avenue, Suite 010 Fort Collins, Colorado 80524 N O R T H E RN PHONE: 970.221.4158 FAX: 970.221.4159 www.northernengineering.com ( IN FEET ) 0 1 INCH = 30 FEET 30 30 60 90 KEYMAP DRAINAGE SUMMARY TABLE DESIGN POINT BASIN ID TOTAL AREA (acres) C2 C100 2-yr Tc (min) 100-yr Tc (min) Q2 (cfs) Q100 (cfs) 1 A1 0.55 0.95 1.00 5.0 5.0 1.49 5.46 1 A2 0.10 0.31 0.39 15.5 14.0 0.06 0.26 2 A3 0.47 0.91 1.00 5.0 5.0 1.23 4.71 3 A4 0.25 0.84 1.00 5.0 5.0 0.59 2.45 4 A5 0.10 0.88 1.00 5.0 5.0 0.26 1.03 5 A6 0.18 0.85 1.00 5.0 5.0 0.43 1.77 6 A7 0.14 0.25 0.31 5.0 5.0 0.10 0.43 7 B1 0.32 0.63 0.79 6.9 5.0 0.53 2.53 8 B2 0.27 0.95 1.00 5.0 5.0 0.73 2.67 9 B3 0.12 0.88 1.00 5.0 5.0 0.30 1.18 10 B4 0.11 0.88 1.00 5.0 5.0 0.28 1.10 11 B5 0.22 0.29 0.36 16.0 14.6 0.11 0.51 13 UD2 0.04 0.42 0.53 10.9 10.1 0.04 0.17 13 UD3 0.10 0.31 0.39 11.1 10.5 0.06 0.29 13 UD4 0.27 0.79 0.99 5.0 5.0 0.61 2.67 12 UD1 0.03 0.26 0.32 5.0 5.0 0.02 0.08 12 UD5 0.03 0.25 0.31 5.0 5.0 0.02 0.09 LEGEND: 5013 PROPOSED CONTOUR 93 EXISTING CONTOUR PROPERTY BOUNDARY EXISTING STORM SEWER 1. THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE COMMENCING NEW CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE FOR FOR ALL UNKNOWN UNDERGROUND UTILITIES. 2. REFER TO THE "PRELIMINARY DRAINAGE AND EROSION CONTROL REPORT FOR THE OVERLOOK BY NORTHERN ENGINEERING, DATED MARCH 30, 2016 FOR ADDITIONAL INFORMATION. NOTES: FLOW PATH DRAINAGE BASIN BUBBLE A DESIGN POINT A BASIN BOUNDARY PROPOSED STORM SEWER FOR DRAINAGE REVIEW ONLY NOT FOR CONSTRUCTION Tc (min) 100-yr Tc (min) Q2 (cfs) Q100 (cfs) 1 H1 0.23 0.86 1.00 5.1 5.0 0.56 2.27 2 H2 3.04 0.25 0.31 27.0 25.0 1.05 4.78 Project Location: Calculations By: Required Volume Water Surface Elevation (WSE) Project Number: Project Location: Calculations By: Required Volume Water Surface Elevation (WSE) Sub-Basin(s) S. Thomas Rainfall Intensity taken from the Fort Collins Stormwater Criteria Manual (FCSCM), Tables RA-7 and RA-8 March 29, 2016 Intensity, i10 (in/hr) C10 Q = C f ( C )( i )( A ) 3/29/2016 12:11 PM D:\Projects\1174-001\Drainage\Hydrology\1174-001_Proposed_Rational_Calcs.xlsx\Runoff 5 A6 No 0.85 0.85 1.00 95 4.21% 2.9 2.9 1.1 110 1.73% 2.63 0.7 5.0 5.0 5.0 6 A7 No 0.25 0.25 0.31 N/A N/A N/A N/A N/A N/A N/A 5.0 5.0 5.0 TOTAL BASIN A TOTAL BASIN A 15.5 15.5 14.0 7 B1 No 0.63 0.63 0.79 202 5.94% 6.9 6.9 4.6 N/A N/A N/A 6.9 6.9 5.0 8 B2 No 0.95 0.95 1.00 70 17.14% 0.9 0.9 0.6 N/A N/A N/A 5.0 5.0 5.0 9 B3 No 0.88 0.88 1.00 174 5.40% 3.1 3.1 1.4 16 3.13% 3.54 0.1 5.0 5.0 5.0 10 B4 No 0.88 0.88 1.00 138 5.22% 2.8 2.8 1.3 N/A N/A N/A 5.0 5.0 5.0 11 B5 No 0.29 0.29 0.36 179 2.07% 16.0 16.0 14.6 N/A N/A N/A 16.0 16.0 14.6 TOTAL BASIN B TOTAL BASIN B 16.0 16.0 14.6 13 UD2 No 0.42 0.42 0.53 47 4.26% 5.3 5.3 4.5 965 2.07% 2.88 5.6 10.9 10.9 10.1 13 UD3 No 0.31 0.31 0.39 47 4.26% 6.2 6.2 5.6 882 2.27% 3.01 4.9 11.1 11.1 10.5 13 UD4 No 0.79 0.79 0.99 17 4.71% 1.4 1.4 0.5 440 1.93% 2.78 2.6 5.0 5.0 5.0 TOTAL BASIN UD2-UD4 TOTAL BASIN UD2-UD4 11.1 11.1 10.5 12 UD1 No 0.26 0.26 0.32 21 7.62% 3.7 3.7 3.4 N/A N/A N/A 5.0 5.0 5.0 12 UD5 No 0.25 0.25 0.31 16 15.00% 2.6 2.6 2.4 N/A N/A N/A 5.0 5.0 5.0 TOTAL SITE TOTAL SITE 16.0 16.0 14.6 * Time of Concentrations are calculated for the entire basin and used for both the Impervious and Pervious portions of the basins. PROPOSED TIME OF CONCENTRATION COMPUTATIONS S. Thomas March 29, 2016 Design Point Sub-Basin Overland Flow Gutter/Pipe Flow Time of Concentration (Equation RO-4) ( ) 3 1 1 . 87 1 . 1 * S Ti C Cf L - = 3/29/2016 12:11 PM D:\Projects\1174-001\Drainage\Hydrology\1174-001_Proposed_Rational_Calcs.xlsx\Tc A2 0.10 0.00 0.01 0.00 0.00 Clayey | Average 2% to 7% 0.091 0.31 0.31 0.39 7% A3 0.47 0.37 0.07 0.00 0.00 Clayey | Average 2% to 7% 0.028 0.91 0.91 1.00 93% A4 0.25 0.16 0.05 0.00 0.00 Clayey | Average 2% to 7% 0.037 0.84 0.84 1.00 83% A5 0.10 0.00 0.09 0.00 0.00 Clayey | Average 2% to 7% 0.010 0.88 0.88 1.00 81% A6 0.18 0.14 0.02 0.00 0.00 Clayey | Average 2% to 7% 0.027 0.85 0.85 1.00 84% A7 0.14 0.00 0.00 0.00 0.00 Clayey | Average 2% to 7% 0.140 0.25 0.25 0.31 0% TOTAL BASIN A 1.79 0.66 0.25 0.00 0.54 Clayey | Average 2% to 7% 0.332 0.82 0.82 1.00 77% B1 0.32 0.12 0.05 0.00 0.00 Clayey | Average 2% to 7% 0.147 0.63 0.63 0.79 53% B2 0.27 0.00 0.00 0.00 0.27 Clayey | Average 2% to 7% 0.000 0.95 0.95 1.00 90% B3 0.12 0.06 0.05 0.00 0.00 Clayey | Average 2% to 7% 0.012 0.88 0.88 1.00 86% B4 0.11 0.07 0.03 0.00 0.00 Clayey | Average 2% to 7% 0.012 0.88 0.88 1.00 87% B5 0.22 0.00 0.01 0.00 0.00 Clayey | Average 2% to 7% 0.205 0.29 0.29 0.36 5% TOTAL BASIN B 1.04 0.25 0.14 0.00 0.27 Clayey | Average 2% to 7% 0.376 0.70 0.70 0.87 60% UD2 0.04 0.00 0.01 0.00 0.00 Clayey | Average 2% to 7% 0.031 0.42 0.42 0.53 22% UD3 0.10 0.00 0.01 0.00 0.00 Clayey | Average 2% to 7% 0.088 0.31 0.31 0.39 8% UD4 0.27 0.14 0.07 0.00 0.00 Clayey | Average 2% to 7% 0.063 0.79 0.79 0.99 74% TOTAL BASIN UD2-UD4 0.41 0.14 0.09 0.00 0.00 Clayey | Average 2% to 7% 0.181 0.64 0.64 0.80 54% UD1 0.03 0.00 0.00 0.00 0.00 Clayey | Average 2% to 7% 0.026 0.26 0.26 0.32 1% UD5 0.03 0.00 0.00 0.00 0.00 Clayey | Average 2% to 7% 0.028 0.25 0.25 0.31 0% TOTAL SITE 3.29 1.06 0.48 0.00 0.81 Clayey | Average 2% to 7% 0.943 0.75 0.75 0.94 67% Composite Runoff Coefficient with Adjustment PROPOSED COMPOSITE % IMPERVIOUSNESS AND RUNOFF COEFFICIENT CALCULATIONS 3/29/2016 12:10 PM D:\Projects\1174-001\Drainage\Hydrology\1174-001_Proposed_Rational_Calcs.xlsx\Composite C March 29, 2016 Design Point Sub-Basin Overland Flow Gutter/Pipe Flow Time of Concentration (Equation RO-4) ( ) 3 1 1 . 87 1 . 1 * S Ti C Cf L - = 3/29/2016 12:08 PM D:\Projects\1174-001\Drainage\Hydrology\1174-001_Existing_Rational_Calcs.xlsx\Tc H2 3.04 0.00 0.00 0.00 0.00 Clayey | Average 2% to 7% 3.038 0.25 0.25 0.31 0% TOTAL SITE 3.27 0.17 0.03 0.00 0.00 Clayey | Average 2% to 7% 3.067 0.29 0.29 0.37 6% 1. Table RO-11 | Rational Method Runoff Coefficients for Composite Analysis Composite Runoff Coefficient with Adjustment EXISTING COMPOSITE % IMPERVIOUSNESS AND RUNOFF COEFFICIENT CALCULATIONS 3/29/2016 12:08 PM D:\Projects\1174-001\Drainage\Hydrology\1174-001_Existing_Rational_Calcs.xlsx\Composite C