HomeMy WebLinkAboutBROOKFIELD SECOND FILING, TRACTS D & E - PDP/FDP - FDP150025 - REPORTS - STORMWATER MANAGEMENT PLAN (3)STORMWATER MANAGEMENT PLAN (SWMP)
BROOKFIELD REPLAT A
Fort Collins, CO
July 14, 2015
Prepared for:
Landmark Construction Solutions
1170 W. Ash Street #100
Windsor, CO 80550
970-330-4316
Prepared by:
301 N. Howes Street, Unit 100
Fort Collins, Colorado 80521
Phone: 970.221.4158
www.northernengineering.com
Project Number: 374-020
This Drainage Report is consciously provided as a PDF.
Please consider the environment before printing this document in its entirety.
When a hard copy is absolutely necessary, we recommend double-sided printing.
301 N. Howes Street, Suite 100, Fort Collins, CO 80521 970.221.4158 www.northernengineering.com
July 14, 2015
Landmark Construction Solutions
1170 W. Ash Street #100
Windsor, CO 80550
RE: Stormwater Management Plan
Brookfield Replat A
To Whom It May Concern:
Northern Engineering Services, Inc. is pleased to submit this Stormwater Management Plan for
Brookfield Replat A. This report outlines Best Management Practices (BMPs) to be implemented
with the proposed construction in order to minimize potential pollutants in stormwater discharges.
We have prepared this report to accompany the Colorado Department of Public Health and
Environment General Permit for Stormwater Discharge Associated with Construction Activities (aka,
Stormwater Discharge Permit or SDP). The General Permit No. for this SDP is (to be filled-in by
permittee) and the Certification No. for this SDP is (to be filled-in by permittee). The Permit
Certification is Effective beginning (to be filled-in by permittee), and initial certification expires (to be
filled-in by permittee). A copy of the issuance cover letter can be found in the Appendix D of this
document (to be provided by permittee).
Please note: this Stormwater Management plan (including the Site Maps) is not a static document.
It is a dynamic device that should be kept current and logged as construction takes place. As such,
this version was prepared to facilitate initial plan approvals and permitting, but does not necessarily
reflect the final version, or the transitions throughout the construction process. As the site develops
and changes, the Contractor is expected and encouraged to make changes to what is contained
herein so that the SWMP works as effectively and efficiently as possible. It shall be the
responsibility of the SWMP Administrator and/or the permit holder (or applicant thereof) to ensure
the plan is properly maintained and followed.
If you should have any questions or comments as you review this report, please feel free to contact
us at your convenience.
Sincerely,
NORTHERN ENGINEERING SERVICES, INC.
Ryan Banning, PE
Brookfield Replat A
Stormwater Management Plan
TABLE OF CONTENTS
Vicinity Map
1.0 General Requirements ............................................................................................... 1
1.1 Objectives .................................................................................................................. 1
1.2 SMWP Availability ...................................................................................................... 1
1.3 Definitions.................................................................................................................. 1
1.4 Additional Permitting ................................................................................................... 1
2.0 Narrative Site Description .......................................................................................... 2
2.1 Existing Site Description .............................................................................................. 2
2.2 Nature of Construction Activity ..................................................................................... 2
2.3 Sequence of Major Activities ......................................................................................... 2
2.4 Site Disturbance ......................................................................................................... 3
2.5 Existing Data .............................................................................................................. 3
2.6 Existing Vegetation ...................................................................................................... 3
2.7 Potential Pollution Sources ........................................................................................... 3
2.8 Non-stormwater discharges .......................................................................................... 4
2.9 Receiving Waters ........................................................................................................ 4
3.0 Stormwater Management Controls .............................................................................. 4
3.1 SWMP Administrator ................................................................................................... 4
3.2 Best Management Practices (BMP’s) for Stormwater Pollution Prevention .......................... 5
3.3 Structural Practices for Erosion and Sediment Control ..................................................... 5
3.4 Non-Structural Practices for Erosion and Sediment Control .............................................. 7
3.5 Phased BMP Installation .............................................................................................. 9
3.6 Material Handling and Spill Prevention ........................................................................ 10
3.7 Dedicated Concrete or Asphalt Batch Plant .................................................................. 10
3.8 Vehicle Tracking Control ............................................................................................ 12
3.9 Waste Management and Disposal ............................................................................... 12
3.10 Groundwater and Stormwater Dewatering .................................................................... 12
4.0 Final Stabilization and Long-Term Stormwater Management ........................................ 12
4.1 Final Stabilization ..................................................................................................... 12
4.2 Long-Term Stormwater Management ........................................................................... 13
5.0 Inspection, Maintenance and Record Keeping ............................................................ 13
5.1 BMP Inspection ........................................................................................................ 13
5.2 BMP Maintenance .................................................................................................... 13
5.3 Record Keeping ........................................................................................................ 13
6.0 Additional SWMP and BMP Resources ...................................................................... 15
References 16
Brookfield Replat A
Stormwater Management Plan
APPENDICES:
APPENDIX A – Site Maps
APPENDIX B – Erosion Control Details
APPENDIX C – Landscape Plan
APPENDIX D – Copies of Permits/Applications
APPENDIX E – Inspection Logs
APPENDIX F – Erosion Control Escrow Estimate
APPENDIX G – Contractor Inserts (as needed)
Brookfield Replat A
Stormwater Management Plan 1
1.0 General Requirements
1.1 Objectives
The objective of a Stormwater Management Plan (SWMP) is to identify all potential sources of
pollution likely to occur as a result of construction activity associated with the site construction, and
to describe the practices that will be used to reduce the pollutants in stormwater discharges from
the site. The SWMP must be completed and implemented at the time the project breaks ground,
and revised as necessary as construction proceeds to accurately reflect the conditions and practices
at the site.
This report summarizes the Stormwater Management Plan for the construction activity that will
occur with Brookfield Replat A in Fort Collins, CO. This plan has been prepared according to
regulations of the Colorado Department of Public Health and Environment (CDPHE), Water Quality
Control Division.
1.2 SMWP Availability
This report is intended to remain on the aforementioned construction site to allow for maintenance
and inspection updates, and for review during inspection.
1.3 Definitions
BMP – Best Management Practice encompassing a wide range of erosion and sediment control
practices, both structural and non-structural in nature, which are intended to reduce or eliminate
any possible water quality impacts from stormwater leaving a construction site.
Erosion Control BMPs – Practices that PREVENT the erosion of soil, such as minimizing the amount
of disturbed area through phasing, temporary stabilization, and preserving existing vegetation.
Sediment Control BMP’s – Practices to REMOVE sediment from runoff, such as sediment basins,
silt fence, or inlet protection.
Non-structural BMP’s – The implementation of methods, practices, and procedures to minimize
water quality impacts, such as the preservation of natural vegetation, preventive maintenance and
spill response procedures.
Structural BMP’s – Physical devices that prevent or minimize water quality impacts, such as
sediment basins, inlet protection, or silt fence.
1.4 Additional Permitting
As mentioned above, this Stormwater Management Plan is associated with the Colorado
Department of Public Health and Environment Stormwater Permit issued by the Water Quality
Control Division of the Colorado Department of Public Health and Environment (CDPHE).
Additional Environmental permitting not described in this report may be required as a part of this
project. An example is the Construction Dewatering Permit for groundwater. Another example is
the Air Pollution Emission Notice (APEN). The CDPHE website contains links to both of these
permits, as well as many other potential permits. The Contractor is responsible for ensuring the
proper permits are acquired.
CDPHE Construction Permit Website:
http://www.colorado.gov/cs/Satellite/CDPHE-WQ/CBON/1251596875260
Brookfield Replat A
Stormwater Management Plan 2
2.0 Narrative Site Description
2.1 Existing Site Description
Located in the Northwest ¼ of Section 4, Township 6 North, Range 68 West of the 6th Prime
Meridian, City of Fort Collins, County of Larimer, State of Colorado. The site is a part of the
Brookfield Subdivision. The existing site is comprised of mostly vacant land with bare soils, natural
grasses and vegetation. Bounded to the east by the Fossil Creek Inlet Ditch, to the west by the
dedicated right of way of Brookfield Drive, to the south by Precision Drive, and to the north by
undeveloped property.
2.2 Wind and Rainfall Erodibility
The site is located within a moderate risk Erodibility Zone per the City of Fort Collins Wind
Erodibility Map. According to the Natural Resources Conservation Service website -
www.websoilsurvey.nrcs.usda.gov, the applicable soil erosion factor (K), which indicates the
susceptibility of a soil to sheet and rill erosion, is 0.25. This value is indicative of soils moderately
susceptible to rainfall erosion.
Impervious area (i.e., roof area, concrete walks and asphalt/paver parking area) and landscaping
will permanently stabilize the areas disturbed by the proposed construction activity; therefore, the
likelihood of erosion and sediment problems occurring on-site is minimal. During the interim period,
in which the disturbed areas are open, the BMPs described herein were selected to prevent erosion
and limit sediment migration.
2.3 Nature of Construction Activity
The proposed project site plan is composed of 2-Story Multi-Family Housing (condos/townhomes).
This site will employ many water quality features and runoff reduction facilities including porous
pavers, drywells, and rain gardens. The installation of proposed utilities (e.g., electric, gas, sanitary
sewer, domestic water and storm drain) will occur next. While building foundations are being
constructed, concrete curbs will be installed around the proposed parking areas. A permeable paver
section within the access drives and parking areas will likely follow completion of exterior
construction. The fine grading of the landscaped areas and the installation of landscaping will mark
the completion of the construction activities.
2.4 Sequence of Major Activities
To complete the project, many basic categories of construction activity will take place. The first
part of the project will consist of overlot grading. Within this phase, protection will need to be
supplied to the existing streets and inlets, as well as other perimeter protection. With the
surroundings, type of perimeter protection will vary due to the differing types of ground material. It
will be the Contractor’s responsibility to implement the appropriate measure to suit the installation
and type of ground material. This will be followed by utility installation and foundation excavation.
Vertical construction of the 2-Story Multi-Family Housing will commence after foundation and
underground work is complete. New curb/gutter, paving, and sidewalks are expected to begin after
the building is dried in and tradecrafts move inside. Installation of the permeable paver system is
likely to occur at this time. The final stages of site construction will be fine grading of the areas
around the buildings, and the installation of landscaping throughout the project. The
aforementioned sequencing is an initial best guess, and is subject to change at the Contractor’s
discretion.
Brookfield Replat A
Stormwater Management Plan 3
2.5 Site Disturbance
The site disturbance will occur in and off of the project property is approximately 7.7 acres.
Grading of the entire site is expected in order to reach final grades.
2.6 Existing Data
In order to complete the associated construction plans, a topographical survey of the site was
completed. This survey consisted of field measurements made by TST, Inc.
In addition to the field survey, a geotechnical report was used to determine existing soil types found
on-site. According to the NRCS Hyrdologic Soils Group classifications, the soils for the area
consists of layers of clay loam and gravelly sand loam. These soils are classified as Hydrologic Soil
Group C and have a low infiltration rate.
2.7 Existing Vegetation
The existing site is comprised of mostly vacant land with bare soils, natural grasses and vegetation.
The approximate percent existing vegetative cover is 60%. It is highly recommended that pre-
construction photos be taken to clearly document vegetative conditions prior to any disturbance
activities.
2.8 Potential Pollution Sources
As is typical with most construction sites, there are a number of potential pollution sources which
could affect water quality. It is not possible for this report to identify all materials that will be used
or stored on the construction site. It is the sole responsibility of the Contractor to identify and
properly handle all materials that are potential pollution sources. The following are some common
examples of potential pollution sources:
Exposed and stored soils
Management of contaminated soils
Off-site tracking of soils and sediment
Loading and unloading operations
Outdoor storage of building materials, fertilizers, chemicals, etc.
Vehicle and equipment maintenance and fueling
Significant dust or particulate generating processes
Routine maintenance activities involving fertilizers, pesticides, detergents, fuels, solvents, oils, etc.
On-site waste disposal practices (waste piles, dumpsters, etc.)
Concrete truck/equipment washing
Non-industrial waste sources that may be significant, such as worker trash and portable toilets
Uncovered trash bins
Other areas or procedures where potential spills can occur
Stockpiling of materials that can be transported to receiving waterway(s)
Management of Contaminated Soils: We are not aware of on-site contaminated soils. However, the
contractor should conduct a thorough, pre-construction environmental site assessment. If
contaminated soils are discovered, the contractor will identify appropriate practices and procedures
for the specific contaminants discovered on-site.
Brookfield Replat A
Stormwater Management Plan 4
Loading and Unloading Operations: During site demolition, material loading and unloading will
occur on-site. As site development and building construction progresses, space constraints will limit
the number of on-site locations for loading and unloading activities to the site. The contractor will
be responsible for the proper handling and management of traffic control and pollution sources
during loading and unloading operations.
Dedicated Asphalt and Concrete Batch Plants: Neither a dedicated asphalt or concrete batch plant
will be constructed on-site.
2.9 Non-stormwater discharges
The Stormwater Construction Permit only covers discharges composed entirely of stormwater.
Emergency firefighting water is the only authorized exception. Concrete Washout water can NOT be
discharged to surface waters or to storm sewer systems without separate permit coverage. The
discharge of Concrete Washout water to the ground, under specific conditions, may be allowed by
the Stormwater Construction Permit when appropriate BMPs are implemented.
The discharge of pumped stormwater, ONLY, from excavations, ponds, depressions, etc. to surface
waters, or to a municipal storm sewer system is allowed by the Stormwater Construction Permit, as
long as the dewatering activity and associated BMPs are identified in the Stormwater Management
Plan (SWMP) and are implemented in accordance with the SWMP.
Aside from the exceptions noted above, non-stormwater discharges must be addressed in a separate
permit issued for that discharge. If groundwater is encountered, and dewatering is required, a
Construction Dewatering Permit must be acquired from the Colorado Department of Public Health
and Environment.
2.10 Receiving Waters
The north and east section of the site will remain mostly undeveloped but it will continue to sheet
flow drain to the Fossil Creek Inlet Ditch per the previously approved plans.
The remainder of the site will collect in storm sewers and gutters, being conveyed to the site
detention pond to the southeast. The final release from this existing pond is also the Fossil Creek
Inlet Ditch.
3.0 Stormwater Management Controls
3.1 SWMP Administrator
A SWMP Administrator must be designated in conjunction with the Stormwater Permit. This person
shall be responsible for developing, implementing, maintaining, and revising the SWMP. The
SWMP Administrator will also be the contact for all SWMP-related issues and will be the person
responsible for the accuracy, completeness, and implementation of the SWMP. The Administrator
should be a person with authority to adequately manage and direct day-to-day stormwater quality
management activities at the site.
Brookfield Replat A
Stormwater Management Plan 5
The SWMP Administrator for this site is:
Name: (to be filled-in by permittee)
Company: (to be filled-in by permittee)
Phone: (to be filled-in by permittee)
E-mail: (to be filled-in by permittee)
3.2 Best Management Practices (BMP’s) for Stormwater Pollution Prevention
Beginning from mobilization, and throughout the entire construction of the project, erosion control
devices shall be installed to ensure minimal pollutant migration. These erosion control devices may
be installed in phases, or not at all, depending on actual conditions encountered at the site. It is
the responsibility of the Contractor to make the determination as to what practices should be
employed and when. In the event that a review agency deems BMPs to be insufficient, it shall be
the responsibility of the contractor to implement modifications as directed.
Best Management Practices (BMPs) are loosely defined as a method, activity, maintenance
procedure, or other management practice for reducing the amount of pollution entering a water
body. The term originated from rules and regulations in Section 208 of the Clean Water Act.
Details for Structural and Non-Structural BMPs have been included in Appendix B. These details
should be used for additional information on installation and maintenance of BMPs specified in this
report. It is also intended to serve as a resource for additional BMPs that may be appropriate for
the site that have not specifically been mentioned in the report.
3.3 Structural Practices for Erosion and Sediment Control
Structural BMPs are physical devices that are implemented to prevent erosion from happening or to
limit erosion once it occurs. These devices can be temporary or permanent, and installation of
individual components will vary depending on the stage of construction.
A table depicting construction sequence and BMP application/removal has been placed on the
“Dynamic Site Plan” to help document the implementation of these BMPs. Refer to the Stormwater
Management Plan Static Site Plan in the Appendix for the assumed location of all BMPs.
Construction Details for Temporary BMPs are located in the Appendix for reference.
Again, the final determination for which BMP’s will be installed, where they will be located, and
when they will be installed shall be made by the Contractor, along with all documentation
throughout the construction process.
Silt Fencing (Phase I)
Silt fencing shall be provided to prevent migration of sediment off-site or into adjacent properties.
All silt fencing shall be installed prior to any land disturbing activity (demolition, stockpiling,
stripping, grading, etc.). Silt fencing is to be installed prior to site excavation or earthwork
activities.
Inspections of the silt fence should identify tears or holes in the material, and should check for
slumping fence or undercut areas that allow flows to bypass the fencing. Damaged sections of
fencing should be repaired or replaced to ensure proper functioning. Sediment accumulated behind
the silt fence should be removed to maintain BMP effectiveness, typically before it reaches a depth
of 6 inches.
At a minimum, it is suggested that silt fencing shall be located along the northern, western, eastern
Brookfield Replat A
Stormwater Management Plan 6
and southern limits of disturbance with multiple rows to the east approaching Fossil Creek Inlet
Ditch. Silt fencing can installed in conjunction with/adjacent to construction or security fencing.
Sediment Control Logs may also be substituted in lieu of silt fencing, as appropriate. See below for
a description of Sediment Control Logs.
Sediment Control Log – aka “Straw Wattles” (Phase I)
A Sediment Control Log is a linear roll made of natural materials, such as straw, coconut fiber, or
other fibrous material trenched into the ground and held with a wooden stake. Sediment Control
Logs can be used in many instances. Examples include perimeter control for stockpiles, as part of
inlet protection designs, as check dams in small drainage ways, on disturbed slopes to shorten flow
lengths, or in lieu of silt fencing (where appropriate).
Sediment Control Logs should be inspected for excess sediment accumulation. Sediment should be
removed prior to reaching half the height of the log.
At a minimum, Sediment Control Logs should be used around soil stockpiles (including landscape
material), drainage swales, and at all stormwater discharge locations other than inlets. This
includes in swales between buildings after vertical construction but prior to stabilization.
Vehicle Tracking Control Pads (Phase I)
Vehicle tracking control pads shall be provided to minimize tracking of mud and sediment onto
paved surfaces and neighboring roadways. All vehicle tracking control pads shall be installed prior
to any land disturbing activity (demolition – as necessary, stockpiling, stripping, grading, etc.).
Location of vehicle tracking control pads will be located at any and all existing and future vehicle
accesses being used during any of the construction phases. These locations will primarily be
dictated by gates or openings in the temporary construction fencing that is expected to be installed.
Vehicle tracking control pads are to be installed prior to demolition (as appropriate), site excavation
or earthwork activities.
Vehicle tracking pads should be inspected for degradation and aggregate material should be
replaced as needed. If the area becomes clogged with water, excess sediment should be removed.
Aggregate material should remain rough, and at no point should aggregate be allowed to compact in
a manner that causes the tracking pad to stop working as intended.
Suggested locations for a vehicle tracking pad is at the proposed access to the site from Brookfield
and Northern Lights Drives.
Inlet Protection (Phase I & II)
Inlet protection shall be provided for existing inlets to prevent sediment transport from adjacent
earthwork disturbance. Installation of these filters shall occur before adjacent earth disturbing
activities (Phase I implementation). Wattle type filters are to be implemented for new and existing
inlets where asphalt does not exist. For these inlets, if pavement is constructed adjacent to the
structure or if the area adjacent to the inlet is changed such that the wattle type filter is no longer
effective, it shall be the responsibility of the Contractor to ensure that an appropriate method is
used instead. For example, the wattle filter could be reused, or a gravel-block inlet filter may be
installed. It will be left to the discretion of the Contractor as to whether replacement of any inlet
filter is necessary.
Inlet protection should be inspected regularly for tears that can result in sediment entering an inlet.
Inlet protection should also be inspected for sediment accumulation upstream of the inlet, and
sediment should be removed when the less than half of the capacity is available, or per
Brookfield Replat A
Stormwater Management Plan 7
manufacturer specifications.
The Contractor shall provide inlet protection for all proposed inlets as they are installed (Phase II
implementation) and at all existing inlets adjacent the site on Northern Lights Drive, Precision Drive,
and Custer Drive (Phase I). The outlet structure north of the site should also be protected and
inspected to prevent illicit discharges.
Concrete Washout Area (Phase II-III)
A concrete washout should be provided on the site. The washout can be lined or unlined excavated
pits in the ground, commercially manufactured prefabricated containers, or aboveground holding
areas. The concrete washout must be located a minimum of 400 feet from any natural drainage
way or body of water, and at least 1000 feet from any wells or drinking water sources. Washout
areas should not be located in an area where shallow groundwater may be present. Contractor
shall clearly show the desired location and access to the Concrete Washout Area on the Stormwater
Management Plan - Dynamic Site Plan. Contractor shall place a Vehicle Tracking Pad if the
selected location for the Concrete Washout Area is detached from pavement. Clear signage
identifying the concrete washout should also be provided.
The Concrete Washout Area should be inspected regularly. Particular attention should be paid to
signage to ensure that the area is clearly marked. Confirmation that the washout is being used
should also be noted to ensure that other undesignated areas of the site are not being used
incorrectly as a concrete washout.
An appropriate location for the concrete washout area is located interior to the site, away from
discharge points. This location is a suggestion only, and can be relocated at the discretion of the
Contractor.
Permanent/Established Vegetation (Phase IV)
Permanent or established vegetation and landscaping is considered a permanent form of sediment
and erosion control for common open spaces, steep slopes and areas not exposed to prolonged
scour velocities, or acute incipient motion bed shear stresses that will create soil erosion, rill
formation and subsequent sediment transport. Areas where the previous conditions apply will
contain sufficient permanent BMPs, such as riprap or cobble mulch. Permanent vegetation shall
conform to an approved Landscaping Plan.
3.4 Non-Structural Practices for Erosion and Sediment Control
Non-Structural BMPs are practices or activities that are implemented to prevent erosion from
happening or to limit erosion once it occurs. These BMPs can be a practice resulting in physical
change to the site, such as mulching or slope stabilization. They can also result in behavioral
changes on the site, such as changes to construction phasing to minimize exposure to weather
elements, or increased employee awareness gained through training.
Protection of Existing Vegetation (Phases I-IV)
Protection of existing vegetation on a construction site can be accomplished through installation of a
construction fence around the area requiring protection. In cases where up-gradient areas are
disturbed, it may also be necessary to install perimeter controls to minimize sediment loading to
sensitive areas such as wetlands.
Trees that are to remain after construction is complete must be protected. Most tree roots grow
within the top 12”-18” of soil, and soil compaction is a significant threat to tree health. As such,
particular care should be taken to avoid activities within the drip-line of the tree. Direct equipment
damage should also be prevented. The most effective way to ensure the health of trees is to
Brookfield Replat A
Stormwater Management Plan 8
establish a protection zone at the drip-line of the tree to prevent unintended activity in the area
directly surrounding the tree.
Fencing should be inspected and repaired when needed. If damage occurs to a tree, an arborist
should be consulted on how to care for the tree. If a tree is damage beyond repair, the City Forester
should be consulted on remediation measures.
Existing vegetation should be preserved to the east of the north and east of the limit of disturbance.
Stockpile Management (Phases I-IV)
Stockpile management should be utilized to minimize erosion and sediment transport from soil
stockpiles. In general, soil stockpiles should be located a minimum of 100 feet from any drainage
way and 50 feet from any storm sewer inlets. Where practical, choose a stockpile location that will
remain undisturbed for the longest period of time as the phases of construction progress. Sediment
control BMPs should be placed around the perimeter of the stockpile, and a designated access point
on the upstream side of the stockpile should be identified. BMPs such as surface roughening,
temporary seeding, mulching, erosion control blankets, or soil binders should be used to stabilize
the stockpile surface.
As a part of stockpile management, regular inspections of the perimeter controls should be
completed. If BMPs have been utilized to stabilize the surface of the stockpile, they should be
inspected and repaired as needed.
While significant soil stockpiles are not expected with this project, it is possible that foundation
excavation or the delivery landscaping material may generate temporary stockpiles. The location of
any such stockpiles shall be the responsibility of the SWMP Administrator.
Mulching (Phase I-IV)
Mulching helps reduce erosion by protecting bare soil from rainfall impact, increasing infiltration,
and reducing runoff. Although often applied in conjunction with temporary or permanent seeding, it
can also be used for temporary stabilization of areas that cannot be reseeded due to seasonal
constraints. The most common type of mulch used is hay or grass that is crimped into the soil to
keep it secure. However, crimping may not be practical on slopes steeper than three to one
(3H:1V).
The Contractor shall mulch all planted areas within twenty-four (24) hours after planting. Only
weed-free and seed-free straw mulch may be used. Straw mulch should be applied at two (2) tons
per acre, and shall be adequately secured by crimping, tackifier, netting or blankets. Hydraulic
mulching may also be used on steep slopes or where access is limited. In the case that hydraulic
mulching is utilized, the Contractor shall use wood cellulose fibers mixed with water at two
thousands to two thousand five hundred (2,000-2,500) pounds per acre and organic tackifier at
one hundred to four hundred (100-400) pounds per acre.
Wind Erosion/Dust Control (Phase I-IV)
Wind Erosion and Dust Control BMP’s help to keep soil particles from entering the air as a result of
land disturbing construction activities. Examples include use of a water truck or irrigation/sprinkler
system to wet the top layer of disturbed soil, seeding and mulching, soil binders, or wind fences.
If a water truck or irrigation/sprinkler system is utilized, monitoring to ensure that sufficient water is
applied is crucial to ensuring soil particles don’t become airborne. Equally important is monitoring
for overwatering, as too much water can lead to increased erosion.
Street Sweeping (Phases I -IV)
Brookfield Replat A
Stormwater Management Plan 9
Street sweeping should be used to remove sediment that has been tracked onto adjacent roadways.
Roadways should be inspected at least once a day, and sediment should be removed as needed. A
check of the area inlet protection should be completed after sweeping to ensure nothing was
displaced during sweeping operations. Street sweeping can reduce the sediment washed into the
existing storm drain system. Street sweeping may be necessary on the existing hardscape areas
which receive runoff from the disturbed areas.
Saw Cutting Pollution Prevention (Phase I)
The following protocol is recommended to prevent dust and slurry from asphalt and concrete saw
cutting activities from migrating into the existing storm drain system.
Slurry and cuttings shall be vacuumed during cutting and surfacing operations
Slurry and cuttings shall not remain on permanent concrete or asphalt pavement
overnight
Slurry and cuttings shall not drain to any natural or constructed drainage conveyance
Collected slurry and cuttings shall be disposed of in a manner that does not violate
groundwater or surface water standards
Good Housekeeping Practices (All phases)
Good housekeeping practices that will prevent pollution associated with solid, liquid, and hazardous
construction-related materials and wastes should be implemented throughout the project.
Examples of good housekeeping include providing an appropriate location for waste management
containers, establishing proper building material staging areas, designating paint and concrete
washout areas, establishing proper equipment/vehicle fueling and maintenance practices.
Development of a spill prevention and response plan is another example of Good Housekeeping
practices that should be used on the project. The following items are detailed examples of some of
the good housekeeping practices that should be utilized throughout the project. It should be noted
that a complete list of practices and detailed discussion regarding good housekeeping has been
included with Appendix B, sheets GH-1 – GH-6.
Street Sweeping and Vacuuming – Street sweeping and vacuuming should be used to remove
sediment that has been tracked onto adjacent roadways. Roadways should be inspected at least
once a day, and sediment should be removed as needed. A check of inlet protection should be
completed after sweeping to ensure nothing was displaced during sweeping operations.
Waste Management – Designate trash and bulk waste collection areas on-site. When possible,
materials should be recycled. Hazardous material waste should be segregated from other solid
waste. Waste collection areas should be located away from streets, gutters, watercourses, and
storm drains. Dumpsters should be located near site entrances to minimize traffic on disturbed
soils, and they should be placed on a level soil surface.
Establish Proper Building Material Handling and Staging areas – Clearly designate site areas for
staging and storage of building materials. Provide appropriate BMPs to ensure that spills or leaks
are contained.
Establish Proper Equipment/Vehicle Fueling and Maintenance Practices – If needed, create a
clearly designated on-site fueling and maintenance area that is clean and dry. Provide appropriate
BMPs to ensure that spills or leaks are contained.
3.5 Phased BMP Installation
Brookfield Replat A
Stormwater Management Plan 10
It is important to recognize the four (4) major Development Phases as defined by the State of
Colorado’s Stormwater Discharge Permit (SDP). These four development phases (referred to as
Sequencing by the City of Fort Collins) have been distinguished to aid in the appropriate timing of
installation/implementation of BMPs at different stages of the construction process. These phases
are described as follows:
Phase I – Grading Stage; BMPs for initial installation of perimeter controls
Phase II – Infrastructure Stage; BMPs for utility, paving and curb installation
Phase III – Vertical Construction Stage; BMPs for individual building construction.
Phase IV – Permanent BMPs and final site stabilization.
Included in the back map pockets are five Site Plans: a “Static” Site Plan and four “Dynamic” Site
Plans. The “Static” plan serves to display the overall management plan all at once. However,
proper implementation of BMPs does not occur at once, and certain BMPs may move location in
the construction process; therefore, the “Dynamic” Site Plans are intended for the Contractor to
write in the BMP symbols to document the location and time the BMPs are installed and
maintained throughout the entire construction process.
3.6 Material Handling and Spill Prevention
Potential pollution sources, as discussed in earlier sections, are to be to be identified by the
Contractor. Spill prevention procedures are to be determined and put in place prior to construction
by the Contractor. A spill and flooding response procedure must also be determined and put in
place prior to construction by the Contractor. Additionally, steps should be taken to reduce the
potential for leaks and spills to come in contact with stormwater runoff, such as storing and
handling toxic materials in covered areas or by storing chemicals within berms or other secondary
containment devices.
A notification procedure must be put in place by the Contractor, by which workers would first notify
the site construction superintendent, who would then notify the SWMP Administrator. Depending
on the severity of the spill, the site construction superintendent and SWMP Administrator would
possibly notify the Colorado Department of Public Health and Environment - Water Quality Control
Division, downstream water users, or other appropriate agencies. The release of any chemical, oil,
petroleum product, sewage, etc., which enter waters of the State of Colorado (which include
surface water, ground water, and dry gullies or storm sewers leading to surface water) must be
reported immediately to the Division’s emergency spill reporting line at (877) 518-5608. All
spills that will require cleanup, even if the spill is minor and does not need to be reported to the
state, should still be reported to the City of Fort Collins Utilities office at 970-221-6700.
While not expected with this project, it will be the responsibility of the Contractor to designate a
fueling area and take the necessary precautions to ensure that no stormwater pollution occurs in the
event that a fueling area is needed. Fueling areas shall be located a minimum 100 feet from all
drainage courses. A 12-inch high compacted earthen ridge capable of retaining potential spills
shall enclose fueling areas. Other secondary containment devices can be used instead of the
earthen ridge. The area shall be covered with a non-porous lining to prevent soil contamination.
Printed instructions for cleanup procedures shall be posted in the fueling area and appropriate fuel
absorbents shall be available along with containers for used absorbents within the fueling area.
3.7 Dedicated Concrete or Asphalt Batch Plant
There are not any dedicated concrete or asphalt batch plants anticipated with this project. In the
event that a plant is needed, the Contractor should be aware that additional permitting will be
Brookfield Replat A
Stormwater Management Plan 11
required. In particular, an Air Pollutant Emission Notice (APEN) will need to be obtained from the
CDPHE.
Brookfield Replat A
Stormwater Management Plan 12
3.8 Vehicle Tracking Control
In addition to the vehicle tracking pads discussed previously, additional measures can be taken to
minimize and control sediment discharges from the site due to vehicle tracking. These measures
can include fencing around the site to control access points. Regular street sweeping can also be
used to minimize the transmission of sediment from the site due to vehicles leaving the site. The
use of gravel parking areas and wash racks can also be implemented to ensure minimal vehicle
tracking from the site.
3.9 Waste Management and Disposal
It will be the responsibility of the Contractor to designate a concrete truck chute washout area and
to clearly identify that area. Detailed information about the design and maintenance of the Concrete
Washout can be found under the Structural Practices section of this report. At no time should
untreated wash water be allowed to discharge from the site or to enter a storm drain system or
stream. Upon completion of construction activities the concrete washout material shall be removed
and properly disposed of prior to the area being restored.
Any waste material that currently exists on the site or that is generated by construction will be
disposed of in such a manner as to not cause pollutants in stormwater discharges. If waste is to be
stored on-site, it shall be in an area located a minimum of 100 feet from all drainage courses.
Whenever waste is not stored in a non-porous container, it shall be in an area enclosed by a 12-
inch high compacted earthen ridge or some other approved secondary containment device. The area
shall be covered with a non-porous lining to prevent soil contamination. Whenever precipitation is
predicted, the waste shall be covered with a non-porous cover, anchored on all sides to prevent its
removal by wind, in order to prevent precipitation from leaching out potential pollutants from the
waste. On-site waste disposal practices, such as dumpsters, should be covered or otherwise
contained as to prevent dispersion of waste materials from wind. It shall also be the responsibility
of the Contractor to maintain a clean jobsite as to prevent dispersion of waste material and potential
pollutants into adjacent properties or waterways.
The location of, and protective measures for, temporary restroom facilities shall be the responsibility
of the SWMP Administrator.
3.10 Groundwater and Stormwater Dewatering
The BMPs selected for construction dewatering vary depending on the site-specific features, such as
soils, topography, discharge quantities, and discharge location. Typically, dewatering involves
pumping water from an inundated area to a BMP, prior to the water being released downstream
into a receiving waterway, sediment basin, or well-vegetated area. Acceptable BMPs included
discharging water into a sediment trap or basin, using a dewatering filter bag, or using a series of
sediment logs. A settlement tank or an active treatment system can also be utilized. Another
commonly used method to handle the pumped water is the “sprinkler method,” which involves
applying the water to vegetated areas through a perforated discharge hose. Dispersal from a water
truck for dust control can also be used to disperse the pumped water.
4.0 Final Stabilization and Long-Term Stormwater Management
4.1 Final Stabilization
All disturbed areas will be seeded, crimped and mulched or sod in accordance to an approved
Landscaping Plan. As defined by the Colorado Department of Public Health and Environment in
the General Permit Application for Stormwater Discharges, “Final stabilization is reached when all
soil disturbing activities at the site have been completed, and uniform vegetative cover has been
Brookfield Replat A
Stormwater Management Plan 13
established with a density of at least 70 percent of pre-disturbance levels or equivalent permanent,
physical erosion reduction methods have been employed.”
4.2 Long-Term Stormwater Management
The method of long-term stormwater management will take place within the paver section before
being discharged into the Dixon Canyon Lateral. All disturbed areas will receive permanent paving
or will be vegetated per and approved Landscaping Plan.
5.0 Inspection, Maintenance and Record Keeping
5.1 BMP Inspection
All temporary erosion control facilities shall be inspected at a minimum of once every two (2) weeks
and after each significant storm event or snowmelt. Repairs or reconstruction of BMPs, as
necessary, shall occur as soon as possible in order to ensure the continued performance of their
intended function. It is the responsibility of the SWMP Administrator to conduct bi-weekly
inspections, maintain BMPs if needed, to keep records of site conditions and inspections, and to
update the SWMP as necessary.
The construction site perimeter, disturbed areas, all applicable/installed erosion and sediment
control measures, and areas used for material storage that are exposed to precipitation shall be
inspected for evidence of, or the potential for, pollutants entering the drainage system. Erosion and
sediment control measures identified in the SWMP shall be observed to ensure that they are
operating correctly. Particular attention should be paid to areas that have a significant potential for
stormwater pollution, such as demolition areas, concrete washout locations, and vehicle entries to
the site. The inspection must be documented to ensure compliance with the permit requirements.
5.2 BMP Maintenance
Any BMP’s not operating in accordance with the SWMP must be addressed as soon as possible,
immediately in most cases, to prevent the discharge of pollutants. If modifications are necessary,
such modifications shall be documented so that the SWMP accurately reflects on-site conditions.
The SWMP needs to accurately represent field conditions at all times.
Uncontrolled releases of mud, muddy water, or measurable amounts of sediment found off-site will
be recorded with a brief explanation of the measures taken to clean-up the sediment that has left
the site, as well as the measures taken to prevent future releases. This record shall be made
available to the appropriate public agencies (Colorado Department of Public Health and
Environment, Water Quality Control Division; Environmental Protection Agency; City of Fort Collins;
etc.) upon request.
Preventative maintenance of all temporary and permanent erosion control BMPs shall be provided
in order to ensure the continued performance of their intended function. Temporary erosion control
measures are to be removed after the site has been sufficiently stabilized as determined by the City
of Fort Collins. Maintenance activities and actions to correct problems shall be noted and recorded
during inspections.
Inspection and maintenance procedures specific to each BMP identified with this SWMP are
discussed in Section 3. Details have also been included with Appendix B.
5.3 Record Keeping
Documentation of site inspections must be maintained. The following items are to be recorded and
kept with the SWMP:
Brookfield Replat A
Stormwater Management Plan 14
Date of Inspection
Name(s) and title(s) of personnel making the inspection
Location(s) of sediment discharges or other pollutants from the site
Location(s) of BMP’s that need to be maintained
Location(s) of BMP’s that failed to operate as designed or proved inadequate
Locations(s) where additional BMP’s are needed that were not in place at the time of inspection
Deviations from the minimum inspection schedule
Descriptions of corrective action taken to remedy deficiencies that have been identified
The report shall contain a signed statement indicating the site is in compliance with the permit to the
best of the signer’s knowledge and belief after corrective actions have been taken.
Provided within Appendix E of this SWMP is an Example Inspection Log to aid in the record keeping
of BMP inspections and maintenance. Photographs, field notebooks, drawings and maps should be
included by the SWMP Administrator when appropriate.
In addition to the Inspection Log, records should be kept documenting:
BMP maintenance and operation
Stormwater contamination
Contacts with suppliers
Notes on the need for and performance of preventive maintenance and other repairs
Implementation of specific items in the SWMP
Training events (given or attended)
Events involving materials handling and storage
Contacts with regulatory agencies and personnel
Notes of employee activities, contact, notifications, etc.
Records of spills, leaks, or overflows that result in the discharge of pollutants must be documented
and maintained. A record of other spills that are responded to, even if they do not result in a
discharge of pollutants, should be made. Information that should be recorded for all occurrences
includes the time and date, weather conditions, reasons for the spill, etc. Some spills may need to
be reported to authorities immediately. Specifically, a release of any chemical, oil, petroleum
product, sewage, etc., which may enter waters of the State of Colorado (which include surface
water, ground water and dry gullies or storm sewers leading to surface water) must be reported to
the CDPHE.
Additionally, the “Dynamic Site Plan” is intended to be a “living” document where the SWMP
Administrator can hand write the location of BMPs as they are installed to appropriately reflect the
current site conditions. Also on the “Dynamic Site Plan” is a “Table of Construction Sequence and
BMP Application/Removal” that the SWMP Administrator can use to document when BMPs were
installed or removed in conjunction with construction activities. These items have been included as
an aid to the SWMP Administrator, and other methods of record keeping are at his or her discretion.
This Stormwater Management Plan (both the text and map) is not a static document. It
is a dynamic device intended to be kept current and logged as construction takes place.
It shall be the responsibility of the SWMP Administrator and/or the permit holder (or
applicant thereof) to ensure the plan is properly maintained and followed. Diligent
administration is critical, including processing the Notice to Proceed and noting on the
Stormwater Management Plan the dates that various construction activities occur and
respective BMPs are installed and/or removed.
Brookfield Replat A
Stormwater Management Plan 15
6.0 Additional SWMP and BMP Resources
Urban Drainage and Flood Control District
Urban Storm Drainage Criteria Manual - Volume 3 “Best Management Practices”
Website: http://www.udfcd.org/downloads/down_critmanual_volIII.htm
Colorado Department of Transportation
Erosion Control and Stormwater Quality Guide
BMP Field Academy
Website: http://www.coloradodot.info/programs/environmental/water-quality/documents/erosion-storm-quality
EPA Menu of BMP’s
Construction Site Storm Water Runoff Control
Website: http://water.epa.gov/polwaste/npdes/swbmp/Construction-Site-Stormwater-Run-Off-Control.cfm
International Stormwater Best Management (BMP) Database
Rocky Mountain Education Center
Website: http://www.bmpdatabase.org/
Rocky Mountain Education Center
Red Rocks Community College, Lakewood
Website: http://www.rmecosha.com/
Keep It Clean Partnership
Boulder
Website: http://www.keepitcleanpartnership.org/
Brookfield Replat A
Stormwater Management Plan 16
References
1. Drainage Letter Report for Brookfield Replat, Northern Engineering Services, July 14,
2015 (NE Project No. 374-020)
2. Soil Resource Report for Larimer County Area, Colorado, Natural Resources
Conservation Service, United States Department of Agriculture.
3. Urban Storm Drainage Criteria Manual, Volumes 1-3, Urban Drainage and Flood Control
District, Water Resources Publications, LLC., Denver, Colorado, Updated November
2010.
APPENDIX A
SITE MAPS
UD
UD
UD UD
UD UD
UD UD
20' DRAINAGE EASEMENT
�
�
W
COVERED
ENTRY
ENTRY
COVERED
DECK
COVERED
ENTRY
COVERED
ENTRY
COVERED
ENTRY
DECK
DECK DECK
DECK
BLDG 9
BLDG 8
BLDG 11
BLDG 12 BLDG 13
BLDG 37
BLDG 36
BLDG 35
LOT 1
LOT 2
LOT 3
LOT 4
LOT 5
LOT 6
LOT 7
LOT 8
LOT 9
LOT 10
LOT 11
LOT 12
COVERED
ENTRY
ENTRY
COVERED
DECK
COVERED
ENTRY
COVERED
ENTRY COVERED
ENTRY
DECK
DECK DECK
DECK
COVERED
ENTRY
ENTRY
COVERED
DECK
APPENDIX B
EROSION CONTROL DETAILS
No. Revisions: By: Date:
REVIEWED BY:
R. Banning
DESIGNED BY:
DRAWN BY:
SCALE:
DATE:
July 13, 2015
PROJECT:
374-020
Sheet
Of 33
BROOKFIELD REPLAT A
T���� �������� ���
����������� �� �������
�������� �� N�������
E���������� S�������, I��.
��� ��� ��� �� �� ���� ���
��� ���� �� ������������
������ ������ ��� ������ ��
� P����������� E������� ��
��� ������ �� N�������
E���������� S�������, I��.
NOT FOR CONSTRUCTION
REVIEW SET
07/13/15
E N G I N E E R I N G
� � � � � � ��
301 N���� H���� S�����, S���� 100
F��� C������, C������� 80521
PHONE: 970.221.4158
���.�������������������.���
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE, OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
K��� ����'� �����.
C��� ������ ��� ���.
R
EC2
EROSION CONTROL DETAILS
N.A.
B. Ruch
NTS
NOT TO SCALE
000
EC2
SWALE WATTLE DIKE
1"x 1" WOOD STAKES
18"-24"
BAILING WIRE OR
NYLON ROPE
WATTLE "A" WATTLE "B"
1' 1' 2'
TYP.
1' 1'
WATTLES - DETAIL B
W2 NOTES:
INSTALLATION:
STAKES SHOULD BE DRIVEN ACROSS FROM EACH OTHER
AND ON EACH SIDE OF THE WATTLE. LEAVING 4"-6" OF
No. Revisions: By: Date:
REVIEWED BY:
R. Banning
DESIGNED BY:
DRAWN BY:
SCALE:
DATE:
July 13, 2015
PROJECT:
374-020
Sheet
Of 33
BROOKFIELD REPLAT A
T���� �������� ���
����������� �� �������
�������� �� N�������
E���������� S�������, I��.
��� ��� ��� �� �� ���� ���
��� ���� �� ������������
������ ������ ��� ������ ��
� P����������� E������� ��
��� ������ �� N�������
E���������� S�������, I��.
NOT FOR CONSTRUCTION
REVIEW SET
07/13/15
E N G I N E E R I N G
� � � � � � ��
301 N���� H���� S�����, S���� 100
F��� C������, C������� 80521
PHONE: 970.221.4158
���.�������������������.���
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE, OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
K��� ����'� �����.
C��� ������ ��� ���.
R
EC3
EROSION CONTROL DETAILS
N.A.
B. Ruch
NTS
INLET PROTECTION - AREA INLET IN SUMP
Urban Drainage and Figure C5-21
Flood Control District
Drainage Criteria Manual (V.3)
AREA INLET - PLAN
SECTION A ROCK FILTER JOINT DETAIL
INLET PROTECTION CONTINUED
1-1/2" CRUSHED
ROCK ENCLOSED
IN WIRE MESH
FILTERED
RUNOFF
AREA INLET
10' MIN.
2" IN SOIL
0" ON PAVEMENT
12" 12"
APPENDIX C
LANDSCAPE PLAN
APPENDIX D
COPIES OF PERMITS/APPLICATIONS
For Agency Use Only
Permit Number Assigned
COR03-
Date Received /_ /_
Month Day Year
COLORADO DISCHARGE PERMIT SYSTEM (CDPS)
STORMWATER DISCHARGE ASSOCIATED WITH CONSTRUCTION ACTIVITIES APPLICATION
PHOTO COPIES, FAXED COPIES, PDF COPIES OR EMAILS WILL NOT BE ACCEPTED.
Please print or type. Original signatures are required. All items must be completed accurately and in their entirety for
the application to be deemed complete. Incomplete applications will not be processed until all information is received
which will ultimately delay the issuance of a permit. If more space is required to answer any question, please attach
additional sheets to the application form. Applications must be submitted by mail or hand delivered to:
Colorado Department of Public Health and Environment
Water Quality Control Division
4300 Cherry Creek Drive South
WQCD-P-B2
Denver, Colorado 80246-1530
Any additional information that you would like the Division to consider in developing the permit should be provided with
the application. Examples include effluent data and/or modeling and planned pollutant removal strategies.
PERMIT INFORMATION
Reason for Application: NEW CERT
RENEW CERT EXISTING CERT #
Applicant is: Property Owner Contractor/Operator
A. CONTACT INFORMATION - NOT ALL CONTACT TYPES MAY APPLY * indicates required
*PERMITTEE (If more than one please add additional pages)
*ORGANIZATION FORMAL NAME:
1) *PERMITTEE the person authorized to sign and certify the permit application. This person receives all
permit correspondences and is legally responsible for compliance with the permit.
Responsible Position (Title):
Currently Held By (Person):
Telephone No:_
email address
Organization:
Mailing Address:
City:_ State: Zip:
This form must be signed by the Permittee (listed in item 1) to be considered complete.
Per Regulation 61 In all cases, it shall be signed as follows:
a) In the case of corporations, by a responsible corporate officer. For the purposes of this section, the responsible
corporate officer is responsible for the overall operation of the facility from which the discharge described in the
application originates.
b) In the case of a partnership, by a general partner.
c) In the case of a sole proprietorship, by the proprietor.
d) In the case of a municipal, state, or other public facility, by either a principal executive officer or ranking elected official
page 1 of 5 revised April 2011
2) DMR COGNIZANT OFFICIAL (i.e. authorized agent) the person or position authorized to sign and certify reports required
by the Division including Discharge Monitoring Reports *DMR’s, Annual Reports, Compliance Schedule submittals,
and other information requested by the Division. The Division will transmit pre-printed reports (ie. DMR’s) to this person.
If more than one, please add additional pages. Same As 1) Permittee
Responsible Position (Title):
Currently Held By (Person):
Telephone No:_
email address
Organization:
Mailing Address:
City:_ State: Zip:
Per Regulation 61 : All reports required by permits, and other information requested by the Division shall be signed by
the permittee or by a duly authorized representative of that person. A person is a duly authorized representative only if:
(i) The authorization is made in writing by the permittee
(ii) The authorization specifies either an individual or a position having responsibility for the overall operation of the
regulated facility or activity such as the position of plant manager, operator of a well or a well field, superintendent,
position of equivalent responsibility, or an individual or position having overall responsibility for environmental matters
for the company. (A duly authorized representative may thus be either a named individual or any individual occupying a
named position); and
(iii) The written authorization is submitted to the Division
3) *SITE CONTACT local contact for questions relating to the facility & discharge authorized by this permit
for the facility.
Same As 1) Permittee
Responsible Position (Title):
Currently Held By (Person):
Telephone No:_
email address
Organization:
Mailing Address:
City:_ State: Zip:
4) * BILLING CONTACT if different than the permittee
Responsible Position (Title):
Currently Held By (Person):
Telephone No:_
email address
Organization:
Mailing Address:
City:_ State: Zip:
Page 2 of 5 revised April 2011
5) OTHER CONTACT TYPES (check below) Add pages if necessary:
ResponsiblePosition (Title):
Currently Held By (Person):
Telephone No:_
email address
Organization:
Mailing Address:
City:_ State: Zip:
o Pretreatment
Coordinator
o Environmental Contact
o Biosolids Responsible
Party
o Property Owner
Inspection Facility Contact
Consultant
Compliance Contact
Stormwater MS4 Responsible
Person
Stormwater Authorized
Representative
Other
B. Permitted Project/Facility Information
Project/Facility Name
Street Address or cross streets
(e.g., “S. of Park St. between 5th Ave. and 10th Ave.”, or “W. side of C.R. 21, 3.25 miles N. of Hwy 10”; A street name without an address,
intersection, mile marker, or other identifying information describing the location of the project is not adequate. For linear projects,
the route of the project should be described as best as possible with the location more accurately indicated by a map.)
City, Zip Code County
Facility Latitude/Longitude— (approximate center of site to nearest 15 seconds using one of
following formats
001A Latitude . Longitude . (e.g., 39.703°, 104.933°’)
degrees (to 3 decimal places) degrees (to 3 decimal places)
or
001A Latitude º ’ " Longitude º ’ " (e.g., 39°46'11"N, 104°53'11"W)
degrees minutes seconds degrees minutes seconds
For the approximate center point of the property, to the nearest 15 seconds. The latitude and longitude must be provided as
either degrees, minutes, and seconds, or in decimal degrees with three decimal places. This information may be obtained from
a variety of sources, including:
o Surveyors or engineers for the project should have, or be able to calculate, this information.
o EPA maintains a web-based siting tool as part of their Toxic Release Inventory program that uses interactive maps and
aerial photography to help users get latitude and longitude. The siting tool can be accessed at
www.epa.gov/tri/report/siting_tool/index.htm
o U.S. Geological Survey topographical map(s), available at area map stores.
o Using a Global Positioning System (GPS) unit to obtain a direct reading.
Note: the latitude/longitude required above is not the directional degrees, minutes, and seconds provided on a site legal
description to define property boundaries.
C. MAP (Attachment) If no map is submitted, the permit will not be issued.
Map: Attach a map that indicates the site location and that CLEARLY shows the boundaries of the area that will be
disturbed. Maps must be no larger than 11x17 inches.
D. LEGAL DESCRIPTION
Legal description: If subdivided, provide the legal description below, or indicate that it is not applicable (do not supply
Township/Range/Section or metes and bounds description of site)
Subdivision(s): Lot(s): Block(s):
OR
Not applicable (site has not been subdivided)
page 3 of 5 revised April 2011
E. AREA OF CONSTRUCTION SITE
Total area of project site (acres): Area of project site to undergo disturbance (acres):
Note: aside from clearing, grading and excavation activities, disturbed areas also include areas receiving
overburden (e.g., stockpiles), demolition areas, and areas with heavy equipment/vehicle traffic and storage
that disturb existing vegetative cover
Total disturbed area of Larger Common Plan of Development or Sale, if applicable:
(i.e., total, including all phases, filings, lots, and infrastructure not covered by this application)
Provide both the total area of the construction site, and the area that will undergo disturbance, in acres. Note: aside
from clearing, grading and excavation activities, disturbed areas also include areas receiving overburden (e.g.,
stockpiles), demolition areas, and areas with heavy equipment/vehicle traffic and storage that disturb existing
vegetative cover (see construction activity description under the APPLICABILITY section on page 1).
If the project is part of a larger common plan of development or sale (see the definition under the APPLICABILITY
section on page 1), the disturbed area of the total plan must also be included.
F. NATURE OF CONSTRUCTION ACTIVITY
Check the appropriate box(s) or provide a brief description that indicates the general nature of the construction activities.
(The full description of activities must be included in the Stormwater Management Plan.)
Single Family Residential Development
Multi-Family Residential Development
Commercial Development
Oil and Gas Production and/or Exploration (including pad sites and associated infrastructure)
Highway/Road Development (not including roadways associated with commercial or residential development)
Other – Description:
G. ANTICIPATED CONSTRUCTION SCHEDULE
Construction Start Date: ___________________________ Final Stabilization Date: _____________________________
Construction Start Date - This is the day you expect to begin ground disturbing activities, including grubbing, stockpiling, excavating,
demolition, and grading activities.
Final Stabilization Date - in terms of permit coverage, this is when the site is finally stabilized. This means that all ground surface
disturbing activities at the site have been completed, and all disturbed areas have been either built on, paved, or a uniform vegetative
cover has been established with an individual plant density of at least 70 percent of pre-disturbance levels. Permit coverage must be
maintained until the site is finally stabilized. Even if you are only doing one part of the project, the estimated final stabilization
date must be for the overall project. If permit coverage is still required once your part is completed, the permit certification may be
transferred or reassigned to a new responsible entity(s).
H. RECEIVING WATERS (If discharge is to a ditch or storm sewer, include the name of the ultimate receiving waters)
Immediate Receiving Water(s):
Ultimate Receiving Water(s):
Identify the receiving water of the stormwater from your site. Receiving waters are any waters of the State of Colorado. This includes
all water courses, even if they are usually dry. If stormwater from the construction site enters a ditch or storm sewer system, identify
that system and indicate the ultimate receiving water for the ditch or storm sewer. Note: a stormwater discharge permit does not
allow a discharge into a ditch or storm sewer system without the approval of the owner/operator of that system.
page 4 of 5 revised April 2011
I. REQUIRED SIGNATURES (Both parts i. and ii. must be signed)
Signature of Applicant: The applicant must be either the owner and/or operator of the construction site. Refer to Part B of the instructions for additional information.
The application must be signed by the applicant to be considered complete. In all cases, it shall be signed as follows: (Regulation 61.4 (1ei)
a) In the case of corporations, by the responsible corporate officer is responsible for the overall operation of the facility from which the discharge
described in the form originates
b) In the case of a partnership, by a general partner.
c) In the case of a sole proprietorship, by the proprietor.
d) In the case of a municipal, state, or other public facility, by either a principal executive officer, ranking elected official, (a principal executive officer
has responsibility for the overall operation of the facility from which the discharge originates).
STOP!: A Stormwater Management Plan must be completed prior to signing the following certifications!
i. STORMWATER MANAGEMENT PLAN CERTIFICATION
“I certify under penalty of law that a complete Stormwater Management Plan, has been prepared for my activity. Based on my inquiry of the person or
persons who manage the system, or those persons directly responsible for gathering the information, the Stormwater Management Plan is, to the best of
my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for falsely certifying the completion of said SWMP,
including the possibility of fine and imprisonment for knowing violations.”
XX
Signature of Legally Responsible Person or Authorized Agent (submission must include original signature) Date Signed
Name (printed) Title
ii. SIGNATURE OF PERMIT LEGAL CONTACT
"I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system
designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons
who manage the system, or those persons directly responsible for gathering the information, the information submitted is to the best of my
knowledge and belief, true, accurate and complete. I am aware that there are significant penalties for submitting false information, including the
possibility of fine and imprisonment for knowing violations."
“I understand that submittal of this application is for coverage under the State of Colorado General Permit for Stormwater Discharges Associated with
Construction Activity for the entirety of the construction site/project described and applied for, until such time as the application is amended or the
certification is transferred, inactivated, or expired.”
XX
Signature of Legally Responsible Person (submission must include original signature) Date Signed
Name (printed Title
DO NOT INCLUDE A COPY OF THE STORMWATER MANAGEMENT PLAN
DO NOT INCLUDE PAYMENT – AN INVOICE WILL BE SENT AFTER THE CERTIFICATION IS ISSUED.
page 5 of 5 revised April 2011
COLORADO DISCHARGE PERMIT SYSTEM (CDPS)
For Agency Use Only
Permit Number Assigned
COG07-______________
Date Received ____/____/____
Month Day Year
CONSTRUCTION DEWATERING INDUSTRIAL WASTEWATER DISCHARGE APPLICATION
PHOTO COPIES, FAXED COPIES, PDF COPIES OR EMAILS WILL NOT BE ACCEPTED.
Please print or type. Original signatures are required. All items must be completed accurately and in their entirety
for the application to be deemed complete. Incomplete applications will not be processed until all information is received
which will ultimately delay the issuance of a permit. If more space is required to answer any question, please attach
additional sheets to the application form. Applications must be submitted by mail or hand delivered to:
Colorado Department of Public Health and Environment
Water Quality Control Division
4300 Cherry Creek Drive South
WQCD-P-B2
Denver, Colorado 80246-1530
Any additional information that you would like the Division to consider in developing the permit should be provided with
the application. Examples include effluent data and/or modeling and planned pollutant removal strategies.
PERMIT INFORMATION
Reason for Application: NEW CERT
RENEW CERT EXISTING CERT #____________________
Applicant is: Property Owner Contractor/Operator
A. Contact Information
Permittee (If more than one please add additional pages)
Organization Formal Name: ___________________________________________________________
1. Permittee the person authorized to sign and certify the permit application. This person receives all permit
correspondences and is legally responsible for compliance with the permit.
Responsible Position (Title): ______________________________________________________________
Currently Held By (Person): _______________________________________________________________
Telephone No:__________________________________________________________________________
email address__________________________________________________________________________
Organization: ___________________________________________________________________________
Mailing Address: ________________________________________________________________________
City:_______________________________ State: ______________________ Zip: ____________________
This form must be signed by the Permittee to be considered complete.
Per Regulation 61: In all cases the permit application shall be signed as follows:
a) In the case of corporations, by a responsible corporate officer. For the purposes of this section, the
responsible corporate officer is responsible for the overall operation of the facility from which the discharge
described in the application originates.
b) In the case of a partnership, by a general partner.
c) In the case of a sole proprietorship, by the proprietor.
d) In the case of a municipal, state, or other public facility, by either a principal executive officer or ranking
elected official
Page 1 of 6 Revised April 2011
Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com
2. DMR Cognizant Official (i.e. authorized agent)—the person or position authorized to sign and certify reports
required by permits including Discharge Monitoring Reports [DMR’s], Annual Reports, Compliance Schedule
submittals, and other information requested by the Division. The Division will send pre-printed reports (e.g. DMR’s) to
this person. If more than one, please add additional pages. Same as 1) Permittee
Responsible Position (Title): _______________________________________________________
Currently Held By (Person): ________________________________________________________
Telephone No:___________________________________________________________________
Email address____________________________________________________________________
Organization: ____________________________________________________________________
Mailing Address: _________________________________________________________________
City:______________________________ State: ______________ Zip: ______________________
Per Regulation 61: All reports required by permits, and other information requested by the Division shall be
signed by the permittee or by a duly authorized representative of that person. A person is a duly authorized
representative only if:
(i) The authorization is made in writing by the permittee;
(ii) The authorization specifies either an individual or a position having responsibility for the overall operation of
the regulated facility or activity such as the position of plant manager, operator of a well or a well field,
superintendent, position of equivalent responsibility, or an individual or position having overall responsibility for
environmental matters for the company. (A duly authorized representative may thus be either a named
individual or any individual occupying a named position); and
(iii) The written authorization is submitted to the Division.
3. Site/Local Contact—contact for questions regarding the facility & discharges authorized by this permit
Same as Permittee—Item 1
Responsible Position (Title): ________________________________________________________
Currently Held By (Person): _________________________________________________________
Telephone No:____________________________________________________________________
Email address_____________________________________________________________________
Organization: _____________________________________________________________________
Mailing Address: __________________________________________________________________
City:______________________________ State: ______________ Zip: _______________________
4. Operator in Responsible Charge Same as Permittee—Item 1
Responsible Position (Title): __________________________________________________________
Currently Held By (Person): ___________________________________________________________
Telephone No:______________________________________________________________________
Email address______________________________________________________________________
Organization: _______________________________________________________________________
Mailing Address: ____________________________________________________________________
City:_______________________________ State: ______________ Zip: ________________________
Certification Type____________________Certification Number________________________________
Page 2 of 6 Revised April 2011
Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com
5. Billing Contact (if different than the permittee)
Responsible Position (Title): _____________________________________________________________
Currently Held By (Person): ______________________________________________________________
Telephone No:_________________________________________________________________________
Email address_________________________________________________________________________
Organization: __________________________________________________________________________
Mailing Address: _______________________________________________________________________
City:______________________________ State: ______________ Zip: ____________________________
6. Other Contact Types (check below) Add pages if necessary:
Responsible Position (Title): ______________________________________________________________
Currently Held By (Person): _______________________________________________________________
Telephone No:__________________________________________________________________________
Email address__________________________________________________________________________
Organization: ___________________________________________________________________________
Mailing Address: ________________________________________________________________________
City:______________________________________ State: ______________ Zip: _____________________
Pretreatment Coordinator
Environmental Contact
Biosolids Responsible Party
Property Owner
Inspection Facility Contact
Consultant
Compliance Contact
Stormwater MS4 Responsible
Person
Stormwater Authorized
Representative
Other ____________________
B. Permitted Project/Facility Information
1. Project/Facility Name ____________________________________________________________________________
Street Address or cross streets_____________________________________________________________________
City, State and Zip Code _____________________________________________County _____________________
Type of Facility Ownership
City Government Corporation Private Municipal or Water District
State Government Mixed Ownership _________________________________
2. Facility Latitude/Longitude—List the latitude and longitude of the excavation(s) resulting in the discharge(s). If the exact excavation
location(s) are not known, list the latitude and longitude of the center point of the construction project. If using the center point, be
sure to specify that it is the center point of construction activity.
001A Latitude __________ . _________ Longitude ___________ . _____________ (e.g., 39.703°, 104.933°’)
degrees (to 3 decimal places) degrees (to 3 decimal places)
or
001A Latitude _____ º _____’ _____" Longitude _____ º _____’ _____" (e.g., 39°46'11"N, 104°53'11"W)
degrees minutes seconds degrees minutes seconds
Horizontal Collection Method: GPS Unspecified Interpolation Map – Map Scale Number__________
Reference Point: Project/Facility Entrance Project/Facility Center/Centroid
Horizontal Accuracy Measure (WQCD Requires use of NAD83 Datum for all references)___________________
(add additional pages if necessary)
Page 3 of 6 Revised April 2011
Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com
B. Permitted Project/Facility Information Continued…
3. Facility Activity and Anticipated Schedule
Dewatering will begin (date) _______________
Estimate how long dewatering will last: Years____________Months_______________Days_________________
Describe Activity e.g., highway bridge and tunnel construction, storm drain expansion, etc. and a description of activities
being performed, including construction schedule and months of operation. Specify source(s) of wastewater to be discharged
(i.e.well, foundation excavation, trenching, etc).
4. Will the discharge go to a ditch or storm sewer? YES NO
If YES, in the appropriate table below include the name of the ultimate receiving waters where the ditch or storm sewer
discharges.
If YES, applicant must contact the owner of the ditch or storm sewer system (prior to discharging) to verify local ordinances
and to determine whether or not additional requirements are going to be imposed by the owner.
5. What type of discharge will this be? Defined Discharge Undefined Discharge
A Defined Discharge is a discharge where the dewatering discharge locations and number of outfalls are known at the time of permit
application.
If discharge is Defined – enter information in table C for Defined Discharges
An Undefined Discharge is a discharge where the exact dewatering discharge locations are unknown at the time of permit application.
The permit applicant must request the maximum number of potential outfalls (discharges) for the permitted facility.
If discharge is Undefined – enter information in table D for Undefined Discharges
Note: For undefined discharges, the site specific sampling and monitoring parameters will be selected based on the potential
pollutant sources found within the entire permitted project area and will be applied to all outfall(s). The most stringent of the
surface water limitations for each identified site specific parameter will be applied to each permitted outfall.
C. Information for Defined Discharge Location(s):
1. In the following table, include the following information for the discharge:
Include the number of discharge points (outfalls);
Include the name of the receiving stream for each Outfall Number. If the discharge is to groundwater fill out discharge
information located next to G001A, G002A, etc.—Please review the Division’s Low Risk Discharge Guidance for
Discharges of Uncontaminated Groundwater to Land to determine if discharges to groundwater can be allowed under
the Guidance in lieu of obtaining a Construction Dewatering Permit.;
Include the approximate location of the discharge (e.g. ―discharge will occur between 5th Avenue and 20th Avenue‖, or ―the
discharge will enter the storm sewer located at the corner of Speer Blvd and 8th Ave., which eventually flows to Cherry Creek‖ ;
Include the maximum anticipated flow rate of the discharge; this can be based on pump capacity or other applicable measure.
OUTFALL
NUMBER
RECEIVING
STREAM(S)
APPROXIMATE LOCATION OF
DISCHARGE
MAXIMUM
FLOW RATE
LATITUDE/LONGITUDE
OF EACH DISCHARGE
OUTFALL
001A
002A
OUTFALL
NUMBER
GROUNDWATER APPROXIMATE LOCATION OF
DISCHARGE
MAXIMUM
FLOW RATE
LATITUDE/LONGITUDE
OF EACH DISCHARGE
OUTFALL
G001A
G002A
Add more pages if necessary
Page 4 of 6 Revised April 2011
Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com
D. Information for Undefined Discharge Location(s):
1. In the following table include the following information for the discharge:
Include the maximum number of potential outfalls (discharges) for the permitted facility/project;
Include the maximum anticipated flow rate of the discharge; this can be based on pump capacity or other applicable measure;
Include the name of all potential receiving streams for the entire project. If the discharge is to groundwater fill out discharge
information located next to G001A, G002A, etc.—Please review the Division’s Low Risk Discharge Guidance for
Discharges of Uncontaminated Groundwater to Land to determine if discharges to groundwater can be allowed under
the Guidance in lieu of obtaining a Construction Dewatering Permit.
Note: For undefined discharges, the site specific sampling and monitoring parameters will be selected based on the potential
pollutant sources found within the entire permitted project area and will be applied to all outfall(s). The most stringent of the surface
water limitations for each identified site specific parameter will be applied to each permitted outfall.
OUTFALL
NUMBER
MAXIMUM FLOW
RATE (GPM) POTENTIAL RECEIVING STREAM(S)
001A
002A
OUTFALL
NUMBER
MAXIMUM FLOW
RATE (GPM)
GROUNDWATER
G001A
GROUNDWATER
G002A
Add more pages if necessary
Sampling and Reporting Requirements for Defined and Undefined Discharges: Sampling must occur at every end-of-
pipe dewatering location (after going through your choice of BMP, if necessary). The permittee will be issued Discharge
Monitoring Report (DMR) forms for all requested outfall numbers. The permittee will be required to submit the DMR forms
for each requested outfall number monthly. For the outfall numbers(s) where no discharge occurred for a given month, the
permittee shall mark ―No Discharge‖ on the DMR forms. The sampling results must be maintained by the permittee.
E. A Location Map for Defined and Undefined Discharges—designating the location of the project/facility, the location of the
discharge point(s)/outfalls—applicable only to defined discharges, and the receiving water(s) listed in Items C & D. A north
arrow shall be shown. This map must be on paper that can be folded to 8 ½ x 11 inches.
F. A Legible Sketch of the Site
1. For Defined Discharges—A legible site sketch shall be submitted and must include: the location of the end of pipe
dewatering discharges at the site (e.g. where the flow will be discharged from the pump or BMP), the BMP(s) that will be
used to treat the discharge(s), and the sampling location(s). Refer to the instructions for additional guidance specific to
sites with multiple potential dewatering locations. This map must be on paper that can be folded to 8 ½ x 11 inches.
OR
2. For Undefined Discharges—A legible site sketch shall be submitted and must include: the limits of the construction site
boundary to include street names (if applicable) or landmarks; description of the BMPs to be implemented; and location of
all potential receiving waters. This map must be on paper that can be folded to 8 ½ x 11 inches.
G. Potential Groundwater Contamination
1. Is this operation located within one mile of a landfill, abandoned landfill or any mine or mill tailings? YES NO
2. Has the dewatering discharge been analyzed for any parameters (pH, Oil and Grease, Metals, Organics, etc.)?
YES NO If YES, please attach a copy of the sampling results.
Page 5 of 6 Revised April 2011
Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com
Note to the applicant: Upon review of the application, the Division may request characterization of the water to be
discharged or analysis of certain parameters once the application has been reviewed. If the Division requests a
representative analysis of the water to be discharged, the application processing time may be lengthened.
3. Has the dewatering area been checked for possible groundwater contamination, such as plumes from leaking
underground storage tanks, mine tailings,etc –or- has a Phase I or Phase II been conducted on the site?
YES NO
If YES, show location of the landfill, tailings, or possible groundwater contamination on the location map or general sketch
map. (Explain the location, extent of contamination, and possible effect on the groundwater pumping from this facility). Or
include a copy of the phase I or Phase II report. If the reports are not available, submit a summary of the results of the
report. If any sampling results are available, please attach a copy of all data.
Note: Contact Water Quality Control Division for the proper water chemistry parameters to report.
H. Additional Information
1. Does the applicant have a Stormwater Permit for Construction Activities? YES NO PENDING
If Yes, Stormwater Construction Permit Number _________________________________
WATER RIGHTS
The State Engineers Office (SEO) has indicated that any discharge that does not return water directly to surface
waters (i.e.land application, rapid infiltration basins, etc.) has the potential for material injury to a water right. As a
result, the SEO needs to determine that material injury to a water right will not occur from such activities. To make
this judgment, the SEO requests that a copy of all documentation demonstrating that the requirements of Colorado
water law have been met, be submitted to their office for review. The submittal should be made as soon as possible
to the following address:
Colorado Division of Water Resources
1313 Sherman Street, Room 818
Denver, Colorado 80203
Should there be any questions on the issue of water rights, the SEO can be contacted at (303) 866-3581. It is
important to understand that any CDPS permit issued by the Division does not constitute a water right. The issuance
of a CDPS permit does not negate the need to also have the necessary water rights in place. Additionally, if the
activity has an existing CDPS permit, there is no guarantee that the proper water rights are in place.
I. Required Certification Signature [Reg 61.4(1)(h)]
"I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in
accordance with a system designed to assure that qualified personnel properly gather and evaluate the information
submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for
gathering the information, the information submitted is to the best of my knowledge and belief, true, accurate and
complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine
and imprisonment for knowing violations."
―I understand that submittal of this application is for coverage under the State of Colorado General Permit for Discharges
Associated with Construction Dewatering for the entirety of the construction site/project described and applied for,
until such time as the application is amended or the certification is transferred, inactivated, or expired.‖
Signature (Legally Responsible Party)_________________________________________Date ________________
Name (printed) _____________________________________________Title______________________________
Page 6 of 6 Revised April 2011
Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com
Construction Dewatering Application Instructions
Item A- Contact Information
Permit Applicant: Provide the company, corporation, or organization name
1. Permittee—Identify the title and name of the individual who is the legally responsible for the permit. The requirement of
who can be listed as the legally responsible party is included in the permit application. Include all requested information such
as the legal party‘s phone number, email address and mailing address. The individual identified here must sign the permit
application—Part I.
2. DMR Cognizant Official—Identify the title and individual‘s name
3. Site Contact—Identify the title and name of individual who is familiar with the day to day operations of the site. This
person will have first-hand information regarding the construction site, discharges occurring on site, and implementation of
BMPs.
4. Operator in Responsible Charge— Identify the title and individual‘s name if there is an Operator in Charge (Not
required)
5. Billing Contact— Identify the title and individual‘s name
6. Other Contacts – Identify the title and individual‘s name for any of the listed descriptions (Not required)
Item B – Permitted Project/Facility Information
1. Name of the project/facility and location; include the name of the project/facility and include a description of the location
of the project/facility. The location may be a physical address or if the exact address is not available you may use an
approximate address such as: the nearest intersection or boundary streets including directional identifiers (e.g., ―South of 14th
Avenue between Sherman St. and Logan St.‖, or ―West side of C.R. 21, 3.25 miles North of Hwy 10‖) or other identifying
information. A street name without an address, intersection, mile marker or other identifying information is not adequate.
2. Latitude/Longitude: For each excavation resulting in a discharge/outfall provide the Latitude/Longitude of the excavation.
If the exact location of the disturbance resulting in discharge is not known, provide the lat/long of the center point of the
construction activity. If identifying the center point of construction activity, make sure to write in ―center point‘ next to
lat/long. The lat/long may be provided as decimal degrees or degrees, minutes, seconds format. This information can be
obtained from a variety of sources, including:
Various Websites: http://terraserver.microsoft.com, http://geocoder.us/, or
www.epa.gov/tri/reports/siting_tool/index.htm
U.S Geological Survey topographical map, available at area map stores
Surveyors or engineers for the construction project should have, or be able to calculate this information using a
Global Positioning System (GPS) unit
Specify whether the Latitude/Longitude information was collected either by using a GPS unit or through Map interpolation.
3. Facility Activity and Schedule: Include the anticipated start date of construction dewatering and provide the length of
time dewatering is anticipated to last. Provide a description of the general nature of the construction activities that are
requiring the dewatering. Also describe if the dewatering discharge is from an open excavation, such as a trench or foundation,
or from groundwater lowering wells. Examples of activity descriptions may include: ‗open trench excavation for installation
of 4,000 linear feet of new water lines‘, or ‗a series of shallow groundwater wells will be installed around the perimeter of the
construction site in order to lower the water table for construction of a new 5,000 square foot music shop—all wells will be
piped to one manifold resulting in one discharge location as indicated on our site sketch.
4. Discharges to ditches and storm sewers: Indicate by checking yes or no whether or not the immediate effluent will be
discharged to a ditch or storm sewer. If yes is marked, the applicant must contact the owner of the ditch or storm sewer
system prior to discharge to verify if the owner will allow a discharge to their system. The owner of the ditch/storm sewer
system may impose additional requirements. Storm drainage systems are typically owned by the city or county they are located
within, and therefore contacting the local city/county is the appropriate place to start. If yes is marked, in Table C or Table D
be sure to include the location of the system and the ultimate receiving waters.
5. Defined or Undefined Discharge: Identify whether the applicant is applying for a Defined or Undefined discharge.
A Defined Discharge is a discharge where the dewatering discharge locations are known at the time of permit application.
If discharge is Defined – enter discharge information in Table C
Page 1 of 3—Revised April 2011
Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com
An Undefined Discharge is a discharge where the exact dewatering discharge locations are unknown at the time of permit
application. The permit applicant must request the maximum number of potential outfalls (discharges) for the permitted
facility/project. If discharge is Undefined – enter discharge information in Table D. The applicant must identify all
potential receiving streams for the entire project.
If the applicant is requesting undefined discharges, the site specific sampling and monitoring parameters will be selected
based on the potential pollutant sources found within the entire permitted project area and will be applied to all outfall(s).
The most stringent of the surface water limitations for each identified site specific parameter will be applied to each
permitted outfall. For example, if the undefined project includes installation of 8 miles of linear pipeline and leaking
underground storage tanks are expected to present in one section of the project, sampling and monitoring for Benzene,
Toluene, Ethyl benzene, and Xylenes will be required for all requested outfall(s).
Item C- Information for Defined Discharge Location(s).
1. If Defined Discharge was marked in Section B.5 fill out Table C. Table C requires the following information:
Number of discharge(s) (outfalls)—Identify the number of outfalls requested in Table C, this includes
discharges to surface water and groundwater. If there are more than two requested discharges to surface water,
attach a separate piece of paper including all requested information.
Name of the receiving water(s)—If the discharge is to a ditch, identify the ditch and the ultimate receiving
water(s). Receiving waters are any waters of the state of Colorado, even if the natural drainage is usually dry. If
discharge is to groundwater, then fill out the appropriate information within Table C next to G001A, G001A. If
there are more than two discharges to groundwater, attach a separate piece of paper including all requested
information. If the applicant is requesting a discharge to groundwater, please review the Division‘s Low Risk
Discharge Guidance for Discharges of Uncontaminated Groundwater to Land.
http://www.cdphe.state.co.us/wq/PermitsUnit/policyguidancefactsheets/policyandguidance/lowriskgwdischargeto
land.pdf
Discharges performed in accordance with the Guidance for Discharges of Uncontaminated Groundwater to Land
do not require a separate construction dewatering permit.
Narrative description of the approximate location of the discharge—Include a narrative description of the
discharge path. For example, ―the dewatering discharge will enter the storm sewer located at 6th Avenue and
Sheridan which flows to Bear Creek‖ or ―the dewatering will discharge to a field located at 66
th
and Farmers
Road with potential to runoff to Sanders Creek‖. If there is more than one known discharge, include this
descriptive information for all known discharges.
Maximum anticipated flow rate of the discharge (in gallons per minute)—Do not leave this section blank.
Include the maximum flow rate. You may estimate the flow contribution based on pump capacity if data is not
available.
Latitude/Longitude of each discharge location—Include the latitude/longitude of each discharge location. See
the instructions B.2 for information on how to obtain latitude/longitude information.
Item D- Information for Undefined Discharge Location(s).
1. If Undefined Discharge was marked in Section B.5 fill out Table D. Table D requires the flowing information:
Maximum number of potential outfalls (discharges) for the permitted facility—The applicant must identify the
maximum number of discharge locations (outfalls) for the entire construction project. If more than 5 outfalls are
requested, attach a separate piece of paper. DMRs will be sent to the permittee for each requested outfall.
Maximum anticipated flow rate of the discharge (in gallons per minute)—Do not leave this section blank. The
flow rate may be estimated based on pump capacity if data is not available.
Name(s) of the all potential receiving stream(s)—Identify all potential receiving streams for the entire project.
If the discharge is to groundwater then fill out the information in Table D next to G001A, G002A, etc.
Page 2 of 3 Revised April 2011
Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com
Item E – Location Map—A location map is required to be submitted with all applications for both defined and undefined
discharges. The location map must include the location of the project/facility, the approximate location of each defined discharge
points, and the identified receiving water(s) listed in Items C or D. The map must have a minimum scale of 1:24000 (the scale of a
USGS 7.5 minute map). A legible submittal is required on paper that can be folded to8 ½ by 11 inches.
Item F- Detailed Sketch of the Site—If a defined discharge is requested please submit a detailed site sketch which includes
the information requested in F.1. If an undefined discharge is requested please submit a detailed site sketch which includes
the information requested in F.2.
1. Detailed Sketch of the Site for Defined Discharges—Must included a detailed sketch of the site showing the location of
end of pipe dewatering discharge(s) at the site—to include the flow line of each requested dewatering discharge. The
location and identification of the structural Best Management Practices (BMPs) used to treat the effluent prior to discharge.
The map shall also include the sampling locations for each requested outfall. A legible submittal is required on paper that
can be folded to 8 ½ by 11 inches.
2. Detailed Sketch of the Site for Undefined Discharges—This map must include the boundary of the construction site
where all potential dewatering could occur. The boundaries should include a northern boundary, an eastern boundary, a
southern boundary and a western boundary. The map must highlight or call out street names that border the project
boundary. If streets are not available, landmarks or mile-markers must be identified. The map must highlight all potential
receiving streams. The map must also include the identification of the structural BMPs used to treat the effluent prior to
discharge. A legible submittal is required on paper that can be folded to 8 ½ by 11 inches.
Item G—Potential Groundwater Contamination
1. Dewatering on/near Landfills, Mines, or Mill Tailings: If the dewatering project is located within one mile of a landfill,
abandoned landfill, mine or mill tailings check yes. In addition, provide as much detail as possible regarding the extent of
contamination and attach all sampling data. Indicate the location of the landfill, mine, etc. on the Location and Detail Maps.
Contamination plume information can be obtained from the following source:
http://www.cdphe.state.co.us/hm/HMSiteCover.htm
2. Sampling Data: If any sampling data is available that is representative of the proposed discharge mark yes. Attach a copy
of all sampling results to the application. If the data was collected for another agency or private company include a brief
description as to why the data was collected.
3. Additional Sources of Contamination: Mark yes if the proposed construction site resulting in a dewatering discharge has
been evaluated for any additional sources of contamination. Additional sources include underground storage tanks, dry
cleaners, voluntary clean-up sites, etc. Also mark yes, if a Phase I or Phase II has been conducted on the property or adjacent
properties. Attach a copy of all records (phase I, phase II, sampling efforts) that could help characterized the water to be
discharged.
Contamination plume information can be obtained from the following source:
http://www.cdphe.state.co.us/hm/HMSiteCover.htm
Item H—Additional Information
1. Stormwater Permit for Construction Activities: If the applicant holds a stormwater permit for construction related
activities (parcels > 1 acre) include the stormwater permit number. If you have applied, or intend to apply but have not yet
obtained coverage and your certification number, indicate ―Pending‖ for this item.
Item I—Signature Requirements—The permit applicant listed in Part A.1 must sign the permit application. Signatures must
meet the requirements established in Regulation 61.4(1)(h).
Page 3 of 3—Revised April 2011
APPENDIX E
INSPECTION LOGS
'3036%(3()4%681)283*86%274368%8-32
(%-0=78361;%8)603+
-REGGSVHERGI[MXLWYFWIGXMSR
7XSVQ[EXIV1EREKIQIRX*MIPH(EMP]-RWTIGXMSR6ITSVX-RWXVYGXMSRW
-RWTIGXEPPIVSWMSRERHWIHMQIRXGSRXVSP&14WXLVSYKLSYXXLIIRXMVIGSRWXVYGXMSRWMXIzSFWIVZIVIGSVHERHHIXIVQMRIXLIMV
IJJIGXMZIRIWW-JEHHMXMSREP&14WEVIRIIHIHSVER]&14MWRSXSTIVEXMRKIJJIGXMZIP]MXWLEPPFIVIGSVHIHSRXLMWJSVQERH
EHHVIWWIHMQQIHMEXIP]
6IGSVHXLIWMXIPSGEXMSR
'3036%(3()4%681)283*86%274368%8-32
(%-0=78361;%8)603+%((-8-32%04%+)
(EXI 4VSNIGXRYQFIV 7YFEGGSYRXRYQFIV
8LIIRXMVIWMXIWLEPPFIMRWTIGXIHXSHIXIVQMRI[LIXLIV&14WEVIFIMRKMQTPIQIRXIHERHQEMRXEMRIHMREGGSVHERGI[MXLXLI
TVSNIGXvWWMXIWTIGMJMG7;14ERHXLI'(477'48LI)VSWMSR'SRXVSP7YTIVZMWSV
APPENDIX F
EROSION CONTROL ESCROW ESTIMATE
Project: Disturbed Acres: 7.70
EROSION CONTROL BMPs Units
Estimated
Quantity
Unit
Price
Total
Price
L.F. 3600 $1.85 $6,660.00
each 5 $220.00 $1,100.00
each 7 $300.00 $2,100.00
each 1 $400.00 $400.00
each 50 $20.00 $1,000.00
each 22 $25.00 $550.00
each 1 $1,200.00 $1,200.00
L.F. 50 $0.50 $25.00
per hour 50 $70.00 $3,500.00
Sub-Total: $16,535.00
1.5 x Sub-Total: $24,802.50
Amount of security: $24,802.50
Total Acres x Price/acre: $6,487.25
$842.50 Sub-Total: $6,487.25
1.5 x Sub-Total: $9,730.88
Amount to Re-seed: $9,730.88
Minimum escrow amount: $3,000.00
Erosion Control Escrow: $24,802.50
Miniumum Escrow Amount
Final Escrow Amount
“The amount of the security must be based on one and one-half times the estimate of the cost to install the approved measures, or one and one-half times the cost to re-vegetate
the disturbed land to dry land grasses based upon unit cost determined by the City's Annual Revegetation and Stabilization Bid, whichever is greater. In no instance, will the
amount of security be less than one thousand five hundred dollars ($1,500) for residential development or three thousand dollars ($3,000) for commercial development”
Sawcutting Pollution Prevention
Street Sweeping and Cleaning
(add all other BMPs for the site in this list)
Reseeding Amount
Unit Price of Seeding per acre:
Vehicle Tracking Control Pad
Example Erosion and Sediment Control Escrow/Security Calculation for
Brookfield Replat A
BMP Amount
Silt Fence
Rock Sock
Curb Inlet Protection
Drop Inlet Protection
Concrete Washout Area
Straw Wattles
APPENDIX G
CONTRACTOR INSERTS
)'7
SV7YTIVMRXIRHIRXWLEPPMHIRXMJ]MJ
EHHMXMSREP&14WEVIRIIHIHGERFIVIQSZIHSVRIIHQEMRXIRERGI8LIGSRHMXMSRSJXLIGYVVIRXP]YWIH&14WWLEPPFI
VIGSVHIHYWMRKSRISVQSVISJXLIJSPPS[MRKPIXXIVW
-
-RGSVVIGX-RWXEPPEXMSR
1
1EMRXIRERGIMWRIIHIH
*
&14JEMPIHXS
STIVEXI
%
%HHMXMSREP&14MWRIIHIH
6
6IQSZI&143RP]&14W[MXLXLIGSRHMXMSRWEFSZIRIIHFIVIGSVHIH
8LI4VSNIGX)RKMRIIV[MPPETTVSZIERHXLI7YTIVMRXIRHIRXWLEPPHMVIGXXLI[SVOEWWSGMEXIH[MXLER]&14WMHIRXMJMIHMRXLMWHEMP]
PSKXSIRWYVIGSQTPMERGI[MXLXLIWMXIWTIGMJMG7;14ERHXLI'(477'4
'(477'47XEXIWw&14WXLEXEVIRSXSTIVEXMRKIJJIGXMZIP]LEZITVSZIRXSFIMREHIUYEXISVLEZIJEMPIHQYWXFI
EHHVIWWIHEWWSSREWTSWWMFPIMQQIHMEXIP]MRQSWXGEWIWx
0SGEXMSR &148]TI 'SRHMXMSR 2SXIW'SQQIRXW
(EXI
'SQTPIXIH
-RMXMEPW
4%SVQ+)3* '(38*
IKTVSNIGXWXEXMSRRYQFIVQMPIQEVOIVMRXIVWIGXMSRUYEHVERXIXG
-RHMGEXIXLIX]TISJ&14EXXLMWPSGEXMSRXLEXVIUYMVIWEXXIRXMSR
IKWMPXJIRGIIVSWMSRPSKWWSMPVIXIRXMSRFPEROIXW
IXG
-HIRXMJ]XLIGSRHMXMSRSJXLI&14YWMRKSRISVQSVISJXLIJSPPS[MRKPIXXIVW
-
-RGSVVIGX-RWXEPPEXMSR
1
1EMRXIRERGI
MWRIIHIH
MIWIHMQIRXRIIHWXSFIVIQSZIH
*
&14*EMPIHXSSTIVEXI
%
%HHMXMSREP&14MWRIIHIH
6
6IQSZIXLI&14
-JEPP&14WEVIMRSTIVEXMRKGSRHMXMSRERHRS&14QEMRXIRERGIMWRIIHIHWMKRERHMRMXMEPXLIFS\XSXLIVMKLXSJXLI
WXEXIQIRX
4VSZMHIXLITVSTSWIHGSVVIGXMZIEGXMSRRIIHIHXSFVMRKXLIEVIESV&14MRXSGSQTPMERGI
(EXIERHMRMXMEP[LIRXLIGSVVIGXMZIEGXMSR[EWGSQTPIXIH
7MKRXLIJSVQ[LIRXLIMRWTIGXMSRLEWFIIRGSQTPIXIH
4PEGIXLIGSQTPIXIHHEMP]WXSVQ[EXIVPSKWLIIX
W
MRXLI7;142SXIFSSO
4%+)3* '(38*SVQ
G
HEMP]WXSVQ[EXIVGSQTPMERGIMRWTIGXMSRWEVIVIUYMVIHSREPPTVSNIGXWLSPHMRKE'SPSVEHS
(MWGLEVKI4IVQMX7]WXIQz7XSVQ[EXIV'SRWXVYGXMSR4IVQMX
'(477'4
8LMWJSVQMWXSFIYWIHEWXLIHEMP]HMEV]XSIZEPYEXI&14WYWIHHYVMRKGSRWXVYGXMSREGXMZMXMIW
7IIXLIMRWXVYGXMSRWJSVQSVIMRJSVQEXMSR
(EXI 4VSNIGXRYQFIV 7YFEGGSYRXRYQFIV
8LIIRXMVIWMXIWLEPPFIMRWTIGXIHXSHIXIVQMRI[LIXLIV&14WEVIFIMRKMQTPIQIRXIHERHQEMRXEMRIHMREGGSVHERGI[MXLXLI
TVSNIGXvWWMXIWTIGMJMG7;14ERHXLI'(477'48LI)VSWMSR'SRXVSP7YTIVZMWSV
)'7
SV7YTIVMRXIRHIRXWLEPPMHIRXMJ]MJ
EHHMXMSREP&14WEVIRIIHIHGERFIVIQSZIHSVRIIHQEMRXIRERGI8LIGSRHMXMSRSJXLIGYVVIRXP]YWIH&14WWLEPPFI
VIGSVHIHYWMRKSRISVQSVISJXLIJSPPS[MRKPIXXIVW
-
-RGSVVIGX-RWXEPPEXMSR
1
1EMRXIRERGIMWRIIHIH
*
&14JEMPIHXS
STIVEXI
%
%HHMXMSREP&14MWRIIHIH
6
6IQSZI&143RP]&14W[MXLXLIGSRHMXMSRWEFSZIRIIHFIVIGSVHIH
9WIXLI
I\XVETEKIEXXLIIRHSJXLMWJSVQMJRIIHIH
8LI4VSNIGX)RKMRIIV[MPPETTVSZIERHXLI7YTIVMRXIRHIRXWLEPPHMVIGXXLI[SVOEWWSGMEXIH[MXLER]&14WMHIRXMJMIHMRXLMWHEMP]
PSKXSIRWYVIGSQTPMERGI[MXLXLIWMXIWTIGMJMG7;14ERHXLI'(477'4
'(477'47XEXIWw&14WXLEXEVIRSXSTIVEXMRKIJJIGXMZIP]LEZITVSZIRXSFIMREHIUYEXISVLEZIJEMPIHQYWXFI
EHHVIWWIHEWWSSREWTSWWMFPIMQQIHMEXIP]MRQSWXGEWIWx
0SGEXMSR &148]TI 'SRHMXMSR 2SXIW'SQQIRXW
(EXI
'SQTPIXIH
-RMXMEPW
%00&147%6)-234)6%8-2+'32(-8-32%2(231%-28)2%2')-72))()(
MRMXMEPXLIFS\XSXLIVMKLX[LIRXLMWETTPMIW
'SQQIRXW+IRIVEPRSXIW
EXXEGLTLSXSWMJRIGIWWEV]
-RWTIGXMSRWMKREXYVI
7YTIVMRXIRHIRXSV)'72EQI
4VMRX 7MKREXYVIEXIWMKRIH (
4%SVQ+)3* '(38*
ANY GAP AT JOINT SHALL BE FILLED
WITH 1 1/2" CRUSHED ROCK AND
WRAPPED WITH ADDITIONAL WIRE
MESH SECURED TO ENDS OF ROCK
REINFORCED BERM
SEE JOINT DETAIL,
THIS SHEET
A
AREA INLET
(TYPE C SHOWN)
REINFORCED ROCK
BERM SEE SB DETAIL
5. REINFORCED ROCK BERM SHALL BE CONSTRUCTED IN ONE PIECE OR SHALL BE CONSTRUCTED USING JOINT DETAIL.
ON ENDS OF BERM.
4. WIRE MESH SHALL BE SECURED USING "HOG RINGS" OR WIRE TIES AT 6-INCH CENTERS ALONG ALL JOINTS AND AT 2-INCH CENTERS
"CHICKEN WIRE"). ROLL WIDTH SHALL BE 48-INCHES.
3. WIRE MESH SHALL BE FABRICATED OF 10 GAUGE WIRE TWISTED INTO A MESH WITH A MAXIMUM OPENING OF 1.0 INCH (COMMONLY TERMED
MINUS). RECYCLED CONCRETE MEETING THIS GRADATION MAY BE USED.
2. CRUSHED ROCK SHALL BE FRACTURED FACE (ALL SIDES) AND SHALL COMPLY WITH GRADATION SHOWN IN CDOT SECT. 703-2, #4 aggregate (1-1/2"
INLET PROTECTION AFTER INLET CONSTRUCTION OF AFTER PAVEMENT SHALL BE INSTALLED WITHIN
48 HOUR AFTER INLET CONSTRUCTION OR PAVING IS COMPLETED.
1.
INLET PROTECTION INSTALLATION NOTES
INLET PROTECTION MAINTENANCE NOTES
OTHERWISE STABILIZED IN A MANNER APPROVED BY THE LOCAL JURISDICTION.
4. WHEN INLET PROTECTION AT AREA INLETS IS REMOVED, THE DISTURBED AREA SHALL BE COVERED WITH TOP SOIL, DRILL SEEDED AND CRIMP MULCHED, OR
JURISDICTION APPROVES EARLIER REMOVAL OF INLET PROTECTION IN STREETS.
3. INLET PROTECTION IS TO REMAIN IN PLACE UNTIL THE UPSTREAM DISTURBED AREA IS STABILIZED AND GRASS COVER IS APPROVED, UNLESS THE LOCAL
INCHES OF THE CREST.
2. SEDIMENT ACCUMULATED UPSTREAM OF INLET PROTECTION SHALL BE REMOVED WHEN THE SEDIMENT DEPTH UPSTREAM OF ROCK BERM IS WITHIN 2-1/2
NECESSARY. INSPECT MORE FREQUENTLY DURING WINTER CONDITIONS DUE TO FREEZE/THAW PROBLEMS. REPAIRS AS NEEDED.
1. THE SWMP MANAGER SHALL INSPECT INLET PROTECTION WEEKLY, DURING AND AFTER ANY STORM EVENT AND MAKE REPAIRS OR CLEAN OUT AS
DETAIL BASED ON DETAILS PROVIDED BY DOUGLAS COUNTY
MANHOLE
ROCK BERM SHALL
CURB INLET 2"x 4" WOOD STUD EXTENDED
INTO CONCRETE BLOCKS
WIRE ENCLOSED
1 1/2" WASHED ROCK CONCRETE
BLOCKS
CURB INLET
GRAVEL FILTER WIRE SHALL ENCLOSED BE 2"x4" WOOD STUD
OVERFLOW
FILTERED
RUNOFF
%SECTION A-A
A
A
%PLAN VIEW
{CURB INLET GRAVEL FILTER
(CONTINUOUS GRADE)}
%SECTION B-B
%PLAN VIEW
B
B
ROCK BERM SHALL BE PLACED TIGHTLY AGAINST CURB FACE
WIRE ENCLOSED 1 1/2"
WASHED ROCK
CURB AND GUTTER
CURB AND GUTTER
BE PLACED TIGHTLY
AGAINST CURB FACE
GRAVEL FILTER
1/2" TO 1" BELOW TOP OF CURB
TUBULAR
MARKER
IF AREA ADJACENT TO CURB INLET BOX IS NOT STABILIZED, INSTALL A TEMPORARY SEDIMENT/EROSION CONTROL BMP UNTIL THE SURROUNDING AREA IS SUFFICIENTLY STABILIZED.
TUBULAR
MARKER
TUBULAR
MARKER
2' 3'
4'
CURB INLET
WIRE ENCLOSED
SETTLED
RUNOFF
GRAVEL FILTER
CURB INLET MANHOLE
{CURB INLET BLOCK AND GRAVEL FILTER
(INLET IN SUMP)}
INTERIM CONFIGURATION INLET PROTECTION IN STREETS SHALL BE INSTALLED WITHIN 48 HOURS OF POURING INLET. INLET PROTECTION (AFTER PAVING) SHALL BE INSTALLED WITHIN 48
HOURS AFTER PAVING IS PLACED.
WASHED ROCK SHALL COMPLY WITH A 1-1/2" MINUS GRADATION.
WIRE MESH SHALL BE FABRICATED OF 10 GAUGE WIRE TWISTED INTO A MESH WITH A MAXIMUM OPENING OF 1" (COMMONLY TERMED "CHICKEN WIRE"). ROLL WIDTH SHALL BE 48".
TUBULAR MARKERS SHALL MEET REQUIREMENTS OF MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD).
OTHER CURB INLET PROTECTION METHODS WILL BE ALLOWED IF ACCEPTED BY THE CITY.
{GENERAL NOTES:
}1.
2.
3.
4.
5.
THE CONTRACTOR SHALL INSPECT INLET PROTECTION EVERY TWO WEEKS AND AFTER SIGNIFICANT STORM EVENTS AND MAKE REPAIRS OR CLEAN OUT AS NECESSARY.
SEDIMENT ACCUMULATED UPSTREAM OF INLET PROTECTION SHALL BE REMOVED WHEN THE SEDIMENT DEPTH UPSTREAM OF ROCK BERM IS 2 1/2" OF THE CREST.
INLET PROTECTION IS TO REMAIN IN PLACE UNTIL THE UPSTREAM DISTURBED AREA IS STABILIZED AND GRASS COVER IS ACCEPTED. UNLESS THE CITY ACCEPTS EARLIER REMOVAL OF
INLET PROTECTION IN STREETS.
{MAINTENANCE NOTES:
}1.
2.
3.
4" MIN
5" MAX
BMP WIDTH VARIES BMP WIDTH VARIES
BMP WIDTH VARIES BMP WIDTH VARIES
TUBULAR MARKER TUBULAR MARKER
2
NOT TO SCALE
005
EC3
CURB INLET PROTECTION
NOT TO SCALE
006
EC3
AREA INLET PROTECTION
CIP
IP
26
City Engineer Date
Date
Date
Date
Date
Stormwater Utility
Parks & Recreation
Traffic Engineer
Date
APPROVED:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
Water & Wastewater Utility
City of Fort Collins, Colorado
UTILITY PLAN APPROVAL
Environmental Planner
STAKE PROTRUDING ABOVE THE WATTLE. BAILING WIRE OR
NYLON ROPE SHOULD BE TIED TO THE STAKES ACROSS
THE WATTLE. STAKES SHOULD THEN BE DRIVEN UNTIL THE
BAILING WIRE OR NYLON ROPE IS SUFFICIENTLY SNUG TO
THE WATTLE.
WHEN INSTALLING RUNNING LENGTHS OF WATTLES, TO
PREVENT SHIFTING, BUTT THE SECOND WATTLE TIGHTLY
AGAINST THE FIRST. DO NOT OVERLAP THE ENDS. STAKES
SHOULD BE DRIVEN 1 FT. FROM END, ACROSS FROM AND
ON EACH SIDE OF WATTLE LEAVING 4"-6" OF STAKE
PROTRUDING ABOVE THE WATTLE. BAILING WIRE OR
NYLON ROPE SHOULD BE TIED TO STAKES IN AN HOUR
GLASS FORMATION (FRONT TO BACK OF WATTLE "A",
ACROSS TO FRONT OF WATTLE "B", ACROSS TO BACK AND
BACK TO FRONT OF WATTLE "A"). STAKES SHOULD THEN BE
DRIVEN IN UNTIL BAILING WIRE OR NYLON ROPE IS
SUFFICIENTLY SNUG TO THE WATTLE.
4"-6" ABOVE WATTLE AFTER BAILING WIRE
OR NYLON ROPE IS ATTACHED. STAKES
NEED TO BE TAMPED UNTIL WIRE/ROPE IS
SNUG WITH WATTLE.
W2
ENDS OF ADJACENT WATTLES
SHALL BE TIGHTLY ABUTTED
TO PREVENT SEDIMENT BYPASS
WATTLE INSTALLATION
W2 NOTE:
ONLY WATTLES MADE WITH COCONUT
FIBERS SHALL BE USED WHEN
INSTALLATION COMES IN CONTACT WITH A
WATER BODY.
VEHICLE TRACKING CONTROL PAD SHALL BE LOCATED AT EVERY ACCESS POINT TO THE CONSTRUCTION SITE.
A SIGN SHALL BE PLACED NEXT TO THE VEHICLE TRACKING CONTROL PAD TO DESIGNATE THE LOCATION AS THE CONSTRUCTION ENTRANCE/EXIT.
VEHICLE TRACKING CONTROL (VTC) PADS SHALL CONSIST OF HARD, DENSE, DURABLE ROCK, ANGULAR IN SHAPE AND RESISTANT TO WEATHERING. ROUNDED STONE
SHALL NOT BE USED, i.e., RIVER ROCK AND COBBLES. THE ROCK SHALL BE A MINIMUM OF 3" AND A MAXIMUM OF 6" DIAMETER. THE ROCK SHALL HAVE A SPECIFIC
GRAVITY OF AT LEAST 2.6. CONTROL OF GRADATION WILL BE BY VISUAL INSPECTION. NOTE: OTHER MATERIALS, i.e., ROADBASE, MUD MATS, ETC., MAY BE USED IN
PLACE OF ROCK UPON WRITTEN APPROVAL OF THE CITY INSPECTOR.
ANY CRACKED OR DAMAGED CURB AND GUTTER AND SIDEWALK SHALL BE REPLACED BY CONTRACTOR.
INSTALLATION NOTES:
1.
2.
3.
4.
CONTRACTOR SHALL INSPECT VEHICLE TRACKING CONTROL PAD DAILY. ROCK SURFACE SHALL BE CLEAN AND LOOSE ENOUGH TO RUT SLIGHTLY UNDER WHEEL
LOADS AND CAUSE LOOSE ROCK TO DISLODGE MUD FROM TIRES. WHEN ROCK BECOMES COMPACTED OR FILLED WITH SEDIMENT SO THAT THE EFFECTIVENESS OF
THE PAD IS DIMINISHED, CONTRACTOR SHALL RIP, TURN OVER, OR OTHERWISE LOOSEN ROCK, PLACE ADDITIONAL NEW ROCK, OR REPLACE WITH NEW ROCK AS
NECESSARY TO RESTORE EFFECTIVENESS.
SEDIMENT AND OTHER MATERIAL SPILLED, DROPPED OR TRACKED ONTO PAVED SURFACES SHALL BE REMOVED IMMEDIATELY OR BY THE END OF EACH WORKING
DAY.
VEHICLE TRACKING CONTROL PAD SHALL BE REMOVED AT THE END OF CONSTRUCTION. THE AREA SHOULD BE TOPSOILED, SEEDED, CRIMPED, AND MULCHED OR
OTHERWISE STABILIZED.
MAINTENANCE NOTES:
1.
2.
3.
3" - 6" ROCK
CONSTRUCTION FENCE, TYP., TO DISCOURAGE
VEHICLE ACCESS EXCEPT AT VTC
SIGN "CONSTRUCTION ENTRANCE"
R=5'
PAVED SURFACE
20' MIN.
A
10% MAX.
SECTION A
3" - 6" ROCK
NO MATERIALS INCLUDING 2x4'S, PIPES,
DIRT, GRAVEL OR ASPHALT, SHALL BE
PLACED IN GUTTER TO FACILITATE
MOUNTING CURB; HOWEVER, CURB MAY BE
CUT DOWN TO A HEIGHT OF 2" OR HIGHER
FOR EASIER ACCESS AND REPLACED AT
PROJECT COMPLETION. OTHER ACCESS
DEVICES MAY BE USED AS ACCEPTED BY
THE CITY.
%PLAN%
CURB CUT
50' MIN.
2" MIN. 6" MIN.
6" MIN.
VEHICLE TRACKING CONTROL PAD
ALTHOUGH NOT NORMALLY USED, THE CITY RESERVES THE RIGHT TO REQUIRE VEHICLE TRACKING CONTROL WITH A TEMPORARY CATTLE GUARD
AND/OR WHEEL WASH FACILITIES AT SITES WHERE TRACKING ONTO PAVED AREAS BECOMES A SIGNIFICANT PROBLEM AS DETERMINED BY THE CITY
INSPECTOR.
IF VEHICLE TRACKING CONTROL WITH WHEEL WASH FACILITIES ARE REQUIRED, ALL WHEELS ON EVERY VEHICLE LEAVING THE SITE SHALL BE
CLEANED OF MUD USING A PRESSURE-WASHER. THE CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING A WATER SOURCE AND CONSTRUCTING
A WASHWATER SEDIMENT TRAP.
5.
6.
IF VEHICLE WHEEL WASH FACILITIES ARE REQUIRED, CONTRACTOR SHALL INSPECT VEHICLE TRACKING CONTROL AND WHEEL WASH FACILITIES DAILY.
ACCUMULATED SEDIMENTS SHALL BE REMOVED FROM THE PAD SURFACE.
ACCUMULATED SEDIMENT IN THE WASHWATER/SEDIMENT TRAP SHALL BE REMOVED WHEN THE SEDIMENT REACHES AN AVERAGE DEPTH OF 12-INCHES.
4.
5.
COMPACTED BACKFILL
FLOW
SILT FENCE FABRIC (ASTM D6461) ANCHORED IN
TRENCH AND ATTACHED TO POST.
24" MIN
6' MAX
FLOW
TRENCH AND ATTACHED TO POST.
4"x4" TRENCH
SILT FENCE FABRIC (ASTM D6461) ANCHORED IN
18" MIN
24" MIN
42" MIN
POSTS
{PREASSEMBLED SILT FENCE}
JOIN FIRST
ROTATE SECOND
POSTS SHALL OVERLAP
AT JOINTS SO THAT NO
GAPS EXIST IN SILT FENCE.
NOTE:
THICKNESS OF GEOTEXTILE
POST SHALL BE JOINED AS SHOWN, THEN HAS BEEN EXAGGERATED.
ROTATED 180� IN DIRECTION SHOWN AND
DRIVEN INTO THE GROUND.
{SILT FENCE JOINTS}
DRIVE POSTS VERTICALLY INTO THE GROUND TO A MINIMUM DEPTH OF 18".
EXCAVATE A TRENCH APPROXIMATELY 4" WIDE AND 4" DEEP ALONG THE LINE OF POSTS AND
UPSLOPE FROM THE BARRIER.
ANCHOR TRENCH SHALL BE EXCAVATED BY HAND, WITH TRENCHER, OR WITH SILT FENCE
INSTALLATION MACHINE. NO ROAD GRADERS, BACKHOES, ETC. SHALL BE USED.
NOT LESS THAN THE BOTTOM 1' OF THE SILT FENCE FABRIC SHALL BE BURIED IN THE TRENCH.
THE TRENCH SHALL BE COMPACTED BY HAND, WITH "JUMPING JACK" OR BY WHEEL ROLLING.
COMPACTION SHALL BE SUCH THAT THE SILT FENCE RESISTS BEING PULLED OUT OF ANCHOR
TRENCH BY HAND.
SILT FENCE INDICATED IN THE PLANS SHALL BE INSTALLED PRIOR TO ANY LAND-DISTURBING
ACTIVITIES.
USE WOOD POSTS OR OTHER MATERIAL AS ACCEPTED BY THE CITY.
INSTALLATION NOTES:
1.
2.
3.
4.
5.
6.
7.
THE CONTRACTOR SHALL INSPECT SILT FENCE EVERY TWO WEEKS AND AFTER SIGNIFICANT STORM
EVENTS AND MAKE REPAIRS OR CLEAN OUT UPSTREAM SEDIMENT AS NECESSARY.
SEDIMENT ACCUMULATED UPSTREAM OF SILT FENCE SHALL BE REMOVED WHEN THE UPSTREAM
SEDIMENT REACHES A DEPTH OF 6".
SILT FENCE SHALL BE REMOVED WHEN THE UPSTREAM DISTURBED AREA IS STABILIZED AND GRASS
COVER IS ACCEPTED BY THE CITY. IF ANY DISTURBED AREA EXISTS AFTER REMOVAL, IT SHALL BE
SEEDED AND MULCHED OR OTHERWISE STABILIZED IN A MANNER ACCEPTED BY THE CITY.
MAINTENANCE NOTES:
1.
2.
3.
4" MIN.
4" MIN.
1
1
2" x 1
1
2" WOODEN FENCE POSTS
COMPACTED BACKFILL
SILT FENCE
3H:1V OR FLATTER
SIDE SLOPES
12" MIN
8'x 8' MIN
OR AS REQUIRED TO
CONTAIN WASTE CONCRETE
12" 2'-0" MIN.
COMPACTED EMBANKMENT
MATERIAL, TYP.
BERM AROUND PERIMETER
GROUND SURFACE
SIGN TO INDICATE THE
LOCATION OF THE
CONCRETE WASHOUT AREA
CONCRETE WASHOUT AREA
CONCRETE WASHOUT AREA SHALL BE INSTALLED PRIOR TO ANY CONCRETE PLACEMENT ON SITE.
VEHICLE TRACKING CONTROL (DETAIL SW-14) IS REQUIRED IF ACCESS TO CONCRETE WASHOUT AREA IS OFF PAVEMENT.
SIGNS SHALL BE PLACED AT THE CONSTRUCTION ENTRANCE, AT THE WASHOUT AREA, AND ELSEWHERE AS NECESSARY TO CLEARLY INDICATE THE
LOCATION OF THE CONCRETE WASHOUT AREA TO OPERATORS OF CONCRETE TRUCKS AND PUMP RIGS.
THE CONCRETE WASHOUT AREA SHALL BE REPAIRED AND ENLARGED OR CLEANED OUT AS NECESSARY TO MAINTAIN CAPACITY FOR WASTED
CONCRETE.
AT THE END OF CONSTRUCTION, ALL CONCRETE SHALL BE REMOVED FROM THE SITE AND DISPOSED OF AT AN ACCEPTED WASTE SITE.
WHEN THE CONCRETE WASHOUT AREA IS REMOVED, THE DISTURBED AREA SHALL BE SEEDED AND MULCHED OR OTHERWISE STABILIZED IN A
MANNER ACCEPTED BY THE CITY.
{NOTES:
}1.
2.
3.
4.
5.
6.
0" ON BEDROCK
OR HARD SURFACE,
2" IN SOIL
ROCK SOCK SECTION ROCK SOCK PLAN
4" TO 6" MAX AT CURBS,
OTHERWISE 6"-10" DEPENDING
ON EXPECTED SEDIMENT LOADS
ROCK SOCK JOINTING
12"
12"
{ROCK SOCK INSTALLATION NOTES
}1.SEE PLAN VIEW FOR:
- LOCATION (S) OF ROCK SOCKS.
2.CRUSHED ROCK SHALL BE 1{}" (MINUS) IN SIZE WITH A FRACTURED FACE (ALL SIDES) AND SHALL
COMPLY WITH GRADATION SHOWN ON THIS SHEET (1{}" MINUS).
3.WIRE MESH SHALL BE FABRICATED OF 10 GAGE POULTRY MESH, OR EQUIVALENT, WITH A MAXIMUM
OPENING OF {}", RECOMMENDED MINIMUM ROLL WIDTH OF 48".
4.WIRE MESH SHALL BE SECURED USING "HOG RINGS" OR WIRE TIES AT 6" CENTERS ALONG ALL
JOINTS AND AT 2" CENTERS ON ENDS OF SOCKS.
5.SOME MUNICIPALITIES MAY ALLOW THE USE OF FILTER FABRIC AS AN ALTERNATIVE TO WIRE MESH
FOR THE ROCK ENCLOSURE.
GRADATION TABLE
SIEVE SIZE
MASS PERCENT
PASSING SQUARE
MESH SIEVES
NO. 4
2" 100
1-1/2" 90-100
1" 20-55
{3/4}" 0-15
MATCHES SPECIFICATIONS FOR {3/NO. 8}4 COARSE " AGGREGATE FOR CONCRETE PER AASHTO M43. ALL ROCK 0-SHALL 5 BE FRACTURED FACE, ALL SIDES
NOT TO SCALE
004
EC2
ROCK SOCK
WD
NOT TO SCALE
001
EC2
VEHICLE TRACKING CONTROL PAD
NOT TO SCALE
002
EC2
CONCRETE WASHOUT AREA
VTC CWA
NOT TO SCALE
003
EC2
SILT FENCE
SF
SF
RS
25
City Engineer Date
Date
Date
Date
Date
Stormwater Utility
Parks & Recreation
Traffic Engineer
Date
APPROVED:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
Water & Wastewater Utility
City of Fort Collins, Colorado
UTILITY PLAN APPROVAL
Environmental Planner
No. Revisions: By: Date:
REVIEWED BY:
R. Banning
DESIGNED BY:
DRAWN BY:
SCALE:
DATE:
July 13, 2015
PROJECT:
374-020
Sheet
Of 33
BROOKFIELD REPLAT A
T���� �������� ���
����������� �� �������
�������� �� N�������
E���������� S�������, I��.
��� ��� ��� �� �� ���� ���
��� ���� �� ������������
������ ������ ��� ������ ��
� P����������� E������� ��
��� ������ �� N�������
E���������� S�������, I��.
NOT FOR CONSTRUCTION
REVIEW SET
07/13/15
E N G I N E E R I N G
� � � � � � ��
301 N���� H���� S�����, S���� 100
F��� C������, C������� 80521
PHONE: 970.221.4158
���.�������������������.���
COVERED
ENTRY
COVERED
ENTRY
COVERED
ENTRY
DECK DECK
DECK DECK
COVERED
ENTRY ENTRY
COVERED
DECK
COVERED
COVERED ENTRY
ENTRY
COVERED
ENTRY
DECK DECK
DECK
DECK
COVERED
ENTRY ENTRY
COVERED
DECK
COVERED
ENTRY COVERED
ENTRY
COVERED
ENTRY
DECK DECK DECK
DECK
COVERED
ENTRY ENTRY
COVERED
DECK
COVERED
COVERED ENTRY
ENTRY
COVERED
ENTRY
DECK DECK DECK
DECK
TRACT A
TRACT B
BLDG 10
BLDG 14
GARAGE
(TYP.)
GARAGE
(TYP.)
GARAGE
(TYP.)
GARAGE
(TYP.)
GARAGE
(TYP.)
GARAGE
(TYP.)
GARAGE
(TYP.)
GARAGE
(TYP.)
GARAGE
(TYP.)
GARAGE
(TYP.)
GARAGE
(TYP.)
GARAGE
(TYP.)
MORNINGSIDE
VILLAGE CONDOS
OWNER:
MORNINGSIDE VILLAGE
MASTER ASSOCIATION INC.
FOSSIL CREEK RESERVOIR INLET DITCH
OWNER:
IMAGO ENTERPRISES INC
140 PALMER DR.
FORT COLLINS, CO 80525
SF
CIP
RS
VTC
SF SF SF SF SF
SF
SF SF SF SF SF SF SF SF SF SF SF SF
SF SF SF SF SF
SF SF SF SF SF SF SF SF SF SF SF SF SF
RS
RS
RS
RS
VTC
SF
SF
SF
SF
SF
SF
SF
CIP
CIP
CIP
IP
IP
IP
IP
IP
IP
IP
RS
RS
BROOKFIELD DRIVE
NORTHERN LIGHTS DRIVE
LE FEVER DRIVE
PRECISION DRIVE
SF SF SF SF
SF SF SF
SF
SF SF
SF
SF
SF
SF
SF
SF
SF
SF SF
SF SF SF SF
SF SF
SF SF
SF SF SF SF SF SF SF
RS
RS
RS
RS
IP
RS
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
IP
MULCH
WRAP GRATE W/
FILTER FABRIC
CONTRACTOR **MUST**
PREVENT **ALL** TRACKING
OF SEDIMENT AND DEBRIS ONTO
PERVIOUS PAVEMENTS
WRAP GRATE W/
FILTER FABRIC
MULCH
LINE DRYWELL W/
FILTER FABRIC.
REMOVE W/ STABILIZATION
AT CLOSE OF PERMIT.
RAISE LANDSCAPE
DRAINS 1' UNTIL
STABILIZATION
RAISE LANDSCAPE
DRAINS 1' UNTIL
STABILIZATION
TRACK SLOPE &
HYDROMULCH.
INSTALL EC
BLANKET
AS NEEDED TO
STABILIZE
TRACK SLOPE &
HYDROMULCH.
INSTALL EC
BLANKET
AS NEEDED TO
STABILIZE
TRACK SLOPE &
HYDROMULCH.
INSTALL EC BLANKET
AS NEEDED TO STABILIZE
TRACK SLOPE &
HYDROMULCH.
INSTALL EC
BLANKET
AS NEEDED TO
STABILIZE
No. Revisions: By: Date:
REVIEWED BY:
R. Banning
DESIGNED BY:
DRAWN BY:
SCALE:
DATE:
July 13, 2015
PROJECT:
374-020
Sheet
Of 33
BROOKFIELD REPLAT A
T���� �������� ���
����������� �� �������
�������� �� N�������
E���������� S�������, I��.
��� ��� ��� �� �� ���� ���
��� ���� �� ������������
������ ������ ��� ������ ��
� P����������� E������� ��
��� ������ �� N�������
E���������� S�������, I��.
NOT FOR CONSTRUCTION
REVIEW SET
07/13/15
E N G I N E E R I N G
� � � � � � ��
301 N���� H���� S�����, S���� 100
F��� C������, C������� 80521
PHONE: 970.221.4158
���.�������������������.���
EC1
EROSION CONTROL PLAN
R. Banning
A. Boese
1"=50'
24
( IN FEET )
0
1 INCH = 40 FEET
40 40 80 120
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
K��� ����'� �����.
C��� ������ ��� ���.
R
City Engineer Date
Date
Date
Date
Date
Stormwater Utility
Parks & Recreation
Traffic Engineer
Date
APPROVED:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
CHECKED BY:
Water & Wastewater Utility
City of Fort Collins, Colorado
UTILITY PLAN APPROVAL
Environmental Planner
BENCHMARK
BENCHMARK #1:
City of Fort Collins Benchmark 55-01
Elevation= 4947.76 NGVD 29 Unadjusted
BENCHMARK #2:
City of Fort Collins Benchmark 07-07
Elevation= 4975.97 NGVD 29 Unadjusted
NOTE:
ALL BMP'S SHOWN ON THIS PLAN ARE GRAPHIC REPRESENTATIONS ONLY.
FINAL DETERMINATION OF SIZE AND LOCATION SHALL BE DETERMINED BY
THE CONTRACTOR AND DOCUMENTED ON THE DYNAMIC SITE PLAN.
1. CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY CRIMP
MULCHING OR SIMILAR METHODS (AS APPLICABLE).
2. TOTAL DISTURBED AREA = 7.51 ACRES
3. SWMP ADMINISTRATOR:
Contact ________________________________
Company ________________________________
Address ________________________________
Phone________________________________
4. CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE WASHOUT
AREA IF ACCESS IS OFF PAVEMENT.
5. REFER TO THE "STORM WATER MANAGEMENT PLAN & EROSION CONTROL REPORT FOR
BROOKFIELD" BY NORTHERN ENGINEERING, DATED XX/XX/XXXXFOR ADDITIONAL
INFORMATION.
GENERAL NOTES:
LEGEND:
5013
PROPOSED CONTOUR
EXISTING STORM SEWER
PROPOSED STORM SEWER
PROPOSED SWALE
EXISTING CONTOUR
PROPOSED CURB & GUTTER
PROPOSED STORM INLET
PROPOSED CONCRETE
CROSS PAN (TYP.)
PEDESTRIAN ACCESS RAMPS
93
VEHICLE TRACKING CONTROL PAD
SILT FENCE
SWALE WATTLE DIKE
INLET PROTECTION
ROCK SOCK
CONCRETE WASHOUT AREA
TEMPORARY BMP'S
SF
LIMITS OF DISTURBANCE
WD
VTC
SF
IP
RS
CWA
CURB INLET PROTECTION CIP
1.IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES ONLY AS A GUIDELINE TO THE CONTRACTOR. STAGING AND/OR
PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED. ADDITIONAL AND/OR DIFFERENT BMPs FROM THOSE ORIGINALLY
DEPICTED MAY BE NECESSARY DURING CONSTRUCTION DUE TO CHANGING SITE CONDITIONS OR AS REQUIRED BY LOCAL
AUTHORITIES.
2.THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH, GRAPHICAL SYMBOLS MAY NOT BE TO SCALE, NOR ARE THEY
NECESSARILY SHOWN IN THEIR EXACT LOCATION.
3.THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING (CITY, STATE DISCHARGE PERMIT, ETC.) AND COMPLIANCE WITH
GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR (OR PERMIT HOLDER) TO ENSURE EROSION
CONTROL MEASURES ARE PROPERLY MAINTAINED AND FOLLOWED.
4.CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION CONTROL MEASURES ACCORDING THE THE CONSTRUCTION
SEQUENCING AND LEVEL OF SITE STABILIZATION.
5.CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR ALL STORM DRAINS, SWALES, PONDS AND RAIN GARDENS
UNTIL SITE IS FULLY STABILIZED.
6.CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR DOWNSPOUT CONNECTIONS, TO THE STORM DRAIN
SYSTEM, UNTIL CONNECTION IS ESTABLISHED WITH DOWNSPOUT.
7.INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN
WATTLES FOR BARE SOIL, SAND BAGS OR GRAVEL SOCKS FOR PAVEMENT, ETC.)
8.CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES, PARTICULARLY THOSE STEEPER THAN 6:1. CRIMP MULCHING, HYDRO
MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND ADDITIONAL WATTLES OR SILT FENCING MAY BE NECESSARY TO ESTABLISH
VEGETATIVE COVER AND STABILIZE THE SLOPE.
9.ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE NECESSARY TO INSURE THAT EACH BUILDING PAD IS STABILIZED
THROUGHOUT CONSTRUCTION. AT NO TIME SHALL SEDIMENT BE ALLOWED TO CROSS THE PUBLIC SIDEWALKS.
10.CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER PROTECTION FOR AREAS DIRECTING DRAINAGE OFFSITE. PERIMETER
PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN
SEDIMENT CONTROL LOGS OR SILT FENCE FOR BARE SOIL, SAND BAGS OR GRAVEL SOCKS FOR PAVEMENT, ETC.)
11.FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED (100) FEET FROM NATURAL BODY OF WATER, WETLAND, NATURAL
DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS AND FUELING AREA MUST BE SET IN A CONTAINMENT AREA THAT WILL
NOT ALLOW A FUEL SPILL TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY.
12.CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE SANITATION UNITS (CONSTRUCTION TOILETS) SHALL BE LOCATED
AT LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND, OR DRAINAGE WAY. SAID FACILITIES MUST BE SET IN A
CONTAINMENT AREA THAT WILL NOT ALLOW POLLUTANTS TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER,
WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE LOCATED ON FLAT, STABLE GROUND, AND CONSTRUCTION TOILETS SHALL BE
STAKED DOWN.
13.THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE WITH THE CITY'S CONSTRUCTION INSPECTORS BY CEASING
OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO CREATE BLOWING DUST WHICH, IN THE INSPECTOR'S OPINION, IS
HAZARDOUS TO THE PUBLIC HEALTH AND WELFARE.
{14.WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND WINTER MONTHS) INHIBIT PERMANENT SEEDING OPERATIONS,
DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH TACKIFIER OR OTHER MATERIALS APPROVED BY EROSION CONTROL
STAFF TO PREVENT EROSION.
15.SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON PLANTING, REVEGETATION, HARDSCAPE AND OTHER PERMANENT SITE
STABILIZATION METHODS.
EROSION CONTROL NOTES:
TABLE OF CONSTRUCTION SEQUENCE AND BMP APPLICATION
Project: RIGDEN FARM - 14TH FILING
CONSTRUCTION PHASE MOBILIZATION DEMOLITION GRADING
BEST MANAGEMENT PRACTICES (BMPS)
STRUCTURAL "INSTALLATION"
Silt Fence Barriers *
Flow Barriers (Wattles) *
Inlet Filter Bags *
V���������
Temporary Seeding Planting
Mulching / Sealant
Permanent Seeding Planting
Sod Installation
Rolled Products : Netting / Blankets / Mats
Contour Furrows (Ripping / Disking)
Rock Bags *
UTILITIES
INSTALLATION
FLAT WORK
INSTALLATION
VERTICAL
INSTALLATION LANDSCAPE DEMOBILIZATION
Vehicle Tracking Pad *
* All Temporary BMPs to be Removed once Construction is Complete
Any prior inlets that could use protecting
Any prior inlets that could use protecting
Anytime the site will sit dormant longer than 30 Days
Anytime the site will sit dormant longer than 30 Days
Anytime the site will sit dormant longer than 30 Days
MODIFIED RAIN GARDEN