HomeMy WebLinkAboutCAPSTONE COTTAGES - FDP - FDP150046 - PLANS - EROSION CONTROL LETTER/REPORT (4)Project Number: 939-001 Location: Fort Collins, CO
Date: February 15, 2016 Total Acres: 28.62
EROSION CONTROL MEASURE Units
Estimated
Quantity
Unit
Price
Total
Price
L.F. 3849 $1.50 $5,773.50
Construction Fence w/Rock Sock L.F. 0 $4.50 $0.00
each 21 $75.00 $1,575.00
Wattle Dike Inlet Protection L.F. 9068 $1.75 $15,869.00
each 0 $75.00 $0.00
Wattle Dike Swale Protection each 0 $100.00 $0.00
each 3 $300.00 $900.00
each 1 $150.00 $150.00
each 1 $200.00 $200.00
each 0 $75.00 $0.00
L.F. 1000 $1.00 $1,000.00
per hour 25 $60.00 $1,500.00
Sub-Total: $26,967.50
1.5 x Sub-Total: $40,451.25
Amount of security: $40,451.25
Total Acres x $1325/acre: $37,921.50
Sub-Total: $37,921.50
1.5 x Sub-Total: $56,882.25
Cost to Re-seed: $56,882.25
Minimum escrow amount: $3,000.00
Erosion Control Escrow: $56,882.25
NOTE: 'Total Acres' represents total disturbed area.
Capstone Cottages
Erosion Control Cost Estimate
Silt Fencing
Inlet Protection
Wattle Dike Curb Side Check Dam
Vehicle Tracking Control Pads
Option 2 | Cost to Re-seed Disturbed acreage
Option 3 | Miniumum Escrow Amount
Final Escrow Amount
Sediment Trap
Concrete Washout Area
Rock Sock
Sawcutting Pollution Prevention
Street Sweeping and Cleaning
Option 1 | BMP Costs