HomeMy WebLinkAbout2133 TIMBERLINE RD., OFFICE & RESTAURANT - MAJOR AMENDMENT - MJA150009 - SUBMITTAL DOCUMENTS - ROUND 1 - DRAINAGE REPORT2133 TIMBERLINE - LOT 11
Appendix A Impervious Areas
SOUTH TIMBERLINE ROAD
FF= 4946.70
FND #4 REBAR
w/ RPC LS 37987,NE
DESIGN BY OTHER
(FOR REFERENCE ONLY)
FND #4 REBAR
FND #4 REBAR w/ RPC LS 33106,KSI
FND #4 REBAR w/ RPC LS 33106,KSI
w/ RPC LS 37987,NE
FND #4 REBAR
w/ RPC LS 34995,KSI
FND NAIL & SHINER
LS 34995,KSI
(FOR REFERENCE ONLY)
EXISTING 8" WIDE
MASONRY WALL
309
C603
3' CONCRETE PAN
PROPOSED BIO
SWALE CHANNEL 308
C603
CURB CUT
MATCH EXISTING
PROPOSED STEP
POROUS
PAVEMENT
ROOF DRAIN TO
BIO-SWALE
2.49
POROUS
PAVEMENT
49'-10"
2133 TIMBERLINE - LOT 11
Appendix B Erosion Control Report
2133 TIMBERLINE - LOT 11
PROJECT ECR
Page 1 of 5
APPENDIX A – EROSION CONTROL REPORT
A. Proposed Construction Area
i. Developed Conditions – The proposed site is located at the northwest corner of the
Timberline Rd. and Nancy Gray Ave., in Fort Collins. Currently, the proposed site
development area contains an established detention pond and outlet along the eastern
edge of the site. The proposed building will have an 85’ setback from Timberline road.
Vegetative Cover has been established in the detention pond.
ii. Rainfall Erodibility – Rainfall erosion will be controlled through use of temporary
construction BMPs until permanent vegetative cover has reached 70% percent of
groundcover. Opportunities for rainfall erosion include sheet flow across the site during
earthwork operations and utility installations.
iii. Proposed Rainfall Erosion and Sediment Control Methods – Primary methods will
include silt fence installation on the east and south lot limits and inlet and channel
protection with gravel bags to both slow and filter runoff water before it enters any
structures or channel outletting to the detention pond. A stabilized construction
entrance will be utilized at the site ingress/egress point.
iv. Site Phasing and BMP Installation Schedule – The site construction will take place in the
following order:
1. Installation of site BMPs
i. Stabilized Construction Entrance
ii. Silt Fence
iii. Inlet protection on existing inlets
2. Site Utility Installation
i. Installation of inlet control in new inlets and channels as they are
finished
3. Building Foundation and Earthwork
4. Vertical building construction and ongoing utilities
5. Finished site grading, hardscaping and paving
6. Landscaping and Irrigation installation
B. Stormwater Management Controls
i. SWMP Administrator
1. During construction, the SWMP administrator will be the earthwork and utility
contractor. Until such time as that contractor has been selected, the SWMP
Administrator will be Bill Renz, Project Manager-Ditesco. He will be responsible
2133 TIMBERLINE - LOT 11
PROJECT ECR
Page 2 of 5
for developing, implementing, maintaining, and revising the SWMP and will
address all aspects of the site SWMP.
i. Bill Renz – Ditesco Project Manager
1315 Oakridge Drive, Suite 120
Fort Collins, CO 80525
970.219.0157
ii. Identification of Potential Pollution Sources
1. All disturbed and stored soils – there will be disturbed soils onsite through
excavation and vehicle/equipment movement. Soils will be
stockpiled/permanently embanked onsite. Excess soil will be transported
offsite. Soil stockpiles left undisturbed for a period greater than 30 days will be
mulched and seeded.
2. Vehicle tracking of sediments – most vehicle and equipment travel will risk
sediment tracking until final pavement is installed. A stabilized construction
entrance will be used for the site. Surrounding roadways will be swept if
sediment is tracked onto the roadway.
3. Management of contaminated soils – soils may be contaminated through spills
during fueling operation or equipment oil leaks. The contractor will keep spill
kits onsite during the project and will excavate and remove contaminated kit
materials and soil and dispose through the proper waste stream.
4. Loading and unloading operations – Loading and unloading operations will take
place within the site for materials to be incorporated in the project. Vehicles
will use the stabilized entrance for ingress/egress.
5. Outdoor storage activities (building materials, fertilizers, chemicals, etc.)
Storage of materials will be in a designated area. Any chemicals used during
construction, concrete cure, etc., will be stored on secondary containment.
6. Vehicle and equipment maintenance and fueling – Maintenance and fueling will
be done in the field at the location of the equipment on grade. Spills will be
addressed through item 3 of this section.
7. Significant dust or particulate generating processes – dust may be generated
from vehicle tracking or portions of backfill operation. The site will be kept from
producing dust through watering of any exposed soils.
8. Routine maintenance activities involving fertilizers, pesticides, detergents, fuels,
solvents, oils, etc. – Fueling, lubrication, and maintenance operations will take
place within the project limits on grade. No fertilizers pesticides or detergents
are planned for use on site.
9. On-site waste management practices (waste piles, liquid wastes, dumpsters,
etc.) Roll-off Dumpsters will be utilized for the site and will be hauled off at
2133 TIMBERLINE - LOT 11
PROJECT ECR
Page 3 of 5
regular intervals. Any liquid waste generated will be contained. Concrete
process water will be addressed through the next item in the section.
10. Concrete truck/equipment washing, including the concrete truck chute and
associated fixtures and equipment – A concrete wash out will be utilized for all
concrete placement operations. A sign will be posted clearly showing the
washout location.
11. Dedicated asphalt and concrete batch plants – no asphalt or concrete batch
plants will be erected onsite.
12. Non-industrial waste sources such as worker trash and portable toilets –
Portable toilets will be staged onsite. Trash receptacles will be emptied
regularly.
13. Other areas or procedures where potential spills can occur – No other areas
qualify for this section.
C. Dryland Vegetation
i. All areas will be hardscaped, sodded, or mulched. Existing open areas have already
been seeded.
D. Detailed Sequence of Construction Activities
i. It is anticipated that this project will begin construction during 2016 and will be
completed within a year.
ii. Installation of site BMPs
1. Stabilized Construction Entrance
2. Silt Fence
3. Inlet protection on existing inlets
iii. Site Utility Installation
1. Installation of drainage facilities
2. Installation of inlet control/BMPs in new inlets and channels as they are finished
iv. Building Foundation and Earthwork
v. Vertical building construction and ongoing utilities
vi. Finished site grading, hardscaping and paving
vii. Landscaping and Irrigation installation
1. Seeding and mulching
2. Tree planting
3. Shrub planting
viii. Vegetative cover establishment period
ix. Removal of silt fence and inlet protection
x. BMPs will be inspected for effectiveness and maintained after each runoff event and
every 14 days at a minimum during construction.
E. Erosion Control Security Calculations
2133 TIMBERLINE - LOT 11
PROJECT ECR
Page 4 of 5
Project: Disturbed Acres: 1.31
EROSION CONTROL BMPs Units
Estimated
Quantity
Unit
Price
Total
Price
LF 440 $2.50 $1,100.00
EA 3 $150.00 $450.00
EA 1 $750.00 $750.00
EA 1 $1,100.00 $1,100.00
Sub-Total: $3,400.00
1.5 x Sub-Total: $5,100.00
Amount of security: $5,100.00
Total Acres x Price/acre: $1,299.99
$995.00 Sub-Total: $1,299.99
1.5 x Sub-Total: $1,949.98
Amount to Re-seed: $1,949.98
Minimum escrow amount: $3,000.00
Erosion Control Escrow: $5,100.00
Reseeding Amount
Miniumum Escrow Amount
Timberline Lot 11
Unit Price of Seeding per acre:
“The amount of the security must be based on one and one-half times the estimate of the cost to install the approved measures, or one and one-half times
the cost to re-vegetate the disturbed land to dry land grasses based upon unit cost determined by the City's Annual Revegetation and Stabilization Bid,
whichever is greater. In no instance, will the amount of security be less than one thousand five hundred dollars ($1,500) for residential development or three
thousand dollars ($3,000) for commercial development”
Inlet Protection (IP)
Concrete Washout (CW)
(add all other BMPs for the site in this list)
Final Escrow Amount
Example Erosion and Sediment Control Escrow/Security
Calculation for The City of Fort Collins
BMP Amount
Silt Fence (SF)
Vehicle Tracking Control (VTC)
SOUTH TIMBERLINE ROAD
FF= 4946.70
FND #4 REBAR
w/ RPC LS 37987,NE
DESIGN BY OTHER
(FOR REFERENCE ONLY)
FND #4 REBAR
FND #4 REBAR w/ RPC LS 33106,KSI
FND #4 REBAR w/ RPC LS 33106,KSI
w/ RPC LS 37987,NE
FND #4 REBAR
w/ RPC LS 34995,KSI
FND NAIL & SHINER
LS 34995,KSI
DESIGN BY OTHER
(FOR REFERENCE ONLY)
SF
SF
VTC
CIP3
EXISTING 8" WIDE
CONCRETE WALL
IP
IP
C301
6
EROSION CONTROL PLAN
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's
R
City of Fort Collins, Colorado
Date
Date
Date
Date
Date
Date
City Engineer
Traffic Engineer
Parks & Recreation
Stormwater Utility
Water & Wastewater Utility
SHEET NO.
15-01-29
PROJECT NO.
SHEET INDEX
DESIGNED BY:
DRAWN BY:
APPROVED BY:
SCALE:
SHEET SUBSET:
TIMBERLINE CENTER
SECOND FILING LOT 1 DATE:
NONE
December 21, 2015
K. Meyer
R. Bunner
K. Meyer
NOT FOR CONSTRUCTION
2133 TIMBERLINE - LOT 11
Appendix C Drainage Sub-Basins
BM 4-07
SOUTH TIMBERLINE ROAD
DESIGN BY OTHER
(FOR REFERENCE ONLY)
EXISTING 8" WIDE
MASONRY WALL
FF= 4946.70
3
2
C701
14
DRAINAGE EXHIBIT
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's
R
City of Fort Collins, Colorado
Date
Date
Date
Date
Date
Date
City Engineer
Traffic Engineer
Parks & Recreation
Stormwater Utility
Water & Wastewater Utility
SHEET NO.
15-01-29
PROJECT NO.
SHEET INDEX
DESIGNED BY:
DRAWN BY:
APPROVED BY:
SCALE:
SHEET SUBSET:
TIMBERLINE CENTER
SECOND FILING LOT 1 DATE:
NONE
December 21, 2015
K. Meyer
R. Bunner
K. Meyer
NOT FOR CONSTRUCTION
1"=30'
30' 0 30' 60' 90'
LEGEND:
NOTES:
A
A
FOR DRAINAGE REVIEW ONLY
NOT FOR CONSTRUCTION
1"=20'
20' 0 20' 40' 60'
LEGEND:
SF
VTC
NOTES:
IP