HomeMy WebLinkAboutSAINT JOHN XXIII CATHOLIC CHURCH AND LOMBARDY STUDENT HOUSING - PDP190001 - SUBMITTAL DOCUMENTS - ROUND 2 - EROSION CONTROL LETTER/REPORTErosion Control Review : Comments & Redlines Project Information Project Name: ______________________________ Project Number: ____________________ Prior Name(s): ______________________________ Prior Number(s): ______________________ Round _____ Date Submitted: _____________ Comment Due Date: _____________ Total Disturbance __________ SF GPS Lat _______________ GPS Long _______________ Sensitive Area _____ Steep Slopes (3H:1V) _____ Project Comments: Information Only: The site disturbs more than 10,000 sq. ft. and therefore Erosion and Sediment Control Materials need to be submitted. The erosion control requirements are located in the Stormwater Design Criteria in Chapter 2 Section 6.0 a copy of the requirements can be found at www.fcgov.com/erosion For Final: Please submit an Erosion Control Plans to meet City Criteria. For Final: Please resubmit an Erosion Control Report to meet City Criteria. Development Agreement: Please submit an Erosion Control Escrow / Security Calculation based upon the accepted Erosion Control Plans to meet City Criteria. Information only: Based upon the area of disturbance, State permits for stormwater will be required since the site is over an acre and should be pulled before Construction Activities begin. Other Comments: ____ Staff Dev Review Coordinator ______________ Zoning ______________ Planner ______________ Engineer______________ Water Utilities Reviewer ______________ Developing Party Owner ______________ Owner’s Company ____________ Developer ______________ Developer’s Company ____________ EC Design Engineer ______________ EC Design Firm ______________ Review Information Reviewer: _____________________ Received: _____________ Completed Review: __________ Cursory Review Time (hr.): __________ Full Review (hr.): __________ Phone Correspondence (hr.): __________ Email Correspondence (hr.): __________ Internal Staff Coordination (hr.): __________ Applicant Meeting (hr.): __________ Enter all hours round to the nearest 0.25 (15 min) B M VAULT F.O. VAULT ELEC TELE VAULT ELEC VAULT ELEC C VAULT ELEC VAULT ELEC ELEC C VAULT ELEC ELEC BRKR ELEC BRKR ELEC BRKR ELEC BRKR ELEC BRKR VAULT ELEC VAULT ELEC VAULT ELEC VAULT VAULT ELEC ELEC VAULT TELE VAULT ELEC CONTROL IRR CONTROL IRR CONTROL IRR VAULT F.O. T T T ELEC VAULT ELEC T ELEC ELEC CONTROL IRR M CONTROL IRR ELEC BRKR ELEC BRKR ELEC BRKR ELEC BRKR ELEC BRKR ELEC BRKR T ELEC BRKR ELEC BRKR ELEC BRKR ELEC BRKR ELEC BRKR ELEC BRKR ELEC BRKR ELEC T ELEC X X X ST ST ST ST ST ST UD UD UD UD UD UD UD UD UD UD UD UD UD UD UD UD UD UD D N UP UP X X X X X X X X X X X X X X X X X DN UP DN UP DN UP DN X TF TF TF TF X UNIVERSITY AVENUE UNIVERSITY AVENUE SOUTH SHIELDS STREET CITY PARK AVENUE WEST ELIZABETH STREET WEST ELIZABETH STREET NICOL CAMPUS WEST 1205 W. ELIZABETH ST. A NICOL CAMPUS WEST LIMITED 1213 W. ELIZABETH ST. GLEASON/WESTSIDE INVESTMENTS LLC 1301 W. ELIZABETH ST. JDH2 INVESTMENTS LLC 1305 W. ELIZABETH ST. PHILLIPS DAVID J LIVING TRUST (.615) 1335 W. ELIZABETH ST. 160 1221 W. ELIZABETH ST. 100-YR FLOODWAY (PER CSU CLOMR) 100-YR FLOODPLAIN (PER CSU CLOMR) CONNECT TO EXISTING STORM INLET EXISTING STORM DRAIN PROPOSED STORM DRAIN PROPOSED STORM DRAIN PROPOSED INLET PROPOSED INLET EXISTING CONCRETE PAN EXISTING PROPOSED CONCRETE PAN INLET PROPOSED INLET PROPOSED 2' SIDEWALK CULVERT PROPOSED 2' PROPOSED CONCRETE PAN STORMTECH CHAMBERS PROPOSED INLET EXISTING INLET PROPOSED AREA DRAIN BASIN PROPOSED AREA DRAIN BASIN PROPOSED UNDERDRAIN PROPOSED UNDERDRAINS PROPOSED UNDERDRAIN CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF CF 100-YR FLOODPLAIN (PER CSU CLOMR) 100-YR FLOODPLAIN (PER CSU CLOMR) PROPOSED AREA DRAIN BASIN PROPOSED 10' CONCRETE PAN VTC CWA CF WD RS PP IP IP IP IP IP IP IP IP IP IP CF CF CF CF IP RS RS RS RS RS BLDG A BLDG B BLDG C CHURCH BLDG SAINT JOHN XXIII AND LOMBARDY STUDENT HOUSING Sheet These drawings are instruments of service provided by Northern Engineering Services, Inc. and are not to be used for any type of construction unless signed and sealed by a Professional Engineer in the employ of Northern Engineering Services, Inc. NOT FOR CONSTRUCTION REVIEW SET E NGINEER ING N O R T H E RN FORT COLLINS: 301 North Howes Street, Suite 100, 80521 GREELEY: 820 8th Street, 80631 970.221.4158 northernengineering.com of 18 C700 EROSION CONTROL PLAN 15 NORTH ( IN FEET ) 1 inch = ft. 60 0 60 Feet 60 120 180 CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE, OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. CALL UTILITY NOTIFICATION CENTER OF COLORADO Know what'sbelow. Call before you dig. R TABLE OF CONSTRUCTION SEQUENCE AND BMP APPLICATION Project: Saint John XXIII and Lombardy Student Housing CONSTRUCTION PHASE MOBILIZATION DEMOLITION GRADING BEST MANAGEMENT PRACTICES (BMPS) Structural "Installation" Flow Barriers (Bales, Wattles, etc.) (RS) UTILITIES INSTALLATION FLAT WORK INSTALLATION VERTICAL INSTALLATION LANDSCAPE DEMOBILIZATION Concrete Washout Area (CWA) * All Temporary BMPs to be Removed once Construction is Complete Vehicle Tracking Pad * (VTC) Construction Fence (CF) NORTH 1. IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES ONLY AS A GUIDELINE TO THE CONTRACTOR. STAGING AND/OR PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED. ADDITIONAL AND/OR DIFFERENT BMPs FROM THOSE ORIGINALLY DEPICTED MAY BE NECESSARY DURING CONSTRUCTION DUE TO CHANGING SITE CONDITIONS OR AS REQUIRED BY LOCAL AUTHORITIES. 2. THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH, GRAPHICAL SYMBOLS MAY NOT BE TO SCALE, NOR ARE THEY NECESSARILY SHOWN IN THEIR EXACT LOCATION. 3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING (CITY, STATE DISCHARGE PERMIT, ETC.) AND COMPLIANCE WITH GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR (OR PERMIT HOLDER) TO ENSURE EROSION CONTROL MEASURES ARE PROPERLY MAINTAINED AND FOLLOWED. 4. CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION CONTROL MEASURES ACCORDING THE THE CONSTRUCTION SEQUENCING AND LEVEL OF SITE STABILIZATION. 5. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR ALL STORM DRAINS, SWALES, PONDS AND RAIN GARDENS UNTIL SITE IS FULLY STABILIZED. 6. CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR DOWNSPOUT CONNECTIONS, TO THE STORM DRAIN SYSTEM, UNTIL CONNECTION IS ESTABLISHED WITH DOWNSPOUT. 7. INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN WATTLES FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.) 8. CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES, PARTICULARLY THOSE STEEPER THAN 6:1. CRIMP MULCHING, HYDRO MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND ADDITIONAL WATTLES OR SILT FENCING MAY BE NECESSARY TO ESTABLISH VEGETATIVE COVER AND STABILIZE THE SLOPE. 9. CONTRACTOR IS RESPONSIBLE FOR PREVENTING SEDIMENT FROM UNSTABILIZED LANDSCAPE AREAS FROM MIGRATING ONTO AND ENTERING THE PERMEABLE PAVER SYSTEMS UNTIL UPGRADIENT TRIBUTARY AREAS ARE FULLY STABILIZED. 10. ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE NECESSARY TO ENSURE THAT EACH BUILDING PAD IS STABILIZED THROUGHOUT CONSTRUCTION. WATTLES SHALL BE PROVIDED AROUND BUILDING PAD SIDES TO ENSURE AT NO TIME SHALL SEDIMENT BE ALLOWED TO CROSS THE PUBLIC SIDEWALKS. 11. CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER PROTECTION FOR AREAS DIRECTING DRAINAGE OFFSITE. PERIMETER PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN SEDIMENT CONTROL LOGS OR SILT FENCE FOR BARE SOIL, GRAVEL SOCKS FOR PAVEMENT, ETC.) 12. FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED (100) FEET FROM NATURAL BODY OF WATER, WETLAND, NATURAL DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS AND FUELING AREA MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW A FUEL SPILL TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY. 13. CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE SANITATION UNITS (CONSTRUCTION TOILETS) SHALL BE LOCATED AT LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND, OR DRAINAGE WAY. SAID FACILITIES MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW POLLUTANTS TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE LOCATED ON FLAT, STABLE GROUND, AND CONSTRUCTION TOILETS SHALL BE STAKED DOWN. 14. THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE WITH THE CITY'S CONSTRUCTION INSPECTORS BY CEASING OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO CREATE BLOWING DUST WHICH, IN THE INSPECTOR'S OPINION, IS HAZARDOUS TO THE PUBLIC HEALTH AND WELFARE. 15. WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND WINTER MONTHS) INHIBIT PERMANENT SEEDING OPERATIONS, DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH TACKIFIER OR OTHER MATERIALS APPROVED BY EROSION CONTROL STAFF TO PREVENT EROSION. 16. CONTRACTOR SHALL EXERCISE CAUTION TO PROTECT RAIN GARDENS AND MODIFIED RAIN GARDEN FROM SEDIMENTATION. THIS INCLUDES EDUCATING SUBCONTRACTORS ON-SITE. 17. SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON PLANTING, REVEGETATION, HARDSCAPE AND OTHER PERMANENT SITE STABILIZATION METHODS. 18. DIRT AND DEBRIS FROM CONSTRUCTION ACTIVITIES TRACKED ON CITY STREETS SHALL BE KEPT TO A MINIMUM AND CLEANED NIGHTLY OR AT THE SUGGESTION OF THE CITY'S EROSION CONTROL INSPECTOR. 19. CONTRACTOR SHALL KEEP CONSTRUCTION VEHICLES ENTERING AND EXITING SITE TO A MINIMUM. 20. THE CONTRACTOR SHALL, AT ALL TIMES DURING AND AFTER SYSTEM INSTALLATION, PREVENT SEDIMENT, DEBRIS, AND DIRT FROM ANY SOURCE FROM ENTERING THE PERMEABLE PAVEMENT SYSTEM. LOOSE MATERIALS SHALL NOT BE STORED ON THE PERMEABLE PAVEMENT AREA. MUD AND SEDIMENT-LADEN RUNOFF SHOULD BE KEPT AWAY FROM THE PAVEMENT AREA. TEMPORARILY DIVERT RUNOFF OR INSTALL SEDIMENT CONTROL MEASURES AS NECESSARY TO REDUCE THE AMOUNT OF SEDIMENT RUN-ON TO THE PAVEMENT. SURFACE PROTECTION COULD INCLUDE COVERING AREAS OF THE PAVEMENT, PROVIDING ALTERNATIVE CONSTRUCTION VEHICLE ACCESS, AND PROVIDING EDUCATION TO ALL PARTIES WORKING ONSITE. EROSION CONTROL NOTES: BENCHMARK NOTE: ALL BMPS SHOWN ON THIS PLAN ARE GRAPHIC REPRESENTATIONS ONLY. FINAL DETERMINATION OF SIZE AND LOCATION SHALL BE DETERMINED BY THE CONTRACTOR AND DOCUMENTED ON THE DYNAMIC SITE PLAN. 1. CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY CRIMP MULCHING OR SIMILAR METHODS. 2. TOTAL DISTURBED AREA = 5.56 ACRES 3. SWMP ADMINISTRATOR: Contact ________________________________ Company ________________________________ Address ________________________________ Phone________________________________ 4. CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE WASHOUT AREA IF ACCESS IS OFF PAVEMENT. 5. REFER TO THE PRELIMINARY DRAINAGE REPORT FOR SAINT JOHN XXIII AND LOMBARDY STUDENT HOUSING, DATED FEBRUARY 6, 2019, BY NORTHERN ENGINEERING, FOR ADDITIONAL INFORMATION. 6. FOR ADDITIONAL INFORMATION SEE SEPARATE STORMWATER MANAGEMENT PLAN / EROSION CONTROL REPORT FOR SAINT JOHN XXIII AND LOMBARDY STUDENT HOUSING. 7. CONTRACTOR SHALL INSTALL PAVERS AS LATE AS FEASIBLE IN THE CONSTRUCTION PROCESS AND SHALL PROTECT IN PLACE ONCE INSTALLED TO PREVENT SEDIMENT LOADING OF THIS DRAINAGE FACILITY DURING CONSTRUCTION. GENERAL NOTES: LEGEND: PROPOSED CONTOUR PROPOSED STORM SEWER PROPOSED SWALE EXISTING CONTOUR PROPOSED CURB & GUTTER PROPERTY BOUNDARY PROPOSED INLET VEHICLE TRACKING CONTROL PAD CONSTRUCTION FENCE w/ ROCK SOCK CF CONCRETE WASHOUT ROCK SOCK CWA RS VTC CF WATTLE DIKE WD INLET PROTECTION IP PAVER PROTECTION PP PROJECT DATUM: NAVD88 CITY OF FORT COLLINS BENCHMARK 20-97 AT THE SOUTHWEST CORNER OF WEST ELIZABETH AND CONSTITUTION AVE. ON A CONCRETE TRAFFIC SIGNAL BASE. ELEV.= 5050.15 CITY OF FORT COLLINS BENCHMARK 19-97 AT THE SOUTHEAST CORNER OF WEST ELIZABETH AND SHIELDS ST., ON A CONCRETE TRAFFIC SIGNAL BASE. ELEV.= 5025.74 PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) FOR THEIR VERTICAL DATUMS. IF NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) IS REQUIRED FOR ANY PURPOSE, THE FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED DATUM (PRIOR CITY OF FORT COLLINS DATUM) = NAVD88 - 3.18' BASIS OF BEARINGS THE BASIS OF BEARINGS IS THE EAST LINE OF THE SOUTHEAST QUARTER OF SECTION 15-7-69 AS BEARING SOUTH 00° 29' 45" WEST (ASSUMED BEARING).