PRELIMINARY DRAINAGE AND
EROSION CONTROL REPORT FOR
River District Block 8 Mixed Use
Fort Collins, Colorado
Prepared for:
Blue Ocean Enterprises
401 West Mountain Ave.
Fort Collins, CO 80521
Prepared by:
200 South College Avenue, Suite 10
Fort Collins, Colorado 80524
Phone: 970.221.4158 Fax: 970.221.4159
www.northernengineering.com
Project Number: 838-013
This Drainage Report is consciously provided as a PDF.
Please consider the environment before printing this document in its entirety.
When a hard copy is absolutely necessary, we recommend double-sided printing.
December 2, 2015
City of Fort Collins
Stormwater Utility
700 Wood Street
Fort Collins, Colorado 80521
RE: Preliminary Drainage and Erosion Control Report for
River District Block 8 Mixed Use
Dear Staff:
Northern Engineering is pleased to submit this Preliminary Drainage and Erosion Control Report
for your review. This report accompanies the Project Development Plan submittal for the
proposed River District Block 8 Mixed Use development.
This report has been prepared in accordance to Fort Collins Stormwater Criteria Manual (FCSCM),
and serves to document the stormwater impacts associated with the proposed project. We
understand that review by the City is to assure general compliance with standardized criteria
contained in the FCSCM.
If you should have any questions as you review this report, please feel free to contact us.
Sincerely,
NORTHERN ENGINEERING SERVICES, INC.
Aaron Cvar, PhD, PE
Senior Project Engineer
River District Block 8 Mixed Use
Preliminary Drainage Report
TABLE OF CONTENTS
I. GENERAL LOCATION AND DESCRIPTION ................................................................... 1
A. Location ............................................................................................................................................. 1
B. Description of Property ..................................................................................................................... 1
C. Floodplain.......................................................................................................................................... 4
II. DRAINAGE BASINS AND SUB-BASINS ....................................................................... 4
A. Major Basin Description .................................................................................................................... 4
B. Sub-Basin Description ....................................................................................................................... 4
III. DRAINAGE DESIGN CRITERIA ................................................................................... 5
A. Regulations........................................................................................................................................ 5
B. Four Step Process .............................................................................................................................. 5
C. Development Criteria Reference and Constraints ............................................................................ 5
D. Hydrological Criteria ......................................................................................................................... 6
E. Hydraulic Criteria .............................................................................................................................. 6
F. Modifications of Criteria ................................................................................................................... 6
IV. DRAINAGE FACILITY DESIGN .................................................................................... 6
A. General Concept ............................................................................................................................... 6
B. Specific Details .................................................................................................................................. 7
V. CONCLUSIONS ........................................................................................................ 8
A. Compliance with Standards .............................................................................................................. 8
B. Drainage Concept .............................................................................................................................. 8
References ......................................................................................................................... 9
APPENDICES:
APPENDIX A – Hydrologic Computations
APPENDIX B – Erosion Control Report
APPENDIX C – Reference Material – Selected Portions of the Downtown River District
Improvement Plans (February 2012)
River District Block 8 Mixed Use
Preliminary Drainage Report
LIST OF TABLES AND FIGURES:
Figure 1 – Aerial Photograph ................................................................................................ 2
Figure 2– Proposed Site Plan ................................................................................................ 3
Figure 3 – Existing Floodplains ............................................................................................. 4
MAP POCKET:
Proposed Drainage Exhibit
River District Block 8 Mixed Use
Preliminary Drainage Report 1
I. GENERAL LOCATION AND DESCRIPTION
A. Location
1. Vicinity Map
2. The project site is located in the west quarter of Section 12, Township 7 North,
Range 69 West of the 6th Principal Meridian, City of Fort Collins, County of Larimer,
State of Colorado.
3. The proposed development site is situated along the south side of Willow Street, just
southeast of the intersection of Linden Street and Willow Street.
4. The proposed development site is in the City of Fort Collins Old town Basin. Typical
detention requirements for this basin are to detain the difference between the 100-
year developed inflow rate and the historic 2-year release rate. However, the
Downtown River District Improvement Project, which includes a new storm main in
Willow Street, will allow for the site to release undetained into this new public storm
main. Details of this new storm main are discussed further below.
5. The project site is located within existing downtown development, and is surrounded
by existing businesses. The existing Ranchway Feeds site is located on the north side
of Willow Street, directly across from the proposed development site.
6. Minimal offsite flows from the west and south are received by the project site.
Existing drainage systems in Linden Street and Willow Street convey the majority of
offsite drainage approaching the site.
B. Description of Property
1. The development area is roughly 1.24 net acres, as identified on the Drainage Exhibit.
River District Block 8 Mixed Use
Preliminary Drainage Report 2
Figure 1 – Aerial Photograph
2. The subject property is currently undeveloped ground. The ground cover generally
consists of gravel surfacing. Existing ground slopes are mild to moderate (i.e., 1 -
6±%) through the interior of the property. General topography slopes from southwest
to northeast.
3. According to the United States Department of Agriculture (USDA) Natural Resources
Conservation Service (NRCS) Soil Survey website:
http://websoilsurvey.nrcs.usda.gov/app/WebSoilSurvey.aspx,
the site consists of Paoli Fine Sandy Loam (Hydrologic Soil Group B).
4. The proposed project site plan is composed of the development of a distillery and
restaurant. Associated roadways, water and sewer lines will be constructed with the
development.
River District Block 8 Mixed Use
Preliminary Drainage Report 3
Figure 2– Proposed Site Plan
5. The Cache La Poudre river is located just north of the proposed development site.
6. The proposed land use is Commerical.
River District Block 8 Mixed Use
Preliminary Drainage Report 4
C. Floodplain
Figure 3 –Area Floodplain Mapping
1. No portion of the subject property is encroached by the adjacent FEMA 100-year
floodplain (Cache La Poudre River located just north of the site).
II. DRAINAGE BASINS AND SUB-BASINS
A. Major Basin Description
2. The proposed development site is in the City of Fort Collins Old Town Basin. Typical
detention requirements for this basin are to detain the difference between the 100-
year developed inflow rate and the historic 2-year release rate. However, the
Downtown River District Improvement Project Plans (Please see Appendix C), provide
a storm system in Willow Street which will serve as an outfall for the entire site. This
public storm main has been designed to convey fully developed undetained flows from
the project site, as well as other areas of the Downtown River District southeast to the
Udall regional water quality pond. The storm main is slated to begin construction
January 2016.
B. Sub-Basin Description
3. The subject property historically drains overland from southwest to northeast. An
existing area inlet in Willow Street captures runoff within the curb and gutter of
Willow. Stormwater is then conveyed via the existing storm pipe in Willow north to
the Cache La Poudre River. A more detailed description of the project drainage
patterns follows in Section IV.A.4., below.
River District Block 8 Mixed Use
Preliminary Drainage Report 5
III. DRAINAGE DESIGN CRITERIA
A. Regulations
There are no optional provisions outside of the FCSCM proposed with the proposed
project.
B. Four Step Process
The overall stormwater management strategy employed with the proposed project utilizes
the “Four Step Process” to minimize adverse impacts of urbanization on receiving waters.
The following is a description of how the proposed development has incorporated each
step.
Step 1 – Employ Runoff Reduction Practices
Several techniques have been utilized with the proposed development to facilitate the
reduction of runoff peaks, volumes, and pollutant loads as the site is developed from the
current use by implementing multiple Low Impact Development (LID) strategies including:
Conserving existing amenities in the site including the existing vegetated areas.
Providing small pockets of vegetated open areas as much as possible throughout the
site to reduce the overall impervious area and to minimize directly connected
impervious areas (MDCIA).
Step 2 – Implement BMPs That Provide a Water Quality Capture Volume (WQCV) with
Slow Release
The efforts taken in Step 1 will facilitate the reduction of runoff; however, urban
development of this intensity will still generate stormwater runoff that will require
additional BMPs and water quality. The majority of stormwater runoff from the site will by
onsite LID features as discussed below.
Step 3 – Stabilize Drainageways
There are no major drainageways within the subject property. While this step may not
seem applicable to proposed development, the project indirectly helps achieve stabilized
drainageways nonetheless. By providing water quality where none previously existed,
sediment with erosion potential is removed from the downstream drainageway systems.
Furthermore, this project will pay one-time stormwater development fees, as well as
ongoing monthly stormwater utility fees, both of which help achieve City-wide drainageway
stability.
Step 4 – Implement Site Specific and Other Source Control BMPs.
The proposed project will improve upon site specific source controls compared to historic
conditions:
The proposed development will eliminate sources of potential pollution previously left
exposed to weathering and runoff processes.
C. Development Criteria Reference and Constraints
The subject property is surrounded by currently developed properties. Thus, several
constraints have been identified during the course of this analysis that will impact the
proposed drainage system including:
Existing elevations along the property lines will generally be maintained.
As previously mentioned, overall drainage patterns of the existing site will be
maintained.
River District Block 8 Mixed Use
Preliminary Drainage Report 6
Elevations of existing downstream facilities that the subject property will release to
will be maintained.
D. Hydrological Criteria
1. The City of Fort Collins Rainfall Intensity-Duration-Frequency Curves, as depicted in
Figure RA-16 of the FCSCM, serve as the source for all hydrologic computations
associated with the proposed development. Tabulated data contained in Table RA-7
has been utilized for Rational Method runoff calculations.
2. The Rational Method has been employed to compute stormwater runoff utilizing
coefficients contained in Tables RO-11 and RO-12 of the FCSCM.
3. Three separate design storms have been utilized to address distinct drainage
scenarios. A fourth design storm has also been computed for comparison purposes.
The first design storm considered is the 80th percentile rain event, which has been
employed to design the project’s water quality features. The second event analyzed is
the “Minor,” or “Initial” Storm, which has a 2-year recurrence interval. The third
event considered is the “Major Storm,” which has a 100-year recurrence interval.
The fourth storm computed, for comparison purposes only, is the 10-year event.
4. No other assumptions or calculation methods have been used with this development
that are not referenced by current City of Fort Collins criteria.
E. Hydraulic Criteria
1. As previously noted, the subject property maintains historic drainage patterns.
2. All drainage facilities proposed with the project are designed in accordance with
criteria outlined in the FCSCM and/or the Urban Drainage and Flood Control District
(UDFCD) Urban Storm Drainage Criteria Manual.
3. As stated above, no portion of the subject property is located in a FEMA regulatory
floodplain or floodway.
4. The proposed project does not propose to modify any natural drainageways.
F. Modifications of Criteria
1. The proposed development is not requesting any modifications to criteria at this time.
IV. DRAINAGE FACILITY DESIGN
A. General Concept
1. The main objectives of the project drainage design are to maintain existing drainage
patterns, and to ensure no adverse impacts to any adjacent properties.
2. The Downtown River District Improvement Project Plans (Please see Appendix C),
provide a storm system in Willow Street which will serve as an outfall for the entire
site. This public storm main has been designed to convey fully developed undetained
flows from the project site, as well as other areas of the Downtown River District
southeast to the Udall regional water quality pond. Because of this detention and
quantity treatment (extended detention) is not required for the site. The new storm
main is slated for a beginning construction date of January 2016.
River District Block 8 Mixed Use
Preliminary Drainage Report 7
3. The drainage patterns anticipated for proposed drainage basins are described below.
Basin 1
Basins 1 consists of rooftop area and parking/drive area. A permeable paver system
will intercept a portion of the flows from Basin 1. Inlets as well as the subdrain
system for the pavers will be designed at Final within the parking area which will fully
capture and direct 100-year flows into the new storm main in Willow Street.
Basin OS1
Basin OS1 consists of a portion of the rooftop of an adjacent building to the southwest
and a small strip of ground between this building and the proposed development site.
A portion of the runoff from this basin will infiltrate in the proposed permeable paver
system to be placed along the south side of the proposed building. The remainder of
flows will be routed via surface flow into the parking/drive area near the entry point
along Willow Street.
A full-size copy of the Drainage Exhibit can be found in the Map Pocket at the end of
this report.
B. Specific Details
1. Detention and water quality treatment in the form of extended is not required
due to the Downtown River District Improvement Project Plans as discussed
above.
2. LID features will be further detailed at Final Design. Table 2, below, provides
preliminary areas of permeable pavers and traditional pavement. These areas
represent the current preliminary design, and may change at Final; however,
we will meet or exceed the requirement of 25% of paved surfaces to be
constructed as permeable paved surfaces at Final design. In addition to
permeable pavers, tree wells will be placed along the north side of the
proposed building. Building roof drains will be designed to tie to these tree
wells, allowing for filtration of rooftop runoff and enhancement of water
quality. Details of the tree wells and the roof drain system will be provided at
Final design.
TABLE 2 – Preliminary Pavement LID Summary
Pavement
Area
(sq.ft.) LID ? Percent
Traditional
Concrete/Asphalt
8,760 no 72%
Permeable Pavers 3,450 yes 28%
Totals 12,210 - 100%
1. Represents "new/additional" pavement beyond the existing
condition.
River District Block 8 Mixed Use
Preliminary Drainage Report 8
3. Standard Operating Procedures (SOP) Manual will be provided by the City of
Fort Collins in the Development Agreement.
4. The drainage features associated with the proposed project are all private facilities,
located on private property.
V. CONCLUSIONS
A. Compliance with Standards
1. The drainage design proposed with the proposed project complies with the City of Fort
Collins’ Stormwater Criteria Manual.
2. The drainage design proposed with this project complies with the Old Town Master
Plan.
3. The drainage plan and stormwater management measures proposed with the
proposed development are compliant with all applicable State and Federal regulations
governing stormwater discharge.
B. Drainage Concept
1. The drainage design proposed with this project will effectively limit any potential
damage associated with its stormwater runoff by directing developed flows into the
new public storm main in Willow Street.
2. The drainage concept for the proposed development is consistent with the Old Town
Master Plan.
River District Block 8 Mixed Use
Preliminary Drainage Report 9
References
1. Fort Collins Stormwater Criteria Manual, City of Fort Collins, Colorado, as adopted by Ordinance No.
174, 2011, and referenced in Section 26-500 (c) of the City of Fort Collins Municipal Code.
2. Larimer County Urban Area Street Standards, Adopted January 2, 2001, Repealed and
Reenacted, Effective October 1, 2002, Repealed and Reenacted, Effective April 1, 2007.
3. Soils Resource Report for Larimer County Area, Colorado, Natural Resources Conservation
Service, United States Department of Agriculture.
4. Urban Storm Drainage Criteria Manual, Volumes 1-3, Urban Drainage and Flood Control
District, Wright-McLaughlin Engineers, Denver, Colorado, Revised April 2008.
APPENDIX A
HYDROLOGIC COMPUTATIONS
CHARACTER OF SURFACE:
Runoff
Coefficient
Percentage
Impervious Project: 838-013
Streets, Parking Lots, Roofs, Alleys, and Drives: Calculations By: ATC
Asphalt ……....……………...……….....…...……………….………………………………… 0.95 100% Date:
Concrete …….......……………….….……….………………..….…………………………… 0.95 90%
Gravel ……….…………………….….…………………………..…………………………… 0.50 40%
Roofs …….…….………………..……………….……………………………………………. 0.95 90%
Pavers…………………………...………………..……………………………………………. 0.40 22%
Lawns and Landscaping
Sandy Soil ……..……………..……………….…………………………………………….. 0.15 0%
Clayey Soil ….….………….…….…………..………………………………………………. 0.25 0% 2-year Cf
= 1.00 100-year Cf = 1.25
Basin ID
Basin Area
(s.f.)
Basin Area
(ac)
Area of
Asphalt
(ac)
Area of
Concrete
(ac)
Area of
Roofs
(ac)
Area of
Gravel
(ac)
Area of
Lawns and
Landscaping
(ac)
2-year
Composite
Runoff
Coefficient
10-year
Composite
Runoff
Coefficient
100-year
Composite
Runoff
Coefficient
Composite
% Imperv.
H1 53806 1.24 0.000 0.000 0.000 1.235 0.000 0.50 0.50 0.63 40%
HISTORIC COMPOSITE % IMPERVIOUSNESS AND RUNOFF COEFFICIENT CALCULATIONS
Runoff Coefficients are taken from the City of Fort Collins Storm Drainage Design Criteria and Construction Standards, Table 3-3. % Impervious taken from UDFCD USDCM, Volume I.
10-year Cf = 1.00
9/15/2014
Overland Flow, Time of Concentration:
Project: 838-013
Calculations By:
Date:
Gutter/Swale Flow, Time of Concentration:
Tt = L / 60V
Tc = Ti + Tt (Equation RO-2)
Velocity (Gutter Flow), V = 20·S½
Velocity (Swale Flow), V = 15·S½
NOTE: C-value for overland flows over grassy surfaces; C = 0.25
Is Length
>500' ?
C*Cf
(2-yr
Cf=1.00)
C*Cf
(10-yr
Cf=1.00)
C*Cf
(100-yr
Cf=1.25)
Length,
L
(ft)
Slope,
S
(%)
Ti
2-yr
(min)
Ti
10-yr
(min)
Ti
100-yr
(min)
Length,
L
(ft)
Slope,
S
(%)
Velocity,
V
(ft/s)
Tt
(min)
Length,
L
(ft)
Slope,
S
(%)
Velocity,
V
(ft/s)
Tt
(min)
2-yr
Tc
Rational Method Equation: Project: 838-013
Calculations By:
Date:
From Section 3.2.1 of the CFCSDDC
Rainfall Intensity:
H1 H1 1.24 17 17 14 0.50 0.50 0.63 1.78 3.04 6.71 1.1 1.9 5.2
Intensity,
i10
(in/hr)
Rainfall Intensity taken from the City of Fort Collins Storm Drainage Design Criteria (CFCSDDC), Figure 3.1
C10
Area, A
(acres)
Intensity,
i2
(in/hr)
100-yr
Tc
(min)
HISTORIC RUNOFF COMPUTATIONS
C100
Design
Point
Flow,
Q100
(cfs)
Flow,
Q2
(cfs)
10-yr
Tc
(min)
2-yr
Tc
(min)
C2
Flow,
Q10
(cfs)
Intensity,
i100
(in/hr)
Basin(s)
ATC
9/15/2014
Q C f C i A
CHARACTER OF SURFACE:
Runoff
Coefficient
Percentage
Impervious Project: 838-013
Streets, Parking Lots, Roofs, Alleys, and Drives: Calculations By: ATC
Asphalt ……....……………...……….....…...……………….………………………………… 0.95 100% Date:
Concrete …….......……………….….……….………………..….…………………………… 0.95 90%
Gravel ……….…………………….….…………………………..…………………………… 0.50 40%
Roofs …….…….………………..……………….……………………………………………. 0.95 90%
Pavers…………………………...………………..……………………………………………. 0.40 22%
Lawns and Landscaping
Sandy Soil ……..……………..……………….…………………………………………….. 0.15 0%
Clayey Soil ….….………….…….…………..………………………………………………. 0.25 0% 2-year Cf
= 1.00 100-year Cf = 1.25
Basin ID
Basin Area
(s.f.)
Basin Area
(ac)
Area of
Asphalt
(ac)
Area of
Concrete
(ac)
Area of
Roofs
(ac)
Area of
Gravel
(ac)
Area of
Lawns and
Landscaping
(ac)
2-year
Composite
Runoff
Coefficient
10-year
Composite
Runoff
Coefficient
100-year
Composite
Runoff
Coefficient
Composite
% Imperv.
1 53806 1.24 Note: For preliminary calculations, Composite Runoff Coefficients are 0.95 0.95 1.00 90%
OS1 5564 0.13 based on an assumed imperviousness of 90% and COFC Storm Drainage 0.95 0.95 1.00 90%
Design Criteria Table 3-3
DEVELOPED COMPOSITE % IMPERVIOUSNESS AND RUNOFF COEFFICIENT CALCULATIONS
Runoff Coefficients are taken from the City of Fort Collins Storm Drainage Design Criteria and Construction Standards, Table 3-3. % Impervious taken from UDFCD USDCM, Volume I.
10-year Cf = 1.00
11/1/2014
Overland Flow, Time of Concentration:
Project: 838-013
Calculations By:
Date:
Gutter/Swale Flow, Time of Concentration:
Tt = L / 60V
Tc = Ti + Tt (Equation RO-2)
Velocity (Gutter Flow), V = 20·S½
Velocity (Swale Flow), V = 15·S½
NOTE: C-value for overland flows over grassy surfaces; C = 0.25
Is Length
>500' ?
C*Cf
(2-yr
Cf=1.00)
C*Cf
(10-yr
Cf=1.00)
C*Cf
(100-yr
Cf=1.25)
Length,
L
(ft)
Slope,
S
(%)
Ti
2-yr
(min)
Ti
10-yr
(min)
Ti
100-yr
(min)
Length,
L
(ft)
Slope,
S
(%)
Velocity,
V
(ft/s)
Tt
(min)
Length,
L
(ft)
Slope,
S
(%)
Velocity,
V
(ft/s)
Tt
(min)
2-yr
Tc
Rational Method Equation: Project: 838-013
Calculations By:
Date:
From Section 3.2.1 of the CFCSDDC
Rainfall Intensity:
1 1 1.24 7 7 6 0.95 0.95 1.00 2.60 4.44 9.63 3.0 5.2 11.9
OS1 OS1 0.13 5 5 5 0.95 0.95 1.00 2.85 4.87 9.95 0.3 0.6 1.3
Area, A
(acres)
Intensity,
i2
(in/hr)
100-yr
Tc
(min)
DEVELOPED RUNOFF COMPUTATIONS
C100
Design
Point
Flow,
Q100
(cfs)
Flow,
Q2
(cfs)
10-yr
Tc
(min)
2-yr
Tc
(min)
C2
Flow,
Q10
(cfs)
Intensity,
i100
(in/hr)
Basin(s)
ATC
11/1/2014
Intensity,
i10
(in/hr)
Rainfall Intensity taken from the City of Fort Collins Storm Drainage Design Criteria (CFCSDDC), Figure 3.1
C10
Q C f C i A
40
Table RO-10
Rational Method Minor Storm Runoff Coefficients for Zoning Classifications
Description of Area or Zoning Coefficient
R-F 0.3
U-E 0.3
L-M-In 0.55
R-L, N-C-L 0.6
M-M-N, N-C-M 0.65
N-C-B 0.7
Business:
C-C-N, C-C-R, C-N, N-C, C-S 0.95
R-D-R, C-C, C-L 0.95
D, C 0.95
H-C 0.95
C-S 0.95
Industrial:
E 0.85
I 0.95
Undeveloped:
R-C, T 0.2
P-O-L 0.25
For guidance regarding zoning districts and classifications of such districts please refer to
Article Four of the City Land Use Code, as amended.
41
Table RO-11
Rational Method Runoff Coefficients for Composite Analysis
Character of Surface Runoff Coefficient
Streets, Parking Lots,
Drives:
Asphalt 0.95
Concrete 0.95
Gravel 0.5
Roofs 0.95
Recycled Asphalt 0.8
Lawns, Sandy Soil:
Flat <2% 0.1
Average 2 to 7% 0.15
Steep >7% 0.2
Lawns, Heavy Soil:
Flat <2% 0.2
Average 2 to 7% 0.25
Steep >7% 0.35
(4) A new Section 2.9 is added, to read as follows:
2.9 Composite Runoff Coefficient
Drainage sub-basins are frequently composed of land that has multiple surfaces or zoning
classifications. In such cases a composite runoff coefficient must be calculated for any
given drainage sub-basin.
The composite runoff coefficient is obtained using the following formula:
( )
t
n
i
i i
A
C A
C
∑
= = 1
*
(RO-8)
Where: C = Composite Runoff Coefficient
Ci = Runoff Coefficient for Specific Area (Ai)
Ai = Area of Surface with Runoff Coefficient of Ci, acres or feet2
n = Number of different surfaces to be considered
At = Total Area over which C is applicable, acres or feet2
(5) A new Section 2.10 is added, to read as follows:
42
2.10 Runoff Coefficient Adjustment for Infrequent Storms
The runoff coefficients provided in tables RO-10 and RO-11 are appropriate for use with
the 2-year storm event. For storms with higher intensities, an adjustment of the runoff
coefficient is required due to the lessening amount of infiltration, depression retention,
evapo-transpiration and other losses that have a proportionally smaller effect on storm
runoff. This adjustment is applied to the composite runoff coefficient.
These frequency adjustment factors are found in Table RO-12.
Table RO-12
Rational Method Runoff Coefficients for Composite Analysis
Storm Return Period
(years)
Frequency Factor
Cf
2 to 10
11 to 25
26 to 50
51 to 100
1.00
1.10
1.20
1.25
Note: The product of C times Cf cannot exceed the value of 1, in the cases where it does a value of
1 must be used
(6) Section 3.1 is deleted in its entirety.
(7) Section 3.2 is deleted in its entirety.
(8) Section 3.3 is deleted in its entirety.
(9) A new Section 4.3 is added, to read as follows:
4.3 Computer Modeling Practices
(a) For circumstances requiring computer modeling, the design storm hydrographs must
be determined using the Stormwater Management Model (SWMM). Basin and
conveyance element parameters must be computed based on the physical characteristics
of the site.
(b) Refer to the SWMM Users’ Manual for appropriate modeling methodology, practices
and development. The Users’ Manual can be found on the Environmental Protection
Agency (EPA) website (http://www.epa.gov/ednnrmrl/models/swmm/index.htm).
(c) It is the responsibility of the design engineer to verify that all of the models used in
the design meet all current City criteria and regulations.
4.3.1 Surface Storage, Resistance Factors, and Infiltration
Table RO-13 provides values for surface storage for pervious and impervious surfaces
and the infiltration rates to be used with SWMM. Table RO-13 also lists the appropriate
infiltration decay rate, zero detention depth and resistance factors, or Manning’s “n”
values, for pervious and impervious surfaces to be used for SWMM modeling in the city
of Fort Collins.
33
(11) Section 4.0 is amended to read as follows:
4.0 Intensity-Duration-Frequency Curves for Rational Method:
The one-hour rainfall Intensity-Duration-Frequency tables for use the Rational Method
of runoff analysis are provided in Table RA-7 and in Table RA-8.
Table RA-7 -- City of Fort Collins
Rainfall Intensity-Duration-Frequency Table
for Use with the Rational Method
(5 minutes to 30 minutes)
2-Year 10-Year 100-Year
Duration
(min)
Intensity
(in/hr)
Intensity
(in/hr)
Intensity
(in/hr)
5 2.85 4.87 9.95
6 2.67 4.56 9.31
7 2.52 4.31 8.8
8 2.4 4.1 8.38
9 2.3 3.93 8.03
10 2.21 3.78 7.72
11 2.13 3.63 7.42
12 2.05 3.5 7.16
13 1.98 3.39 6.92
14 1.92 3.29 6.71
15 1.87 3.19 6.52
16 1.81 3.08 6.3
17 1.75 2.99 6.1
18 1.7 2.9 5.92
19 1.65 2.82 5.75
20 1.61 2.74 5.6
21 1.56 2.67 5.46
22 1.53 2.61 5.32
23 1.49 2.55 5.2
24 1.46 2.49 5.09
25 1.43 2.44 4.98
26 1.4 2.39 4.87
27 1.37 2.34 4.78
28 1.34 2.29 4.69
29 1.32 2.25 4.6
30 1.3 2.21 4.52
34
Table RA-8 -- City of Fort Collins
Rainfall Intensity-Duration-Frequency Table
for Use with the Rational Method
(31 minutes to 60 minutes)
2-Year 10-Year 100-Year
Duration
(min)
Intensity
(in/hr)
Intensity
(in/hr)
Intensity
(in/hr)
31 1.27 2.16 4.42
32 1.24 2.12 4.33
33 1.22 2.08 4.24
34 1.19 2.04 4.16
35 1.17 2.0 4.08
36 1.15 1.96 4.01
37 1.16 1.93 3.93
38 1.11 1.89 3.87
39 1.09 1.86 3.8
40 1.07 1.83 3.74
41 1.05 1.8 3.68
42 1.04 1.77 3.62
43 1.02 1.74 3.56
44 1.01 1.72 3.51
45 0.99 1.69 3.46
46 0.98 1.67 3.41
47 0.96 1.64 3.36
48 0.95 1.62 3.31
49 0.94 1.6 3.27
50 0.92 1.58 3.23
51 0.91 1.56 3.18
52 0.9 1.54 3.14
53 0.89 1.52 3.1
54 0.88 1.5 3.07
55 0.87 1.48 3.03
56 0.86 1.47 2.99
57 0.85 1.45 2.96
58 0.84 1.43 2.92
59 0.83 1.42 2.89
60 0.82 1.4 2.86
35
(12) A new Section 4.1 is added, to read as follows:
4.1 Intensity-Duration-Frequency Curves for SWMM:
The hyetograph input option must be selected when creating SWMM input files.
Hyetographs for the 2-, 5-, 10-, 25-, 50-, and 100-year City of Fort Collins rainfall events
are provided in Table RA-9.
Table RA-9 – City of Fort Collins
Rainfall Intensity-Duration-Frequency Table
for Use with SWMM
2-Year 5-Year 10-Year 25-Year 50-Year 100-Year
Duration
(min)
Intensity
(in/hr)
Intensity
(in/hr)
Intensity
(in/hr)
Intensity
(in/hr)
Intensity
(in/hr)
Intensity
(in/hr)
5 0.29 0.40 0.49 0.63 0.79 1.00
10 0.33 0.45 0.56 0.72 0.90 1.14
15 0.38 0.53 0.65 0.84 1.05 1.33
20 0.64 0.89 1.09 1.41 1.77 2.23
25 0.81 1.13 1.39 1.80 2.25 2.84
30 1.57 2.19 2.69 3.48 4.36 5.49
35 2.85 3.97 4.87 6.30 7.90 9.95
40 1.18 1.64 2.02 2.61 3.27 4.12
45 0.71 0.99 1.21 1.57 1.97 2.48
50 0.42 0.58 0.71 0.92 1.16 1.46
55 0.35 0.49 0.60 0.77 0.97 1.22
60 0.30 0.42 0.52 0.67 0.84 1.06
65 0.20 0.28 0.39 0.62 0.79 1.00
70 0.19 0.27 0.37 0.59 0.75 0.95
75 0.18 0.25 0.35 0.56 0.72 0.91
80 0.17 0.24 0.34 0.54 0.69 0.87
85 0.17 0.23 0.32 0.52 0.66 0.84
90 0.16 0.22 0.31 0.50 0.64 0.81
95 0.15 0.21 0.30 0.48 0.62 0.78
100 0.15 0.20 0.29 0.47 0.60 0.75
105 0.14 0.19 0.28 0.45 0.58 0.73
110 0.14 0.19 0.27 0.44 0.56 0.71
115 0.13 0.18 0.26 0.42 0.54 0.69
120 0.13 0.18 0.25 0.41 0.53 0.67
36
RAINFALL INTENSITY-DURATION-FREQUENCY CURVE
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00
STORM DURATION (minutes)
RAINFALL INTENSITY (inches/hour)
2-Year Storm 10-Year Storm 100-Year Storm
Figure RA-16 City of Fort Collins Rainfall Intensity-Duration-Frequency Curves
(13) Section 5.0 is deleted in its entirety.
(14) Section 6.0 is deleted in its entirety.
(15) Section 7.0 is deleted in its entirety.
(16) Section 7.1 is deleted in its entirety.
(17) Section 7.2 is deleted in its entirety.
(18) Section 7.3 is deleted in its entirety.
(19) Section 8.0 is deleted in its entirety.
(20) Table RA-1 is deleted in its entirety.
DRAINAGE CRITERIA MANUAL (V. 1) RUNOFF
Table RO-3—Recommended Percentage Imperviousness Values
Land Use or
Surface Characteristics
Percentage
Imperviousness
Business:
Commercial areas 95
Neighborhood areas 85
Residential:
Single-family *
Multi-unit (detached) 60
Multi-unit (attached) 75
Half-acre lot or larger *
Apartments 80
Industrial:
Light areas 80
Heavy areas 90
Parks, cemeteries 5
Playgrounds 10
Schools 50
Railroad yard areas 15
Undeveloped Areas:
Historic flow analysis 2
Greenbelts, agricultural 2
Off-site flow analysis
(when land use not defined)
45
Streets:
Paved 100
Gravel (packed) 40
Drive and walks 90
Roofs 90
Lawns, sandy soil 0
Lawns, clayey soil 0
* See Figures RO-3 through RO-5 for percentage imperviousness.
C A = K A + ( 1 . 31 i 3 − 1 . 44 i 2 + 1 . 135 i − 0 . 12 ) for CA ≥ 0, otherwise CA = 0 (RO-6)
C CD = K CD + ( 0 . 858 i 3 − 0 . 786 i 2 + 0 . 774 i + 0 . 04 ) (RO-7)
C B = (CA + C CD ) 2
2007-01 RO-9
Urban Drainage and Flood Control District
DRAINAGE CRITERIA MANUAL (V. 1) RUNOFF
Table RO-5— Runoff Coefficients, C
Percentage
Imperviousness Type C and D NRCS Hydrologic Soil Groups
2-yr 5-yr 10-yr 25-yr 50-yr 100-yr
0% 0.04 0.15 0.25 0.37 0.44 0.50
5% 0.08 0.18 0.28 0.39 0.46 0.52
10% 0.11 0.21 0.30 0.41 0.47 0.53
15% 0.14 0.24 0.32 0.43 0.49 0.54
20% 0.17 0.26 0.34 0.44 0.50 0.55
25% 0.20 0.28 0.36 0.46 0.51 0.56
30% 0.22 0.30 0.38 0.47 0.52 0.57
35% 0.25 0.33 0.40 0.48 0.53 0.57
40% 0.28 0.35 0.42 0.50 0.54 0.58
45% 0.31 0.37 0.44 0.51 0.55 0.59
50% 0.34 0.40 0.46 0.53 0.57 0.60
55% 0.37 0.43 0.48 0.55 0.58 0.62
60% 0.41 0.46 0.51 0.57 0.60 0.63
65% 0.45 0.49 0.54 0.59 0.62 0.65
70% 0.49 0.53 0.57 0.62 0.65 0.68
75% 0.54 0.58 0.62 0.66 0.68 0.71
80% 0.60 0.63 0.66 0.70 0.72 0.74
85% 0.66 0.68 0.71 0.75 0.77 0.79
90% 0.73 0.75 0.77 0.80 0.82 0.83
95% 0.80 0.82 0.84 0.87 0.88 0.89
100% 0.89 0.90 0.92 0.94 0.95 0.96
TYPE B NRCS HYDROLOGIC SOILS GROUP
0% 0.02 0.08 0.15 0.25 0.30 0.35
5% 0.04 0.10 0.19 0.28 0.33 0.38
10% 0.06 0.14 0.22 0.31 0.36 0.40
15% 0.08 0.17 0.25 0.33 0.38 0.42
20% 0.12 0.20 0.27 0.35 0.40 0.44
25% 0.15 0.22 0.30 0.37 0.41 0.46
30% 0.18 0.25 0.32 0.39 0.43 0.47
35% 0.20 0.27 0.34 0.41 0.44 0.48
40% 0.23 0.30 0.36 0.42 0.46 0.50
45% 0.26 0.32 0.38 0.44 0.48 0.51
50% 0.29 0.35 0.40 0.46 0.49 0.52
55% 0.33 0.38 0.43 0.48 0.51 0.54
60% 0.37 0.41 0.46 0.51 0.54 0.56
65% 0.41 0.45 0.49 0.54 0.57 0.59
70% 0.45 0.49 0.53 0.58 0.60 0.62
75% 0.51 0.54 0.58 0.62 0.64 0.66
80% 0.57 0.59 0.63 0.66 0.68 0.70
85% 0.63 0.66 0.69 0.72 0.73 0.75
90% 0.71 0.73 0.75 0.78 0.80 0.81
95% 0.79 0.81 0.83 0.85 0.87 0.88
100% 0.89 0.90 0.92 0.94 0.95 0.96
2007-01 RO-11
Urban Drainage and Flood Control District
RUNOFF DRAINAGE CRITERIA MANUAL (V. 1)
TABLE RO-5 (Continued)—Runoff Coefficients, C
Percentage
Imperviousness Type A NRCS Hydrologic Soils Group
2-yr 5-yr 10-yr 25-yr 50-yr 100-yr
0% 0.00 0.00 0.05 0.12 0.16 0.20
5% 0.00 0.02 0.10 0.16 0.20 0.24
10% 0.00 0.06 0.14 0.20 0.24 0.28
15% 0.02 0.10 0.17 0.23 0.27 0.30
20% 0.06 0.13 0.20 0.26 0.30 0.33
25% 0.09 0.16 0.23 0.29 0.32 0.35
30% 0.13 0.19 0.25 0.31 0.34 0.37
35% 0.16 0.22 0.28 0.33 0.36 0.39
40% 0.19 0.25 0.30 0.35 0.38 0.41
45% 0.22 0.27 0.33 0.37 0.40 0.43
50% 0.25 0.30 0.35 0.40 0.42 0.45
55% 0.29 0.33 0.38 0.42 0.45 0.47
60% 0.33 0.37 0.41 0.45 0.47 0.50
65% 0.37 0.41 0.45 0.49 0.51 0.53
70% 0.42 0.45 0.49 0.53 0.54 0.56
75% 0.47 0.50 0.54 0.57 0.59 0.61
80% 0.54 0.56 0.60 0.63 0.64 0.66
85% 0.61 0.63 0.66 0.69 0.70 0.72
90% 0.69 0.71 0.73 0.76 0.77 0.79
95% 0.78 0.80 0.82 0.84 0.85 0.86
100% 0.89 0.90 0.92 0.94 0.95 0.96
RO-12 2007-01
Urban Drainage and Flood Control District
APPENDIX B
EROSION CONTROL REPORT
River District Block 8 Mixed Use
Preliminary Erosion Control Report
EROSION CONTROL REPORT
A comprehensive Erosion and Sediment Control Plan (along with associated details) will be included
with the final construction drawings. It should be noted, however, that any such Erosion and
Sediment Control Plan serves only as a general guide to the Contractor. Staging and/or phasing of
the BMPs depicted, and additional or different BMPs from those included may be necessary during
construction, or as required by the authorities having jurisdiction.
It shall be the responsibility of the Contractor to ensure erosion control measures are properly
maintained and followed. The Erosion and Sediment Control Plan is intended to be a living
document, constantly adapting to site conditions and needs. The Contractor shall update the
location of BMPs as they are installed, removed or modified in conjunction with construction
activities. It is imperative to appropriately reflect the current site conditions at all times.
The Erosion and Sediment Control Plan shall address both temporary measures to be implemented
during construction, as well as permanent erosion control protection. Best Management Practices
from the Volume 3, Chapter 7 – Construction BMPs will be utilized. Measures may include, but are
not limited to, silt fencing along the disturbed perimeter, gutter protection in the adjacent roadways
and inlet protection at existing and proposed storm inlets. Vehicle tracking control pads, spill
containment and clean-up procedures, designated concrete washout areas, dumpsters, and job site
restrooms shall also be provided by the Contractor.
Grading and Erosion Control Notes can be found on the Utility Plans. The Final Plans will contain a
full-size Erosion Control sheet as well as a separate sheet dedicated to Erosion Control Details. In
addition to this report and the referenced plan sheets, the Contractor shall be aware of, and adhere
to, the applicable requirements outlined in the Development Agreement for the development. Also,
the Site Contractor for this project will be required to secure a Stormwater Construction General
Permit from the Colorado Department of Public Health and Environment (CDPHE), Water Quality
Control Division – Stormwater Program, prior to any earth disturbance activities. Prior to securing
said permit, the Site Contractor shall develop a comprehensive StormWater Management Plan
(SWMP) pursuant to CDPHE requirements and guidelines. The SWMP will further describe and
document the ongoing activities, inspections, and maintenance of construction BMPs.
APPENDIX C
REFERENCE MATERIAL – SELECTED PORTIONS OF THE DOWNTOWN RIVER DISTRICT
IMPROVEMENT PLANS (FEBRUARY 2012)
MAP POCKET
DRAINAGE EXHIBIT
(min)
10-yr
Tc
(min)
100-yr
Tc
(min)
11No0.95 0.95 1.00 80 1.00% 2.5 2.5 1.7 401 0.60% 1.55 4.3 0 0.00% N/A N/A 7 7 6
OS1 OS1 No 0.95 0.95 1.00 30 1.00% 1.5 1.5 1.0 138 0.75% 1.73 1.3 0 0.00% N/A N/A 5 5 5
DEVELOPED TIME OF CONCENTRATION COMPUTATIONS
Gutter Flow Swale Flow
Design
Point
Basin
Overland Flow
ATC
11/1/2014
Time of Concentration
(Equation RO-4)
3
1
1 . 87 1 . 1 *
S
Ti C Cf L
(min)
10-yr
Tc
(min)
100-yr
Tc
(min)
H1 H1 No 0.50 0.50 0.63 146 1.60% 11.6 11.6 9.2 383 0.40% 1.26 5.0 0 0.00% N/A N/A 17 17 14
HISTORIC TIME OF CONCENTRATION COMPUTATIONS
Gutter Flow Swale Flow
Design
Point
Basin
Overland Flow
ATC
9/15/2014
Time of Concentration
(Equation RO-4)
3
1
1 . 87 1 . 1 *
S
Ti C Cf L