March 20, 2015
Brad March
March, Olive & Pharris, LLC
110 East Oak Street, Suite 200
Fort Collins, CO 80524
RE: March, Olive, & Pharris, LLC Law Offices, PDP140008, Round Number 3
Comment Summary:
Department: Planning Services
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
Topic: General
03/17/2015: The trash enclosure location needs to be selected. Please choose one
and eliminate the other.
09/02/2014: The trash enclosure needs to be resolved if showing new enclosure on
site then it will need to be on a concrete pad with a walk-in access.
07/14/2014: The trash enclosure needs to be designed with walk-in access without
having to open the main service gate and located on a concrete pad at least 20ft
from a public sidewalk.
Comment Number: 1 Comment Originated: 07/16/2014
03/17/2015: A land use table is has still not been added. This needs to be in clude
on the site plan. The use you are requesting is Offfices, financial services and
clinics in the list ofpermitted uses.
09/02/2014: Where is the existing use and the proposed use table?
07/16/2014: A land use table should be included on the site plan indicating the
existing use and the new proposed use and a parking table (both vehicle and bicycle
spaces).
Comment Number: 3 Comment Originated: 07/16/2014
Please see the following summary of comments from City staff and outside reviewing agencies for
your submittal of the above referenced project. If you have questions about any comments, you may
contact the individual commenter or direct your questions through the Project Planner, Noah Beals, at
970-416-2313 or nbeals@fcgov.com.
Page 1 of 7
03/17/2015: The planting legend on the landscape plan should include quantities.
09/02/2014: This site/landscape plan will need to show the righ-of-way
improvements such as sidewalk location and street trees.
The juniper bed dimensions should be labeled and the number of plants to be
planted in a planting table.
07/16/2014: Is this a combined site and landscape plan? If so the landscaping
should be included. Please outline the juniper planting bed and number of plants in
each.
Comment Number: 4 Comment Originated: 07/16/2014
03/17/2015: What is the drive aisle width of the compact spaces?
09/02/2014: The stall dimensions will need to be labeled. It seems that there is not
enough aisle room for stall labeled 11 and 10 possibly more depending on the stall
dimensions.
Comment Number: 6 Comment Originated: 09/02/2014
03/17/2015: Stalls along the north property line will need to be surfaced with asphalt
or concrete.
The new parking areas are required a 5ft landscape setback. This can be reduced
through additional screening. It is suggest a 3ft wrought-iron fence with vegetation
could provide adequate screening. This would be both the north and south parking
areas.
09/02/2014: Stalls along north property line will need to be surfaced with asphalt or
concrete.
What screening of the vehicle use area along the north property line is included?
Comment Number: 7 Comment Originated: 09/02/2014
03/17/2015: The dissolving of the agreement can be as a condition of approval of
PDP, but must be complete for Final Plan approval.
09/03/2014: The agreement to dissolve the old agreement will need to be
completed before going to public hearing.
Comment Number: 8 Comment Originated: 09/03/2014
03/17/2015: The sheet numbering will need to be revised to the correct number of
sheets this can also be done through a sheet index.
Comment Number: 9 Comment Originated: 03/17/2015
03/17/2015: Plans will need to be on 24"36" sheets.
Comment Number: 10 Comment Originated: 03/17/2015
Department: Engineering Development Review
Contact: Sheri Langenberger, 970-221-6573, slangenberger@fcgov.com
Topic: General
Page 2 of 7
09/01/14: This is labeled on the plans. Additional information on the dedication
process and cost can be found at: http://www.fcgov.com/engineering/devrev.php
The deed will need to be finalized and accepted prior to final approval of this project.
07/15/2014: Additional right-of-way needs to be dedicated along the frontage of the
property. I don¿t know exactly how much is to be dedicated, but want right-of-way
so that there is 17 feet from the existing flowline of the street. The distance allows
for the future parkway and detached sidewalk that is a part of the college avenue
cross section.
Comment Number: 2 Comment Originated: 07/15/2014
03/18/15: The applicant will need to get an access permit from CDOT for the
existing driveway prior to starting the driveway work. 09/01/14: Since the driveway
will not be closing the applicant will need to work with CDOT regarding a
new/updated access permit for this driveway. The driveway shall be a one way
driveway and that needs to be noted on the site plan and appropriate signage shown
to be installed on the plans, so it is clear that cars are not to enter from the wrong
way. 07/15/2014: For the driveway closure:
The applicant will need to get an access permit from CDOT for the closure (no
cost).
The driveway cut would need to be replaced along College Ave with vertical curb
and gutter.
Comment Number: 6 Comment Originated: 07/15/2014
03/18/15: I will provide a copy of this document at our wednesday morning meeting.
09/03/2014: A development agreement will need to be entered into for the site. I will
send out the information for development agreement sheet and that will need to be
returned.
Comment Number: 9 Comment Originated: 09/03/2014
03/18/2015: Showing a trash enclosure adjacent to the alley. Where are the doors?
They can’t swing into the alley. Need to provide a design for this or notes that
identify where the door locations will be and that they are not to swing into the alley.
Comment Number: 11 Comment Originated: 03/18/2015
In reading the comment responses it states that there will be pervious pavers
installed for the parking area along the north side of the lot. There is no way in
looking at the plan that that could be known that that is the intent.03/18/2015:
Comment Number: 12 Comment Originated: 03/18/2015
03/18/2015: If you are dedicating 9 feet of right-of-way then the distance on the
plans should not be labeled as +- 9 feet but as a definitive 9.0 feet.
Comment Number: 13 Comment Originated: 03/18/2015
The ROW dedication document. We will not accept this with a reference to a site
plan within the legal description. 03/18/2015:
Comment Number: 14 Comment Originated: 03/18/2015
Department: Environmental Planning
Contact: Lindsay Ex, 970-224-6143, lex@fcgov.com
Topic: General
07/11/2014: No comments.
Comment Number: 1 Comment Originated: 07/11/2014
Department: Forestry
Contact: Tim Buchanan, 970-221-6361, tbuchanan@fcgov.com
Topic: Landscape Plans
Page 3 of 7
03/17/2015:
Further discussion of this item appears needed in reference to location of the trash
facility if required and the alternatives under discussion related to placing parking
near the tree.
09/03/2014:
The current plan shows the alternate trash enclosure location at the large
cottonwood at the SE corner of the site. The parking stall just to the west appears to
be less than 3 feet from the tree. The extent of the pavers near this tree is not very
not clear.
Please review these conflicts and consider if the parking stall can be shifted to the
west or possibly not included to provide better protection to the tree. The City
Forester is available to meet on site if needed to help evaluate.
Comment Number: 8 Comment Originated: 09/03/2014
03/17/2015:
Thank you for adding the proposed Yellowood tree NW of the building. Mitigation
trees need to be upsized, and in the case of Yellowwood which is an ornamental
tree the mitigation size is 2.5 inch caliper. Please record the size of the Yellowwood
in the Tree/Planting Legend as 2.5 inch caliper.
Comment Number: 9 Comment Originated: 03/17/2015
Department: Historical Preservation
Contact: Karen McWilliams, 970-224-6078, kmcwilliams@fcgov.com
Topic: General
07/07/2014: This property currently is under consideration by the Landmark
Preservation Commission and Council for Fort Collins Landmark designation. The
property has previously been found to be eligible for local designation for both its
architecture and historical associations. The property is also likely to be eligible for
listing on both the State and National Registers.
Comment Number: 1 Comment Originated: 07/07/2014
07/07/2014: The plans have been reviewed for compliance with Section 3.4.7 of the
Land Use Code, and for compliance with the criteria in Section 14-48 of the City
Code, which includes the Secretary of the Interior's Standards. The plans comply
with all applicable standards.
Comment Number: 2 Comment Originated: 07/07/2014
Department: Internal Services
Contact: Russell Hovland, 970-416-2341, rhovland@fcgov.com
Topic: Building Insp Plan Review
07/17/2014:
A house changing occupancy to commercial must apply for a building permit and
the building code requires the building meet current code in some aspects. For
details contact Russ at 416-2341.
Comment Number: 1 Comment Originated: 07/17/2014
Department: Light And Power
Contact: Doug Martine, 970-224-6152, dmartine@fcgov.com
Topic: General
Page 4 of 7
06/30/2014: The existing electric service provides for up to 150 amps. If additional
electric service capacity is needed, please coordinate with Light & Power
Engineering at (970)221-6700.
Comment Number: 1 Comment Originated: 06/30/2014
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler@poudre-fire.org
Topic: General
FIRE ACCESS
03/18/2015: Contrary to the applicant's comment in the most recent response
letter, fire access requirements for this site have NOT been met. Prior fire
department comment from 09/03/2014 (below), remains active. An Emergency
Access Easement on the property will be needed or the building will require a fire
sprinkler system as a means for offsetting the lack of access condition. Fire lane
standards require 20' width but the fire marshal will allow a four foot width reduction
(to 16'). Plan revisions will need to be reviewed prior to approval.
09/03/2014: FIRE LANES
The issue of fire access to this property needs to be revisited. It's now my
understanding the proposal to share a drive aisle with the commercial property to
the south has been rescinded and fire access will need to be achieved on-site as
we cannot take access off of College Ave. Please contact me to discuss this
further. Code reference provided below.
Code language and Fire lane specifications are provided below.
IFC 503.1.1: Fire Lanes shall be provided to within 150' of all portions of the building,
as measured by an approved route around the exterior of the building. When fire
lanes cannot be provided, the fire code official is authorized to increase the
dimension of 150 feet if the building is equipped throughout with an approved,
automatic fire-sprinkler system.
FIRE LANE SPECIFICATIONS
A fire lane plan shall be submitted for approval prior to installation. In addition to the
design criteria already contained in relevant standards and policies, any new fire
lane must meet the following general requirements:
> Shall be designated on the plat as an Emergency Access Easement.
> Maintain the required 20 foot minimum unobstructed width & 14 foot minimum
overhead clearance.
> Be designed as a flat, hard, all-weather driving surface capable of supporting 40
tons.
> Dead-end fire access roads in excess of 150 feet in length shall be provided with
an approved area for turning around fire apparatus.
> The required turning radii of a fire apparatus access road shall be a minimum of
25 feet inside and 50 feet outside. Turning radii shall be detailed on submitted plans.
> Be visible by painting and/or signage, and maintained unobstructed at all times.
> Additional access requirements exist for buildings greater than 30' in height. Refer
to Appendix D of the 2012 IFC or contact PFA for details.
International Fire Code 503.2.3, 503.2.4, 503.2.5, 503.3, 503.4 and Appendix D;
FCLUC 3.6.2(B)2006 and Local Amendments.
Comment Number: 2 Comment Originated: 03/18/2015
Department: Stormwater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Page 5 of 7
Topic: General
03/17/2015: This needs to be done for the pavers.
09/04/2014: Reminder comment.
07/18/2014: Please provide a design for the water quality mitigation and LID
treatment required for the new impervious area.
Comment Number: 2 Comment Originated: 07/18/2014
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: General
03/17/2015: We don't like the reference to the Site Plan in the right of way
dedication. Please confirm that this is allowed.
Comment Number: 11 Comment Originated: 03/17/2015
Topic: Landscape Plans
03/17/2015: We will require a 24"x36" sheet when filed.
Comment Number: 7 Comment Originated: 03/17/2015
03/17/2015: There are line over text issues. See redlines.
Comment Number: 8 Comment Originated: 03/17/2015
03/17/2015: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
Comment Number: 9 Comment Originated: 03/17/2015
03/17/2015: Please remove the "+/-" from the dimension for the additional College
Avenue right of way dedicated, or dimension the new right of way being dedicated.
This must be clearly defined.
Comment Number: 10 Comment Originated: 03/17/2015
Topic: Site Plan
03/17/2015: There are still line over text issues. See redlines.
09/02/2014: There are still line over text issues. See redlines.
07/14/2014: There are line over text issues. See redlines.
Comment Number: 2 Comment Originated: 07/14/2014
03/17/2015: This has not been corrected.
09/02/2014: We will require a 24"x36" sheet when filed.
Comment Number: 4 Comment Originated: 09/02/2014
03/17/2015: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
Comment Number: 5 Comment Originated: 03/17/2015
03/17/2015: Please remove the "+/-" from the dimension for the additional College
Avenue right of way dedicated, or dimension the new right of way being dedicated.
This must be clearly defined.
Comment Number: 6 Comment Originated: 03/17/2015
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinson@fcgov.com
Topic: Site Plan
Page 6 of 7
03/17/2015: The response letter indicates that the application for the change in use
permit from CDOT is attached. I didn't see it in the packet. This permit will be
needed to be completed before the applicant can use the driveway in the manner
shown.
09/02/2014: Since the shared drive concept is abandoned, the existing drive will be
used. CDOT appears to be supportive of this. The drive needs to be one way
(inbound only), and a change in use permit will be needed from CDOT.
07/16/2014: The shared driveway off College Avenue needs to function as an
appropriate high volume drive that accesses a state highway. If it's being used for
2-way traffic, it would need to accommodate 2-way traffic for at least some distance
from street.
Comment Number: 2 Comment Originated: 07/16/2014
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson@fcgov.com
Topic: General
07/02/2014: Irrigation plans are required no later than at the time of building permit.
The irrigation plans must comply with the provisions outlined in Section 3.2.1(J) of
the Land Use Code. Direct questions concerning irrigation requirements to Eric
Olson, at 221-6704 or eolson@fcgov.com
Comment Number: 1 Comment Originated: 07/02/2014