July 18, 2014
Brad March
March, Olive & Pharris, LLC
110 East Oak Street, Suite 200
Fort Collins, CO 80524
Comment Summary:
Department: Planning Services
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
Topic: General
07/14/2014: The trash enclosure needs to be designed with walk-in access without having to open the
main service gate and located on a concrete pad at least 20ft from a public sidewalk.
Comment Number: 1 Comment Originated: 07/16/2014
07/16/2014: A land use table should be included on the site plan indicating the existing use and the
new proposed use and a parking table (both vehicle and bicycle spaces).
Comment Number: 3 Comment Originated: 07/16/2014
07/16/2014: Is this a combined site and landscape plan? If so the landscaping should be included.
Comment Number: 4 Comment Originated: 07/16/2014
07/16/2014: Please show the pedestrian paths from the parking lot areas to entrances. This should
include the breeze way.
Comment Number: 5 Comment Originated: 07/16/2014
Department: Engineering Development Review
Contact: Sheri Langenberger, 970-221-6573, slangenberger@fcgov.com
Topic: General
07/15/2014: If the project is to be called March, Olive and Pharris LLC Law Offices then the plans need
to contain this name as well. The project name and that contained on the plans needs to be
consistant.
Comment Number: 1 Comment Originated: 07/15/2014
Please see the following summary of comments from City staff and outside reviewing agencies for your submittal of
the above referenced project. If you have questions about any comments, you may contact the individual
commenter or direct your questions through the Project Planner, Noah Beals, at 970-416-2313 or
nbeals@fcgov.com.
RE: March, Olive, & Pharris, LLC Law Offices, PDP140008, Round Number 1
Page 1 of 6
07/15/2014: Additional right-of-way needs to be dedicated along the frontage of the property. I don’t
know exactly how much is to be dedicated, but want right-of-way so that there is 17 feet from the
existing flowline of the street. The distance allows for the future parkway and detached sidewalk that is
a part of the college avenue cross section.
Comment Number: 2 Comment Originated: 07/15/2014
07/15/2014: The existing sidewalk is narrow and can either be widened by adding onto this sidewalk
(minimum addition is 4 feet in width) or the sidewalk can be detached along the property’s frontage (6
foot detached). Either wa y we can work the sidewalk around the existing trees.
Comment Number: 3 Comment Originated: 07/15/2014
07/15/2014: The shared driveway. Is this to be considered a one-way driveway? If not will probably
need to widen the driveway some. Need an access that works and as shown the driveway is narrow
for a 2-way driveway. The standard for a 2-way driveway is 24 feet minimum. What is the driveway
width and what can be achieved? It is not very clear how the access will work and the parking for this
site and the adjacent site will be accessed.
Comment Number: 4 Comment Originated: 07/15/2014
07/15/2014: Add the following note to the site plan.
Damaged curb, gutter and sidewalk existing prior to construction, as well as streets, sidewalks, curbs
and gutters, destroyed, damaged or removed due to construction of this project, shall be replaced or
restored in like kind at the Developer’s expense prior to the acceptance of completed improvements
and/or prior to the issuance of the first Certificate of Occupancy. The limits of the repairs will be
identified in the field by the City Engineering Inspector prior to and over the course of the project and
will not be shown on the plans.
Comment Number: 5 Comment Originated: 07/15/2014
07/15/2014: For the driveway closure:
The applicant will need to get an access permit from CDOT for the closure (no cost).
The driveway cut would need to be replaced along College Ave with vertical curb and gutter.
Comment Number: 6 Comment Originated: 07/15/2014
07/15/2014: For the shared driveway:
CDOT would need to issue a new permit for the additional traffic to the existing access. The permit
would be written to both property owners unless there’s an easement or some other kind of document
ensuring that the new business would have access.
Comment Number: 7 Comment Originated: 07/15/2014
Department: Environmental Planning
Contact: Lindsay Ex, 970-224-6143, lex@fcgov.com
Topic: General
07/11/2014: No comments.
Comment Number: 1 Comment Originated: 07/11/2014
Department: Forestry
Contact: Tim Buchanan, 970-221-6361, tbuchanan@fcgov.com
Topic: Landscape Plans
Page 2 of 6
07/16/2014:
The two street trees that are dead and dying are described as being removed and replaced. Two
skyline Honeylocust 2.0 inch caliper could be labeled on the plan as the replacement trees.
Comment Number: 1 Comment Originated: 07/16/2014
07/16/2014:
Add the tree protection specifications found in LUC 3.2.1 G 1-7
Comment Number: 2 Comment Originated: 07/16/2014
07/16/2014:
Please provide a copy to the City Forester and project planner of the written aerial tree evaluation with
recommendations that was discussed at the site meeting for the Cottonwood at the southeast corner
and west most spruce.The aerial evaluation should be conducted by a licensed and certified arborist
using a bucket truck or climber to examine the upper portion of these trees. The report can be used to
determine what action should be taken on the spruce and cottonwood. If the spruce is recommended
for removal then planting a replacement spruce in that area would help keep the original planting
scheme.
After the evaluation is complete the action that would be taken on these two trees can be finalized on
the plan and its tree inventory.
Comment Number: 3 Comment Originated: 07/16/2014
07/16/2014:
The following is the tree inventory information that could be placed on the plan.
Number Species location Size Condition
#1 Lanceleaf Cottonwood SE 64 inch dia fair to good Preserve/evaluate
#2 Spruce east spruce 16 inch dia fair Preserve
#3 Spruce middle spruce 28 inch dia Fair to good Preserve
#4 Spruce west spruce 20 inch dia Fair Preserve/evaluate
#5 Ash S. street tree 4 inch dia dying remove/replace
#6 Walnut n. street tree 11 inch dia dead remove/replace
#7 A. elm and S. elm (8) north thicket 2-12inch dia poor remove/wild origin
Comment Number: 4 Comment Originated: 07/16/2014
07/16/2014:
The border around the spruces to retain along the south boundary should minimize any root
excavation. It would be good to specify how that would be done. The permeable pavers used are
very good treatment over roots. Minimizing any excavation into the root system will be an important
part of their installation.
Comment Number: 5 Comment Originated: 07/16/2014
Department: Historical Preservation
Contact: Karen McWilliams, 970-224-6078, kmcwilliams@fcgov.com
Topic: General
07/07/2014: This property currently is under consideration by the Landmark Preservation Commission
and Council for Fort Collins Landmark designation. The property has previously been found to be
eligible for local designation for both its architecture and historical associations. The property is also
likely to be eligible for listing on both the State and National Registers.
Comment Number: 1 Comment Originated: 07/07/2014
Page 3 of 6
07/07/2014: The plans have been reviewed for compliance with Section 3.4.7 of the Land Use Code,
and for compliance with the criteria in Section 14-48 of the City Code, which includes the Secretary of
the Interior's Standards. The plans comply with all applicable standards.
Comment Number: 2 Comment Originated: 07/07/2014
Department: Internal Services
Contact: Russell Hovland, 970-416-2341, rhovland@fcgov.com
Topic: Building Insp Plan Review
07/17/2014:
A house changing occupancy to commercial must apply for a building permit and the building code
requires the building meet current code in some aspects. For details contact Russ at 416-2341.
Comment Number: 1 Comment Originated: 07/17/2014
Department: Light And Power
Contact: Doug Martine, 970-224-6152, dmartine@fcgov.com
Topic: General
06/30/2014: The existing electric service provides for up to 150 amps. If additional electric service
capacity is needed, please coordinate with Light & Power Engineering at (970)221-6700.
Comment Number: 1 Comment Originated: 06/30/2014
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler@poudre-fire.org
Topic: General
07/15/2014: Per Fire Marshal, Bob Poncelow, existing fire access and water supply are appropriate
for this site. No further comment.
Comment Number: 1 Comment Originated: 07/15/2014
Department: Stormwater Engineering
Contact: Jesse Schlam, 970-218-2932, jschlam@fcgov.com
Topic: Erosion Control
07/16/2014: The site disturbs more than 10,000 sq-ft, therefore Erosion and Sediment Control Materials
need to be submitted for FDP. The erosion control requirements are in the Stormwater Design Criteria
under the Amendments of Volume 3 Chapter 7 Section 1.3.3. Current Erosion Control Materials
Submitted dose not meet requirements. Please submit; Erosion Control Plan, Erosion Control Report,
and an Escrow / Security Calculation. If you need clarification concerning this section, or if there are
any questions please contact Jesse Schlam 970-218-2932 or email @ jschlam@fcgov.com
Comment Number: 1 Comment Originated: 07/16/2014
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: General
07/18/2014: Please provide a design for the water quality mitigation and LID treatment required for the
new impervious area.
Comment Number: 2 Comment Originated: 07/18/2014
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Page 4 of 6
Topic: Site Plan
07/14/2014: Please remove "For" from the sub-title. See redlines.
Comment Number: 1 Comment Originated: 07/14/2014
07/14/2014: There are line over text issues. See redlines.
Comment Number: 2 Comment Originated: 07/14/2014
07/14/2014: Please rotate all marked text 180 degrees. See redlines.
Comment Number: 3 Comment Originated: 07/14/2014
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinson@fcgov.com
Topic: Site Plan
07/16/2014: Internal circulation is hard to decipher. Please provide more information on where
vehicles will access site (shared drive, alley etc?) and how they will move around the site. The pass
through appears very narrow.
Comment Number: 1 Comment Originated: 07/16/2014
07/16/2014: The shared driveway off College Avenue needs to function as an appropriate high volume
drive that accesses a state highway. If it's being used for 2-way traffic, it would need to accommodate
2-way traffic for at least some distance from street.
Comment Number: 2 Comment Originated: 07/16/2014
07/16/2014: Transportation Planning staff notes that the sidewalk along College needs improvements -
although it can likely stay attached much like other properties in the area, it will need to be widened.
Comment Number: 3 Comment Originated: 07/16/2014
07/16/2014: Transportation Planning staff notes thatinternal pedestrian circulation is unclear. Where is
the walkway for people to get from their parking spaces to the front door?
Comment Number: 4 Comment Originated: 07/16/2014
07/16/2014: Transportation Planning staff notes that the handicapped parking stall is in an ackward
location (does it meet dimensional standards?). How will a wheel chair user get from this stall to a
building entrance?
Comment Number: 5 Comment Originated: 07/16/2014
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson@fcgov.com
Topic: General
07/02/2014: Irrigation plans are required no later than at the time of building permit. The irrigation plans
must comply with the provisions outlined in Section 3.2.1(J) of the Land Use Code. Direct questions
concerning irrigation requirements to Eric Olson, at 221-6704 or eolson@fcgov.com
Comment Number: 1 Comment Originated: 07/02/2014
Department: Water-Wastewater Engineering
Contact: Roger Buffington, 970-221-6854, rbuffington@fcgov.com
Topic: General
Page 5 of 6
07/15/2014: The existing water service to the property is a 3/4" service connecting to the water main in
College.
Comment Number: 1 Comment Originated: 07/15/2014
07/15/2014: The sewer service to the property connects to the sanitary sewer in the alley to the east of
the site.
Comment Number: 2 Comment Originated: 07/15/2014
07/15/2014: If there are no changes to thee existing water sewer services, there are no comments at
this time.
Comment Number: 3 Comment Originated: 07/15/2014
Department: Zoning
Contact: Gary Lopez, 970-416-2338, glopez@fcgov.com
Topic: Building Elevations
06/30/2014: Please show elevations of the proposed Porte Cochere extention.
Comment Number: 1 Comment Originated: 06/30/2014
Topic: Site Plan
06/30/2014: Is there a handicap ramp proposed? Please show location if so.
Comment Number: 2 Comment Originated: 06/30/2014
06/30/2014: The diaginol parking will require some of the spaces to "pass through" on to the adjoing
lot as vehicles parked in the three spaces to the west of the designated "pass through" should not
have to back up to through the lane to pull forward throught the pass through. In addition the
designated pass through area doesn't appear to be wide enough as a one way isle width should be at
least 12' wide.
Comment Number: 3 Comment Originated: 06/30/2014
06/30/2014: The handicap space is unsufficient in width. Even with one HC space it should be a
minimuim of 8' wide and another 8' of a hatched out area for access out and into a van.
Comment Number: 4 Comment Originated: 06/30/2014