HomeMy WebLinkAboutLEMAY AVENUE CRAFT BREWERY & SELF-STORAGE FACILITY - PDP - PDP150009 - SUBMITTAL DOCUMENTS - ROUND 1 - PROJECT NARRATIVEPROPOSED DEVELOPMENT SCHEDULE
Development Schedule
• Construction Start: Spring 2016
• Construction Completion: Spring 2017
Development Construction
• The Lemay Avenue Property is proposed to be constructed as two separate phases of
development and shall include the following.
Lot 1-Block 1(1.066 Acres): The Craft Brewery Building being approximately 7219 Square Feet
shall be built after the completion of the Self-Storage facility located on Lot 2; unless a Tenant
Brewer is identified during the construction of the Self-Storage facility at which time
construction of the brewery would begin.
• Lot 2-Block 1(4.536 Acres): The Self-Storage site and buildings being approximately 104,000
Square Feet shall be the first phase of development and shall include the construction of the
following improvements:
1. Construction of the interim roadway design of Buckingham Street including curb/gutter
and sidewalk along the south side of Buckingham, widening of the north side of
Buckingham, roadway restriping and drainage improvements to Buckingham and the
Lemay Avenue west roadside swale. Along Lemay Avenue from Buckingham Street to the
south property boundary a new 8’ wide concrete pedestrian walk will be constructed no
other improvements to the Lemay Ave. roadway are anticipated.
2. Landscape and irrigation along the south tree lawn of Buckingham Street and landscape
and irrigation along the west side of Lemay Avenue between the existing edge of asphalt
and the new 8 foot wide pedestrian walk will be constructed from, Buckingham St. to the
south property boundary.
3. The access Drive from Buckingham into the site will be constructed including all parking
lot areas and private drives, curb/gutter and sidewalk, pervious pavers, parking lot site
lighting, parking lot striping and associated parking lot landscape and irrigation.
4. 7 Self-Storage buildings including buildings, curb/gutters and private drives, water, sewer
and storm drainage utilities and services to each building, site perimeter fencing and gates,
detention pond and LID storm drainage improvements, all landscape and irrigation
contained within Lot 2 including the detention pond area, Lemay Avenue Streetscape
landscape located between the west edge of the new 8’ pedestrian walk and the
building/fence line, landscape and irrigation of the west property boundary and soft swale
areas.
• Lot 3-Block 1(0.173 Acres): Lot 3 is intended as a future building and expansion site for either
the Craft Brewery or Self-Storage facility. It will initially be used as a construction staging area
for the construction of Lot 1, Craft Brewery and Lot 2, Self-Storage buildings. Once the
construction of both of these building is complete the site will be landscaped and irrigated as
shown on the PDP Landscape Plans. Any development of Lot 3 will be subject to the review
and approval of a future Project Development Plan.