HomeMy WebLinkAboutRIVER MODERN - PDP - PDP150005 - SUBMITTAL DOCUMENTS - ROUND 1 - TRAFFIC STUDYRiver Modern
Traffic Impact Study
KJH Commercial, LLC
Fort Collins, Colorado
March 3, 2015
Prepared By:
Sustainable Traffic Solutions, Inc.
823 West 124th Drive
Westminster, CO 80234
303.589.6875
Joseph L. Henderson, PE, PTOE
STS
Table of Contents
Page
1.0 Introduction ................................................................................................... 1
2.0 Project Description ........................................................................................ 1
2.1 Existing and Proposed Streets and Intersections .................................... 1
2.2 Study Assumptions .................................................................................. 1
3.0 Existing Conditions ....................................................................................... 2
3.1 Existing Traffic Volumes .......................................................................... 2
3.2 Level-of-Service Analysis ........................................................................ 2
4.0 Site Generated Traffic Volumes ................................................................... 2
4.1 Trip Generation ........................................................................................ 2
4.2 Trip Distribution and Assignment ............................................................. 2
5.0 Year 2017 Background Traffic Volumes ...................................................... 2
5.1 Level-of-Service Analysis ........................................................................ 2
6.0 Year 2017 Total Traffic Volumes .................................................................. 3
6.1 Level-of-Service Analysis ........................................................................ 3
7.0 Auxiliary Lane Analysis ................................................................................ 3
8.0 Appropriateness of Access Locations ........................................................ 3
9.0 Intersection Sight Distance .......................................................................... 4
10.0 Pedestrian and Bicycle Facilities ................................................................. 4
11.0 Appropriateness of Existing Signing and Markings ................................... 5
12.0 Conclusions ................................................................................................... 5
List of Tables
Table 1 – Intersection Operational Summary
Table 2 – Trip Generation Estimate
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
Table of Contents (Continued)
List of Figures
Figure 1 – Vicinity Map
Figure 2 – Site Plan
Figure 3 – Existing Peak Hour Weekday Traffic Volumes
Figure 4 – Trip Distribution
Figure 5 – Trip Assignment
Figure 6 – Year 2017 Background Traffic Volumes
Figure 7 – Year 2017 Term Total Traffic Volumes
Figure 8 – Need for an Eastbound Left Turn Lane
Figure 9 – Need for a Westbound Right Turn Lane
Figure 10 – Pedestrian and Bicycle Facility Map
List of Appendices
Appendix A Traffic Count Data
Appendix B Synchro Analysis Results
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
ii
River Modern
Traffic Impact Study
1.0 Introduction
KJH Commercial, LLC is proposing to develop a parcel at 900 East Stuart Street in
Fort Collins (see Figure 1). The development is proposed to include 30 single family
dwelling units and a daycare facility with capacity for 42 children.
This traffic study has been prepared in conformance with Chapter 4 of the City of
Fort Collins requirements for traffic studies1. Based on the trip generation, the study
was designed to meet the requirements for the traffic memorandum.
2.0 Project Description
2.1 Existing and Proposed Streets and Intersections
Stuart Street will border the south side of the development and the main access will
be at Stuart Street / Cherokee Drive (See Figure 2). Stuart Street is classified as a
minor collector street by the City of Fort Collins2. A second access to Stuart Street is
proposed on the east edge of the development to allow outbound traffic for the
daycare business.
2.2 Study Assumptions
A scoping meeting was held with Martina Wilkinson with the City on January 27th to
establish the assumptions for the study. The Transportation Impact Study Base
Assumptions worksheet is contained in Appendix A.
The following assumptions were utilized for this study.
• Short Term Horizon. The study assumes that the development will be
completed in 2017.
• Growth Rate. A 1.5% annual growth rate was assumed.
• Saturation Flow Rate. The saturation flow rate was assumed to be 1,900
passenger vehicles / hour / lane.
• Peak Hour Factor. The peak hour factor for the existing traffic was used for
the analysis of the existing and Year 2017 traffic.
• Truck Percentage. The percentage of trucks was assumed to be 2%.
1 Larimer County Urban Area Street Standards. City of Fort Collins. April 1, 2007.
2 Fort Collins Transportation Master Plan 2004 – Figure 5.1. City of fort Collins. February 2004.
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
1
3.0 Existing Conditions
3.1 Existing Traffic Volumes
Peak hour turning movement counts were collected by All Traffic Data on Tuesday
February 3, 2015. A summary of the data is contained in Figure 3 and the raw data
are contained in Appendix A.
3.2 Level-of-Service Analysis
To evaluate the performance of the intersections within the study area, the level-of-
service (LOS) was calculated using Synchro software. This software package
utilizes criteria described in the Highway Capacity Manual3. LOS is a measure used
to describe operational conditions at an intersection. LOS categories ranging from A
to F are assigned based on the predicted delay in seconds per vehicle for the
intersection as a whole, as well as for individual turning movements. LOS A
indicates very good operations, and LOS F indicates poor, congested operations.
Based on Table 4-3 of the City standards, acceptable operation for a stop controlled
intersection is LOS E or better.
The analysis shows that the intersection is currently operating at LOS A during the
morning and evening peak hours (see Table 1). The Synchro output is contained in
Appendix B.
4.0 Site Generated Traffic Volumes
4.1 Trip Generation
In order to determine the traffic impacts associated with the development, the
amount of traffic generated by the proposed development was estimated using trip
generation rates contained in the Institute of Transportation Engineers Trip
Generation manual4. Trip generation for the development is contained in Table 2.
4.2 Trip Distribution and Assignment
The trip distribution for the development was assumed based on the existing and
future traffic patterns and proposed site access. Figure 4 contains the distribution for
the development and the assignment is contained in Figure 5.
5.0 Year 2017 Background Traffic Volumes
Traffic volumes at the study area intersections were inflated to Year 2017 levels that
are expected to be present prior to occupancy of the development. The morning and
evening peak hour volumes are contained in Figure 6.
5.1 Level-of-Service Analysis
The intersection is expected to operate at LOS A during the morning and evening
peak hours (see Table 1).
3 Highway Capacity Manual. Transportation Research Board. 2010.
4 Trip Generation – 9th Edition. Institute of Transportation Engineers. September 2012.
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
2
6.0 Year 2017 Total Traffic Volumes
The projected peak hour volumes at the completion of the project were developed by
adding the development traffic (Figure 5) to the background traffic (Figure 6). The
total traffic volumes are contained in Figure 7.
6.1 Level-of-Service Analysis
The intersections are expected to operate at LOS A during the morning and evening
peak hours following occupancy of the development (see Table 1).
7.0 Auxiliary Lane Analysis
The need for an eastbound left turn lane on Stuart Street at Cherokee Drive was
evaluated based on criteria contained in the NCHRP 2795. Volumes contained in
Figure 7 were used for the analysis. Using the nomograph contained in Figure 4-12,
a left turn lane is not warranted at completion of the development. The results of the
analysis are shown in Figure 8.
The need for a westbound right turn lane on Stuart Street at Cherokee Drive was
also evaluated based on criteria contained in NCHRP 279. Volumes contained in
Figure 7 were used for the analysis. Using the guidelines for two-lane highways that
are contained in Figure 4-23, a right turn lane is not warranted at the completion of
the development. The results of the analysis are shown in Figure 9.
8.0 Appropriateness of Access Locations
Two accesses are proposed on Stewart Street that are separated by approximately
120’. A two-way access aligns with Cherokee Drive and the other is an outbound
access for the daycare business. It is on the eastern edge of the development and
within 30’ of an adjacent residential driveway.
The driveway spacing criteria for a minor collector includes:
• Distance between “high volume” driveways – 175’
• Distance between driveway edges – 30’
The City standards do not define “high volume”, however, neither of these driveways
would be considered high volume.
The access that aligns with Cherokee Drive will actually be offset by 2.4’ to the west
of the south leg of the intersection resulting in a non-standard condition. There are
two reasons why this offset is acceptable. First, the redirect taper resulting from the
offset needs to be considered because it will impact north/south traffic crossing
Stuart Street. Based on Table 4-9 of the CDOT Access Code6, a 15:1 redirect taper
is allowed for a posted speed of 30 MPH, or less. The CDOT Access Code is based
on AASHTO guidelines. At a 15:1 taper rate, 2.4’ would be traveled in 36’.
Considering that Stuart Street is about 42’ wide, the redirect taper rate is less than
15:1. Therefore, this aspect of the offset shouldn’t impact motorists. Second, the
offset is in a positive direction so that the opposing left turning traffic from Stuart
5 Intersection Channelization Design Guide – National Cooperative Highway Research Program Report 279.
Transportation Research Board. November 1985.
6 State Highway Access Code. Transportation Commission of Colorado. March 2002.
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
3
Street to Cherokee Drive will not conflict. These facts show that the offset will not
impact motorists.
The outbound access for the daycare business will be within 30’ of the adjacent
residential driveway. The volume of traffic on these two driveways will be low and
the likelihood of conflict between the two driveways is minimal. If two motorists
approached Stewart Street from the adjacent driveways at the same time, they will
be able to see each other and avoid entering the street at the same time.
9.0 Intersection Sight Distance
The City’s criteria for minimum intersection sight distance on a minor collector street
is 660’ (Table 7-3). Applying this standard to the corridor would result in the removal
of a substantial amount of parking which would impact the River Modern
development and adjacent residences. Considering that there are no parking
restrictions along the corridor at other intersections, STS is proposing that no parking
restrictions be imposed as a result of this development. The exception is at marked
pedestrian crossings and a marked crossing is not assumed at Cherokee Drive.
10.0 Pedestrian and Bicycle Facilities
The pedestrian and bicycle level-of-service was evaluated based on Section 4.5.3.B
and Appendix H of the City standards. The development is less the ¼ mile from
Prospect Road which is classified as an “Activity Corridor / Center”, therefore the
criteria for that location type was used in the analysis. The development is adjacent
to Spring Creek Trail and the developer is proposing a connection to the trail which
connects to Prospect Road via Robertson Street and Ukiah Lane. Indian Hills Park
is directly across Stewart Street from the development.
Since the development is within the Activity Corridor / Center of Prospect Road, the
minimum level-of-service for each criterion is LOS B. The following is a review of the
criterion based on the City standards:
• Directness. The trail connection proposed by the developer will provide a
route to Prospect Road that is less than 1.4 ratio of actual distance to
minimum distance resulting in LOS A.
• Continuity. The sidewalks on Stewart Street connecting the development
with the network are approximately 5’ wide and attached to the back of curb.
The standard cross section for a minor collector has 5’ detached walks,
therefore, the level-of-service is LOS B.
• Street Crossings. This criteria would apply to crossing Stewart Street to
reach Indian Hills Park. The park is directly across Stewart Street from the
development. A marked crossing exists at Brookhaven Circle East and
pedestrian ramps exist on both sides of Stuart Street. Parking has been
restricted at the crossing and the sight distance should be adequate. The
level-of-service is either LOS A or LOS B.
• Visual Appeal and Pedestrian Amenities. The Spring Creek Trail is in a
natural environment and Stewart Street is a landscaped corridor. The
amenities of a commercial corridor do not exist on Stewart Street resulting in
LOS B.
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
4
• Security. Street lighting is assumed on Stewart Street, however, there is no
street lighting on the Spring Creek Trail. There are good site lines on Stewart
Street, however, the natural character of the Spring Creek Trial would result
in some obstructed site lines. Considering that street lighting would not be
appropriate for the Spring Creek Trail, the lack of lighting should not reduce
the level-of-service. Therefore, the level-of-service is LOS B.
• Surface Condition. The Spring Creek Trail and the sidewalks on Stewart
Street are concrete and in good condition resulting in LOS A.
11.0 Appropriateness of Existing Signing and Markings
Based on the findings of the study, no changes are required to the existing signing
and markings.
12.0 Conclusions
STS has drawn the following conclusions as a result of the study:
• Intersection Level-of-Service. The intersection of Stuart Street / Cherokee
Drive is currently operating at LOS A and will continue to do so following the
completion of this development. The outbound access for the daycare
business will also operate at LOS A.
• Offset of the North Leg of Cherokee Drive. The new north leg of Cherokee
Drive is proposed to be offset by 2.4’. The study concludes that this offset is
acceptable.
• Location of Outbound Daycare Driveway. The outbound access for the
daycare business is proposed to be located within 30’ of an adjacent
residential driveway. The study conclude that this location is acceptable.
• Pedestrian and Bicycle Level-of Service. The analysis performed in the
study concludes that the level-of-service for the pedestrians and cyclists will
be LOS A and LOS B. Therefore, the facilities are acceptable based on City
standards.
• Auxiliary Lanes. The study reviewed the need for left and right turn lanes on
Stuart Street at Cherokee Drive and concluded that they are not required.
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
5
Tables
Table 1 – Intersection Operational Summary
Table 2 – Trip Generation Estimate
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
River Modern
LOS
3/2/2015
1:26 PM
Delay LOS Delay LOS Delay LOS Delay LOS Delay LOS Delay LOS
Stuart Street / Cherokee Drive 0.2 A 0.2 A 0.2 A 0.2 A 0.8 A 0.7 A
Northbound Left Turn plus Right Turn 10 A 10.2 B 10 A 10.3 B --- --- --- ---
Westbound Left Turn plus Thru 7.7 A 8 A 7.7 A 8 A --- --- --- ---
Northbound Left Turn plus Thru plus Right Turn --- --- --- --- --- --- --- --- 10.2 B 10.3 B
Eastbound Left Turn plus Thru plus Right Turn --- --- --- --- --- --- --- --- 7.8 A 7.9 A
Westbound Left Turn plus Thru plus Right Turn --- --- --- --- --- --- --- --- 7.7 A 8 A
Southbound Left Turn plus Thru plus Right Turn --- --- --- --- --- --- --- --- 11.4 B 12.4 B
Stuart Street / Daycare Exit 0.4 A 0.4 A
Southbound Left Turn plus Right Turn 10.9 B 11.8 B
Intersection
Year 2017 Background
Morning Evening
Year 2017 Total
Morning Evening
Table 1. Intersection Operational Summary
Morning Evening
Intersection does not exist. Intersection does not exist.
Existing
C:\Users\Joe\Documents\Projects\Active\River Modern\Project\Excel\River Modern
Trip Gen
3/2/2015
1:26 PM
Rate Total In Out Rate Total In Out Rate Total In Out
Single Family Detached Housing 210 30 DU 9.52 286 143 143 0.75 23 6 17 1.00 30 19 11
Day Care Center 565 42 Students 4.38 184 92 92 0.80 34 18 16 0.81 34 16 18
Total --- 470 235 235 --- 56 23 33 --- 64 35 29
Notes:
2. The land use estimate was provided by KJH Commercial, LLC.
1. Trip generation estimates are based on rates contained in Trip Generation, 9th Edition (Institute of Transportation Engineers, 2012).
Table 2. Trip Generation Estimate
Land Use 2 ITE Code 1 Size Unit
Average Daily Trips Morning Peak Hour Trips Evening Peak Hour Trips
Figures
Figure 1 – Vicinity Map
Figure 2 – Site Plan
Figure 3 – Existing Peak Hour Weekday Traffic Volumes
Figure 4 – Trip Distribution
Figure 5 – Trip Assignment
Figure 6 – Year 2017 Background Traffic Volumes
Figure 7 – Year 2017 Term Total Traffic Volumes
Figure 8 – Need for an Eastbound Left Turn Lane
Figure 9 – Need for a Westbound Right Turn Lane
Figure 10 – Pedestrian and Bicycle Facility Map
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
Stuart Street
Columbia Road
Drake Road
Prospect Road
College Avenue
Lemay Avenue
Stover Street
PROJECT
SITE
Cherokee Drive
LEGEND
- Collector
- 4 Lane Arterial
- 6 Lane Major Arterial
- Local
Scale 1" = 750' Date March 3, 2015 Drawn by JBH Job # KJH Commercial, LLC Figure 1
River Modern Traffic Impact Study
VICINITY MAP
- 2 Lane Arterial
Stuart Street
Cherokee Drive
Daycare
Outbound Daycare Access
Scale 1" = 100' Date March 3, 2015 Drawn by JBH Job # KJH Commercial, LLC Figure 2
River Modern Traffic Impact Study
SITE PLAN
Stuart Street
Prospect Road
Lemay Avenue
Cherokee Drive
A / A
A / A
Stover Street
LEGEND
- Morning / Evening
Peak Hour Traffic Volumes
- Approach Laneage
X / X - Morning / Evening
Peak Hour LOS
Scale 1" = 750' Date March 3, 2015 Drawn by JBH Job # KJH Commercial, LLC Figure 3
River Modern Traffic Impact Study
EXISTING TRAFFIC VOLUMES
50%
50%
Cherokee Drive
Stuart Street
Prospect Road
Stover Street
Scale 1" = 500' Date March 3, 2015 Drawn by JBH Job # KJH Commercial, LLC Figure 4
River Modern Traffic Impact Study
TRIP DISTRIBUTION
Stuart Street
Columbia Road
Prospect Road
Lemay Avenue
Cherokee Drive
Stover Street
LEGEND
- Morning / Evening
Peak Hour Traffic Volumes
- Movement
Scale 1" = 750' Date March 3, 2015 Drawn by JBH Job # KJH Commercial, LLC Figure 5
River Modern Traffic Impact Study
TRIP ASSIGNMENT
Stuart Street
Columbia Road
Prospect Road
Lemay Avenue
Cherokee Drive
A / A
A / A
LEGEND
- Morning / Evening
Peak Hour Traffic Volumes
- Approach Laneage
X / X - Morning / Evening
Peak Hour LOS
Stover Street
Scale 1" = 750' Date March 3, 2015 Drawn by JBH Job # KJH Commercial, LLC Figure 6
River Modern Traffic Impact Study
YEAR 2017 BACKGROUND TRAFFIC VOLUMES
Stuart Street
Columbia Road
Prospect Road
Lemay Avenue
Cherokee Drive
Stover Street
LEGEND
- Morning / Evening
Peak Hour Traffic Volumes
- Approach Laneage
X / X - Morning / Evening
Peak Hour LOS
A / A
A / A
Scale 1" = 750' Date March 3, 2015 Drawn by JBH Job # KJH Commercial, LLC Figure 7
River Modern Traffic Impact Study
YEAR 2017 TERM TOTAL TRAFFIC VOLUMES
Peak Hour
AM
PM
% LT's
5%
6%
Advancing
208
268
Opposing
220
241
4%
3%
Scale NTS Date March 3, 2015 Drawn by JBH Job # KJH Commercial, LLC Figure 8
River Modern Traffic Impact Study
NEED FOR AN EASTBOUND LEFT TURN LANE
Peak Hour
AM
PM
Advancing
220
241
RT Volume
12
18
AM PM
Scale NTS Date March 3, 2015 Drawn by JBH Job # KJH Commercial, LLC Figure 9
River Modern Traffic Impact Study
NEED FOR A WESTBOUND RIGHT TURN LANE
R = 1320'
Stuart Street
Prospect Road
Project Site Spring Creek
Trail
Scale 1" = 500' Date March 3, 2015 Drawn by JBH Job # KJH Commercial, LLC Figure 10
River Modern Traffic Impact Study
PEDESTRIAN AND BICYCLE FACILITY MAP
Appendix A
Traffic Count Data
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
File Name : #1 CHEROKEE&STUARTAM
Site Code : 1
Start Date : 2/3/2015
Page No : 2
CHEROKEE DR
Southbound
E STUART ST
Westbound
CHEROKEE DR
Northbound
E STUART ST
Eastbound
Start
Time
Right Thru Left Peds App. Total Right Thru Left Peds App. Total Right Thru Left Peds App. Total Right Thru Left Peds App. Total Int. Total
Peak Hour Analysis From 07:00 AM to 08:45 AM - Peak 1 of 1
Peak Hour for Entire Intersection Begins at 07:00 AM
07:00 AM 0 0 0 0 0 0 34 0 0 34 1 0 1 0 2 0 44 0 0 44 80
07:15 AM 0 0 0 0 0 0 59 1 0 60 1 0 0 0 1 0 54 0 1 55 116
07:30 AM 0 0 0 0 0 0 56 0 0 56 1 0 0 0 1 0 53 0 0 53 110
07:45 AM 0 0 0 0 0 0 44 0 0 44 1 0 0 0 1 0 40 0 0 40 85
Total Volume 0 0 0 0 0 0 193 1 0 194 4 0 1 0 5 0 191 0 1 192 391
% App. Total 0 0 0 0 0 99.5 0.5 0 80 0 20 0 0 99.5 0 0.5
PHF .000 .000 .000 .000 .000 .000 .818 .250 .000 .808 1.00 .000 .250 .000 .625 .000 .884 .000 .250 .873 .843
CHEROKEE DR
E STUART ST
E STUART ST
CHEROKEE DR
Right
0
Thru
0
Left
0
Peds
0
Out In Total
0 0 0
Right
0
Thru
193
Left
1
Peds
0
Out In Total
195 194 389
Left
1
Thru
0
Right
4
Peds
0
Out In Total
1 5 6
Left
0
File Name : #1 CHEROKEE&STUARTPM
Site Code : 1
Start Date : 2/3/2015
Page No : 2
CHEROKEE DR
Southbound
E STUART ST
Westbound
CHEROKEE DR
Northbound
E STUART ST
Eastbound
Start
Time
Right Thru Left Peds App. Total Right Thru Left Peds App. Total Right Thru Left Peds App. Total Right Thru Left Peds App. Total Int. Total
Peak Hour Analysis From 04:00 PM to 05:45 PM - Peak 1 of 1
Peak Hour for Entire Intersection Begins at 04:30 PM
04:30 PM 0 0 0 0 0 0 53 0 0 53 1 0 0 0 1 1 46 0 1 48 102
04:45 PM 0 0 0 0 0 0 41 0 0 41 1 0 0 1 2 0 42 0 1 43 86
05:00 PM 0 0 0 0 0 0 50 1 0 51 2 0 0 2 4 0 86 0 0 86 141
05:15 PM 0 0 0 0 0 0 62 1 0 63 3 0 0 0 3 1 68 0 0 69 135
Total Volume 0 0 0 0 0 0 206 2 0 208 7 0 0 3 10 2 242 0 2 246 464
% App. Total 0 0 0 0 0 99 1 0 70 0 0 30 0.8 98.4 0 0.8
PHF .000 .000 .000 .000 .000 .000 .831 .500 .000 .825 .583 .000 .000 .375 .625 .500 .703 .000 .500 .715 .823
CHEROKEE DR
E STUART ST
E STUART ST
CHEROKEE DR
Right
0
Thru
0
Left
0
Peds
0
Out In Total
0 0 0
Right
0
Thru
206
Left
2
Peds
0
Out In Total
249 208 457
Left
0
Thru
0
Right
7
Peds
3
Out In Total
4 10 14
Left
0
Appendix B
Synchro Analysis Results
Sustainable Traffic Solutions, Inc.
River Modern Traffic Impact Study KJH Commercial, LLC
Fort Collins, Colorado March 3, 2015
3: Cherokee Drive/Site Access & Stuart Street Existing
900 E. Stuart Timing Plan: AM
Henderson - Sustainable Traffic Solutions, Inc. Synchro 8 Report
2/27/2015
Intersection
Int Delay, s/veh 0.2
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Vol, veh/h 0 191 0 1 193 0 1 0 4 0 0 0
Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0
Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 87 87 87 81 81 81 63 63 63 92 92 92
Heavy Vehicles, % 2 2 2 2 2 2 2 2 2 2 2 2
Mvmt Flow 0 220 0 1 238 0 2 0 6 0 0 0
Major/Minor Major1 Major2 Minor1 Minor2
Conflicting Flow All 238 0 0 220 0 0 461 461 220 464 461 238
Stage 1 - - - - - - 220 220 - 241 241 -
Stage 2 - - - - - - 241 241 - 223 220 -
Critical Hdwy 4.12 - - 4.12 - - 7.12 6.52 6.22 7.12 6.52 6.22
Critical Hdwy Stg 1 - - - - - - 6.12 5.52 - 6.12 5.52 -
Critical Hdwy Stg 2 - - - - - - 6.12 5.52 - 6.12 5.52 -
Follow-up Hdwy 2.218 - - 2.218 - - 3.518 4.018 3.318 3.518 4.018 3.318
Pot Cap-1 Maneuver 1329 - - 1349 - - 511 497 820 508 497 801
Stage 1 - - - - - - 782 721 - 762 706 -
Stage 2 - - - - - - 762 706 - 780 721 -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 1329 - - 1349 - - 511 497 820 504 497 801
Mov Cap-2 Maneuver - - - - - - 511 497 - 504 497 -
Stage 1 - - - - - - 782 721 - 762 705 -
Stage 2 - - - - - - 761 705 - 774 721 -
Approach EB WB NB SB
HCM Control Delay, s 0 0 10 0
HCM LOS B A
Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBR SBLn1
Capacity (veh/h) 732 1329 - - 1349 - - -
HCM Lane V/C Ratio 0.011 - - - 0.001 - - -
HCM Control Delay (s) 10 0 - - 7.7 0 - 0
HCM Lane LOS B A - - A A - A
HCM 95th %tile Q(veh) 0 0 - - 0 - - -
3: Cherokee Drive/Site Access & Stuart Street Existing
900 E. Stuart Timing Plan: PM
Henderson - Sustainable Traffic Solutions, Inc. Synchro 8 Report
2/27/2015
Intersection
Int Delay, s/veh 0.2
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Vol, veh/h 0 242 2 2 206 0 0 0 7 0 0 0
Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0
Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 72 72 72 83 83 83 63 63 63 92 92 92
Heavy Vehicles, % 2 2 2 2 2 2 2 2 2 2 2 2
Mvmt Flow 0 336 3 2 248 0 0 0 11 0 0 0
Major/Minor Major1 Major2 Minor1 Minor2
Conflicting Flow All 248 0 0 339 0 0 591 591 338 596 592 248
Stage 1 - - - - - - 338 338 - 253 253 -
Stage 2 - - - - - - 253 253 - 343 339 -
Critical Hdwy 4.12 - - 4.12 - - 7.12 6.52 6.22 7.12 6.52 6.22
Critical Hdwy Stg 1 - - - - - - 6.12 5.52 - 6.12 5.52 -
Critical Hdwy Stg 2 - - - - - - 6.12 5.52 - 6.12 5.52 -
Follow-up Hdwy 2.218 - - 2.218 - - 3.518 4.018 3.318 3.518 4.018 3.318
Pot Cap-1 Maneuver 1318 - - 1220 - - 419 420 704 415 419 791
Stage 1 - - - - - - 676 641 - 751 698 -
Stage 2 - - - - - - 751 698 - 672 640 -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 1318 - - 1220 - - 418 419 704 408 418 791
Mov Cap-2 Maneuver - - - - - - 418 419 - 408 418 -
Stage 1 - - - - - - 676 641 - 751 697 -
Stage 2 - - - - - - 749 697 - 661 640 -
Approach EB WB NB SB
HCM Control Delay, s 0 0.1 10.2 0
HCM LOS B A
Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBR SBLn1
Capacity (veh/h) 704 1318 - - 1220 - - -
HCM Lane V/C Ratio 0.016 - - - 0.002 - - -
HCM Control Delay (s) 10.2 0 - - 8 0 - 0
HCM Lane LOS B A - - A A - A
HCM 95th %tile Q(veh) 0 0 - - 0 - - -
3: Cherokee Drive/Site Access & Stuart Street Year 2017 Background
900 E. Stuart Timing Plan: AM
Henderson - Sustainable Traffic Solutions, Inc. Synchro 8 Report
2/27/2015
Intersection
Int Delay, s/veh 0.2
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Vol, veh/h 0 197 0 1 199 0 1 0 4 0 0 0
Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0
Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 87 87 87 81 81 81 63 63 63 92 92 92
Heavy Vehicles, % 2 2 2 2 2 2 2 2 2 2 2 2
Mvmt Flow 0 226 0 1 246 0 2 0 6 0 0 0
Major/Minor Major1 Major2 Minor1 Minor2
Conflicting Flow All 246 0 0 226 0 0 474 474 226 478 474 246
Stage 1 - - - - - - 226 226 - 248 248 -
Stage 2 - - - - - - 248 248 - 230 226 -
Critical Hdwy 4.12 - - 4.12 - - 7.12 6.52 6.22 7.12 6.52 6.22
Critical Hdwy Stg 1 - - - - - - 6.12 5.52 - 6.12 5.52 -
Critical Hdwy Stg 2 - - - - - - 6.12 5.52 - 6.12 5.52 -
Follow-up Hdwy 2.218 - - 2.218 - - 3.518 4.018 3.318 3.518 4.018 3.318
Pot Cap-1 Maneuver 1320 - - 1342 - - 501 489 813 498 489 793
Stage 1 - - - - - - 777 717 - 756 701 -
Stage 2 - - - - - - 756 701 - 773 717 -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 1320 - - 1342 - - 501 489 813 494 489 793
Mov Cap-2 Maneuver - - - - - - 501 489 - 494 489 -
Stage 1 - - - - - - 777 717 - 756 700 -
Stage 2 - - - - - - 755 700 - 767 717 -
Approach EB WB NB SB
HCM Control Delay, s 0 0 10 0
HCM LOS B A
Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBR SBLn1
Capacity (veh/h) 723 1320 - - 1342 - - -
HCM Lane V/C Ratio 0.011 - - - 0.001 - - -
HCM Control Delay (s) 10 0 - - 7.7 0 - 0
HCM Lane LOS B A - - A A - A
HCM 95th %tile Q(veh) 0 0 - - 0 - - -
3: Cherokee Drive/Site Access & Stuart Street Year 2017 Background
900 E. Stuart Timing Plan: PM
Henderson - Sustainable Traffic Solutions, Inc. Synchro 8 Report
2/27/2015
Intersection
Int Delay, s/veh 0.2
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Vol, veh/h 0 249 2 2 212 0 0 0 7 0 0 0
Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0
Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 72 72 72 83 83 83 63 63 63 92 92 92
Heavy Vehicles, % 2 2 2 2 2 2 2 2 2 2 2 2
Mvmt Flow 0 346 3 2 255 0 0 0 11 0 0 0
Major/Minor Major1 Major2 Minor1 Minor2
Conflicting Flow All 255 0 0 349 0 0 607 607 347 613 609 255
Stage 1 - - - - - - 347 347 - 260 260 -
Stage 2 - - - - - - 260 260 - 353 349 -
Critical Hdwy 4.12 - - 4.12 - - 7.12 6.52 6.22 7.12 6.52 6.22
Critical Hdwy Stg 1 - - - - - - 6.12 5.52 - 6.12 5.52 -
Critical Hdwy Stg 2 - - - - - - 6.12 5.52 - 6.12 5.52 -
Follow-up Hdwy 2.218 - - 2.218 - - 3.518 4.018 3.318 3.518 4.018 3.318
Pot Cap-1 Maneuver 1310 - - 1210 - - 408 411 696 405 410 784
Stage 1 - - - - - - 669 635 - 745 693 -
Stage 2 - - - - - - 745 693 - 664 633 -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 1310 - - 1210 - - 407 410 696 398 409 784
Mov Cap-2 Maneuver - - - - - - 407 410 - 398 409 -
Stage 1 - - - - - - 669 635 - 745 692 -
Stage 2 - - - - - - 744 692 - 653 633 -
Approach EB WB NB SB
HCM Control Delay, s 0 0.1 10.3 0
HCM LOS B A
Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBR SBLn1
Capacity (veh/h) 696 1310 - - 1210 - - -
HCM Lane V/C Ratio 0.016 - - - 0.002 - - -
HCM Control Delay (s) 10.3 0 - - 8 0 - 0
HCM Lane LOS B A - - A A - A
HCM 95th %tile Q(veh) 0 0 - - 0 - - -
3: Cherokee Drive/Site Access & Stuart Street Year 2017 Total
900 E. Stuart Timing Plan: AM
Henderson - Sustainable Traffic Solutions, Inc. Synchro 8 Report
2/27/2015
Intersection
Int Delay, s/veh 0.8
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Vol, veh/h 11 197 0 1 207 12 1 0 4 8 0 9
Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0
Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 87 87 87 81 81 81 63 63 63 85 85 85
Heavy Vehicles, % 2 2 2 2 2 2 2 2 2 2 2 2
Mvmt Flow 13 226 0 1 256 15 2 0 6 9 0 11
Major/Minor Major1 Major2 Minor1 Minor2
Conflicting Flow All 270 0 0 226 0 0 523 525 226 520 517 263
Stage 1 - - - - - - 252 252 - 265 265 -
Stage 2 - - - - - - 271 273 - 255 252 -
Critical Hdwy 4.12 - - 4.12 - - 7.12 6.52 6.22 7.12 6.52 6.22
Critical Hdwy Stg 1 - - - - - - 6.12 5.52 - 6.12 5.52 -
Critical Hdwy Stg 2 - - - - - - 6.12 5.52 - 6.12 5.52 -
Follow-up Hdwy 2.218 - - 2.218 - - 3.518 4.018 3.318 3.518 4.018 3.318
Pot Cap-1 Maneuver 1293 - - 1342 - - 465 458 813 467 462 776
Stage 1 - - - - - - 752 698 - 740 689 -
Stage 2 - - - - - - 735 684 - 749 698 -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 1293 - - 1342 - - 454 452 813 459 456 776
Mov Cap-2 Maneuver - - - - - - 454 452 - 459 456 -
Stage 1 - - - - - - 743 690 - 731 688 -
Stage 2 - - - - - - 724 683 - 734 690 -
Approach EB WB NB SB
HCM Control Delay, s 0.4 0 10.2 11.4
HCM LOS B B
Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBR SBLn1
Capacity (veh/h) 702 1293 - - 1342 - - 586
HCM Lane V/C Ratio 0.011 0.01 - - 0.001 - - 0.034
HCM Control Delay (s) 10.2 7.8 0 - 7.7 0 - 11.4
HCM Lane LOS B A A - A A - B
HCM 95th %tile Q(veh) 0 0 - - 0 - - 0.1
6: Stuart Street & Daycare Exit Year 2017 Total
900 E. Stuart Timing Plan: AM
Henderson - Sustainable Traffic Solutions, Inc. Synchro 8 Report
2/27/2015
Intersection
Int Delay, s/veh 0.4
Movement EBL EBT WBT WBR SBL SBR
Vol, veh/h 0 201 212 0 8 8
Conflicting Peds, #/hr 0 0 0 0 0 0
Sign Control Free Free Free Free Stop Stop
RT Channelized - None - None - None
Storage Length - - - - 0 -
Veh in Median Storage, # - 0 0 - 0 -
Grade, % - 0 0 - 0 -
Peak Hour Factor 87 87 81 81 85 85
Heavy Vehicles, % 2 2 2 2 2 2
Mvmt Flow 0 231 262 0 9 9
Major/Minor Major1 Major2 Minor2
Conflicting Flow All 262 0 - 0 493 262
Stage 1 - - - - 262 -
Stage 2 - - - - 231 -
Critical Hdwy 4.12 - - - 6.42 6.22
Critical Hdwy Stg 1 - - - - 5.42 -
Critical Hdwy Stg 2 - - - - 5.42 -
Follow-up Hdwy 2.218 - - - 3.518 3.318
Pot Cap-1 Maneuver 1302 - - - 535 777
Stage 1 - - - - 782 -
Stage 2 - - - - 807 -
Platoon blocked, % - - -
Mov Cap-1 Maneuver 1302 - - - 535 777
Mov Cap-2 Maneuver - - - - 535 -
Stage 1 - - - - 782 -
Stage 2 - - - - 807 -
Approach EB WB SB
HCM Control Delay, s 0 0 10.9
HCM LOS B
Minor Lane/Major Mvmt EBL EBT WBT WBR SBLn1
Capacity (veh/h) 1302 - - - 634
HCM Lane V/C Ratio ---- 0.03
HCM Control Delay (s) 0 - - - 10.9
HCM Lane LOS A - - - B
HCM 95th %tile Q(veh) 0 - - - 0.1
3: Cherokee Drive/Site Access & Stuart Street Year 2017 Total
900 E. Stuart Timing Plan: PM
Henderson - Sustainable Traffic Solutions, Inc. Synchro 8 Report
2/27/2015
Intersection
Int Delay, s/veh 0.7
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Vol, veh/h 17 249 2 2 221 18 0 0 7 5 0 6
Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0
Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 72 72 72 83 83 83 63 63 63 85 85 85
Heavy Vehicles, % 2 2 2 2 2 2 2 2 2 2 2 2
Mvmt Flow 24 346 3 2 266 22 0 0 11 6 0 7
Major/Minor Major1 Major2 Minor1 Minor2
Conflicting Flow All 288 0 0 349 0 0 679 687 347 682 678 277
Stage 1 - - - - - - 394 394 - 282 282 -
Stage 2 - - - - - - 285 293 - 400 396 -
Critical Hdwy 4.12 - - 4.12 - - 7.12 6.52 6.22 7.12 6.52 6.22
Critical Hdwy Stg 1 - - - - - - 6.12 5.52 - 6.12 5.52 -
Critical Hdwy Stg 2 - - - - - - 6.12 5.52 - 6.12 5.52 -
Follow-up Hdwy 2.218 - - 2.218 - - 3.518 4.018 3.318 3.518 4.018 3.318
Pot Cap-1 Maneuver 1274 - - 1210 - - 366 370 696 364 374 762
Stage 1 - - - - - - 631 605 - 725 678 -
Stage 2 - - - - - - 722 670 - 626 604 -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 1274 - - 1210 - - 356 361 696 351 365 762
Mov Cap-2 Maneuver - - - - - - 356 361 - 351 365 -
Stage 1 - - - - - - 616 591 - 708 677 -
Stage 2 - - - - - - 714 669 - 602 590 -
Approach EB WB NB SB
HCM Control Delay, s 0.5 0.1 10.3 12.4
HCM LOS B B
Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBR SBLn1
Capacity (veh/h) 696 1274 - - 1210 - - 497
HCM Lane V/C Ratio 0.016 0.019 - - 0.002 - - 0.026
HCM Control Delay (s) 10.3 7.9 0 - 8 0 - 12.4
HCM Lane LOS B A A - A A - B
HCM 95th %tile Q(veh) 0 0.1 - - 0 - - 0.1
6: Stuart Street & Daycare Exit Year 2017 Total
900 E. Stuart Timing Plan: PM
Henderson - Sustainable Traffic Solutions, Inc. Synchro 8 Report
2/27/2015
Intersection
Int Delay, s/veh 0.4
Movement EBL EBT WBT WBR SBL SBR
Vol, veh/h 0 262 232 0 9 9
Conflicting Peds, #/hr 0 0 0 0 0 0
Sign Control Free Free Free Free Stop Stop
RT Channelized - None - None - None
Storage Length - - - - 0 -
Veh in Median Storage, # - 0 0 - 0 -
Grade, % - 0 0 - 0 -
Peak Hour Factor 71 71 83 83 85 85
Heavy Vehicles, % 2 2 2 2 2 2
Mvmt Flow 0 369 280 0 11 11
Major/Minor Major1 Major2 Minor2
Conflicting Flow All 280 0 - 0 649 280
Stage 1 - - - - 280 -
Stage 2 - - - - 369 -
Critical Hdwy 4.12 - - - 6.42 6.22
Critical Hdwy Stg 1 - - - - 5.42 -
Critical Hdwy Stg 2 - - - - 5.42 -
Follow-up Hdwy 2.218 - - - 3.518 3.318
Pot Cap-1 Maneuver 1283 - - - 434 759
Stage 1 - - - - 767 -
Stage 2 - - - - 699 -
Platoon blocked, % - - -
Mov Cap-1 Maneuver 1283 - - - 434 759
Mov Cap-2 Maneuver - - - - 434 -
Stage 1 - - - - 767 -
Stage 2 - - - - 699 -
Approach EB WB SB
HCM Control Delay, s 0 0 11.8
HCM LOS B
Minor Lane/Major Mvmt EBL EBT WBT WBR SBLn1
Capacity (veh/h) 1283 - - - 552
HCM Lane V/C Ratio ---- 0.038
HCM Control Delay (s) 0 - - - 11.8
HCM Lane LOS A - - - B
HCM 95th %tile Q(veh) 0 - - - 0.1
Thru
242
Right
2
Peds
2
Out In Total
206 246 452
Peak Hour Begins at 04:30 PM
Class 1
Peak Hour Data
North
All Traffic Data Services,Inc.
9660 W 44th Ave
Wheat Ridge,CO 80033
www.alltrafficdata.net
Thru
191
Right
0
Peds
1
Out In Total
194 192 386
Peak Hour Begins at 07:00 AM
Class 1
Peak Hour Data
North
All Traffic Data Services,Inc.
9660 W 44th Ave
Wheat Ridge,CO 80033
www.alltrafficdata.net