HomeMy WebLinkAboutTHE LEARNING EXPERIENCE @ MIRAMONT OFFICE PARK - PDP130023 - SUBMITTAL DOCUMENTS - ROUND 1 - PLANNING OBJECTIVESDear City of Fort Collins,
Rubenstein Real Estate, Co., LC, on behalf of Fort Collins Development Co., LLC, has contracted to buy 0.237
acres of land at The Miramont Office Park, Lot 3, Pad E; Larimer County; to build a 10,000 SF “Child
Development Facility” with a contiguous 5,000 SF playground for The Learning Experience “TLE”.
TLE is a privately held company headquartered in Boca Raton, Florida. TLE focuses on early childhood
development for children aging from 6 weeks to 6 six years old, and after school care for children up to 9
years old.
TLE currently has 120 operating facilities and 60 facilities under development in 22 states. This facility will be
the fifth in Colorado.
Please visit TLE at their website: www.thelearningexperience.com
The development of Pad E in Lot 3 includes constructing a 10,000 SF building, a contiguous 5,000 SF
playground, and fully landscaping the pad.
TLE will be an outstanding addition to the Miramont Office Park, and the surrounding neighborhoods. The
facility will allow enrollment up to 170 children and will have a staff of approximately 30. TLE provides the
tools and environment that gives children every opportunity to develop to their greatest potential. TLE has a
cutting edge proprietary curriculum; over 88% of TLE’s 4-year old children are reading. TLE builds a strong
foundation for each child to grow emotionally, socially, and cognitively at his/her own pace.
Adam Rubenstein represents the applicant and is the “Single Point of Contact” for the application; his
information is below:
Adam Rubenstein Office: 720-529-2881
5150 East Yale Circle, Suite 400 Cell: 303-257-1481
Denver, CO 80222 arubenstein@legendretailgroup.com
.
Statement of Planning Objectives (D)
(i) This project is an infill commercial development, which the City of Fort Collins supports.
(ii) The Learning Experience will be taking the last pad in the already existing Miramont Office
Park. We will have a 10,000 sf building with a contiguous 5,000 sf playground. The
playground will be encompassed by an opaque fence that has landscaping surrounding the
exterior. There is an onsite detention pond.
(iii) The Miramont Office Park consists of five pads and five buildings. Each building has a
separate owner. The owners are all a part of the Declaration of Covenants, Conditions, and
Restrictions for the Miramont Office Park dated October 11, 2000 reception # 2000070367
to govern and maintain the office park and common areas. Pad E will be owned by the Fort
Collins Development Co, LLC which is controlled and Managed by John and Adam
Rubenstein. Pad E will be a part of the CCR’s mentioned above.
(iv) The Learning Experience will be licensed for roughly 170 children. The Learning Experience
will employ an estimated 30-35 employees.
(v) The Learning Experience chose the Miramont Office Park for its Ft. Collins home because of
its location off of Harmony Rd and Boardwalk. It is next to several businesses and located in
an established, yet growing community. The Learning Experience building has been
designed to match the rest of the office park. We will have a 5,000 sf playground, with an
opaque fence. We are using an opaque fence for security reasons. We will have landscaping
surrounding the fence to help camouflage the fence.
(vi) Child Care is a permitted use under the current zoning restrictions.
(vii) We are the fifth and last piece to an already existing office park. The City supports infill
projects.
(viii) No neighborhood meeting has taken place.
(ix) The Learning Experience at Miramont Office Park
(E) Attached hereto
(F) No new street names are being proposed
(G) Attached hereto
(H) Gene Vaughan 970.226.3990 work
970.227.5968 mobile
genev@remax.net
Gary Nordic 970.217.1742 mobile
gary@garynordic.com
Ron Young 970.481.0808 mobile
ronyoung@frii.com
(I) John Rubenstein
6310 Lamar, #220
Overland Park, KS 66202
913.362.1999
Adam Rubenstein
5150 East Yale Circle, suite 400
Denver, CO 80222
303.257.1481
(J) Construction schedule
Break ground January/February 2014
Site/utility work 30-45 days
4 months to build the building and furnish the interior
Anticipate an August 2014 opening to the public.
13-16 Not applicable for this project.