July 3, 2013
Mr. Ted Shepard, Chief Planner
City of Fort Collins Planning Department
Development Review Center
281 N. College Ave.
Fort Collins, CO 80524
RE: Aspen Heights Student Housing, FDP130010, Round Number 1
We offer the following responses to staff comments dated May 9, 2013. Consultant responses are noted
in BLUE.
Comment Summary:
Department: Current Planning
Contact: Ted Shepard, 970-221-6343, tshepard@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 05/09/2013
05/09/2013: On the plat, please not that from a street-naming protocol, the suffix for both Steamboat and
Copper Mountain should be "Lane," not "Street." Names have been corrected on the plat, landscape
and site plans.
Comment Number: 2 Comment Originated: 05/09/2013
05/09/2013: Please label the bus stop on all sheets, both Site Plan and Landscape Plan. Bus Stop has
been labeled on the Site Plan and Landscape Plan. A detail for the shelter is shown on sheet 6 of
the Site Plan.
Comment Number: 3 Comment Originated: 05/09/2013
05/09/2013: Staff looks forward to working with the design team on the details of the bus stop. As stated
in a previous comment, the developer has the opportunity to create an identity for the project by
customizing the bus stop in a way that reflects the clubhouse. Regarding the timing of installation of the
bus stop, please add the following note: "Developer shall install the bus stop per the standards of
transfort prior to issuance of Final Certificate of Occupancy for the clubhouse. Bus Stop has been
labeled on the Site Plan and Landscape Plan. A detail for the shelter is shown on sheet 6 of the
Site Plan. The above note has been added to sheet 1 as requested.
Comment Number: 5 Comment Originated: 05/09/2013
05/09/2013: The Vail B is listed as a single family detached but appears from the elevation as a
two-family. (There are two “A-22” sheets, looks like one should be “A-23).) The “Vail B” is a 4-
bedroom, single-family detached. The elevation has been corrected, as has the page numbering
and Index to Drawings.
Comment Number: 6 Comment Originated: 05/09/2013
05/09/2013: Be sure that bike racks do not interfere with landscaping. So noted.
Comment Number: 7 Comment Originated: 05/09/2013
05/09/2013: Staff will advise as to how best to label "New Vine" on the final documents. Please do not
label it as "Pinon" as the name must be selected from an approved list and by City Council. "Pinon" is not
on this list nor has it been selected by City Council. So noted.
2
Comment Number: 8 Comment Originated: 05/09/2013
05/09/2013: There is a typo on the cover sheet of the Site Plan. The correct Land Use Code citation for
the parking table is Section 3.2.2(K)(1). Corrected
Comment Number: 9 Comment Originated: 05/09/2013
05/09/2013: There are some trash enclosures that are not labeled on sheets 9 and 10 of the Site Plan.
The enclosures are labeled. Enclosures outside of the match lines are only labeled on its
respective sheet (not in the overlaps).
Department: Engineering Development Review
Contact: Sheri Langenberger, 970-221-6573, slangenberger@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 05/01/2013
05/01/2013: Plat - I would imagine that the power company that has the major power line easement
across the edge of the property will need to sign the plat. Signature blocks for Poudre Valley REA and
for Excel Energy have been added to the plat.
Comment Number: 2 Comment Originated: 05/01/2013
05/01/2013: See redlines on plat. Redlines have been addressed and returned for your review.
Comment Number: 3 Comment Originated: 05/01/2013
05/01/2013: Site and Landscape plans - The off-site sidewalk is shown as asphalt on the site
plan and concrete on the landscape plans and it is not currently called out on the utility plans. It can be
asphalt, just make sure all the notes match.
Please see sheet 17 of the Grading Plans for the offsite sidewalk connection detail. The alignment
is shown on the Site Plan, Page 5. The sidewalk will be a temporary attached asphalt sidewalk
that will be replaced with detached concrete sidewalk when the adjacent property is developed.
All plans are labeled “asphalt”.
Comment Number: 4 Comment Originated: 05/01/2013
05/01/2013: Site and Landscape plans - Need to show the power poles on these plans. Redwood power
poles are shown on the landscape and site plans.
Comment Number: 5 Comment Originated: 05/01/2013
05/01/2013: Site and Landscape plans - On the overall site plan, need to somehow clarify what portion of
New Vine is being built and what portion is future. The phasing plan (Landscape sheet 2, and 65-68
on the Civil Set) shows the frontage of Vine from the flow-line back, on either side of Blue Spruce
included in the SW phase of the project. All other Vine construction is shown as future on all plan
sets.
Comment Number: 6 Comment Originated: 05/01/2013
05/01/2013: Site and Landscape plans - Please show the new property line as the back of sidewalk
along Conifer and Redwood since that is where it will be once the plat is filed and the sidewalk is built.
The property line is shown back of sidewalk, and reflects the most recent line work submitted for
the plat.
Comment Number: 7 Comment Originated: 05/01/2013
05/01/2013: Site and Landscape plans - You will need to discuss the proposed pedestrian crossings of
Lupine with Traffic Operations as they have criteria for when and where they are allowed and when they
can be striped to determine if what you are proposing will work. There are no mid-block crossings
along Lupine.
Comment Number: 8 Comment Originated: 05/01/2013
05/01/2013: Site and Landscape plans - See additional comments on plans. Redlines have been
addressed and returned for your review.
3
Comment Number: 9 Comment Originated: 05/01/2013
05/01/2013: What plan sheet are you going to show the off-site sidewalk connection and
design? 04/10/12 Need to show the full connection of this. Right now the plans show where it
is to start, but do not yet show how it will tie into the existing walk along Jax. Please see sheet 17 of the
Grading Plans for the offsite sidewalk connection detail. The alignment is shown on the Site Plan,
Page 5. The sidewalk will be a temporary attached asphalt sidewalk that will be replaced with
detached concrete sidewalk when the adjacent property is developed. All plans are labeled
“asphalt”.
1/15/12 A pedestrian connection (sidewalk) from this site along Conifer will need to be
constructed to provide a link from this site to the College Avenue corridor. This off-site
sidewalk can be a temporary asphalt pedestrian connection or a concrete sidewalk in the
ultimate location along this roadway. The City Capital project for North College Ave is underway
and upon completion of that College Ave will have bike lanes and sidewalk along both sides of
it from Conifer south. This site needs to provide a connection to that system. (needs to be
addressed before hearing)
Comment Number: 10 Comment Originated: 05/01/2013
05/01/2013: Need a cross section for Conifer Street showing the temporary sidewalk. A cross section is
shown on sheet 17 of the Grading Plan.
Comment Number: 11 Comment Originated: 05/01/2013
05/01/2013: I will include language in the Development Agreement regarding the portion of Vine Drive
and Lupine Street adjacent to the site that cannot be completed at this time. Noted.
Comment Number: 12 Comment Originated: 05/01/2013
05/01/2013: 04/10/12 As indicated in response letter this New Vine name can remain on the
plans for the time being and will just need to be updated prior to final approval with what ever name has
been determined before that time. Noted. New Vine Drive and Redwood Street will be on separate
construction plans due to the CLOMR delays.
1/15/12 The naming of New Vine will need to be addressed with this project as we can not have two
streets with the name of Vine. Per preliminary discussions with the transportation staff it was felt that a
different name should be assigned to the New Vine alignment. Pinon is a possibility since this is the
name of the street this one will align with across College Ave.
Comment Number: 13 Comment Originated: 05/01/2013
05/01/2013: Due to the change in unit numbers (from the original submittal) and the addition of the club
house the project owes an additional $638 for the PDP TDRF. A check for $638 is included with this
submittal.
04/15/12 As requested, when the clubhouse is shown as part of these drawings the PDP fees for it will
be determined and the credit applied to those fees.
1/15/12 Based on the site plan and plat that was submitted for this site the Transportation Development
Review Fee (TDRF) was overpaid by $15.62. A refund can be provided or a credit of this amount can be
applied to the future FDP application or the additional fees if a clubhouse is added to the plans. The
submitted plans do not include a clubhouse, but the documents indicate that one is to be constructed with
the project. At such time as a clubhouse is added to the project for approval additional TDRF will be
assessed.
Comment Number: 14 Comment Originated: 05/01/2013
05/01/2013: New Vine Drive - Need to show the underdrain for the median in New Vine Drive and how it
ties into the drainage system or the pond. New Vine comments will be addressed when the plan set is
produced in coordination with the CLOMR.
Comment Number: 15 Comment Originated: 05/01/2013
05/01/2013: Street Plans - Need to provide curb return profiles. Curb return profiles are now provided
on all street profile sheets.
4
Comment Number: 16 Comment Originated: 05/01/2013
05/01/2013: Street Plans - Need intersection details. Spot elevations and slopes have been added to
the grading plan (30 scale) at all intersections.
Comment Number: 17 Comment Originated: 05/01/2013
05/01/2013: Street Plans - Are the stationing information at the driveways the centerline station of the
driveways? Need to identify the driveway widths. Driveway widths and centerline stations are now
shown on the street profiles.
Comment Number: 18 Comment Originated: 05/01/2013
05/01/2013: Street Plans - Need striping plans. Signing and striping plans are now included in the
Utility Plans.
Comment Number: 19 Comment Originated: 05/01/2013
05/01/2013: Street Plans - Minimum flow line grade in a sag curve shall be .5%. This needs to be shown
and adjusted for several locations. Noted, flow line grades in sag curves are now a minimum of 0.5%.
Comment Number: 20 Comment Originated: 05/01/2013
05/01/2013: Lupine - Need to show where the property line is and the improvements stop and how the
grading will tie back into grade. Noted, Lupine will stop just short of the property line to so that all
improvements and grading are onsite and offsite grading will not be required.
Comment Number: 21 Comment Originated: 05/01/2013
05/01/2013: Lupine - Minimum flow line grade is .5% Noted, flow line grade in Lupine is now a
minimum of 0.5%.
Comment Number: 22 Comment Originated: 05/01/2013
05/01/2013: Redwood - Need more information provided on the grades and profiles that are being tied
into. Noted, more information is now shown per your redlines
Comment Number: 23 Comment Originated: 05/01/2013
05/01/2013: Redwood - The plans are showing a low point north of New Vine and no inlets are shown at
this time. Noted, this was from an older inlet. The low point is now removed.
Comment Number: 24 Comment Originated: 05/01/2013
05/01/2013: New Vine Drive - Need to provide the 1000 ft off-site design at each end or if your design
ties into the 30% design plans include those sheet(s) in this plan set. New Vine comments will be
addressed when the plan set is produced in coordination with the CLOMR.
Comment Number: 25 Comment Originated: 05/01/2013
05/01/2013: New Vine Drive - What station is the property line? New Vine comments will be addressed
when the plan set is produced in coordination with the CLOMR.
Comment Number: 26 Comment Originated: 05/01/2013
05/01/2013: New Vine Drive - What station is the end of the work and how will the grades tie into existing
grades? Both ends. Are you proposing a temporary curb edge at the east end? New Vine comments
will be addressed when the plan set is produced in coordination with the CLOMR.
Comment Number: 27 Comment Originated: 05/01/2013
05/01/2013: New Vine Drive - The curve information is different than the prior plan? New Vine
comments will be addressed when the plan set is produced in coordination with the CLOMR.
Comment Number: 28 Comment Originated: 05/01/2013
5
05/01/2013: New Vine Drive - I am guessing that the median curb design will be the double curb. A
detail for this will need to be provided. New Vine comments will be addressed when the plan set is
produced in coordination with the CLOMR.
Comment Number: 29 Comment Originated: 05/01/2013
05/01/2013: New Vine Drive - Need information on turn lanes, bay lengths, transition lengths. New Vine
Drive - Need profiles of the median edges. New Vine comments will be addressed when the plan set
is produced in coordination with the CLOMR.
Comment Number: 30 Comment Originated: 05/01/2013
05/01/2013: New Vine Drive - Need turning templates to show that the median noses don’t extend into
the travel paths. This can be exhibits and don’t need to be on these plans. New Vine comments will be
addressed when the plan set is produced in coordination with the CLOMR.
Comment Number: 31 Comment Originated: 05/01/2013
05/01/2013: New Vine Drive - Need to design and provide for pedestrian refuge noses. New Vine
comments will be addressed when the plan set is produced in coordination with the CLOMR.
Comment Number: 32 Comment Originated: 05/01/2013
05/01/2013: New Vine Drive - The station information has not been provided on these profiles. Are you
planning on doing flowline stationing or centerline? If you are doing centerline stationing you will need to
show and use station equations. New Vine comments will be addressed when the plan set is
produced in coordination with the CLOMR.
Comment Number: 33 Comment Originated: 05/01/2013
05/01/2013: Detail 709 has been replaced with a more current design. The updated detail needs to be
used. Detail 709 has been replaced with details City of Fort Collins Construction Details D-10 and
D-10B.
Comment Number: 34 Comment Originated: 05/01/2013
05/01/2013: Additional details needed so far: 1201, 1202, 1413, 1601, 1607, 1606, and 2201. Median
details will also be needed and those for the signing and striping. Additional details 1201, 1202, 1413,
1601, 1607, 1606, 2201, and signing and striping details have been added to the detail sheets.
Median details will be included with the Vine Drive plan set, to be submitted under separate cover.
Comment Number: 35 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - Need to show the street cuts that will be needed for the installation of the
proposed utilities. Street cuts are now shown on the Utility Plans
Comment Number: 36 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - The ramps at Conifer/ Blue Spruce and Lupine/ Redwood need to align with
those across the street. Any conflicting utilities need to be moved to accommodate the ramps. The new
ramps now line up with the existing ramp across the street. Notes have been added to relocate or
adjust existing utilities.
Comment Number: 37 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - Add the street cut note to all utility plan streets. It needs to be on all sheets
showing street cuts. It is not adequate to have the note on the cover sheet. The street cut note has been
added to all utility plan sheets.
Comment Number: 38 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - The utility plans are showing a UGE/COMM line. Is this a private line
6
or a public utility? If private it needs to be sleeved under the row, meet minimum cover requirements
(profile), and a revocable permit will be needed prior to construction of this line. If they are public
(Comcast, Xcel…) then the franchised utility knows what is required. Sleeves are now shown for the
private internet/fiber optic lines and crossings are shown in the public street profiles.
Comment Number: 39 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - Need to identify and label the bus stop improvements. Bus stop
improvements are now labeled on the utility plans
Comment Number: 40 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - Need to show the corner of Redwood/Conifer and the improvements that are to
be done here- ramps. The existing inlet - does it conflict with the ramps? The corners of Redwood &
Conifer are now shown. The inlet and ramps do not conflict as the inlet is only a single inlet and
is shown actual size.
Comment Number: 41 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - Are there ramps across from the ramps that need to be installed at Blue
Spruce/Conifer, Redwood/Conifer, and Lupine/Redwood? If not then this project will need to install those
as well. There are existing ramps across the street at all intersections except at the undeveloped
parcel at the northeast corner of Conifer Street/Blue Spruce Drive. Since there is no sidewalk
along the frontages of this property on both Conifer and Blue Spruce, it will be the responsibility
of that developer to install sidewalk and ramps.
Comment Number: 42 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - The plans show constructing the stormpipes at the sw corner of the site all the
way to the property line and the water line extending past the property line to the west. If these are to be
constructed as shown easements will be needed for the off-site utilities and work. Otherwise the pipes will
need to be shortened so that all excavation and work can be done within the property or row boundaries.
The pipes are now shortened so that excavation work can be completed within property and row
boundaries.
Comment Number: 43 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - Need to show an irrigation service to the median for the landscaping. New Vine
comments will be addressed when the plan set is produced in coordination with the CLOMR.
Comment Number: 44 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - Standards require that a minimum of 3 feet of cover be provided from the top of
pipes to the top of asphalt for lines within and crossing public streets. Many of the stormpipes shown so far
do not meet this requirement. May need to use multiple pipes, elliptical pipes, raise road grades, lower
storm grades or a combination of these solutions. A request for modification of standard has been
included with this submittal for your consideration. The situation has been remediated as much
as possible; please consider this request
Comment Number: 45 Comment Originated: 05/01/2013
05/01/2013: Utility Plans - Need to clearly indicate what pipes are intended to be temporary. Temporary
storm pipes as well as those that are for the future NECCO system are now labeled.
Comment Number: 46 Comment Originated: 05/01/2013
05/01/2013: Grading sheets - Need to show how the proposed grade lines tie into existing grade lines
7
within the property boundaries and/or row or off-site easements will be needed. Grading is now shown to
tie within property and row boundaries.
Comment Number: 47 Comment Originated: 05/01/2013
05/01/2013: Grading sheets - Prior to hearing you provided me an exhibit that showed a pan along the
west property line. This plan does not show that. How will the drainage work along this property line? The
pan is now shown and labeled. The pan will drain to via area inlets to storm drain and then into
the interim detention pond.
Comment Number: 48 Comment Originated: 05/01/2013
05/01/2013: Grading sheets - The pans in the parking lots need to be directed to the curb chases and spot
elevations provided to show that the flow is going to go out that way. May also need slight high points in
the drive so flow is properly directed to the chases in the minor storms. Spot elevations are now
provided to show that the parking drains to the curb chases instead of across the driveway.
Comment Number: 49 Comment Originated: 05/01/2013
05/01/2013: Grading sheets - At the north west corner of Lupine and Redwood – need to show the power
pole and show how the grading can be done around the existing power pole. Also how does that impact
the sidewalk and ramp grades. The grading around the power pole (now shown) will be within 6” of
existing grade and the pole nor the sidewalk or ramps will not be impacted negatively since the
power pole is outside the proposed sidewalk.
Comment Number: 50 Comment Originated: 05/01/2013
05/01/2013: Grading sheets - Will need the power easement owners signature on the sheets showing
grades and improvements under the easement. Acknowledged, the Platte River Power Authority
approval block is now included on the grading sheets.
Comment Number: 51 Comment Originated: 05/01/2013
05/01/2013: Grading sheets - Need to show the grading that will occur in Blondel Street for the installation
of the waterline in this street. The grading is now shown on Blondel over the water line.
Comment Number: 52 Comment Originated: 05/01/2013
05/01/2013: Grading sheets - Need to show the sidewalk on the south side of Vine St that needs to be
installed as per the URA agreement. New Vine comments will be addressed when the plan set is
produced in coordination with the CLOMR.
Comment Number: 53 Comment Originated: 05/01/2013
05/01/2013: Grading sheets - Need a grading sheet for the south portion of Redwood Drive. Redwood
comments will be addressed when the plan set is produced in coordination with the CLOMR.
Comment Number: 54 Comment Originated: 05/01/2013
05/01/2013: Grading sheets - The last set of plans showed a power pole in the NW corner of New Vine
and Redwood Street. How big is this pole and the pad that holds it. What are the power companies
restrictions for grading around these and excavating around them? Not sure that the storm pipe can be in
that close to the pole location. How does the pole impact the sidewalk and ramp grades. The power pole
and widened sidewalk is now shown along with the ramps and how that will work. Grades are
within 6”of existing grades at the power pole. There is approximately 7’ of clearance between the
power pole and the storm drain as currently designed.
8
Comment Number: 55 Comment Originated: 05/01/2013
05/01/2013: Grading sheets - Showing a storm pipe extending past the Redwood Street row going into the
property to the east. If this is to be built with this project than an easement for this construction is needed.
The storm pipe will be stopped within the right-of-way so that an easement will not be required.
Comment Number: 56 Comment Originated: 05/01/2013
05/01/2013: Cover Sheet - A couple of notes on the cover sheet are missing information. The missing
information is now shown on the cover sheet.
Comment Number: 57 Comment Originated: 05/01/2013
05/01/2013: Sheet 2 - See plans for comments. Sheet 2 plan comments have been addressed on the
plans.
Comment Number: 58 Comment Originated: 05/01/2013
05/01/2013: Sheet 3 - General Note 41. The plans appear to be flowline stationing, which is okay this note
just needs to change to reflect this. Sheet 3 now references both centerline and flowline stationing.
Comment Number: 59 Comment Originated: 05/03/2013
05/03/2013: An official written variance for the parking setbacks still needs to be submitted. See 1.9.4 of
the LCUASS for letter criteria.
04/10/12 It looks like the parking setbacks to meet that for the smaller parking lots (40 feet) was applied to
all the parking lots. A variance is needed and will need to be considered if this is the distance you also
wish to use for the large parking lots as well.
1/15/12 Parking setbacks to standards are not being met. In accordance with the standards Figure 19-6
the distance from the flowline to the edge of the first parking stall for the large lots is to be 50 feet and 40
feet for the small parking lots. We can certainly look at a variance request for this. I have not discussed
this with any other the other staff that would also review this variance, so I don’t know if a variance to the
extent the plans are currently designed to would be accepted. (best to be addressed before hearing as it
could impact the parking numbers). A letter of explanation and request for modification of standard is
included with this submittal set for your consideration.
Comment Number: 60 Comment Originated: 05/03/2013
05/03/2013: Traffic Operations and Streets have requested to be routed copies of the utility plans, plat, site
and landscape plans with the next round of review. Sufficient number of copies are included with this
submittal and should be routed per the distribution list provided by Ted Shepard.
Department: Environmental Planning
Contact: Lindsay Ex, 970-224-6143, lex@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 04/23/2013
04/23/2013: Off-site mitigation for the loss of wetlands and prairie dog habitat will be coordinated with the
City's Natural Areas Department prior to signing of the development agreement. Please let me know when
a good time is to set up a meeting to resolve this issue. It might be best for the City to take a stab at the first
draft of the agreement, would that work for you? It appears this will be included with the development
agreement. The Developer would like to review the calculations as soon as possible, so they can
budget for this. Please forward the calculations as soon as possible.
Comment Number: 2 Comment Originated: 04/23/2013
9
04/23/2013: As all of the site's ecological value (except for the trees) will be mitigated for off-site, there is
no longer a need for the establishment of a Natural Habitat Buffer Zone on the plans. Please feel free to
remove that any references to Section 3.4.1 of the Land Use Code. So noted.
Department: Forestry
Contact: Tim Buchanan, 970-221-6361, tbuchanan@fcgov.com
Topic: Landscape Plans
Comment Number: 25 Comment Originated: 05/03/2013
05/03/2013: The landscape architect needs to contact the City Forester to review and discuss several small
changes that need to occur with the street tree design. Information will be provided on items that need to be
addressed. Changes will need to be addressed before final plan. The project LA met with Tim
Buchanan on site on two occasions. The majority of forestry questions were addressed. The
existing trees located off-site are currently being surveyed. Construction impacts will be
assessed once the survey is complete and the off-site plan set is submitted for review.
Comment Number: 26 Comment Originated: 05/03/2013
05/03/2013:
Sheet ENV-1 of 1 the Tree Inventory:
The letters PL are stated to mean Plains cottonwood but in the schedule PC is used. Please address.
Acronyms have been corrected.
The Boxes with the numbers are a little confusing. I suggest the following boxes and totals.
Total number of required mitigation trees 79
Total Plains Cottonwood
Total Peachleaf Willow
Trees retained
Trees removed
Table has been corrected, as suggested.
Add note number 10. If any trees in Gove D, G and H are removed at a future date then the City
Forester will determine if mitigation needs to be revaluated. City Forester must approve any tree removal in
these groves. It appears a small grove of trees will be impacted by the Storm water detention
construction. This is graphically depicted on the tree mitigation plan and shown on the aerial
photography. Numbers of impacted trees have been indicated on the plan.
Add the tree protection specifications found in LUC 3.2.1 G
Tree protection specifications have been added to the Tree Mitigation Plan
Comment Number: 27 Comment Originated: 05/03/2013
05/03/2013: The City Forester recommends using a different ornamental tree than Princess Kay Plum.
Experience has shown that it is very short-lived in Fort Collins. Princess Kay Plum has been replaced
with Ivory Silk Tree Lilac and Thunderchild Crabapple.
10
Comment Number: 28 Comment Originated: 05/03/2013
05/03/2013: General Note21.1.2 should be changed to take out this sentence. Deciduous trees with trunks
large enough to obstruct line of sight for motorist shall be removed by owner. Sentence has been
removed.
Comment Number: 29 Comment Originated: 05/03/2013
05/03/2013: Some landscape contractors prefer to plant trees only 2-3 inches high. This comment is just
for consideration. Tree details have been changed. Please review.
Comment Number: 30 Comment Originated: 05/03/2013
05/03/2013: Previous comment number 23 still needs to be addressed. Please set up an on-site meeting
with the City Forester and a representative from the Engineering Department (Marc Virata) to review the
Redwood Street and Vine Street Alignment impact on the cottonwood trees located by these proposed
roadways. Forestry would like to confirm the actual location of the proposed road improvements by these
trees. The trees that will be impacted along the new roadway alignment for Redwood Drive and
New Vine will be surveyed to determine if any trees can be preserved as a result of construction.
This will be submitted with the Off-site roadway construction plans under separate cover. For the
time being, tree mitigation upsizing of on-site trees will be calculated as if the tree stands in
question will be removed in their entirety. This will be re-visited prior to construction.
Comment Number: 31 Comment Originated: 05/03/2013
05/03/2013: Provide planting detail for trees and shrubs in the detention pond area just off the border of the
project. Include a water basin around trees and shrubs. Details have been edited to include a water
basin for shrubs non-irrigated seed areas.
Comment Number: 32 Comment Originated: 05/03/2013
05/03/2013: Please add this sentence at the end of General Note number 8. This includes trees and
shrubs in the detention pond and all trees, shrubs and irrigated lawn in parkways and in the median located
outside of the project perimeter. This note was added to Note number 8.
Comment Number: 33 Comment Originated: 05/03/2013
05/03/2013: Further define the maintenance responsibility of landscaping outside the limits of
development. This includes trees and shrubs in the detention pond, surface maintenance of the detention
pond, surface maintenance of parkways and landscaping in the median. Contact Bill Whirty, Manager of
Parks, and Hank Richardson, Storm Water Utility, to obtain further definition if the City will take over
maintenance of these areas and if so what their process would be for source of water, irrigation plan
approval, establishment maintenance period and acceptance maintenance. Include appropriate notes to
define the information and decisions provided by these two staff City Staff members. Maintenance
responsibility will be assigned in the Development Agreement for the Off-site improvements that
will be submitted under separate cover. The shrubs along the north and west perimeter of the
detention pond will be maintained by the Aspen Heights Developer.
Comment Number: 34 Comment Originated: 05/03/2013
05/03/2013: The median landscape design needs to be coordinated with Pet Wray of the Planning
Department for review and approval. Design should be to City Streetscape and Median standards. So
noted. Final design will be submitted along with the Off-site Constrution documents which will be
submitted for review under separate cover.
11
Department: Light and Power
Contact: Doug Martine, 970-224-6152, dmartine@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 04/05/2013
04/05/2013: The sewer manhole on the west side of Blue Spruce (appx.120 ft. north of Lupine) needs to
be relocated into the street instead of being in line with the parkway. Acknowledged, the sewer manhole
has been moved as requested.
Comment Number: 2 Comment Originated: 04/05/2013
04/05/2013: The water services to many buildings are shown going to very near the corner of the building.
These need to be relocated toward the center of the building to provide 10 feet clearance to the electric
service and meter which will be on the side corner of the building. Acknowledged, the water and sewer
services have been relocated to provide 10 foot of clearance between electrical where possible
and 5’ elsewhere (approximate max depth of bury) as discussed in your email on 5/24/13.
Comment Number: 3 Comment Originated: 04/05/2013
04/05/2013: The sewer service to the 3rd building east of Blue Spruce on the west side of Echo Mountain
Ln. needs to be relocated so it doesn't go through the island. This will allow for a pad type electric
transformer to be placed in the island. Acknowledged, sewer service has been relocated
Comment Number: 4 Comment Originated: 04/05/2013
04/05/2013: The sewer service to the 4th building east of Blue Spruce on the south side of La Garita Ln.
needs to be relocated so it doesn't go through the island. This will allow for a pad type electric transformer
to be placed in the island. Acknowledged, sewer service has been relocated.
Comment Number: 5 Comment Originated: 04/05/2013
04/05/2013: The developer will need to coordinate power requirements to the clubhouse with Light &
Power Engineering (970)221-6700. Acknowledged, the developer is coordinating with Light & Power
Engineering regarding the clubhouse power requirements.
Comment Number: 6 Comment Originated: 04/05/2013
04/05/2013: After the plan is finalized, an AutoCad drawing (version 2008) of the site plan needs to be sent
to Terry Cox at TCOX@FCGOV.COM. Acknowledged, the required AutoCAD drawing will be sent to
Terry Cox when the plan is finalized.
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler@poudre-fire.org
Topic: General
Comment Number: 01 Comment Originated: 05/03/2013
05/03/2013: FYI ONLY - Response to comment no. 5 (originated 01/05/2012): The HMIA pertaining to pool
chemistry, storage of pesticides, etc. may be supplied at time of building permit. Acknowledged.
Comment Number: 02 Comment Originated: 05/03/2013
05/03/2013: RESIDENTIAL WATER SUPPLY Further review of hydrant placement and possible infill along
Conifer and Redwood Streets is required. It may be necessary to add a hydrant at the corner of Redwood
12
and Lupine and another to Conifer Street between Redwood and Blue Spruce. A site plan detailing all
locations of proposed hydrant and along with existing hydrants which surrounding the development is
requested. Acknowledged, the utility plan now shows all existing and proposed hydrants
surrounding the developments.
Department: Stormwater Engineering
Contact: Jesse Schlam, 970-218-2932, jschlam@fcgov.com
Topic: Erosion Control
Comment Number: 1 Comment Originated: 04/16/2013
04/16/2013: The site disturbs more than 10,000 sq-ft therefore Erosion and Sediment Control Materials
need to be submitted for FDP. The erosion control requirements are in the Stormwater Design Criteria
Under the Amendments of Volume 3 Chapter 7 Section 1.3.3. Current Erosion Control Materials Submitted
do not meet requirements. Please resubmit Erosion Control Plan corrected with redlines. Please submit
and Erosion Control Report, and Please submit an Escrow/ Security Calculation. If you need clarification
concerning this section, or if there are any questions please contact Jesse Schlam 970-218-2932 or email
@ jschlam@fcgov.com. Acknowledged, the erosion control plan is now shown with redlines
addressed along with the utility plans and the drainage report. The Erosion Escrow/Security
Estimate is included in the Drainage and Erosion Control Report.
Department: Stormwater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: Floodplain
Comment Number: 2 Comment Originated: 05/01/2013
05/01/2013: 1. Please address all the red-lined comments on the Plat, Site Plan, Construction Drawings
and Drainage Report.
2. As was noted in the previous review, parts of Redwood Street and new Vine Drive are located in the Dry
Creek floodway. The street improvements, installation of utilities, landscaping, etc. proposed for
construction within that floodway cannot occur until a CLOMR has been approved by FEMA. The plans for
this development cannot be approved until the CLOMR process has been completed.
Acknowledged, red-lined comments are now addressed as requested. Redwood and new Vine
Drive have been separated from the development utility plans to allow for separate processing of
the CLOMR.
Topic: General
Comment Number: 3 Comment Originated: 05/01/2013
05/01/2013: Repeat Comment.
01/10/2012: The construction of Vine Drive will alter existing drainage patterns from areas within Dry Creek
basin northwest of the site. These flows need to be shown how they pass the site and Vine Drive. This will
require a revision to the City's master plan model hydrology, which is the responsibility of the Developer.
Acknowledged, this analysis will be provided with the CLOMR. Redwood and new Vine Drive have
been separated from the development utility plans to allow for separate processing of the CLOMR.
Comment Number: 4 Comment Originated: 05/01/2013
05/01/2013: No hydraulic design submitted. Drainage report looks to be similar to the preliminary drainage
report.
01/17/2012: The hydraulic (including inlets, storm sewers, street capacity, etc.) and erosion control design
13
for this Development will be reviewed during final compliance after a public hearing. Acknowledged, a
hydraulic design was submitted, but to better analyze the site drainage, a SWMM model has been
provided along with inlet sizing, storm sewer sizing, street capacity calculations, etc. Please see
the revised drainage report.
Comment Number: 5 Comment Originated: 05/01/2013
05/01/2013: Repeat Comment.
04/12/2012: Please show all the capital improvements to be built with this development on the plans that
was agreed upon in the letter dated March 20, 2012 by Owen Consulting. Acknowledged, all agreed
upon improvements are shown.
Comment Number: 6 Comment Originated: 05/01/2013
05/01/2013: More detail is needed on the grading plan to show these flows will actually flow north-south
and not get caught between the two properties in low lying areas.
04/12/2012: All off-site drainage flowing onto the site needs to be direct through the site safely and per
City's criteria. The western edge of the site looks like it needs more detail to determine if this will occur and
if off-site easements are required. Acknowledged, additional detail requested is now shown including
along the western edge of the site as well as in the low lying areas to provide positive drainage.
Comment Number: 7 Comment Originated: 05/01/2013
05/01/2013: In general the grading plan needs to be more detailed to ensure proper construction. Suggest
removing the drainage plan from the grading plan. The drainage basin lines are thick and interfere with
grading info. : Acknowledged, additional detail requested is now shown to provide positive
drainage. The drainage and grading plans are also separated to clarify the design.
Comment Number: 8 Comment Originated: 05/01/2013
05/01/2013: Please verify the pond excavation will not affect any of the existing trees. The pond excavation
will impact a small tree stand on the north side of the detention pond where at the outfall. The majority of
the trees will not be impacted. Please review the tree mitigation plan included with the Landscape
Plan, and coordinate with Tim Buchanan, who has been apprised of tree removal plans.
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Building Elevations
Comment Number: 30 Comment Originated: 05/06/2013
05/06/2013: There are line over text issues on several sheets. See redlines. Acknowleged.
Comment Number: 31 Comment Originated: 05/06/2013
05/06/2013: There are issues between the index on sheet A-1 and the actual sheet titles. See redlines.
The sheet index has been corrected, along with the addition of several new elevations. The index should
be correct at this time.
Comment Number: 32 Comment Originated: 05/06/2013
05/06/2013: Please correct the number on sheet A-23. Complete
Comment Number: 33 Comment Originated: 05/06/2013
14
05/06/2013: There is a text over text issue on sheets A-11 & A-23. See redlines. Complete
Comment Number: 34 Comment Originated: 05/06/2013
05/06/2013: There is cut off text on sheets A-11 & A-13. See redlines. Complete.
Comment Number: 35 Comment Originated: 05/06/2013
05/06/2013: Please mask all text that is in hatching on sheet A-25. See redlines. Masking is sometimes
not successful when translating AutoCad drawings to other formats. This will only be used when
absolutely necessary. Thank you for your patience.
Topic: Construction Drawings
Comment Number: 36 Comment Originated: 05/07/2013
05/07/2013: There are line over text issues on several sheets. See redlines. Complete
Comment Number: 37 Comment Originated: 05/07/2013
05/07/2013: There are text over text issues on several sheets. See redlines. Complete
Comment Number: 38 Comment Originated: 05/07/2013
05/07/2013: There are matchline issues on sheets 14, 15, 37, 38, 41 & 42. See redlines. Match lines
have been corrected.
Comment Number: 39 Comment Originated: 05/07/2013
05/07/2013: Please correct the title of sheet 15. See redlines. Corrected
Comment Number: 40 Comment Originated: 05/07/2013
05/07/2013: There are 2 keymaps shown over top of one another on sheet 16. See redlines. Corrected
Comment Number: 41 Comment Originated: 05/07/2013
05/07/2013: Please rotate the "elevation" text on sheets 17-42, to make it plan readable. See redlines.
Corrected.
Comment Number: 42 Comment Originated: 05/07/2013
05/07/2013: Please move the north arrow down away from the linework on sheet 18. See redlines.
Corrected.
Comment Number: 43 Comment Originated: 05/07/2013
05/07/2013: There is cut off text on sheets 27, 30 & 34. See redlines. Corrected.
Topic: Landscape Plans
Comment Number: 23 Comment Originated: 05/06/2013
05/06/2013: No irrigation plans as referenced in the index on sheet LS-1 were in our review set. Full
irrigation plans to be provided for building permit review, prior to construction. Irrigation plans
are not included in the Landscape Set at this time.
Comment Number: 24 Comment Originated: 05/06/2013
05/06/2013: Please label Future Vine Drive on sheet LS-2. “Future Vine Drive” has been labeled. The
official street name has yet to be determined.
Comment Number: 25 Comment Originated: 05/06/2013
15
05/06/2013: Please correct the sheet number of LS-3. See redlines. Corrected.
Comment Number: 26 Comment Originated: 05/06/2013
05/06/2013: There are line over text issues on several sheets. See redlines. Corrected.
Comment Number: 27 Comment Originated: 05/06/2013
05/06/2013: There is a text over text issue on sheet LS-6. See redlines. Corrected.
Comment Number: 28 Comment Originated: 05/06/2013
05/06/2013: Please correct the matchline number on sheets LS-8 & LS-12. See redlines. Corrected.
Comment Number: 29 Comment Originated: 05/06/2013
05/06/2013: What is the black block at the bottom left corner of sheet LS-14? The white-out / mask
feature in AutoCAD sometimes shows up as a black box in the PDF version of the drawing sets.
These will be limited as much as possible and monitored in the final submittal sets.
Topic: Lighting Plan
Comment Number: 44 Comment Originated: 05/07/2013
05/07/2013: Are there lighting plans with this project? If so, we will need to review them. There will be no
lighting, with the exception of City street lighting and wall mounted lighting at the entries of each
building. No lighting plan is required at this time.
Topic: Plat
Comment Number: 1 Comment Originated: 05/06/2013
05/06/2013: Are there any Lienholders for this property? If so, please add the Lienholder signature block.
There are no lienholders for this property. The property owners are Breckenridge Group, Fort
Collins Colorado, LLC.
Comment Number: 2 Comment Originated: 05/06/2013
05/06/2013: Please add a note on sheet 1 with the proposed use, ownership and who will maintain the
Tracts. Proposed use is residential homes and open space; ownership and maintenance of the
entire project will be accomplished by Breckenridge Group, Fort Collins, Colorado, LLC. This is
stated on the plat. The entire project will be leased by the bedroom, primarily to students.
Comment Number: 3 Comment Originated: 05/06/2013
05/06/2013: Please add "Lot Areas" to the tables on sheet 2. See redlines. Complete
Comment Number: 4 Comment Originated: 05/06/2013
05/06/2013: Please remove the zoning information from sheets 2, 3 & 4. See redlines. Complete
Comment Number: 5 Comment Originated: 05/06/2013
05/06/2013: Please label the centerline of the PSCO gas line easement along Blue Spruce Drive on sheet
3. See redlines. Complete.
Comment Number: 6 Comment Originated: 05/06/2013
05/06/2013: Please add a note to the Blocks, to see sheet 2 for the lot areas. See redlines. Complete
Comment Number: 7 Comment Originated: 05/06/2013
05/06/2013: Please make sure that all text is plan readable. Complete.
16
Comment Number: 8 Comment Originated: 05/06/2013
05/06/2013: Please label the 50' drainage easement at the south end also. See redlines. Complete.
Comment Number: 9 Comment Originated: 05/06/2013
05/06/2013: Please make sure that all easements have bearings & distances, and are locatable.
Complete.
Comment Number: 10 Comment Originated: 05/06/2013
05/06/2013: It looks like the symbol is not on the actual boundary at the northwest corner of Lupine Drive &
Redwood Street. Either adjust the symbol or provide a bearing & distance to the actual corner. Corrected.
Comment Number: 11 Comment Originated: 05/06/2013
05/06/2013: Please make sure that all easements are labeled correctly. See redlines. Complete
Comment Number: 12 Comment Originated: 05/06/2013
05/06/2013: Please label the east line of the southwest quarter of the section. Complete
Comment Number: 13 Comment Originated: 05/06/2013
05/06/2013: Please label the FEMA 100-year floodplain line shown on sheet 4. See redlines. Complete
Comment Number: 14 Comment Originated: 05/06/2013
05/06/2013: Please clarify the bearing & distance shown on sheet 4. Is it for the centerline of Redwood
Street? Complete.
Comment Number: 15 Comment Originated: 05/06/2013
05/06/2013: Please provide current monument records for the public land corners shown. Monument
Records are included with this submittal set, and are on the submittal disk.
Topic: Site Plan
Comment Number: 16 Comment Originated: 05/06/2013
05/06/2013: There are line over text issues on several sheets. See redlines. Complete
Comment Number: 17 Comment Originated: 05/06/2013
05/06/2013: Please spell out the street names on all sheets. See redlines. Complete
Comment Number: 18 Comment Originated: 05/06/2013
05/06/2013: Please make sure that the street names match the names on the Subdivision Plat. Complete
Comment Number: 19 Comment Originated: 05/06/2013
05/06/2013: Why are the setbacks along Conifer & Redwood Streets shown to the old right of way line?
See redlines. The setbacks have been adjusted to reflect 15’ from the new R.O.W. line
Comment Number: 20 Comment Originated: 05/06/2013
05/06/2013: Please explain "New Vine TBD" shown on sheets 4 & 12. See redlines. The official name
for the “New Vine” roadways has not yet been determined. Ted Shepard has assembled a searing
committee to suggest a new name for City Council approval. Until a name has been determined,
the project will move forward with “New Vine” TBD label.
Comment Number: 22 Comment Originated: 05/06/2013
17
05/06/2013: There is some text shown at the top of sheet 13. If it is not needed, please remove it. See
redlines. Corrected.
Department: Traffic Operation
Contact: Ward Stanford, 970-221-6820, wstanford@fcgov.com
Topic: Construction Drawings
Comment Number: 2 Comment Originated: 04/30/2013
04/30/2013: No S&S plans received. Please provide with subsequent submittals. Acknowledged
03/12/2012: (PDP Comment) Please include signing and striping plans with subsequent submittals.
Comment Number: 3 Comment Originated: 04/30/2013
04/30/2013: No Plat provided. Unable to verify addition of sight distance easements shown on Utility and
Site Plans. Please provide with subsequent submittals. Acknowledged
03/12/2012: (PDP Comment) Looks like a small sight distance easement may be necessary at the SW
corner of Redwood and Conifer. Please verify.
Comment Number: 5 Comment Originated: 05/02/2013
05/02/2013: Traffic S & PM NOTES; please revise all instances of City of Fort Collins Engineer to state
City of Fort Collins Traffic Engineer. This is a permanent NOTES change. Please revise your NOTES file.
Acknowledged, all instances of Traffic S & PM notes have been revised
Comment Number: 6 Comment Originated: 05/02/2013
05/02/2013: Please add the following notes to the Street Improvement Notes: 31. The Developer shall
submit a Construction Traffic Control Plan, in accordance with MUTCD, to the appropriate Right-of-Way
authority. (Local Entity, County or State), for approval, prior to any construction activities within, or affecting,
the Right-of-Way. The Developer shall be responsible for providing any and all traffic control devices as
may be required by the construction activities.
32. Prior to the commencement of any construction that will affect traffic signs of any type, the
contractor shall contact Local Entity Traffic Operations Department, who will temporarily remove or relocate
the sign at no cost to the contractor; however, if the contractor moves the traffic sign then the contractor will
be charged for the labor, materials and equipment to reinstall the sign as needed.
33. The Developer is responsible for all costs for the initial installation of traffic signing and striping for the
Development related to the Development’s local street operations. In addition, the Developer is responsible
for all costs for traffic signing and striping related to directing traffic access to and from the Development.
Acknowledged, notes 31-33 have been added.
Topic: Site Plan
Comment Number: 4 Comment Originated: 04/30/2013
18
04/30/2013: Please remove all cross walk striping on internal streets (Site and Landscape Plans). There
will be no mid-block pedestrian striping along the internal streets. Striping was suggested by
Planning Staff, but are now in concurrence with your assessment.
Department: Water-Wastewater Engineering
Contact: Roger Buffington, 970-221-6854, rbuffington@fcgov.com
Topic: Construction Drawings
Comment Number: 1 Comment Originated: 04/30/2013
04/30/2013: In most cases, at locations where water mains intersect, the number of valves should be equal
to the number of pipes coming into that point minus one. See redlined utility plans. Acknowledged, # of
valves have been corrected.
Comment Number: 2 Comment Originated: 04/30/2013
04/30/2013: At fire hydrant locations revised the notes to indicate 8" x 6" swivel tee with thrust block and 6"
gate valve. Acknowledged, 8”x6” swivel tees are now shown.
Comment Number: 3 Comment Originated: 04/30/2013
04/30/2013: Align the water mains to stay within the drives and a minimum of 5 feet from the curbs
wherever possible. Acknowledged, water main locations have been re-aligned as requested
Comment Number: 4 Comment Originated: 04/30/2013
04/30/2013: Provide water and sewer services for the clubhouse. Acknowledged, water and sewer
services are now shown for the clubhouse
Comment Number: 5 Comment Originated: 04/30/2013
04/30/2013: Show curb stop and meter pit locations, and label water service sizes.
Comment Number: 6 Comment Originated: 04/30/2013
04/30/2013: Add fire hydrant at intersection of "New Vine" and Blondel. Acknowledged, the hydrant
south of Vine has been moved to the intersection
Comment Number: 7 Comment Originated: 04/30/2013
04/30/2013: Add steel casings where the water and sewer mains cross under storm drains 24" or larger.
Label the diameter and thickness of the casings. Where applicable, move fittings out of casing area.
Acknowledged, steel casings have been added for 24” and larger storm drain and water/sewer
crossings. Fittings have been moved out of the casing areas.
Comment Number: 8 Comment Originated: 04/30/2013
04/30/2013: Pothole 24" ELCO water main and show in profile on Sht 18. Acknowledged, the 24” ELCO
water main is now potholed and shown.
Comment Number: 9 Comment Originated: 04/30/2013
04/30/2013: At point where sanitary crosses under (or at bottom of) drainage channel, provide details
showing how sanitary will be protected from scour and from freezing. Acknowledged, the crossing is
now shown as encased
Comment Number: 10 Comment Originated: 04/30/2013
04/30/2013: Show ALL water main and sanitary sewer crossings on the storm drain profiles.
Acknowledged, all water main and sanitary sewer crossings are shown on the storm drain
19
profiles.
Comment Number: 11 Comment Originated: 04/30/2013
04/30/2013: Add the Std Details noted on Sht 47. Acknowledged, the Std. Details requested have
been added
Comment Number: 12 Comment Originated: 04/30/2013
04/30/2013: See redlined utility plans for other comments. Acknowledged, all redlines have been
addressed.
Comment Number: 13 Comment Originated: 05/02/2013
05/02/2013: Show/label all irrigation taps. Acknowledged, irrigation taps are now shown and labeled
Comment Number: 14 Comment Originated: 05/02/2013
05/02/2013: Now that water/sewer services and underground electric/communication lines are shown, it is
strongly suggested that a utility coordination meeting be scheduled to work out potential conflicts. At
present, it appears that there will likely be conflicts between meter pits and the underground
electric/communication facilities and what appears to be gas mains. : Acknowledged, a utility
coordination meeting was held on May 15, and coordination efforts have been coordinated to a
point that the design shown will work during construction.
Topic: General
Comment Number: 15 Comment Originated: 05/02/2013
05/02/2013: Meter pits cannot be installed in drive or parking areas. In some places, there does not
appear to be adequate easement and space for the curb stops and meter pits. Acknowledged
Department: Zoning
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 04/15/2013
04/15/2013: Two of the building elevations labeled single family appear to actually be duplexes, "The
Durango" and "The Vail B". This has been corrected, along with the addition of several additional
building elevations.
Comment Number: 2 Comment Originated: 04/15/2013
04/15/2013: The parking and residential unit summary tables need to indicate how many two-family are 2
bedrooms and how many are 3 bedrooms. This is necessary for the single family attached also. The “A”
units each have 2-bedrooms, the “B” Units each have 3 bedrooms. The “C” units have 2-bedroom
units on each end, with 3-bedroom units in the center. The “D” units have 4 bedrooms, and “E”
units have 5 bedrooms. This information is included on the Title Page of the Architectural
Elevations. The Site Plan Data Table now includes bedroom information as it relates to parking
requirements and eventual extra-occupancy requests for the “D” and “E” units. Also, an
addressing plan and assigned addresses has been created. Please call Deanne Frederickson
(970) 674-3323 to request a copy.
Comment Number: 3 Comment Originated: 04/15/2013
04/15/2013: Does the applicant want to identify what site and landscape improvements will be tied to what
20
buildings through a landscape phasing plan? Yes. An attempt at Landscape Phasing has been
included on Page 2 of the Landscape Plan. Basically, the Developer would like to build the club
house initially, so they can use it as a construction office and pre-leasing facility. They would like
to be able to receive a C of O for this building independently with landscape improvements (or a
letter of credit). They would then like to build a few of the residential units adjacent to the
clubhouse to be used as models. It is requested that foundation plantings are tied to the
individual buildings while street trees and open space landscape are phased with the construction
phasing of the project.
Comment Number: 4 Comment Originated: 04/15/2013
04/15/2013: Where is the bicycle parking? The bicycle parking is now shown on the Site Plan and the
Landscape Plan. There is bicycle parking provided for each building, and a number of them
provided at the clubhouse.
Comment Number: 5 Comment Originated: 04/15/2013
04/15/2013: Mechanical/utility equipment locations should be identified on the plans with notes on how
such equipment will be screened. Meters will be placed on each building as shown on the site plan
and the utility plans. Screening will be accomplished with foundation plantings along the frontage
of every building.