Opinion of Probable Cost
Cash in Leiu Items
For: Buckingham Place Second Filing
Date: 5/4/2013
ITEM 1: Cash in lieu for Frontage Improvements
Estimated Item
Units Unit Cost Quantity Cost
Local Street Construction LF $204.00 125.5 $25,602
Item 1 Total $25,602
ITEM 2: Cash in Leiu to Construct the New Coy Ditch
Estimated Item
Units Unit Cost Quantity Cost
30" CMP LF $45.00 126 $5,670
APEX
30" CMP LF $45.00 126 $5,670
Regrading at property line LS $500.00 1 $500
Subtotal $6,170
Surveying and Construction Management
Survey LS $400.00 1 $400
Construction Management @ 5% LS $300.00 1 $300
Mobilization @ 5% LS $300.00 1 $300
Subtotal $1,000
Subtotal $7,170
Contingency (15%) $1,076
Item 2 Total $8,246