HomeMy WebLinkAboutLDS TEMPLE - PDP - PDP120029 - SUBMITTAL DOCUMENTS - ROUND 2 - REVISIONS (3)Terracon Consultants, Inc. 1901 Sharp Point Drive, Suite C Fort Collins, Colorado 80525
P [970] 484-0359 F [970] 484-0454 www.terracon.com
January 8, 2013
The Church of Jesus Christ of Latter-day Saints
50 East North Temple, 10th Floor
Salt Lake City, Utah 84150
Attn: Mr. John Stoddard
P: (801) 249-7132
E: stoddardJB@ldschurch.org
Re: Supplemental Geotechnical Engineering Recommendations
Fort Collins Temple
Southeast of South Timberline Road and East Trilby Road
Fort Collins, Colorado
Terracon Project No. 20115025
In this letter, Terracon Consultants, Inc. (Terracon) presents Supplemental Geotechnical
Engineering Recommendations for the Fort Collins Temple. These recommendations
supplement our Geotechnical Engineering Report; dated August 19, 2011(Project No.
20115025).
Background Information
In contacts with members of the project team, we were informed that the widening of South
Timberline Road planned as part of the project will require reconfiguration of the existing
drainage swale along the eastern side of the roadway south of Majestic Drive as well as
construction of curb, gutter and new pavements. We were informed that the City of Fort Collins
has expressed concerns about slope erosion and other issues at this location. Terracon was
requested to provide geotechnical engineering recommendations to address the City of Fort
Collins concerns and recommendations to be considered by other members of the design team
for this section of site development.
To assist with our analysis, we were provided with conceptual civil drawings related to the
roadway widening showing the existing site grades as well as proposed site grades and planned
construction. The conceptual drawings indicate the existing slope on the eastern side of the
drainage swale south of Majestic Drive and the Temple property and north of Rock Castle Lane
is as steep as about 2:1 (h:v). New construction will require placing fill into the existing drainage
swale and construction of curb and gutter at the toe of the slope. Following construction of the
new curb, gutter and roadway, the backfill placed behind the new curb and gutter will be
blended into the existing slope. The roadway and curb and gutter construction may require
minor temporary excavation into the existing slope.
Supplemental Geotechnical Engineering Report
Fort Collins Temple ■ Fort Collins, Colorado
January 8, 2013 ■ Terracon Project No. 20115025
Responsive ■ Resourceful ■ Reliable 2
Geotechnical Recommendations
We did not complete exploratory borings within the existing drainage swale along the proposed
widening alignment. However, our experience indicates the subgrade soils that will provide
support of the proposed curb, gutter and pavements along the drainage swale are likely clayey
soils similar to the surficial soils within the Temple site. These soils may be moist and may
require stabilization prior to placement of new fill and construction of the proposed
improvements.
Prior to fill placement and roadway construction, we recommend stripping and removing existing
vegetation and other deleterious materials from below the proposed pavements and areas
planned to receive fill. If unstable conditions are encountered or develop during construction,
workability may be improved by scarifying and drying; however, allowing the clays to dry out
below the optimum moisture content is not recommended. As an alternative, affected areas
could be over-excavated and replaced with granular materials and/or non- to low expansive
imported materials. If necessary, crushed concrete and/or rock could be tracked or “crowded”
into the unstable subgrade until a stable working surface is attained.
In order to reduce the risk for erosion of the compacted fill placed behind the proposed curb and
gutter, we recommend placing fill and/or backfill in 6-inch maximum lifts, moisture conditioning
and compacting as described below. Engineered fill should be placed and compacted in
horizontal lifts, using equipment and procedures that will produce recommended moisture
contents and densities throughout the lift.
Item Description
Fill lift thickness 6 -inches or less in loose thickness
Compaction requirements (clay)
95 percent of the maximum dry unit weight as determined by
ASTM D 698
Moisture content cohesive soil
(clay)
-1 to +2% of the optimum moisture content in pavement
areas
Moisture content cohesionless soil
(sand)
-3 to +3 % of the optimum moisture content
1. We recommend engineered fill be tested for moisture content and compaction during placement.
Should the results of the in-place density tests indicate the specified moisture or compaction limits
have not been met, the area represented by the test should be reworked and retested as required
until the specified moisture and compaction requirements are achieved.
2. Specifically, moisture levels should be maintained low enough to allow for satisfactory compaction
to be achieved without the fill material pumping when proof-rolled.