July 03, 2012
Dave Derbes
Brinkman Partners, LLC
3003 E Harmony Rd, Suite 300
Fort Collins, CO 80528
RE: 1409 W Elizabeth Street Student Apartments - Fairview Shopping Center Filing Four, PDP120009,
Round Number 2
Please see the following summary of comments from City staff and outside reviewing agencies for your
submittal of the above referenced project. If you have questions about any comments, you may contact the
individual commenter or direct your questions through the Project Planner, Courtney Levingston, at
970-416-2283 or clevingston@fcgov.com.
Comment Summary:
Department: Current Planning
Contact: Courtney Levingston, 970-416-2283, clevingston@fcgov.com
Topic: General
Comment Number: 2 Comment Originated: 04/03/2012
04/04/2012: Staff is wondering if bollards are the best option to contain C.B.&Potts spill over
parking. Would signage be a more appropriate first step and see if that addresses any
potential issues? While there is nothing that I am aware of in the Code that precludes bollards
(no PFA issues), Staff suggests reconsidering the bollard approach.
Bollards have been removed.
Comment Number: 5 Comment Originated: 06/12/2012
06/12/2012: For final, please provide detail on the retaining wall.
A concrete curb detail has been added to sheet LS501.
Topic: Landscape Plans
Comment Number: 1 Comment Originated: 06/05/2012
06/05/2012: Regarding Roger Buffington's comment requesting showing the water and sewer
lines on the landscape plan, I don't see those. This may be important because if a tree on the
south edge of the property is precluded because of these lines, that is an important detail to
know prior to hearing.
All utilities are shown on the plan set.
Topic: Site Plan
Comment Number: 4 Comment Originated: 06/19/2012
06/19/2012: For final, please correct the data table on LS101 with the correct number of
parking.
The data table has been updated on sheet LS101.
Department: Current Planning
Contact: Courtney Levingston, 970-416-2283, clevingston@fcgov.com
Topic: Site Plan
Comment Number: 5 Comment Originated: 07/03/2012
07/03/2012: Per the condition of approval, please lable the sidewalk width next to the building
to ensure it is 6 feet wide.
The sidewalk has been labeled 6’.
Department: Engineering Development Review
Contact: Marc Virata, 970-221-6567, mvirata@fcgov.com
Topic: Construction Drawings
Comment Number: 7 Comment Originated: 04/04/2012
06/05/2012: Carried over for review at Final.
04/04/2012: Please indicate north flowline information and roadway lane striping on Elizabeth
Street to ascertain how the approximate area of the proposed patch situates with the "as-built"
condition of Elizabeth Street.
Done.
Topic: General
Department: Engineering Development Review
Contact: Marc Virata, 970-221-6567, mvirata@fcgov.com
Topic: General
Comment Number: 3 Comment Originated: 04/04/2012
06/05/2012: The revised site plan along with the variance request generally appears
acceptable. Please verify the intent with a couple of existing items:
1) The label of the fire hydrant shown on the site plan is "relocated fire hydrant", is it intended to
be moved, or kept in the same location, which appears to be in intention based upon the
measurement?
Existing hydrant to remain.
2) There is an existing manhole directly west of the main driveway and south of the existing
sidewalk, is it intended that this is relocated, otherwise the sidewalk/truncated dome on the
west side of the driveway would conflict.
Lid to be replaced with pedestrian-rated cover, and adjusted to grade.
3) The water meter shown on the drawing appears to be in measure, about 1 foot into the
sidewalk, is the intention to keep the meter in the sidewalk?
Meter pit to be located in private plaza.
4) The indication of the retaining wall to be flush with the sidewalk and provide elevation from
the tree roots?
Sidewalk to be down at/near existing top back of curb elevation. Tree/tree root zone to be 6”-12”
higher than sidewalk elevation.
04/04/2012: The proposal of an 8 foot attached sidewalk is of question. The City's view is that
(per the Conceptual Review comments) an attached sidewalk matching the Campus West
Redevelopment is the ideal specification for an attached sidewalk. This sidewalk dimension for
the Campus West Redevelopment is 12 feet and ideally this proposal should match this width
(and is also the proposed width of the redevelopment property next door). The site visit with
Northern and Brinkman identified some potential restriction points to meeting the ideal width:
the tree in front of the Wendy's and a light pole along with a fire hydrant. We were realizing that
the tree in front of Wendy's would likely need to narrow from an ideal width in order to not
impact the tree but thought that the 12 foot width could be likely achieved along the rest of the
corridor. The light pole and fire hydrant, while being existing restriction points, we did not
necessarily conclude that these appurtenances could stay as is. With the drawing submitted it
shows that with the 8 foot attached sidewalk, the light pole would be fully in the sidewalk and
the fire hydrant is partially in the sidewalk as well. The City would conclude that these
appurtenances should be moved as they're awkwardly situated in the 8 foot attached sidewalk,
which would have the design then look towards more of the ideal sidewalk width. (Doug Martine
with Light and Power noted that the cost to move the pole so it's not within/abutting the sidewalk
is no different to achieve 2 foot separation from the proposed 8 foot sidewalk to vs. a more
ideal sidewalk width with further separation.) We would need to evaluate any proposal that does
not incorporate the 12' attached sidewalk through a variance request in coordination with
Planning.
Acknowledged.
Department: Engineering Development Review
Contact: Marc Virata, 970-221-6567, mvirata@fcgov.com
Topic: General
Comment Number: 8 Comment Originated: 04/04/2012
06/05/2012: The site plan drawing doesn't show concrete sidewalk across the driveways,
typically a note indicates concrete to property line for the driveways.
A note has been added to sheet LS101.
04/04/2012: Both drive approaches would need to have additional concrete added in order for
the sidewalk to lead to a concrete section, not partial concrete/asphalt. The access ramp
leading to a curb for the eastern exit driveway is awkward as well with the curb needing to be
pulled back.
Acknowledged.
Topic: Plat
Comment Number: 2 Comment Originated: 04/04/2012
06/05/2012: The plat language appears to be the same and has not been revised.
04/04/2012: The plat language has been updated. Please provide the more updated certificate
of dedication, repair and maintenance language. Language has been updated.
Comment Number: 5 Comment Originated: 04/04/2012
06/05/2012: Carried over for reference.
Acknowledged.
04/04/2012: The private access and shared parking easement indicated on the plat would
need to be recorded prior to the recordation of the plat.
Topic: Site Plan
Comment Number: 10 Comment Originated: 04/04/2012
06/05/2012: The site plan should show concrete scoring indicative of the sidewalk intending to
meander around the relocated light pole.
Scoring has been added.
Comment Number: 11 Comment Originated: 06/05/2012
06/05/2012: The site plan should label the existing and proposed property lines to illustrate
where the property boundary situates in relation to the proposed sidewalk design.
Property lines have been shown and labeled on the site plan.
Department: Light And Power
Contact: Doug Martine, 970-224-6152, dmartine@fcgov.com
Topic: General
Comment Number: 5 Comment Originated: 05/29/2012
05/29/2012: Relocation of the streetlight at Elizabeth St. will be at the expense of the
developer.
Acknowledged.
Department: PFA
Contact: Ron Gonzales, 970-416-2864, rgonzales@poudre-fire.org
Topic: General
Comment Number: 1. Comment Originated: 03/27/2012
03/27/2012: A communication evaluation is required for this 3-story edifice to validate fire
department communications. If not, a bi-directional antenna is required to enhance PFA
communications within and out of the building.
Acknowledged.
Department: Stormwater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: Floodplain
Department: Stormwater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: Floodplain
Comment Number: 2 Comment Originated: 04/06/2012
1. A request has been made to allow a 2,000-3,000 s.f. basement for storage. Per Section
10-38, no new basement may be constructed below the regulatory flood protection elevation in
a new residential structure.
Acknowledged.
2. No-Rise Certification is needed for the work proposed in the floodway (replacement of the
sidewalk with an 8-ft. attached walk) along Elizabeth Street. Technical analysis will be needed
to justify the no-rise condition.
Acknowledged.
3. The floodway and flood fringe boundaries must be included on the plat. Include a note to
inform that the boundaries are from the proposed waiver request and explain why the current
effective model is not being used. Also include the name of the City Basin (Canal Importation)
and the City Benchmark and its associated elevation.
Current effective floodway and flood fringe boundaries are shown on the plat. The waiver is solely
for BFE and does not apply to the floodplain boundaries shown on the plat.
4. The notes from the Floodplain Exhibit (Sheet C4.1) should also be included on the plat.
Shown on the plat.
5. NAVD88 elevations are not required in City Basins, only FEMA basins. Please remove
NAVD88 elevations from the Floodplain Exhibit, etc.
Done.
6. The Drainage Letter does not have any floodplain information within the body of the letter.
Please add the information requested within the 'City's Floodplain Review Checklist 100%
Development Review Submittals'. Also within the letter, please explain why the floodplain
waiver is needed, how it will be obtained and how it will be used, etc.
This information will be forthcoming.
7. Please note on the plans that the floodplain boundaries, cross-section, base flood
elevations, etc. are based upon the waiver request and not on the current effective model.
The waiver request will be noted on the plans.
8. The boundaries and locations of the cross sections and BFE's that are shown on the
Floodplain Exhibit (Sheet C4.1) appear to be from the current effective model, while the
elevations noted are from the waiver request. All of this information should match what is
proposed in the waiver request.
This will be discussed further with Floodplain Staff.
9. The HVAC shown on the Floodplain Exhibit (Sheet C4.1) is shown at the same elevation as
the Regulatory Flood Protection Elevation. We suggest that the equipment be elevated more
than that. If there is any sort of error during construction that results in the equipment being less
than the RFPE, it will be have to me moved prior to the issuance of the Elevation Certificate.
That could be very expensive and time consuming. Somewhere in the submittal a note was
included that stated that the HVAC equipment was to be located on the roof. If that is the case,
remove the HVAC from the Floodplain Exhibit.
The detail has been revised. (HVAC equipment will be on the roof)
10. Please note all red-lined comments on the plat, site plan and utility plans and make
corrections as indicated.
Acknowledged.
11. Please refer to the City's 'Floodplain Review Checklist 100% Development Review
Submittals' in preparation of the plans. It can be found at
http://www.fcgov.com/utilities/what-we-do/stromwater/flooding/forms-documents.
Acknowledged.
Topic: General
Comment Number: 1 Comment Originated: 04/04/2012
04/04/2012: Stormwater is ready for a hearing. Comments may apply during final compliance
Acknowledged.
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Building Elevations
Comment Number: 28 Comment Originated: 06/06/2012
06/06/2012: There are line over text issues on sheet PDP-1.
The line over text issue has been eliminated
Topic: Construction Drawings
Comment Number: 17 Comment Originated: 03/29/2012
06/06/2012: We were not routed plans this round, so we don't know if these issues were
corrected.
03/29/2012: Please add descriptions to the benchmarkson sheet C0.0.
Done.
Comment Number: 18 Comment Originated: 03/29/2012
06/06/2012: We were not routed plans this round, so we don't know if these issues were
corrected.
03/29/2012: The bearing in the Basis Of Bearings statement on sheet C0.0 doesn't match the
Subdivision Plat.
This has been corrected.
Comment Number: 19 Comment Originated: 03/29/2012
06/06/2012: We were not routed plans this round, so we don't know if these issues were
corrected.
03/29/2012: There are line over text & text over text issues on sheets C1.0, C4.0 & C4.1.
This has been corrected.
Topic: Lighting Plan
Comment Number: 15 Comment Originated: 03/29/2012
06/06/2012: We were not routed plans this round, so we don't know if these issues were
corrected.
03/29/2012: There are line over text issues on sheet E0.1.
Acknowledged.
Comment Number: 16 Comment Originated: 03/29/2012
06/06/2012: We were not routed plans this round, so we don't know if these issues were
corrected.
03/29/2012: Please add a north arrow to sheet E0.1.
Acknowledged.
Topic: Plat
Comment Number: 5 Comment Originated: 03/29/2012
06/06/2012: This has not been addressed. LS 20123 is R. A. Bradshaw. This has been corrected.
03/29/2012: Please correct the surveyor's name at the center of section 15.
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Plat
Comment Number: 6 Comment Originated: 03/29/2012
06/06/2012: There are still minor line over text issues. This has been corrected.
03/29/2012: There is a minor line over text issue.
Acknowledged.
Comment Number: 8 Comment Originated: 03/29/2012
06/06/2012: These have not been provided. These are required per Development Review
Submittal Requirement 3(v).
Attached to this submittal.
03/29/2012: Please provide monument records for all public land corners shown on the Plat.
Comment Number: 9 Comment Originated: 03/29/2012
06/06/2012: This has not been completely addressed. This has been corrected.
03/29/2012: See redlines regarding the Basis Of Bearings statement. Acknowledged.
Comment Number: 20 Comment Originated: 06/06/2012
06/06/2012: THe subdivision Plat boundary does not close. This has been corrected.
Comment Number: 21 Comment Originated: 06/06/2012
06/06/2012: Please add "(M) measured" to all bearings & distances on the boundary.
This has been corrected.
Comment Number: 22 Comment Originated: 06/06/2012
06/06/2012: Please describe the NW corner of the outer boundary, and add it to the legend.
This has been corrected.
Comment Number: 23 Comment Originated: 06/06/2012
06/06/2012: Are the 10" utility easements at the north & south ends of the property existing?
Yes, see plat.
Comment Number: 24 Comment Originated: 06/06/2012
06/06/2012: There is no monument shown at the SE corner of the boundary.
This has been corrected.
Comment Number: 25 Comment Originated: 06/06/2012
06/06/2012: Please add the internal distance along the west boundary line. See redlines.
This has been corrected.
Comment Number: 26 Comment Originated: 06/06/2012
06/06/2012: Please see the note & distances along the east line of the boundary.
This has been corrected.
Comment Number: 27 Comment Originated: 06/06/2012
06/06/2012: Please correct the Surveyor's name in the Basis of Bearings statement.
This has been corrected.
Department: Water-Wastewater Engineering
Contact: Roger Buffington, 970-221-6854, rbuffington@fcgov.com
Topic: Construction Drawings
Comment Number: 2 Comment Originated: 04/03/2012
04/03/2012: Add note to coordinate with Water Utilities (970-416-2165) on the abandonment of
the 1" water service.
Done.
Comment Number: 4 Comment Originated: 04/03/2012
04/03/2012: See redlined plans for other comments.
Acknowledged.
Department: Water-Wastewater Engineering
Contact: Roger Buffington, 970-221-6854, rbuffington@fcgov.com
Topic: Construction Drawings
Comment Number: 5 Comment Originated: 06/05/2012
06/05/2012: Ready for hearing. Will check remaining comments at final.
Acknowledged.