STATEMENT OF PLANNING OBJECTIVES
Re -Submittal of Preliminary PUD
Glaser Associates Architects
Loveland, Colorado
August 14, 1980
Since approval of the Preliminary PUD by the Fort Collins city
'council on December 4, 1979, the design for Phase One of the
First Christian Church has been modified to be enlarged from
50,000 square feet in floor area to approximately 54,000 square
feet. Since this constitutes an increase of more than 5%, we
are submitting Phase One for re -approval as a Preliminary PUD.
Please note that other aspects of the project such as intended
use, design of the building, parking and drive configurations,
and compliance with the building height regulations (which does
not effect Phase One) have not been significantly changed. The
landscaping, also as previously submitted, reflects the land-
scape plan for the total development of the Master Plan.
Although the increase in floor area exceeds 5% of Phase One,
it constitutes only approximately a 3% increase to the total
complex. Therefore the Master Plan is not being re -submitted
for P&Z.Board or council review.
The time schedule will be changed only to reflect our start of
construction which is anticipated in November, 1980. There-
fore, completion of Phase One would occur within two years, or
by October of 1982.