HomeMy WebLinkAboutHAMPSHIRE POND EAST PUD PRELIMINARY AND FINAL - 44 93C - SUBMITTAL DOCUMENTS - ROUND 1 - GEOTECHNICAL (SOILS) REPORTof maximum density and optimum moisture for these materials. Tests
for this determination will be made using methods conforming to
requirements of ASTM D698. Copies of the results of these tests
will be furnished to the contractor. These test results shall be
the basis of control for' compaction effort.
D E N S I T Y T E S T S
The density and moisture content_,,,of.each layer of compacted fill s_
wi11 be determined by the soils. engineer in accordance with ASTM
D1556 or D2167. Any material found not to comply with the minimum
specified density shall be recompacted until the required density
is obtained. The, results of all density tests will be furnished
to both the owner and the contractor by the soils engineer.
4
optimum compaction. The moisture shall be uniform throughout the
fill. The contractor may be required to add necessary moisture to
the backfill material in the excavation if, in the opinion of the
soils engineer, it is not possible to obtain uniform moisture
content by adding water'on the fill surface. If, in the opinion
of the soils engineer, the material proposed for use in the
compaction is too wet to permit adequate compaction, it shall be
dried in an acceptable manner prior to placement and compaction.
C O M P A C T I O N
When an acceptable uniform moisture content is obtained, each layer
shall be compacted by a method acceptable to the soils engineer and
as specified in the foregoing report as determined by the standard
Proctor test (ASTM D698). Compaction shall be performed by rolling
with approved tamping rollers, pneumatic -tired rollers, three -wheel
power rollers, or other approved equipment well -suited to the soil
being compacted. If a sheepsfoot roller is used, it shall be
provided with cleaner bars attached in a manner which would prevent
the accumulation of material between the tamper feet. The roller
should be so designed that the effective weight can be increased.
M O I S T U R E- D E N S I T Y D E T E R M I N A T I O N
Samples of representative fill materials to be placed shall be
furnished by the contractor to the soils engineer for determination
3
P R E P A R A T I O N O F S U B G R A D E
All topsoil and vegetation shall be removed to a depth satisfactory
to the soils engineer before beginning preparation of the subgrade.
The subgrade surface oC the area to be filled shall be scarified
to a minimum depth of six (6) inches, moistened as necessary, and
compacted in a manner specified below for the subsequent layers of
fill. Fill shall not be placed `on frozen or muddy ground.
P L A C I N G F I L L
No sod, brush or frozen material or other deleterious or unsuitable
material shall be placed in the fill. Distribution of material in
the fill shall be such as to preclude the formation of lenses of
material differing from the surrounding material. The materials
shall be delivered and spread on the fill surface in such a manner
as will result in a uniformly compacted fill. Prior to compacting,
each layer shall have a maximum thickness of eight (8) inches and
its upper surface shall be relatively horizontal.
M O I S T U R E C O N T R O L
The fill material in each layer, while being compacted, shall as
nearly as practical contain the amount of moisture required for
j 2
f
APPENDIX A
Suggested Specifications for Placement of Compacted Earth Fills
and/or Backfills.
G E N E R A L
A soils engineer shall be the owner's representative to supervise
and control all compacted fill and/or compacted backfill on the
project. The soils engineer shall approve all earth materials
prior to their use, the methods of placing, and the degree of
compaction obtained. A certificate of approval from the soils
engineer will be required prior to the owner's final acceptance of
the filling operations.
M A T E R I A L S
The soils used for compacted fill beneath interior floor slabs and
backfill around foundation walls shall be impervious and non -
swelling for the depth shown on the drawings. No material shall
be placed for fill which has a maximum dimension of six (6) inches
or greater. All materials used in either compacted fill or
compacted backfill shall be subject to the approval of the soils
engineer.
1
5UMMAiR**� Or- T E6T 5 Table No.
Unconfined
Standard
Sample
Hole
Depth
Moisture
Dry
% paesing
Liquid
Plasticity
Compreaetve
Penetration
Deed tion
p
No.
(ft.Jp
Content f7b)
�mm
Limit
Index
Strength
Teat
(PCF�y
CPSF)
1
5-6
6.7
20/12
Clayey sand
2
2-3
8.4
112.3
---
Clayey sand
2
3-4
5.9
12/12
Clayey sand
2
7-8
5.9
11/12
Clayey sand
2
15-16
16.6
12/12
Clayey sand
3
3-4
4.7
6/12
Clayey sand
3
9-10
3.6
31/12
Gravelly sand
4
5-6
3.6
25/12
Clayey sand
5
2-3
4.7.
107.9
---
Sandy clay
5
3-4
5.7
14/12
Clayey sand
5
7-8
5.6
21/12
Clayey sand
5
15-16
15.5
15/12
Sandy clay
3
8-9
-2.3
9.4
np
np
Gravelly sand
4
1-3
---
21
np
np
A-2-4(0)
I
FOUNDATION 4 SOILS ENGINEERING Project No. 1163-20-01-01 FIG. 6
4
r%
ME
G-3RA 1N 51 ZE D 15TR1 BUT I ON CURVE
O
we w M ae r a v a ♦ w yr aw r w r i
am H re.uraw a�
TEST HOLE NO. 4_ CURVE A
DEPTH (Ft-) 1-4
SAMPLE OF CLAYEY SAND
a
to 0
TEST HOLE NO. 3 CURVE B
DEPTH (F!J 8-9
SAMPLE OF GRAVELLY SAND
FOUNDATION 4 SOILS ENGINEERING JOB NO. 1163-30-01-01 FIGURE NO. 5
100
w
8m
10
60
60
40
30
20
10
6
4
2
Project No. 1163-30-01-01
LOAD (.Per) 6mm WOO BOW
Inundated Test Pole No. 2
Sample \ Depth (Ft,) 2-3
Sample of CLAYEY SAND
Moisture Content (96) 8.4 Dry Density (PCF) 1123
LOAD (psi) 500 1000 5000 wwo
Inundated Test Pole No. 5
Sample \ Depth Cfta 2-3
Sample of SANDY CLAY, sl. gravelly
Moisture Content l90 4.1 Dry Density (PC7) 101.9
6WELL -CONSOLIDATION TEST
FOUNDATION 4 SOILS ENGINEERING FIGURE NO. 4
Elevation 1m3
(Feet)
1
M
Oi�f NC- LOCHS
NO.1 NO2 NO3 NOA NOB
Elevation
(Feet) 105
II
♦
'�12
ri
31.
12
2
Y12
'2/12
/ ,san g,--sT -Qravelly,s.mos,
/ stiff, brown "/t2
SAND with lenses of clay t
gravel, al. to v. moist, mad. drilled 6/18/95
All soil and/or rock contacts shown are approximate.
FOUNDATION 4 SOILS ENGINEERING JOB NO. 1163-30-01-01 FIGURE NO. 3
es
as
:"
'15
LE�ENE) of 5�rM5OL5
l
Fill materials
Caravel
Sand
Stlt
Clay
Weathered bedrock
S(Itstone
Glaystone
Sandstone
Limestone
Igneous * Metamorphic
rocks
Symbols may be
combined to
represent mixtures.
N
Shelby sample
Standard
Penetration
Test sample f
Caroundwa ter
level
f 6/12 indicates that 6 blows
of a 1400 hammer falling 30'
was required to penetrate 12'
FOUNDATION 4 SOILS ENGINEERINCa
Project No.--I63-2o of-ol
�u�a �u¢ TII�cIN 9.op.00,mN W} '
I p
i
i ti 1:
ih�' �wtirtt)to nr
of :t --Ci• 9t �e� F z
N J
i
i
y p i
� I
F 1
orcr Golk1 w5
�-fGYJ
50FRING LOCATION MAF
FOUNDATION 4 SOILS ENGINEERING FIGURE NO.
I
The test holes drilled were spaced to obtain a reasonably accurate
4 picture of subsurface conditions for design purposes. These
variations are sometimes sufficient to necessitate modifications
f
in design.
The methods used for the analysis and recommendations for construc-
tion on soils is not an exact science. Engineering judgement and
experience in addition to the laboratory and field analysis are
used to make these recommendations. Therefore, the recommendations
and solutions made in this report cannot be considered risk -free
and are not a guarantee of the performance of the structures. The
recommendations included in this report are our best estimates of
the measures that are necessary to help the proposed structures
perform in a satisfactory manner. The contractor and owners should
understand the risks of construction at this site. The contractor
and owners must decide what level of risks and measures are
acceptable.
:3 We recommend that construction be observed by a qualified soils
technician trained and experienced in the field to take advantage
of all opportunities to recognize some undetected condition which
might affect the performance of the foundation systems and pavement
structure.
14
�.i
I
the hot bituminous pavement (HBP) shall meet Grading C or CX of
Colorado Department of Transportation Standards and have a R,-value
of 95. The remaining HBP shall meet Grading G or better of CDOT
Standards and have an Rt-value of 95. All work shall be done in
accordance "with City of'Fort Collins standards.
Addition stabilization techniques of the subgrade may be required
if conventional moisture control/compaction techniques will not
result in a non -yielding subgrade. A proof -roll with heavy
equipment is recommended to determine if any soft, yielding areas
exist. Stabilization recommendations such as fly ash, lime, or
geotextiles can be made if needed.
G E N E R A L I N F O R M A T I O N
The data presented herein were collected to help develop designs
and cost estimates for this project. Professional judgments on
design alternatives and criteria are presented in this report.
These are based on evaluation of technical information gathered,
partly on our understanding of the characteristics of the structure
proposed, and partly on our experience with subsurface conditions
in the area. We do not guarantee the performance of the project
in any respect, only that our engineering work and judgments
rendered meet the standard of care of our profession.
13
R-value of the Subgrade = 12.2 (MR = 7771)
Serviceability Loss (Apsi) = 2.5
Design Life = 20 years
Structural Coefficients
Hot Bituminous Pavement (HBP) = 0.40
Aggregate Base Course (ABC) = 0.10
s
Local (Water Blossom Lane)
(DTN = 5, 18k ESAL = 36,500, Reliability Factor = 65%, Structural
Number = 1.66)
Option 1 Option 2
HBP 3" 5"
ABC
TOTAL 8" 5"
All subgrade shall be scarified and recompacted to at least 95% of
standard Proctor and recompacted at plus or minus two percent (+2%)
of optimum moisture content. All Aggregate Base Course (ABC) shall
meet Class 5 or 6 of Colorado Department of Transportation (CDOT)
Standards and have an R-value of 72 or greater. All subbase shall
meet Class 1 or better of CDOT Standards and have an R-value of 68
or greater. All subbase and aggregate base course shall be
compacted to 95% of modified Proctor. The top two (2) inches of
12
I
foundation walls should be well -cured, braced or subfloor installed
__. prior to backfilling. Past experience has shown that severe damage
could occur to the foundation walls if excessively expansive
material is placed for backfill and allowed to become wet.
The backfill placed immediately adjacent to the foundation walls,
if not properly compacted, can be expected to settle with resulting
damage to sidewalks, driveway aprons, and other exterior slabs -on -
grade. To avoid settlement and disfigurement of the slabs in the
event •that the backfill is not properly compacted, we recommend
that. concrete slabs which must span the backfill be supported by
the foundation walls. This is conventionally done by use of a
brick ledge or haunch. Exterior slabs should not be dowelled to
the foundation wall. The slab should be reinforced as necessary
for the span involved.
PAVEMENT RECOMMENDAT ION S
It is our understanding that the roadway for the project will be
paved utilizing a flexible pavement section. This pavement design
was determined by using the 1990 Colorado Department of Transporta-
tion's (CDOT) Roadway Design Manual and Pavement Analysis Software
which utilizes the 1993 AASHTO "Guide for the Design of Pavement
Structures." Other factors used for the design were based on City
of Fort Collins criteria. The following criteria was used in the
pavement section recommendations.
11
Finished grade should be sloped away from the structure on all
sides to give positive drainage. A minimum of twelve (12) inches
fall in the first ten (10) feet is recommended. Sprinkling systems
should not be installed within ten (10) feet of the structure.
Downspouts are recommended and should be arranged to carry drainage
from the roof at least five (5) feet beyond. the foundation walls.
0
Plantings are not recommended around the perimeter of the founds-
tions. However, if the owners are willing to accept the risks of
foundation and slab movement, low water use plant (xeriscape)
varieties could be used. A horizontal impervious membrane, such
as polyethylene, should not be used next to the foundation wall.
We recommend the use of a landscape fabric which will allow normal
evaporation in lieu of a plastic membrane. All plants located next
to the foundation should be hand watered only using the minimum
amount of water.
Backfill around the outside perimeter of the structure, except as
noted above, should be compacted from optimum moisture to three
percent (3$) above optimum moisture, and from eighty-five percent
(85%) to ninety percent (90%) of Standard Proctor Density as
determined by ASTM Standard Test D-698. The Backfill should be
mechanically compacted in loose lifts not to exceed twelve (12)
inches. Expansive soils and/or bedrock fragments should not be
used for backfill materials. If imported material is used, the
i
soil should be relatively impervious and non -expansive. The
10
'7
1
( slabs should be constructed using a sulfate resistant concrete
f containing a Type I/II cement.
S I T E G R A.D I N G A N D U T I L I T I E S
Specifications pertaining to site grading are included below and
in Appendix A of this report. It is recommended that the upper ten
(10) inches of the subgrade below paved and filled areas be
stripped and stockpiled for reuse in planted areas. The upper six
(6) inches of the subgrade below paved and filled areas should be
scarified and recompacted plus or minus two percent (±2%) of
optimum moisture to at least ninety-five percent (95%) of Standard
Proctor Density ASTM D-698-78 (See Appendix A of this report).
Additional fill should consist of the onsite soil or imported
materials approved by the geotechnical engineer. Fill should be
placed in uniform six to eight (6-8) inch lifts and mechanically
compacted plus or minus two percent (±2%) of optimum moisture to
at least ninety-five percent (95%) of Standard Proctor Density ASTM
D-698-78.
L A N D S C A P I N G A N D D R A I N A G E
Every precaution should be taken to prevent wetting of the subsoils
and percolation of water down along the foundation elements.
9
4 The foundation walls and other structural elements should be
designed by a qualified structural engineer for the appropriate
loading conditions. All footings or pads should be placed below
any topsoil or fill unless the fill has specifically been placed
1
and compacted for support of footings or pads. All exterior
footings, pads, and grade beams should be placed below frost depth
(thirty (30) inches in this area) to provide adequate cover for
frost protection.
F L O O R S L A B S
Soils at proposed foundation elevations are stable at their natural
moisture condition. However, should moisture contents of the upper
F
i
clays increase, slight heaving may result. This phenomenon can
result in heaving and/or cracking of the slabs -on -grade. With the
above in mind, construction of the structure, as much as possible,
should be done to accommodate movement of the slabs without damage.
Slabs should be constructed "free-floating", isolated from all
bearing members, reinforced with wire mesh (or equivalent), and
jointed frequently. Slabs -on -grade in habitable or storage areas
should be underlain with a four (4) inch layer of clean gravel or
crushed rock to help distribute floor loads and provide a capillary
break. Positive drainage should be provided for the gravel
underlayment to prevent pooling of water beneath the slab. All
0
{ 1. All footings, pads, and\or grade beams should be below frost
r depth. Frost depth in this area is considered to be thirty
(30) inches.
2. Foundation walls should be reinforced with rebar to span an
unsupported length of ten (10) feet or between each pad.
Rebar should be run continuously around corners and be
properly spliced. Foundations should be designed by a
Registered Engineer for the conditions described in this
report.
3. Bearing walls should be omitted in the basement. Partitions
- located over slabs -on -grade should be hung from the floor
joists and beams supported by adjustable steel columns. A one
(1) inch void should be constructed under all partition walls
located over slabs.
4. All footings, pads, and/or grade beams should bear on similar
strata.
5. We recommend the performance of an excavation inspection for
each lot to make a final determination on foundation type.
6. All concrete shall be composed of Type I/II sulfate resistant
cement.
7
F O U N D A T I O N R E C O M M E N D A T I O N S
Spread Footings and/or Grade Beams
Based upon conditions observed in the field, laboratory tests and
the anticipated loading of the structure, we feel that the
structure. should be supported by a continuous balanced spread
footing and/or grade beam foundation. The footings and/or grade
beams should be placed on the natural, undisturbed clays or sands.
The footings should be designed for a maximum allowable bearing
capacity of 1500 pounds per square foot (dead load plus 112 live
load).
If isolated areas of loose or soft soils are exposed during final
footing excavation and open hole inspection, these soil areas
should be removed down to undisturbed, acceptable soils prior to
placement of the footings. Footings can then be placed directly
upon the acceptable soil, or the excavation can be backfilled up
to the desired footing bearing elevation. The fill should extend
a minimum of three (3) feet beyond each side of any footings, pads
or grade beams. All fill should be placed and compacted in
accordance with the recommendations contained in the Section "Site
Grading and Utilities", and Appendix A of this report. All fill
shall be tested and approved by the Engineer.
The following recommendations should be followed in the design of
the foundation system:
6
s
E.
E S U B S U R F A C E C O N D I T I O N S
Generally, a thin layer of sandy clay overlies sands with clay and
gravel lenses to the depths explored. Free groundwater was not
' encountered in the borings.
Clays' containing moderate amounts of sand and slight amounts of
gravel were encountered in the upper one to two (1 - 2) feet of the
borings. These deposits are of low plasticity, exhibiting low to
moderate bearing capacities with little to no swelling when wetted.
Sands containing lenses of clay and gravel were encountered from
_._ below the upper, clays to the depths explored. These deposits
exhibit low to moderate bearing capacities with no swell potential
when wetted.
Groundwater observations were made as the borings were being
advanced and immediately after completion of the drilling opera-
tion. At the time of our field investigation, groundwater was not
encountered. The groundwater table can be expected to fluctuate
throughout the year depending upon variations in precipitation,
surface irrigation and runoff on the site. The ambient groundwater
table at the site is not expected to rise to a level which would
affect basement level construction unless a source of water not
presently contributing becomes available.
5
stability characteristics. These include swelling, compres-
sibility, collapse and shear strength of the soil and/or rock.
One dimensional consolidation -swell tests were performed on
selected samples to evaluate the expansive, compressive and
collapsing nature of the soils and/or bedrock stratum. In the
consolidation -swell test, a trimmed specimen is placed in a one-
dimensional confinement ring and -a vertical load is applied. After
seating, the sample is inundated with water and the height change
of the specimen is recorded. The confining load is then incremen-
tally increased until the specimen is compressed to its original
volume. Results of those tests are presented at the end of this
-- report.
A calibrated hand penetrometer was used to estimate the approximate
unconfined compressive strength of selected samples. The calibra-
ted hand penetrometer has been correlated with unconfined compres-
sion tests and provides a better estimate of soil consistency than
visual examination alone.
As part of the testing program, an R-value, Atterberg Limits and
gradation analyses were conducted on selected samples to determine
the plasticity and texture of the soils and to classify the soil
in accordance with AASHTO Classification.
n
standard penetration tests are shown on each boring log. The
transition between different strata can be and most often is
gradual.
An index of soils relative density and consistency was obtained by
use of the standard penetration test, ASTM Standard Test D-1586.
The penetration test result listed on the log is the number of
blows required to drive the two (2) inch split -spoon sampler twelve
(12) inches (or as shown) into undisturbed soil by a one hundred
and forty (140) pound hammer dropped thirty (30) inches.
Undisturbed samples for use in the laboratory were taken in three
(3) inch O.D. thin wall samplers (Shelby), pushed hydraulically
into the soil in accordance with ASTM D-1587. in this sampling
procedure, a seamless steel tube with a beveled cutting edge is
pushed hydraulically into the ground to obtain a relatively
undisturbed sample of cohesive or moderately cohesive soil. All
samples were sealed in the field and preserved at natural moisture
content until time of test.
L A B O R A T O R Y T E S T I N G P R O C E D U R E S
The recovered samples were tested in the laboratory to measure
their dry unit weights, natural water contents, and for classifica-
tion purposes. Selected samples were tested for strength and
3
F I E L D I N V E S T I G A T I O N
The field investigation consisted of five (5) borings at selected
locations on the site. Distances.between borings are as indicated
on the attached test boring location map, Figure 1. The borings
were advanced using a four (4) inch diameter continuous flight
power auger. All borings were continued to depths considered
sufficient for the purposes of this report as set forth in the
scope.
The borings were laid out by Foundation & Soils Engineering, Inc.
personnel based on a sketch provided by the client. Distances from
the referenced features to the boring locations, as indicated on
the attached diagram, are approximate and were made by pacing.
Angles for locating the borings were estimated. Elevations of the
borings are approximate and were obtained using a level and rod.
The elevations were referenced to an assumed elevation of one
hundred (100) feet using Test Hole No. 1. The approximate location
of the benchmark is shown on the attached boring location map,
Figure 1. The locations and elevations of the borings should be
considered only to the degree implied by the methods used to make
those measurements.
Complete logs of the boring operations were compiled by a represen-
tative of our firm as the borings were advanced. The approximate
location of soil and rock contacts, free groundwater levels, and
2
S C 0 P E
The following report presents the results of our subsurface
investigation on Hampshire Ponds East P.U.D., Fort Collins,
Colorado. This investigation was performed for Bret Larimer, Ltd.
at the request of Mr. Bret Larimer.
We understand the site is to be developed into multi -family
townhomes. Construction is to be typical wood frame type and brick
veneer and as such, should generate only light loading, on the
order of 1,000 to 2,000 PLF. Concentrated loads, if any, should
not exceed 15 to 20 KIPS.
The purpose of this investigation is to identify subsurface condi-
tions and to obtain test data to properly design and construct the
foundation systems, floor slabs, and roadway pavement. The
conclusions and recommendations presented in this report are based
upon the acquired field and laboratory data and previous experience
with similar subsurface conditions in the area.
1_ S I T E D E S C R I P T I O N
The site is located in west Fort Collins, south of Drake Road on
water Blossom Lane. The 3+ acre site is relatively flat and is
vegetated with grasses and weeds.
1
TABLE OF CONTENTS
Letter of Transmittal
i
Scope
1
Site Description
1
Field Investigation
2
Laboratory Testing Procedures
3
Subsurface Conditions
5
Foundation Recommendations
6
Floor Slabs
8
Site Grading and Utilities
9
Landscaping and Drainage
9
Pavement Recommendations
11
General Information
13
Test Boring Location Map
Figure 1.
Legend of Soil Symbols
Figure 2
' Boring Logs
Figure 3
Consolidation Swell Tests
Figure 4
Grain Size Distribution Curve
Figure 5
Summary of Test Results
Figure 6
Suggested Specifications for Placement Appendix A
of Compacted Earth Fills and/or Backfills
FOUNDATION Engineering,
AND SOILS II Inc.
l
August 22, 1995
,. commission No.: 1663-30-01-01
Bret Larimer, Ltd.
1600 Horsetooth Road
Fort Collins, Colorado 80526
I
Gentlemen:
The enclosed report presents the results of a subsurface
investigation for Hampshire Pond East P.U.D., Larimer County,
Colorado.
In summary, non -swelling soils were encountered in the borings.
Although the site soils and/or rock are suitable for support of the
proposed structures, care will be needed in both the design and
construction of the buildings to minimize the potential for
foundation and floor slab movement.
The attached geotechnical report presents the results of our
investigation and recommendations concerning design and construc-
tion of the foundation system and support of floor slabs.
We appreciate the opportunity to be of service to you on this
project. If you have any questions, please feel free to call.
Respectfully,
Thomas W. Finley,
Engineering Geologist
Reviewed by:
Kevin W. erson, '.
FOUNDATION & SOILS E,
TWF/jlb
2;�Eil�'f
100 East 3rd Street 9 Loveland, Colorado 80537 • (970) 663-0138
t
i
firm ✓.T' i}U >-: a ��� F " 7
t a !n'r�%'
SUBSURFACE;INVESTIGATION
FOR HAMPSHIRE POND EAST P.U.D.
FORT COLLINS, COLORADO
Prepared for
Bret Larimer, Ltd.
1600 Horsetooth Road
Fort Collins, Colorado 80526
August 22, 1995
Commission No.: 1163-30-01-01
Prepared By
FOUNDATION & SOILS ENGINEERING, INC.
CONSULTING ENGINEERS
100 East Third Street
Loveland, CO 80537