HomeMy WebLinkAboutLIGHTFIELD ENTERPRISES INC PDP AND FDP - FDP150012 - REPORTS - RECOMMENDATION/REPORTStaff Report — Spoons-Lightfield Enterprises, Inc., FDP150012
Administrative Hearing 04-30-2015
Page 8
ATTACHMENTS:
1. Zoning & Site Vicinity Map
2. Applicant's Statement of Planning Objectives
3. Lightfield Enterprises, Inc. Planning Document Set (Site Plan, Landscape Plan,
Elevations & Photometric Plan)
4. LEI Replat
Staff Report — Spoons-Lightfield Enterprises, Inc., FDP150012
Administrative Hearing 04-30-2015
Page 7
M. Section 3.5.1(1) - Outdoor Storage Areas/Mechanical Equipment
The proposed plan is consistent with the requirements of the Land Use
Code in regards to the location of outdoor storage, screening of storage
areas, and screening of rooftop mechanical equipment from public view.
N. Section 3.6.6 — Emergency Access
For the Lightfield site, an emergency access easement is proposed that
runs through the private drive to the northern edge of the site with a
turnaround located next to the bay doors for the shop. The emergency
access easement ensures emergency vehicles can gain proper access
and maneuvering to reach all portions of the proposed building.
4. Findings of Fact/Conclusion:
In evaluating the request for the Lightfield Enterprises, Inc. Project Devleopment
Plan/Final Plan, Staff makes the following findings of fact:
A. The Project Development Plan/Final Plan complies with process located in
Division 2.2 — Common Development Review Procedures for
Development Applications of Article 2 — Administration.
B. The Project Development Plan/Final Plan complies with relevant
standards located in Article 3 — General Development Standards.
C. The Project Development Plan/Final Plan complies with relevant
standards located in Division 4.28 Industrial (1) of Article 4 — Districts.
RECOMMENDATION:
Staff recommends approval of the Spoons-Lightfield Enterprises, Inc., FDP150012.
Staff Report — Spoons-Lightfield Enterprises, Inc., FDP150012
Administrative Hearing 04-30-2015
Page 6
H. Section 3.2.2(K)(5) - Handicap Parking
Parking lots with less than 25 spaces must provide at least 1 handicap
parking space. The parking lot proposed is less than 25 spaces and
provides 1 handicap parking space.
Section 3.2.3 -Solar Access, Orientation, Shading
All developments must be designed to accommodate active and/or
passive solar installations and must not deny adjacent properties access
to sunshine. The proposed building is designed and located to minimize
the casting of shadows on adjacent properties and could accommodate
future active and/or passive solar installations.
J. Section 3.2.4 - Site Lighting
The proposed lighting plan is consistent with the requirements of the Land
Use Code in regards to the general standard, lighting levels and design
standards.
K. Section 3.2.5 - Trash and Recycling Enclosures
Trash and recycling enclosures must be provided in locations abutting
refuse collection or storage areas, shall be designed to allow walk-in
access without having to open the main service gate, shall be screened
from public view and shall be constructed on a concrete pad. The
proposed trash and recycling enclosure abuts storage areas, allows walk-
in access without having to open the main service gate, is screened from
public view and will be built on a concrete pad.
L. Section 3.5.1(E) - Building Materials
All proposed buildings shall use similar materials to existing buildings in
the neighborhood or use similar architectural characteristics if dissimilar
materials are proposed. The proposed building uses similar materials and
architectural details to the existing buildings in the area. The proposed
materials include contrasting split and smooth face concrete masonry
units, metal roofing and metal sun shades.
Staff Report — Spoons-Lightfield Enterprises, Inc., FDP150012
Administrative Hearing 04-30-2015
Page 5
C. Section 3.2.2(C)(5) - Walkways
Walkways must be provided to link sidewalks with building entries through
parking lots. These walkways must also provide direct connections to off -
site pedestrian and bicycle destinations. The Lightfield site provides a
connecting walkway that runs along the perimeter of the drive aisle that
satisfies this standard.
D. Section 3.2.2(D)(1) - Access and Parking Lot Requirements;
PedestrianNehicle Separation
To the maximum extent feasible, pedestrians and vehicles shall be
separated through provision of a sidewalk or walkway. Where complete
separation of pedestrian and vehicles is not feasible, potential hazards
shall be minimized by using landscaping, bollards, special paving, lighting
and other means to clearly delineate pedestrian areas. Lightfield
separates pedestrians from vehicles by providing a sidewalk separated
from the driving and parking area via curb.
E. Section 3.2.2(E) - Parking Lot Layout
The proposed parking lot layout is consistent with requirements of the
Land Use Code in regards to circulation routes, orientation, landscaped
islands, and points of conflict.
F. Section 3.2.2(J) - Setbacks
The proposed parking lot is setback further than the 10-foot minimum from
non -arterial streets and 5-foot minimum along a lot line required per the
Land Use Code.
G. Section 3.2.2(K)(2) — Nonresidential Parking Requirements
The minimum, maximum and proposed parking are contained in the tables
below. Lightfield is providing parking within the range of required parking
and thus meets the requirements of the Land Use Code.
Table 1: Lightfield Enterprises, Inc. Parking
Use
Min. Parking
Max. Parking
Parking
Provided
Office (2,218 sq.
1/1,000 sq. ft. = 3
3/1,000 sq. ft. = 7
3 spaces
ft.)
spaces
spaces
Industrial (10
.5 per employee =
.75 per employee
5 spaces
employees)
5 spaces
= 8 spaces
Total
8 spaces
15 spaces
8 s aces
Staff Report — Spoons-Lightfield Enterprises, Inc.. FDP150012
Administrative Hearing 04-30-2015
Page 4
2. Compliance with Article 4 of the Land Use Code — Industrial (1) Division
4.28:
The project complies with all applicable Article 4 standards as follows:
A. Section 4.28(B)(2) - Permitted Uses
The proposed uses, light industrial and office, are permitted in the
Industrial zone district and are consistent with the district's intent to
provide a wide range of commercial and industrial operations.
B. Section 4.28(D)(1) - Dimensional Standards
Non-residential structures are limited to four stories in height. The Project
Development Plan/Final Plan proposes a two-story structure.
C. Section 4.28(E)(3)(b) - Storage and Operational Areas
Storage, loading and work operations must be screened from view along
district boundary lines and public streets in the I District. The Project
Development Plan/Final Plan proposes a 6-foot high fence surrounding
the storage, loading and work area.
3. Compliance with Article 3 of the Land Use Code — General Development
Standards:
The project complies with all applicable General Development Standards as
follows:
A. Division 3.2.1 - Landscaping and Tree Protection
The proposed landscaping is consistent with requirements of the Land
Use Code in regards to the addition of street trees, parking lot landscaping
and landscape screening from adjacent uses.
B. Section 3.2.2(C)(4)(b) - Bicycle Parking Space Requirements
The minimum number of bicycle parking spaces required for Industrial
uses is 4. The Lightfield site will provide one bike rack that contains 4
bicycle parking spaces.
Staff Report - Spoons-Lightfield Enterprises, Inc., FDP150012
Administrative Hearing 04-30-2015
Page 3
Map 1: Lightfield Enterprises, Inc. Zoning & Site Vicinit
E Prospect Rd
T-i
m
o. a
L U Q
d —
d 6 �
y o a Prospect Pond °2 North
LE a RC
N
L
•N
Cibd y Common Elemen
T
G`
/tea
�Q ocG`
ono a�
Site
f�
f L'MN
°3 6elfish�PonO
o -
a
O
40AS
5 \RC
dO` o'h
T�yt'�R c NancYGrayPJ U'EjQ°\ \�
a 3#' � o • ry
\ o
0 9�
qm e
t .nch = 500 feet
Lightfield Enterprises, Inc. - 2600 Midpoint
Vicinity Map -��
Staff Report — Spoons-Lightfield Enterprises, Inc., FDP150012
Administrative Hearing 04-30-2015
Page 2
• The Project Development Plan/Final Plan complies with relevant standards
located in Division 4.28 Industrial (1) of Article 4 — Districts.
COMMENTS:
1. Background
The property was annexed into the City of Fort Collins as part of the East Prospect
Street Annexation in December 1959. The site was originally platted as Lot 17 of the
Prospect Industrial Park in October 1978.
The surrounding zoning and land uses are as follows:
Direction
Zone District
Existing Land Uses
North
Industrial I
Light industrial, office, school
South
Industrial (1)
Industrial (1)
Light industrial, office
East
Light industrial, office
West
Industrial (1)
Light industrial, office, government
A zoning and site vicinity map is presented on the following page.
City of
Fit Collins
ITEM NO
MEETING DATE
STAFF
2
Apr. 30, 2015
Clay Frickey
ADMINISTRATIVE HEARING OFFICER
PROJECT: Lightfield Enterprises Inc., FDP150012
APPLICANT: Cathy Mathis
The Birdsall Group
444 Mountain Ave.
Berthoud, CO 80513
OWNERS: Lightfield Properties LLC
6330 S College Ave
Fort Collins, CO 80525
PROJECT DESCRIPTION:
This is a request for a consolidated Project Development Plan/ Final Plan for 2600
Midpoint Drive. 2600 Midpoint Drive will contain a new building for Lightfield
Enterprises, formerly Vogel Concrete. The two-story building will contain 2,218 square
feet of offices and a 4,900 square foot shop. Main access to the site will be from a
single point off Midpoint Drive. The access driveway is sized to accommodate concrete
equipment and Poudre Fire Authority requirements for a fire lane. Eight parking spaces
are provided for employees. The site is also being replatted from Lot 17 of the Prospect
Industrial Park to Lot 1 of the LEI Replat.
RECOMMENDATION: Staff recommends approval of Lightfield Enterprises, Inc.,
FDP 150012.
EXECUTIVE SUMMARY:
Staff finds the proposed Lightfield Enterprises, Inc. Project Devleopment Plan/Final Plan
complies with the applicable requirements of the City of Fort Collins Land Use Code
(LUC), more specifically:
• The Project Development Plan/Final Plan complies with the process located in
Division 2.2 — Common Development Review Procedures for Development
Applications of Article 2 — Administration.
• The Project Development Plan/Final Plan complies with relevant standards of
Article 3 — General Development Standards.
Planning Services 281 N College Ave - PO Box 580 - Fort Collins, CO 80522-0580
fcgov.com/developmentreview/ 970.221.6750