HomeMy WebLinkAboutBUENO DRIVE CONDOS - PDP190004 - CORRESPONDENCE - STAFF'S PROJECT COMMENTS2018 International Residential Code (IRC) with local amendments
2018 International Existing Building Code (IEBC) with local amendments
2018 International Energy Conservation Code (IECC) with local amendments
2018 International Mechanical Code (IMC) with local amendments
2018 International Fuel Gas Code (IFGC) with local amendments
2018 International Swimming Pool and Spa Code (ISPSC) with local amendments
2015 International Plumbing Code (IPC) as amended by the State of Colorado
2017 National Electrical Code (NEC) as amended by the State of Colorado
Copies of current City of Fort Collins code amendments can be found at fcgov.com/building.
Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2017.
Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF.
Frost Depth: 30 inches.
Wind Loads:
Risk Category II:
140mph (Ultimate) exposure B or
Front Range Gust Map published by The Structural Engineer's Association of Colorado
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code: 2018 IECC commercial chapter with amendments.
4
Department: Forestry
Contact: Nils Saha, nsaha@fcqov.com
Topic: Landscape Plans
Comment Number: 8
6/6/2019: FOR FINAL PLAN - UPDATED:
Please change the linework for this planting space to show irrigated turf.
04/30/2019: FOR FINAL PLAN
Honeylocust trees have an average canopy spread of 50 feet. The honeylocust
tree proposed next to the trash enclosure will not have adequate space to grow
(see redlines). Additionally, will this planting space be irrigated? If so, please
show on the plan. The honeylocust can be replaced with a smaller, ornamental species, in that case.
Department: Technical Services
Contact: Jeff County, 970-221-6588, (county@fcgov.com
Topic: Easements
Comment Number: 2
04/29/2019: This has been addressed.
03/11/2019: FOR APPROVAL:
There are some issues with the Right Of Way & Utility Easement legal descriptions. See redlines.
Topic: General
Comment Number: 1
06/10/2019: INFORMATION ONLY:
Unless required during PDP, a complete review of all plans will be done at FDP.
04/29/2019: INFORMATION ONLY:
Unless required during PDP, a complete review of all plans will be done at FDP.
03/11/2019: INFORMATION ONLY:
Unless required during PDP, a complete review of all plans will be done at FDP.
Department: Building Services
Contact: Katy Hand, khand@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 6
04/29/2019: BUILDING PERMIT:
Be advised that prescriptive energy compliance with increased insulation
values is required for buildings using electric heat.
Comment Number: 7
04/29/2019: BUILDING PERMIT:
Be advised that this building will be required to provide air barrier details at plan
review and pass a blower door test (<.25cfm/75) prior to issuance of the Certificate of Occupancy.
Comment Number: 8
04/29/2019: BUILDING PERMIT:
Construction shall comply with adopted codes as amended. Current adopted codes are:
2018 International Building Code (IBC) with local amendments
3
05/03/2019: Per the meeting on 5/2/2019, please submit variance to address
outfall issues and LID treatment as discussed - no drainage easement for
historic outfall location, site constraints for LID. Please contact me with any questions. OK for hearing.
Department: Light And Power
Contact: Tyler Siegmund, 970416-2772, tiegmund@fcqov.com
Topic: General
Comment Number: 1
03/12/2019: INFORMATION ONLY: SITE SPECIFIC:
Light and Power has electric facilities along the west side of Bueno Dr that can
be extended into the site to feed the development. To feed the site with 3phase
electric facilities, modifications will apply. Light and Power will need to intercept
existing 3phase lines and at the northwest corner of the site and cut in a new
vault. From the new vault, we will need to trench 3phase lines to the transformer
location. All modifications needed to feed the site will be at the expense of the
developer/owner. Please contact me if you would like to discuss modification fees for this project.
Comment Number: 2
03/12/2019: INFORMATION ONLY:
Electric capacity fees, development fees, building site charges and any system
modification charges necessary to feed the site will apply to this development.
Please contact me or visit the following website for an estimate of charges and fees related to this project:
http://www.fcgov.com/utilities/business/builders-and-developers/plant-investment-development-fees
Comment Number: 5
03/12/2019: INFORMATION ONLY:
Please contact Tyler Siegmund with Light & Power Engineering if you have any
questions at 970.416.2772 Please reference our policies, construction
practices, development charge processes, electric service standards, and use our fee estimator at
http://www.fcgov.com/utilities/business/builders-and-developers
Department: PFA
Contact: Andrew Rosen, 970416-25999 arosen@aoudre-fire.orq
Topic: General
Comment Number: 1
06/04/2019: INFORMATION ONLY:
Please note that the Hydrant test flow is approved for this project. Thank you
Comment Number: 6
06/14/2019: INFORMATION ONLY:
All PFA comments are resolved. Thank you
Comment Number: 7
06/14/2019: BUILDING PERMIT:
When you submit for your building permit though the City of Fort Collins please
be advised Poudre Fire Authority is an additional and separate submittal. The
link for Poudre Fire Authority's plan review application can be found at
https://www.poudre-fire.org/online-services/contractors-plan-reviews-and-permit
s/new-building-plan-review-application.
El
Fort Collins
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6689
970.224.6134 - fax
kgov. corn/developmentreview
June 14, 2019
Brian Shear
Shear Engineering Corp
4836 S College Ave, Suite 12
Fort Collins, CO 80525
RE: Bueno Drive Condos, PDP190004, Round Number 3
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, please contact your Development Review Coordinator Brandy Bethurem Harras at
970.416.2744 or bbethuremharras@fcaov.com.
Comment Summary:
Department: Planning Services
Contact: Pete Wray, 970-221-67547 pwray@fcgov.com
Topic: General
Comment Number: 9
BY HEARING. At staff review, if plans are revised, please submit hearing plan set by June 14.
Department: Stormwater Engineering
Contact: Dan Mogen, 970-305-5989, dmogen@fcgov.com
Topic: General
Comment Number: 2
06/10/2019: FOR FINAL PLAN - UPDATED:
Please see redlined drainage report provided via PDF. I encourage you to
reach out with any questions or to review potential revisions, and I'd be happy to
set up a meeting or conference call to do so.
04/29/2019: Please see updated redlines provided via PDF.
03/08/2019: Please see redlined drainage report (PDF).
Comment Number: 4
06/10/2019: FOR FINAL PLAN - UPDATED:
Variance application is currently under review. OK to proceed to hearing.