HomeMy WebLinkAboutRAINTREE TOWNHOMES PUD PRELIMINARY - 42 93 - CORRESPONDENCE - STAFF'S PROJECT COMMENTSFinal mylars and other documents are due August 19th.
Please be aware that if a development agreement and utility
plans are required with this project, these documents and
plans must be signed prior to the Planning and Zoning Board
Hearing. If not, a condition will be placed on the project
giving you 60 days to finalize the plans and agreement, after
which time, you must submit a request for an extension from
the Planning and Zoning Board.
If you have any questions about these comments or would like to
schedule a time to meet to discuss them, please contact me at 221-
6750.
Sincere y,
Kirsten Whetstone
Project Planner
cc: Kerrie Ashbeck, City Engineering
City Stormwater Utility
Engineering Consultant
zF-i l e-�
a
19. Fence location between units and back lot lines is not clear.
Please show the intended fence locations. Staff suggests that
side yard fencing not extend to the north property line (of
course if this is a ditch access easement, this could not be
fenced). Staff would discourage rear lot fencing. Why fence
off a wonderful open space area, views, and a lose sense of
the expansiveness of the area? Was it your intention to allow
privacy fencing around the patio areas?
20. Overall the project looks great. It is a good layout and a
nice location for this type of project.
21. A formal street width variance needs to be submitted to Kerrie
Ashbeck, signed by a P.E.
22. Staff wonders.whether the setback for unit one is sufficient
and whether 5' more could be achieved by decreasing the width
of some of the open space tracts. Staff thinks that the
masonry wall will help. Please show a detail of this wall and
proposed plantings at the time of final.
23. Please identify on the plat, all solar lots.
24. Please refer to attached comment sheet for Stormwater
comments.
25. Is it possible to make Lot 9 a solar lot? We realize that you
are over the required 650, but it is very close and perhaps
shifting a lot line or two may make that a solar lot as well.
26. Staff does not have a problem with the front setbacks as
proposed, given that there is a 4' "no -mans" ROW land between
the back of walk and property line, which will essentially
allow up to a 20' driveway length before over -hanging into the
sidewalk.
27. Please provide a notary signature for the Owner's
Certification at the time of final.
28. Add a note on the site plan "to bridges over canals" at the
point where the walk on the west side of the Senior Center
heads to the southwest.
29. Transportation would like to discuss the "right turn" only.
If the sign is put up, a pork chop would have to be designed
to provide a guarantee that no left turns would be made.
This concludes staff comments at this time. In order to stay on
schedule for the August 23, 1993 Planning and Zoning.Board hearing,
please note the following deadlines:
Plan revisions are due August 4th, 1993 by 12:00 noon.
PMT1s, colored renderings, and 10 prints are due August 16th.
8. The maintenance area on the south side of the New Mercer Canal
appears to be inadequate according to the Canal Company. They
would like to discuss these plans with the developer. No
bridges will be allowed without written approval. We should
try to set up a meeting, possibly to coincide with the utility
coordination meeting, to discuss treatment of the ditches. We
did not receive comments from the Larimer Canal No. 2 ditch.
9. Evenstar Ct. must meet City street standards for the single
loaded 28' street and cul-de-sac for fire access. A formal
variance request is still needed.
10. The western building appears to be out of compliance with the
150' fire access requirement. Contact Warren Jones about
this.
11. A soils report and traffic study will be required. The soils
report prior to final; the traffic study prior to preliminary.
12. The sidewalk should connect to the Senior Center (it appears
to connect, but a note pointing this connection out would be
a good idea).
13. Engineering would like to discuss the cul-de-sac/parking
design. Should this area be platted as a tract?
14. See the utility plan and plat for additional engineering
comments.
15. Who will be responsible for maintenance of the south bank of
the ditch and the possible ditch rider access? This was not
clear to the ditch company. Planning assumes that everything
within the property lines will be maintained by individual lot
owners and open space areas will be the responsibility of -the
HOA.
16. Parks and Recreation has concerns about storm drainage
regarding drainage onto Rolland Moore Park. Parks owns the
property between the two ditches, immediately north of your
property line, it was platted as part of the Rolland Moore
Park plat. I will verify with Jean Helburg and Steve White
that proposed pedestrian connections to the Senior Center are
adequate. We may want an additional connection at the
northeast corner of the Senior Center parking lot.
17. Parkland fees are currently $625.00 per dwelling unit
collected at the time of building permit issuance. An
increase has been approved by City Council.
18. The parkway area along Shields Street between the sidewalk and
curb is existing and does not have any irrigation. Parks is
requesting that this area be provided with irrigation with the
lawn, please put a note on the plans regarding this.
Commu / Planning and Environmental rvices
Planning Department
City of Fort Collins
July 23, 1993
Kay Force
Jim Sell Design
117 E. Mountain Ave.
Fort Collins, CO 80524
Dear Kay,
Staff has reviewed ypur submittal for Raintree Townhouses PUD and
offers the following ,comments:
1. US West will provide telephone service in accordance with the
rates and tariffs on file with the Colorado Public Utilities
Commission. The developer is responsible for provision of all
trench, street crossings, and ditch crossings for telephone
facilities within the project, and the developer pays up front
construction costs for facilities within the development.
2. Any relocation of existing telephone facilities required by
these plans will be paid for by the developer.
3. Review of these plans should not be construed as a commitment
that telephone facilities sufficient to serve this project are
presently available.
4. Columbine CableVision would like to see rear lot utility
easements on all lots and would like the open space tracts to
be utility easements as well.
5. There is a possible conflict with the trees and electric/gas
lines in the front yard area. Trees will not be allowed to be
planted within 4' of any gas line. A utility coordination
meeting would be required if there is not adequate clearance
for standard utility separation. Please contact Kerrie
Ashbeck at 221-6750 for scheduling this meeting if it is
needed.
6. The closest natural gas source of distribution pressure is at
the Shields and Raintree intersection. The developer will
have to obtain a utility easement either from the existing
private residence adjoining Shields Street, or from the Fort
Collins Senior Center for access for a gas line to serve this
development.
7. There should be at least one handicapped parking space in the
center parking area on Evenstar Court and a ramp at the north
west corner of Evenstar Court and Shields Street.