HomeMy WebLinkAboutHARMONY RIDGE PUD FOURTH REPLAT - FDP180029 - CORRESPONDENCE - STAFF'S PROJECT COMMENTS (3)Department: Environmental Planning
Contact: Stephanie Blochowiak, 970-416-42909 sblochowiak@fcqov.com
Topic: General
Comment Number: 3
06/03/2019: No further comments. Thank you.
Department: Technical Services
Contact: Jeff County, 970-221-6588, icounty@fcgov.com
Topic: Plat
Comment Number: 1
Comment Originated: 06/03/2019
Comment Originated: 12/27/2018
06/03/2019: FOR APPROVAL -UPDATED:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter.
12/27/2018: FOR APPROVAL:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter.
Page 3 of 3
out to me to discuss further.
Department: Planning Services
Contact: Kai Kleer, 970-416-42849 kkleer@fcqov.com
Topic: General
Comment Number: 4
06/04/2019: Ready for Hearing.
Department: Engineering Development Review
Contact: Dave Betley, 970-221-65737 dbetley@fcgov.com
Topic: General
Comment Number: 5
01/04/2019: FOR HEARING:
Comment Originated: 06/04/2019
Comment Originated: 01/04/2019
The applicant needs to pay the required fees for the submittal as required by code.
Contact: Morgan Uhlman, 970-416-4344, muhlman@fcqov.com
Topic: General
Comment Number: 3 Comment Originated: 12/21/2018
12/21/2018: FOR APPROVAL:
Please show sidewalks and curb ramps on the site plan.
Comment Number: 4 Comment Originated: 12/21/2018
06/03/2019: Updated: FOR HEARING:
The sight distance triangle and easement were not shown on the site plan. Thank
you for showing the right leg of the sight distance easement on the utility plans
and the plat, please provide the sight distance triangle the other direction as
well.
12/21/2018: FOR HEARING:
Please show a sight distance triangle for the driveway closest to the comer on
the site plan. LCUASS figure 7-16 details how to calculate the sight triangle:
https://www.larimer.org/sites/default/files/fig 714 733_2016.pdf
Comment Number: 7 Comment Originated: 06/04/2019
06/04/2019: FOR HEARING:
The proposed retaining wall between Lots 1 and 2 and Lots 3 and 4 need to be
setback at least 2' from the back of the sidewalk.
Comment Number: 8 Comment Originated: 06/04/2019
06/04/2019: FOR APPROVAL:
Please see my redlines for more details and minor comments.
Comment Number: 9 Comment Originated: 06/06/2019
06/06/2019: DEVELOPMENT CONSTRUCTION PERMIT:
To determine if this project will need a Development Construction Permit
(DCP) issued before construction can begin, please have your engineer fill out
the "Project Quantity Cost Estimate" spreadsheet at the bottom of the page at
the following link and have it sent to me.
https://www.fcqov.com/engineering/devrev.php
Page 2 of 3
Fort Collins
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
lcgov. com/developmentreview
June 07, 2019
Toby Terhune
Shadow Creek Homes
2535 W 115th Drive
Westminster, CO 80234
RE: Harmony Ridge PUD Fourth Replat, FDP180029, Round Number 2
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, you may contact the Development Review Coordinator, Todd Sullivan, at
970-221-6695 or tsullivan @fc-gov.com .
Comment Summary:
Department: Development Review Coordinator
Contact: Todd Sullivan, 970-221-6695, tsullivan@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 06/04/2019
06/07/2019: The overall request for this project consists of a replat of Lot 13 into 4 separate
lots, and the revised building and landscape plans from the original approved plan for
Lot 13.
As mentioned in Round 1 comments, the project will be reviewed in two separate
processes; this review to include only the replat, and a Minor Amendment review
for the remaining items.
The draft letter provided for the Staff Review Meeting held June 5, 2019 included
comments related to both processes. This letter has been updated to only include
those comments related to the replat. All Minor Amendment comments will be
provided in a separate letter to be issued on June 20, 2019.
Both reviews will run concurrently.
Comment Number: 2 Comment Originated: 06/04/2019
06/07/2019: 1 would like to schedule the Administrative Hearing to be held in the last
week of June (by the 261h) or first week of July (after the 2nd). The scheduling will
be contingent on addressing two of the Engineering items that are noted FOR HEARING.
The hearing requires a public notice to be mailed 14 days prior to the hearing. Please reach