HomeMy WebLinkAboutHANSEN FARM - FDP190010 - SUBMITTAL DOCUMENTS - ROUND 1 - RESPONSE TO STAFF REVIEW COMMENTSquestions or require additional information.
Respectfully,
Mr. Terry W. Farrill, P.E.
District Engineer
RESPONSE: Previous comment
Comment Number:
Comment Originated: 05/01/2018
05/01/2018: SFCSD/FCLWD
The District's signature block is required on the face page only. The District's
current signature block can be downloaded from the District's web site,
FCLWD.com
All easements for water or sanitary sewer must be a minimum width of 20 feet
and 30 feet respectively. The easements must be on the District's standard
easement form or the District's covenants and restrictions must be on the plat.
The District will provide additional comments when the construction drawings
have been submitted for review. Please do not hesitate to contact me at
226-3104, ext. 104, if you have any questions or require additional information.
RESPONSE: Previous comment
13
Department: Outside Agencies
Contact: Don Kapperman,
Topic: General
Comment Number:
Comment Originated: 06/27/2018
6/27/18: Comcast - Please make sure he owner know that Comcast facility
needs to be in at least a 5 foot utility easement.
RESPONSE: Acknowledged
Contact: Rosanna Harris, ,
Topic: Easements
Comment Number:
Comment Originated: 07/17/2018
07/17/2018: New Mercer Ditch Company Comments.
Mr. Wray,
I apologize for the late comment on this matter. The comment sheet was
provided to Mail Creek Ditch Company rather than New Mercer Ditch
Company, the owner of the Mail Creek lateral; and to our legal counsel rather
than New Mercer directly. I just received this morning and had to quickly poll the
Board for its response.
Subsequent to the plans provided, it has been agreed by the developer to
provide a turnaround at the end of the New Mercer access. This will
undoubtedly be shown on the next draft of plans. As to sharing the easement
with a bike path and pedestrian trail, the New Mercer Ditch Company is not in
favor of a shared easement because of safety and public welfare issues with
people being near the ditch structure and because of interference with
maintenance and operations. There are several potential problems with use by
bicycles and pedestrians next to the ditch, including falling into the ditch and
trash disposal. Such use would not be possible during maintenance operations
such as burning the ditch in the spring and when heavy equipment is in use.
This heavy equipment could damage the surface of the shared easement. If the
developer wishes to discuss these concerns in more detail, the Company would
be glad to cooperate.
Rosanna Harris
Secretary -Treasurer
New Mercer Ditch Company
970-874-0189
RESPONSE: Previous comment, this has been addressed
Contact: Terry Ferrill,
Topic: General
Comment Number:
Comment Originated: 10/10/2017
10/10/2017:
The Fort Collins — Loveland Water District and the South Fort Collins Sanitation
District have reviewed the above mentioned project and submit the following
comments.
The submittal did not meet minimum district requirements for review. The
Districts are working with the engineer to revise references, notes, standard
construction requirements, etc.
Please do not hesitate to contact me at 226-3104, ext. 104, if you have any
12
07/16/2018: We will work with you during FDP for the final placement of the
signal poles and cabinet.
RESPONSE: Added Traffic Signal sheet based on exhibit provided by Britney Sorenson. This is
claimed to be all that is necessary for our Utility Plans. City will provide remaining design.
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 10/09/2017
10/09/2017: Irrigation plans are required no later than at the time of building
permit. The irrigation plans must comply with the provisions outlined in Section
3.2.1(J) of the Land Use Code. Direct questions concerning irrigation
requirements to Eric Olson, at 221-6704 or eolson@fcpov.com
RESPONSE: Acknowledged.
Department: Technical Services
Contact: Jeff County, 970-221-6588, *county@fcgov.com
Topic: General
Comment Number: 2 Comment Originated: 10/11/2017
10/15/2018: FOR APPROVAL:
All plans will be reviewed 1 st round of FDP review.
07/17/2018: All plans will be reviewed 1 st round of FDP review.
04/30/2018: All plans will be reviewed 1st round of FDP review.
10/11/2017: All plans will be reviewed at the next round of review.
Topic: Plat
Comment Number: 1
Comment Originated: 10/11/2017
10/15/2018: FOR APPROVAL:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter.
RESPONSE: Updated per redlines
07/17/2018: Please make changes as marked. If changes are not made or you
disagree with comments, please provide written response of why corrections
were not made. Please provide any responses on redlined sheets and/or in
response letter.
04/30/2018: Please make changes as marked. If changes are not made or you
disagree with comments, please provide written response of why corrections
were not made. Please provide any responses on redlined sheets and/or in
response letter.
10/11/2017: Please make changes as marked. If changes are not made or you
disagree with comments, please provide written response of why corrections
were not made. Please provide any responses on redlined sheets and/or in
response letter.
11
Topic: General
Comment Number: 1
Comment Originated: 10/03/2017
10/03/2017: Regarding future development plans for the NC portion of the
Hansen Farm, the historic review of eligibility of the brick residence at 6029 S
Timberline on September 7, 2017 concluded that the property is eligible for
local landmark designation under Fort Collins Standards B (association with
significant historic persons) and C (architecture). No appeals of the decision
were received during the two -week public posting. This recent review updates
that determination and underscores that Land Use Code section 3.4.7, which
guides how developments must treat identified historic resources, will come into
play for any future NC district development proposals for that parcel. Staff can
provide resources and consultation for adaptive reuse options when the timing
for that discussion is right.
Department: Internal Services
Contact: Sarah Carter, 970416-2748, scarter@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 1
Comment Originated: 10/11/2017
10/11/2017: Construction shall comply with adopted codes as amended.
Current adopted codes are:
2015 International Building Code (IBC)
2015 International Residential Code (IRC)
2015 International Energy Conservation Code (IECC)
2015 International Mechanical Code (IMC)
2015 International Fuel Gas Code (IFGC)
2015 International Plumbing Code (IPC) as amended by the State of Colorado
2017 National Electrical Code (NEC) as amended by the State of Colorado
Fort Collins has amendments to most of the codes listed above. See the
fcgov.com/building web page to view them.
Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2017.
Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF.
Frost Depth: 30 inches.
Wind Load: 129vult or 100- MPH 3 Second Gust Exposure B.
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code Single Family; Duplex; Townhomes: 2015 IRC Chapter 11 or
2015 IECC.
Comment Number: 2
Comment Originated: 10/11/2017
10/11/2017: Colorado State statute CRS 9-5 requires this project provide
accessible units. This project has 62 applicable units (townhomes) and will
need to achieve at least 30 points.
Department: Traffic Operation
Contact: Tim Tuttle, 970-221-6820, TTUTTLE@fcgov.com
Topic: General
Comment Number: 9
Comment Originated: 07/16/2018
10
accordingly.
RESPONSE: Updated
Department: Light And Power
Contact: Austin Kreager, 970-224-6152, akreager@fcqov.com
Topic: General
Comment Number: 1 Comment Originated: 07/17/2018
09/27/2017: Light and Power can serve this development with either single
phase or three phase electric distribution. Power can be tied in from the north
west corner of the future development as well as further south on Timberline. (If
three phase is going to be needed, notify light and power ASAP). I do not
currently see any plans that would require three phase power to the site.
Comment Number: 2 Comment Originated: 07/17/2018
09/27/2017: Development charges, electric Capacity Fee, Building Site
charges and any system modification charges necessary will apply to this
development.
Comment Number: 3
Comment Originated: 07/17/2018
09/27/2017: As your project begins to move forward please contact Light and
Power Engineering to coordinate the streetlight, transformer and electric meter
locations, please show the locations on the utility plans. I do not currently see the
electric utility plans on your utility plans. Please keep us in mind as you move
forward.
Comment Number: 4
Comment Originated: 07/17/2018
09/27/2017: Multi family buildings are treated as commercial services;
therefore a(C 1) form must be filled out and submitted to Light & Power
Engineering. All secondary electric service work is the responsibility of the
developer and their electrical consultant or contractor.
Comment Number: 5
Comment Originated: 07/17/2018
09/27/2017: Streetlights will be placed along public streets. A 40 feet
separation on both sides of the light is required between canopy trees and
streetlights. A 15 feet separation on both sides of the light is required between
ornamental trees and streetlights.
Comment Number: 6
Comment Originated: 07/17/2018
09/27/2017: You may contact FCU Light & Power, project engineering if you
have questions. (970) 221-6700. You may reference Light & Powers Electric
Service Standards at
http://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStandar
ds_FI NAL_18November2016_Amendment. pdf
Comment Number: 7
Comment Originated: 10/16/2018
10/16/2018: All comments stand as stated above. Light and Power is ok with
this going to hearing. We will require those C-1 forms and one -line diagrams at
FDP, so please keep that in mind. Thank you.
RESPONSE: Electrical Engineer
Department: Historic Preservation
Contact: Maren Bzdek, 970-221-6206, mbzdek@fcgov.com
91
confusion with addressing numbers. This north to south portion should be given
another name.
RESPONSE: An additional street name has been added.
Comment Number: 10
Comment Originated: 10/16/2018
10/16/2018:
The proposed Emergency Access gate is still noted at Twisted Root and
Timberline Road and is appropriate for this location. It is understood that timing
for the final intersection may be uncertain therefore PFA is requesting updates
as this discussion progresses.
RESPONSE: Acknowledged
Department: Stormwater Engineering
Contact: Jesse Schlam, 970-218-2932, ischlam@fcgov.com
Topic: Erosion Control
Comment Number: 1
Comment Originated: 09/27/2017
10/12/2018: Awaiting FDP submittal.
07/11/2018: Repeat Comments from September 2017
04/30/2018: Repeat comments from September 2017
09/27/2017: Current Erosion Control Materials Submitted do not meet
requirements. The erosion control requirements are in the Stormwater Design
Criteria under the Amendments of Volume 3 Chapter 7 Section 1.3.3. a copy of
the erosion control requirements can be found at www.fcgov.com/eroison. The
Erosion Control Materials will need to be submitted at time of the first round of
FDP. Please submit an Erosion Control Plans as none were included in the
recently received materials and are required to be submitted to meet City
Criteria. Please submit an Erosion Control Report as none was included in the
recently received materials and is required to be submitted to meet City
Criteria. Please submit an Erosion Control Escrow / Security Calculation as
none was included in the recently received materials and is required to be
submitted to meet City Criteria. The site disturbs more than 10,000 sq. ft. and
therefore Erosion and Sediment Control Materials need to be submitted. Based
upon the area of disturbance, State permits for stormwater will be required
since the site is over an acre and should be pulled before Construction
Activities begin. Erosion Control Materials will need to be produced, reviewed,
and accepted to meet City Erosion Control Criteria before Development
Agreement Language can be drafted. If you need clarification concerning the
Erosion Control Material Requirements or Comments presented above please
contact myself. Jesse Schlam (970) 224-6015 ischlam@fcgov.com
RESPONSE: Erosion Control materials submitted
Contact: Wes Lamarque, 970.416-2418, wiamargue@fcgov.com
Topic: General
Comment Number: 8 Comment Originated: 05/01/2018
05/01/2018: Stormwater Utilities is ready for a hearing.
Comment Number: 10 Comment Originated: 10/15/2018
10/15/2018: AT FINAL: The required LID volume for the NE Rain Garden
differs from the Appendix and in the initial text of the report. Please revise
8
RESPONSE: Added gate detail to plans
>The emergency access easement is noted on the Plat to Rosen Drive. After
the conversation about crossing the drainage at the City Meeting 5-2-2018,
PFA is requesting clarification on the status of this access and details of this
crossing, including signage, will be required at time of FDP. This access should
be shown and labeled as such on the Site Plan at that time
RESPONSE:
4-24-2018 UPDATE
The Emergency Access Easement to Rosen Dr is noted in the provided
documents. The timing of installation of this EAE should be coordinated with
PFA prior to time of building permit
10/13/2017: FOLLOW-UP TO CITY STAFF MEETING ON 10/11/2017:
I spoke with Fire Marshal, Bob Poncelow today regarding minimal separation
distance between access points into and out of the proposed Hansen Farm
development. In brief, he believes the two, currently proposed points of access
onto Timberline do not meet minimum code requirements as defined by IFC
D 107.2.
In order to resolve this non-compliance issue, he would either require
Single -Family homes on the western portion of the site to be equipped with a
fire sprinkler system OR approve a temporary fire lane connection to Rosen Dr.
to effectively increase the separation distance between access points. This
would be the same solution which the project team and I briefly discussed at the
end of the city staff meeting on 10/11/17. Please contact me with any questions.
Comment Number: 8
Comment Originated: 04/24/2018
7-6-18 UPDATE
>Due to the setback of the single family attached residences from Knobby Pine
Drive and Burly Tree Drive, the address shall be clearly visible in no less than
10 inch tall numerals.
>To assist with prompt emergency response the full address, including street
name, shall be clearly visible on each residence in no less than 8inch tall
numerals on the elevations that face the alley denoted as Tract H.
>The addressing plan will be provided for approval after a conversation with
GIS. This will be done before Final per project team comment reply letter.
04/24/2018:
ADDRESSING/WAYFINDING
To assist with prompt emergency response, the residences that are located off
the Alley shall have the street name and number of their address clearly visible
on their front and rear elevations. This addressing plan should be provided to
PFA for approval prior to Building Permit.
Comment Number: 9 Comment Originated: 05/02/2018
7-6-18 UPDATE
This will be addressed before final per project team reply comment letter.
RESPONSE: An additional street name has been added.
5-2-2018 UPDATE
STREET NAMES
>The street shown as Burly Tree Drive close to Timberline runs in a north to
south direction then changes to generally east to west which will create
7
project, there are 39 Honeylocust proposed out of 218 canopy shade trees.
Please significantly decrease the number of Honeylocust and incorporate
Catalpa and Elm (David, Accolade, New Horizon).
RESPONSE: Honeylocusts have been significantly reduced.
Comment Number: 19 Comment Originated: 10/16/2018
10/16/2018:
SUBMIT WITH FIRST ROUND FDP SUBMITTAL:
A new requirement, titled "Existing Tree Removal Feasibility Letter" should be
submitted to City Forestry and the Project Planner for review.
Proposals to remove significant existing trees must provide a justification letter
detailing the reason for tree removal. This is required for all development
projects proposing significant tree removal regardless of the scale of the
project. The purpose of this letter is to provide a document of record with the
project's approval and for the City to maintain a record of all proposed
significant tree removals and justifications. Existing significant trees within the
project's Limits of Disturbance (LOD) and within natural area buffer zones shall
be preserved to the extent reasonably feasible. Streets, buildings and lot layouts
shall be designed to minimize the disturbance to significant existing trees.
(Extent reasonably feasible shall mean that, under the circumstances,
reasonable efforts have been undertaken to comply with the regulation, that the
costs of compliance clearly outweigh the potential benefits to the public or would
unreasonably burden the proposed project, and reasonable steps have been
undertaken to minimize any potential harm or adverse impacts resulting from
noncompliance with the regulation.) Where it is not feasible to protect and retain
significant existing tree(s) or to transplant them to another on -site location, the
applicant shall replace such tree(s) according to City mitigation requirements.
RESPONSE: Submitted prior to PDP hearing.
Department: Park Planning
Contact: Suzanne Bassinger, 970-416-4340, sbassinger@fcgov.com
Topic: General
Comment Number: 7
10/15/2018: FOR FINAL
Comment Originated: 10/15/2018
Revise Tract B labeling: Tract B is currently labeled on the plat as "Future
Development". Tract B must be labeled on the plat as "Future Public Park" for
approval of the Final Development Plan. The Development Agreement will
address future transfer of ownership as well as maintenance of Tract B.
RESPONSE: Updated
Department: PFA
Contact: Andrew Rosen, 970-416-2599, arosen@poudre-fire.org
Topic: General
Comment Number: 7
5-2-2018 ACCESS UPDATE
Comment Originated: 04/24/2018
>No Type 3 barricades will be allowed for this project. Appropriate gate plans
should be provided for approval at time of FDP.
10/10/2017:
Include locations of any water or sewer lines on the landscape plan. Please
adjust street tree locations to provide for proper tree/utility separation.
106 between trees and public water, sanitary, and storm sewer main lines
6L between trees and public water, sanitary, and storm sewer service lines
46 between trees and gas lines
Comment Number: 12 Comment Originated: 05/02/2018
10/16/2018:
FINAL PLANT COUNTS WILL BE VERIFIED AT FDP.
RESPONSE: Acknowledged
7/18/2018:
Continued:
It is still my belief that more evergreen trees can be provided on the landscape
plan. Only 17 trees out of 300 are conifers, and more should be incorporated in
place of ornamental trees, especially in the larger open space tracts. Previously
suggested conifer species are great options. A sufficient balance of tree types
and species should be considered on this plan due to its size.
RESPONSE: Provided. There are now more than 100 evergreen trees.
5/1 /2018:
Species selection:
Please incorporate additional evergreen species to provide a more diverse
coniferous palette. Please select species from the following list: Colorado Blue
Spruce, Southwestern White Pine, Bristlecone Pine, Limber Pine, and Bosnian
Pine. In addition, it is my knowledge that Texas Red Oak are not always easily
available in nursery stock, especially in large numbers and upsized calipers.
They are a great tree and should still be noted on the plans, but consider
decreasing the number of this species. Additional Linden, Elm, and Oak
species can be incorporated on the plans to increase the diversity numbers,
too. Elm species we prefer: Accolade, New Horizon, David, Discovery (type of
David). Stay away from Frontier Elm and other cultivars as they are susceptible
to European Elm Scale.
Oak Species we prefer: Heritage Oak (cross btwn Bur and English), straight
English Oak, fastigiate English Oak, Texas Red, Shumard, Chinkapin. Stay
away from Swamp White Oak, White Oak, and Northern Red Oak as they need
more acidic soils than we have in Fort Collins.
Linden s ecies we prefer: Legend, Sentry, Greenspire, Redmond.
Please incorporate additional ornamental species. This is a large
development with many trees and the site will benefit from increased variety of
ornamental species. Please select species from the following list: Japanese
Tree Lilac, Bigtooth Maple,
- Please identify the seedless variety of Kentucky Coffeetree
Espresso on the landscape plans.
City of Fort Collins Forestry Division is close to reaching the maximum
percentage of Honeylocust in Fort Collins6 urban forest. During the
development review process, we see it as an opportune time to educate
landscape architects to use fewer Honeylocust on plan proposals. On this
5
property owners who would need to sign for the dedication of the rights -of -way
and easements, which would need letters of intent from them prior to hearing, or
whether their consent isn't needed.
04/30/2018: Have we received a letter from the Mail Creek Ditch company as a
letter of intent for the work occurring on their property?
Comment Number: 23
Comment Originated: 10/15/2018
10/15/2018: FOR FINAL
In coordinating with Engineering Capital Projects (Nicole Hahn), the City will be
looking for a Traffic Signal Design for the Zephyr/Timberline intersection, in
addition to the standard final level civil drawings.
RESPONSE: Added Traffic Signal sheet based on exhibit provided by Britney Sorenson. This is
claimed to be all that is necessary for our Utility Plans. City will provide remaining design.
Department: Environmental Planning
Contact: Stephanie Blochowiak, 9704164290, sblochowiak@fcqov.com
Topic: General
Comment Number: 25 Comment Originated: 07/16/2018
07/16/2018: Please continue showing separate natural habitat buffer zone only
planting plan(s). This will aid during project Hearing to demonstrate how project
meets LUC 3.4.1 and assists significantly during post -construction landscape
and NHBZ inspections verifying establishment of plant material. Wetland
mitigation requirements are 1:1 thus ensure 0.29 ac wetland is being provided.
RESPONSE: Acknowledged. We will continue to show separate plant lists.
Comment Number: 29 Comment Originated: 10/15/2018
10/15/2018: BY FINAL
The Natural Habitat Buffer Zone (NHBZ) needs to be clearly delineated,
including wetland mitigation area included in detention area, and labeled on the
site, grading, utility, and landscape plans.
RESPONSE: Revised.
Comment Number: 30 Comment Originated: 10/15/2018
10/15/2018: INFORMATION ONLY
Thank you for submitting additional wetland report from Wildlife and Wetland
Consulting. Environmental Planning is ready for Hearing.
Department: Forestry
Contact: Molly Roche, 224-616-1992, mroche@fcqov.com
Topic: Landscape Plans
Comment Number: 5
10/16/2018:
PROVIDE UTILITY LABELS AT FDP.
RESPONSE: Provided.
Comment Originated: 10/11/2017
7/18/2018: Continued
I still do not see utilities labeled on the landscape plans.
RESPONSE: Provided.
4
that the capital project's improvements to Timberline would then provide the
improvements necessary to no longer require the variance request.
04/30/2018: From my perspective, the preliminary design of Timberline Road
provided with the submittal appears good, however additional input from
Capital Projects Engineering (Nicole Hahn and/or Tim Kemp) to coordinate with
the City's project to construct the remaining sections of Tlmberline should also
be considered. There are a few concerns from a coordination and design
consideration:
The project does not appear to be constructing sidewalk along the platted
frontage south of Zephyr Road. The development will need to have this
infrastructure component design and constructed.
The Timberline Road sidewalk along the northern boundary not tying into the
existing sidewalk along Willow Springs is problematic. The project will need to
make the connection to the Willow Springs sidewalk. The City is open to
exploring a design for a protected pedestrian path that is in between the
southbound bikelane and the existing abutment for the ditch crossing as interim
solution.
The developer will need to participate in its local street obligation for the
completion of the Timberline Road improvements to the northern boundary of its
property, including the construction of the culvert improvements.
The projected flowline grade along Timberline across Twisted Root appears too
flat at .3%, but it is presumed with no implementation of a cross pan here, that
spot elevations at the intersection (at time of final) might provide additional
context as to what is happening here.
10/10/2017: The design for Timberline Road should be including an ultimate
design that establishes the flowline, curb gutter and sidewalk on the east side of
Timberline north of Bacon Elementary as evidence of the sufficient
establishment of right-of-way and road width. Coordination on this design
information with the Timberline Road capital improvement project would be
important as well, as there may need to be additional offsite design to the north
to consider existing restrictions (existing trees, etc.) that would alter centerline
roadways alignment and impact the ability to implement ultimate improvements
along Timberline. At time of final plan this would also require cross sections at
50 foot intervals to demonstrate that the additional widening on the west side is
in the ultimate condition upon the construction of the widening on the east side.
Comment Number: 19
10/15/2018: FOR FINAL
Comment Originated: 04/30/2018
The provided letter of intent from David Maitland and Charles Burchett, dated
8/20/2018 addresses this concern. The letter indicated that a crossing
agreement will be required, and the City will need to see evidence of this prior
to final plan approval (or otherwise, a signature block for the ditch lateral on the
civil plans.)
RESPONSE: We are working with Ditch Users on addressing their requests. Either a crossing
agreement or signature block will be included with final plans.
07/18/2018: Northern Engineering has indicated that there are about 12
downstream users of the ditch lateral for which the two road crossings and two
pedestrian crossings would occur. It needs to be verified whether these are
HEARING: All R3 planning comments are resolved. Please revised plans with
R4 comments prior to hearing.
If project is determined to be ready for Type I hearing at staff review meeting on
10/17/18, staff will coordinate with applicant schedule for administrative hearing
for November.
RESPONSE: Acknowledged.
Please include all pertinent plan sets and supporting files for hearing submittal
package, including plat, site, utility, landscape, lighting, Bldg. elevations etc.
Department: Engineering Development Review
Contact: Marc Virata, 970-221-6567, mvirata@fcgov.com
Topic: General
Comment Number: 2
Comment Originated: 10/10/2017
10/15/2018: INFORMATION ONLY
The submitted letter of intent addresses the pre -hearing concern. There may be
concerns or questions at public hearing either from the decision maker, or the
general public, and all parties should be prepared to discuss what scenarios
may ultimately occur. We'll want to ensure that prior to final plan approval, the
direction on these crossings is fully understood.
RESPONSE: Acknowledged
07/17/2018: The plans depict the improvements as to be done by others. A
common understanding between the coordination of the crossings with the
Rennat property/developer would be ideal as information at the public hearing
for the project.
04/30/2018: With the ditch bisecting the development and the property to the
south, this development should be sharing the obligation for the construction of
the crossings with the property to the south, (if not constructing these crossings).
Has the abutting property owner been in contact regarding potential interest in
building the crossings (and dedicating right-of-way for the construction) at this
time? If not, the City would look to collect funds from the developer for its'/z
share in the costs of these crossings.
10/10/2017: The project will need to design the roadway and bike/ped
connections to adjacent developable properties to the south and west. As part
of the PDP, preliminary offsite design 500 feet from the property boundary is
required.
Comment Number: 10 Comment Originated: 10/10/2017
10/15/2018: INFORMATION ONLY
The revised variance request is acceptable. Please allow this comment to serve
as approval of the variance request and should reflect the 10/15/2018 approval
date.
RESPONSE: Acknowledged
07/18/2018: The submitted variance request does not state a position on the
health, safety, and welfare of the general public in the potential granting of the
variance request, which would need to be addressed. It should also be stated
E
Fort Collins
./0'�
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
fcgov. com/developmentreview
October 19, 2018
Kristin Turner
TB Group
444 Mountain Ave
Berthoud, CO 80513
RE: Hansen Farm, PDP170036, Round Number 4
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, you may contact the individual commenter or direct your questions through
the Development Review Coordinator, Tenae Beane, at 970-224-6119 or tbeane@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Pete Wray, 970-221-6754, pwray@fcgov.com
Topic: General
Comment Number:
Comment Originated: 10/12/2018
HEARING: Overall Site Plan. Add Zephyr Drive street name on plan. Revise
off-street parking table total from 122 to 112 spaces.
RESPONSE: Street name has been added. The MF parking spaces listed are based on number
of bedrooms. The math appears to be accurate. This has not been changed. Please provide
additional information if a revision is required.
Comment Number:
Comment Originated: 10/12/2018
HEARING: Overall Natural Habitat and Buffer Zone Sheet 10. Match buffer
symbol in legend with plan (diagonal hatching).
RESPONSE: Revised
Comment Number:
Comment Originated: 10/12/2018
FINAL: For rear building elevations for 4, 5, and 7 plex buildings, will there be a
person door access to garages off alleys, or in lieu of that a push key -pad entry
box? Non -vehicle access should be provided to each unit in alley.
RESPONSE: A keypad entry box.
Comment Number: Comment Originated: 10/12/2018