HomeMy WebLinkAboutHARMONY CROSSING PUD - PRELIMINARY - 65 93A - CORRESPONDENCE - STAFF'S PROJECT COMMENTSThis completes the review comments at this time. Additional
comments may be forthcoming as the various .departments and
reviewing agencies continue to review this request. Please be aware
of the following dates and deadlines to assure your ability to stay
on schedule for the November 15, 1993 Planning and Zoning Board
hearing:
******************************************************************
Plan revisions are due October 27, 1993 by 12:00 noon. Please
contact me for the number of folded revisions required for each
document.
PMT's, renderings, and 8 folded copies of. final revisions (for the
Planning and Zoning Board packets) are due November 8, 1993.
Final documents (including .the signed development agreement,
applicable mylars and utility plans) are due November 12, 1993 by
12:00 noon.
******************************************************************
Please contact me at 221-6750 if you have questions or concerns
related to these comments. I would like to schedule a meeting with
you,.#s soon as possible, if necessary, to discuss these comments.
IlerelyOlt
Project Planner
xc: Kerrie Ashbeck
Sherry Albertson -Clark
Advance Planning
Stormwater Utility
Transportation
Parks & Recreation
Natural Resources
Frank Vaught
RBD inc.
file/Project Planner
Q
18. Fencing on Timberline Road should step down before the cul-de-
sac, at the front yard setback or thebuilding front edge, to
a maximum of 4' in height. The cul-de-sac should not be walled
off from Timberline Road. Fencing along the detention areas
should follow the standard Stormwater Utility requirement of
4' fence height or a 4' solid fence with a 2' open style at
the top.
19. Why is the multi -family component shown as part of Phase 2? Is
it to be part of Harmony Crossing at all?
20. The landscaping on Timberline Road should follow the Harmony
Corridor Design Standards and Guidelines for species selection
and locations.
21. How do you propose to do buffering and noise abatement for the
homes along .the Union Pacific Railroad? Fencing and
landscaping should be indicated on the Site and Landscape
Plans.
22. Required solar orientation ordinance data must be shown on the
final subdivision plat and Site Plan.
23. A legal description for the property should be included on the
final.Site Plan.
24. The total number of lots should be indicated in the LAND USE
BREAKDOWN box on the Site Plan.
25. Some form of traffic study must be submitted with the
preliminary P.U.D. plans and should reference the overall
development plan study. Please contact the Transportation
Division at 221-6608 for their requirements on the level of
information needed.
26. The utility plans should show where the 'off -site sanitary
sewer and water come from. They should also address the off -
site drainage down Timberline Road and the potential need for
an off -site easement across the Dusbabek property.
27. The 6.5 acre size and location of the future multi -family
parcel does not appear to be adequate for good buffering
between the single family residential and community/regional
shopping center. The multi -family could continue across the
entire length of the north property line and provide direct
access to Timberline Road. Also, how many dwelling units are
being envisioned for the multi -family component?
7. A bicycle/pedestrian connection is desirable between this
property and the Oak Ridge Business Park area. This pathway is
likely to occur with a possible future Keenland Drive
connection (,south of Harmony Crossing) under/over the railroad
tracks froiethe west. It is important for development on this
property to plan for future connections.
8. Parkland fees of $779 per dwelling unit will apply to this
development and be collected at the time of issuance of
building permits. The City's neighborhood park for use by this
site will be located next to the Southeast Junior High School,
1/2 mile to the east. The recreational facilities shown on the
Site and Landscape Plans (to be constructed and maintained by
the developer) should comply with ADA guidelines.
9. No good "collector" type access extends through this
neighborhood with the plan as submitted. When Keenland Drive,
to the south, goes through from west to east there should be
a north/south collector connection from Keenland to the
community/regional shopping center to minimize traffic going
out to the arterial street system.
10. The phasing as shown must work from a utility and drainage
standpoint; i.e., each phase must stand alone if construction
is to be phased. Also, full street frontage for all lots in a
phase must be constructed.
11. No soils report was submitted with the preliminary P.U.D. A
soils report must be submitted with the final.
12. Please include sight distance easements, if necessary, -on lots
on the inside of curves and intersections.
13. General Note 3 on the Site Plan indicates a maximum building
height of 40' for this development. With all the buildings
being single family homes, is this realistic?
14. General Note 4 on the Site Plan*should be corrected to reflect
that the existing zoning is Employment Park.
15. The City is recommending that 1 street per lot, per street
frontage should be provided by the developer and indicated on
the Site and Landscape Plans.
16. Do.all the recreation facilities shown on the Landscape Plan
work in the proposed detention area, in terms of how they may
impede flows and storage. Who is responsible for the on -going
maintenance of the detention areas and will the park/detention
area be open to the public?
17. General Note 6 on the Site Plan indicates fencing guidelines
to be provided and consistency of fencing on all lots. The
guidelines, and details, should be submitted.to the City for
review.
Community Planning and Environmental Services
Planning Department
City of Fort Collins
October 15, 1993
Michael A. Messina
Richland Homes
8791 Wolff Court, Suite 200
Westminster, CO. 88830
Dear Michael,
Staff has reviewed your documents for the Harmony Crossing P.U.D.,
Preliminary that were submitted on September 27, 1993 and would
like to offer the following comments:
1. Columbine Cable Television has stated that they would like to
see all utility easements labeled with the sizes indicated on
the subdivision plat. Also, it is unclear as to what is meant
in relation to the easements on Lots 29, 30, and 31. They are
requesting side lot easements on Lots 42, 43, 48, and 49 of
Phase 1 and Lots 80 and 81 of Phase 2.
2. Public Service Company of Colorado has stated that the final
subdivision plat will need to dedicate 9' minimum width
utility easements adjoining the street right-of-way lines on
both sides of all internal streets. No trees will be allowed
to be planted closer than 4' to any natural gas line.
3. A copy of the comments received from U.S. West is. attached to
this letter.
4. The final subdivision plat should be on the standard 24" x 36"
sheet size format. The preliminary subdivision plat measures
30" x 42".
5. Phasing of this development must not produce dead-end streets
over 660' in length. Temporary roads for secondary emergency
access are permissible in some instances. The Poudre Fire
Authority should be consulted with respect to emergency
access. Proposed street names must not duplicate existing
names in the City or fire district.
6. City Light 8 Power has stated that if this area is developed
prior to construction of the east -side of Timberline Road to .
Harmony Road the owner may be required to provide off -site
easements and pay for a temporary electric line from the
southeast corner'of Harmony Road and Timberline.Road.
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 221-6750