HomeMy WebLinkAboutCSU LAKE AND PROSPECT PARKING LOT SITE PLAN ADVISORY REVIEW - SPA190001 - SUBMITTAL DOCUMENTS - ROUND 1 - PROJECT NARRATIVE (3)Construction Plan Key Review Dates (FDP fees, no plat) (assumed timeline) 1. 1/30/2019 Initial Submittal (some overlap with SPAR proposed, this is not a process issue) 2. 2/20/19 Staff comment meeting with Applicant 3. 3/6/19 Resubmittal 4. 3/20/19 Staff comment meeting with Applicant (shave a week off —two week turn around) 5. 4/3/19 Resubmittal (document wrap up) 6. 4/17/19 Staff meeting with Applicant (shave a week off —two week turn around) • 3/6 through 4/17 — Phone/meeting coordination/PDF review and also keep the Wednesday dates. • 4/17 to 4/30 — Schedule DCP meeting, begin coordinating ROW construction, finalize and record any dedication exhibits. Assumed summary of the FDP construction plan sheets will include (see detailed checklist): - detail sheets/notes for the ROW public improvements (plan views and details, AKA Utility Plans) - Traffic (TIS) memo (waived by Martina per CR comments) - overall grading and drainage plans - drainage report - PFA turning templates - landscape plan sheets and details for right of way areas (could include entire site). - overall erosion control plans? (this may not be necessary, pls. coordinate with Jesse) - Offsite easements/dedications (if required) - ROW dedication (or dedication letter) - FDP application form and Planning/TDR fee forms 2 of 2 C'}` , o� Planning, Development and l r Fort Collins Transportation Services Planning Services 281 North College Ave. P.O. Box 580 Fort Collins, CO 80522-0580 970.221.6750 970.224.6134 - fax fcgov. com/currentplanning CSU Lake & Prospect Parking Lot — Key Coordination Dates/Documents Rev. 11-9-2018 SPAR Dates 1. 11/8/2018 Conceptual Review 2. 12/12/18 Neighborhood meeting (mailing 11/28) 3. 12/24/18 Formal SPAR Submittal (represents earliest submittal date after 10 day neighborhood meeting waiting period) 4. 1/16/19 Staff comment meeting with Applicant S. 1/28/19 Finalized SPAR plans due to city staff 6. 2/6/2019 P&Z final Staff Report and any additional Applicant SPAR plans/exhibits for P&Z due 7. 2/7/2019 Mail P&Z notice letter (14 cal. days prior to meeting) 8. 2/15/2019 P&Z Work Session 9. 2/21/2019 P&Z Hearing (work session follow-up due from applicant 2/19), applicant to provide copy of PPT presentation to staff on day of hearing) • Separate City/CSU coordination meetings: site meeting, ROW coordination, other as needed per Tenae/Fred (could start scheduling these now). • SPAR Submittal Documents -- SPAR Plans: (24x36 format preferred, illustrative format but could be construction format): application form, submittal letter (general information about the project intent), site plan, landscape plan, site details (fence section, edge transition section showing parking, sidewalk, landscaping, fencing, context plans. Please include PFA turning templates o the site plan or in separate exhibit. o Could also include other color graphics: street cross-section, proposed grading/drainage plan/contours. o Could include more complete detail to jump start the FDP plan format needed — adding sheets from the list below). loft