HomeMy WebLinkAboutWINDTRAIL TOWNHOMES PUD FINAL - 66 93A - CORRESPONDENCE - RESPONSE TO APPLICANTr
If the staff and the developer disagree over the provisions to
be included in the development agreement, the developer may
present such dispute to the Board for resolution if such
presentation is made at the neat succeeding or second
succeeding monthly meeting of the Board. The Board may table
any such decision, until both the staff and the developer have
had reasonable time to present sufficient information to the
Board to enable it to make its decision. (If the Board elects
to table the decision, it shall also extend the term of this
condition until the date such decision is made).
If this condition is not met within the time established
herein (or as extended, as applicable), then the final
approval of this planned unit development shall become null
and void and of no effect. The date of final approval for
this planned unit development shall be deemed to be the date
that the condition is met, for purposes of determining the
vesting of rights. For purposes of calculating the running of
time for the filing of an appeal pursuant to Chapter 2,
Article 11, Division 3, of the City Code, the 19final decisions,
of the Board shall be deemed to have been made at the time of
this conditional approvals however, in, the event that the
dispute is presented to the Board for resolution regarding
provisions to be included in the development agreement, the
running of time for the filing of an appeal of such 11final
decisional shall be counted from the date of the BoardIs
decision resolving such dispute.
If you have any questions regarding this action by the Planning and
Zoning Board, please feel free to call the Planning Department at
221-6750.
Sincerely:
T..
j4p&o�
Ted Shepard
Senior Planner
xc: #66-93A
r.
r�
Community Planning and Environmental bervices
Planning Department
City of Fort Collins
January 28, 1994
Mr. John McCoy
c/o Ms. Kay Force
Jim Sell Design
117 East Mountain Avenue
Fort Collins, CO 80524
RE: Windtrail Townhomes Final P.U.D.
Dear Kay:
On Monday, January 24, 1994, at the regular meeting of the City of
Fort Collins Planning and Zoning Board, the Board voted unanimously
to approve Windtrail Townhomes Final P.U.D., #66-93A, subject to
the following two conditions:
1. The Planning and Zoning Board approved the above -referenced
project subject tb the developer, the City of Fort Collins, and the
Hill Pond Homeowner's Association working together to solve the
sight distance problems at the Shields Street/Hill Pond Road
intersection. Issues to be investigated include possible removal
of tree trunks, possible modification to the existing median in
Hill Pond Road, and possible widening of the westbound travel lane
for Hill Pond Road.
X. The Planning and Zoning Board approves this planned unit
development final plan upon the condition that the development
agreement, final utility plans, and final P.U.D., plans for
the planned unit development be negotiated between the
developer and City staff and executed by the developer prior
to the second monthly meeting (March 28, 1994) of the Planning
and Zoning Board following the meeting at which this planned
unit development final plan was conditionally approved; or, if
not so executed, that the developer, at said subsequent
monthly meeting, apply to the Board for an extension of time.
The Board shall not grant any such extension of time unless it
shall first find that there exists with respect to said
planned unit development final plan certain specific unique
and extraordinary circumstances which require the granting of
the extension in order to prevent exceptional and unique
hardship upon the owner or developer of such property and
provided that such extension can be granted without
substantial detriment to the public good.
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 - (303) 221-6750