HomeMy WebLinkAboutWATERGLEN PUD - FINAL - 71 93B - CORRESPONDENCE - CITY STAFF (10)of Fort Collins
PROJECT
CONVIlV1ENT SHEET
DATE: 18 June 1994 DEPARTNMNT: S'MRMWqTSR
PROJECT: 71-93A WATERGLEN PUD - Final
PLANNER: Steve Olt
All comments must be received by Friday, 29 July 1994
❑ No Problems
Problems or Concerns. (see below)
This submittal will not be reviewed by the Stormwater Utility
since it does not meet the condition of preliminary approval.
The condition as stated in my comments dated 4/20/94 was that
approval of the major drainage work that is to be done in the
State Right of Way along I-25 be obtained from the Colorado
Department of Transportation PRIOR to final submittal.
Since this condition has not been demonstrably met, this
submittal will be rejected.
Date: zkz Signature:
CHECK IF YOU WISH TO RECEIVE
COPIES OF REVISIONS:
❑ PLAT �• S}w` O I t- .
❑ SITE cc : Lt l G lQcs
❑ LANDSCAPE
❑ UTILITY Cr: k550c-
LC: 7!a_oN;vla
DEVELOPMENT SERVICES CC �
PLANNING DEPARTMENT 281 NORTH COLLEGE P.O.BOX 580 FORT COLLINS, COLORADO 8052N0580 (3031 _I-6750
Utili. Services
Stormwater
City of Fort Collins
July 27,,19.94
Ms. Libbey Glass,
WW Reynolds, Inc.
1600 Specht Point Drive, Suite C
Fort Collins, Colorado 80525
Dear Ms. Glass:
The project comment sheet, for Waterglen PUD - Final, is attached
for your use.
If you have any questions please give me a call.
Sincerely, _
Basil Hamdan
Civil Engineer
235 Mathews Street • P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 221-6589 • FAX (303) 221-6239