HomeMy WebLinkAboutWATERGLEN PUD - FINAL - 71 93B - AGENDA - MEETING COMMUNICATIONAGENDA -WATERGLEN PUD
Coordination Meeting at Fort Collins
1st Floor Planning Conference Room
�p �vaa ya
s,
& Associates, Inc.
o u r e a C o n s u I t o n t s
2995 Cantergreen Court South. Suite C
Bonder. Colorado 80301-5421
Phone (303) 440.3439
FAX (303) 440,3W
1. SUBMISSION DEADLINE - October 5th for Everything or VariesT
• Plat • Water & Sanitary Sewer Utility • Drainage/Grading and Storm Sewer • Roadway
What is the product to be submitted for each and how many copies of each are required?
2. UTILITY MODIFICATIONS:
Gas Utility
Depth of Main Transmission Line (runs east -west thru property)
Requirements of Gas Easement - Main Transmission Line
• Infrastructure Components Crossing thru Easement (roads and utilities)
• Separation Requirement
• Minimum and maximum cover (i.e. impacted by swales and berms, etc.)
1(• Electric Utility:
• Minimum undisturbed distance around towers (cut or fill)
• Requirements of Electric Easement (Main Overhead Lines)
• Infrastructure Components Crossing thru Easement
X • Telephone/Cable Utility:
• Do we need to show Telephone utility trench on the utility drawings?
X• Sanitary Sewer Utility
• Groundwater conditions affecting utility installation
• Groundwater levels
• Location of top of gravel
• System layout
)a Water Utility:
• System Layout (describe)
• Master Meters (5)
• Ownership of Lines - Service Lines in Private Driveways - Dedicate Easements?
• Design Criteria - Review of Layout
• Minimum - Maximum depth for main transmission line under Waterglen Drive?
Drainage Utility:
• Revised grading plan
• Impacts to Drainage Report
• Storm Sewer & Drainage System Layout
• Cooper Slough and Vine Drive Box Culvert
3. ROADWAY MODIFICATIONS:
• Handicap Ramps • Cross Pans Roadway Curvature
• Vine Drive
• Required improvements
• Box Culvert length at Cooper Slough
• Sidewalk?
• Has soils report and recommended pavement sections been approved by City?