Loading...
HomeMy WebLinkAboutALPINE BANK - PDP200020 - - RESPONSE TO STAFF REVIEW COMMENTS 6162 S. Willow Drive, Suite 320 Greenwood Village, CO 80111 303.770.8884 • GallowayUS.com January 20, 2021 Todd Sullivan, Development Review Coordinator City of Fort Collins, Community Development and Neighborhood Services 281 N. College Avenue Fort Collins, CO 80522 RE: Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road Fort Collins, CO Dear Todd, Thank you for the written comments from our first round Preliminary Development Plan and Plat submittals for the referenced location. Please find below our responses to final comments received December 29, 2020. Responses and revised plans are based on these written comments as well as meetings with staff on December 23 and again December 29. To better facilitate your review, we have included the original comments in italicized font, and have provided our responses in bold. Comment Summary: Department: Planning Services Contact: Jason Holland, 970-224-6126, jholland@fcgov.com Topic: General Comment Number: 1 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Site Plan/Landscape Plan: Safety and convenient pedestrian access are concerns with the proposed parking stalls along the alley. How do customers and employees get from t hese spaces to the building entrances safely without walking along the alley’s vehicular travel lanes and along the east/west vehicular drive aisle within the site? Please see related comments below with the Modification request for the alley parking area. Please consider submitting alternative design sketches to refine this area. Response: A pedestrian path has been extended from the south end of these parking stalls to the west to better connect with existing sidewalks already proposed on the south side of the building. This path will allow pedestrian traffic safer and more direct access to the building from the most easterly parking stalls. Comment Number: 2 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Site Plan: Along the alley, please remove the wheel stops. These do not work with 17 ft. depth parking stalls, which are permitted if a 2 ft. overhang is provided. Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 2 of 26 Response: Wheel stops removed as noted. Comment Number: 3 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Building Elevations: Please provide a dimension from finish grade to the highest roof peak of the building. You can then round this up and note this dimension in the land use table (Sheet 1) as the maximum height proposed . Response: Please see Architectural Elevation sheets 3 and 4 for requested dimension. The Land Use Table has been updated as noted. Comment Number: 4 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Building Elevations: For the railing design – is this tube steel? Can you provide more information about the proposed design character of this element and how it fits in with the character of the buildings? Response: Railing will be tube steel and will be organized in a slim line vertical pattern typical of the Craftsman style. Reference Sheet 8 of the Preliminary Development Plan for reference images. Comment Number: 5 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Trash/Recycling Enclosure: We need more detail provided with this design. The exterior elevations should show the side and rear with a brick that matches the new building. Walk-in access must be provided. Plan details must be provided with labels and dimensions. This must also address recycling requirements, container sizes and circulation within the enclosure. Please see the standards outlined in LUC 3.2.5. Lastly, can a 6 ft. enclosure height be used? Response: Revised elevations and details for the trash enclosure have been provided as noted to comply with LUC 3.2.5. We have also incorporated a door for walk-in access as noted. See Sheet 4 (Trash Enclosure) for additional information. Comment Number: 6 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Cover Sheet 1: Please note the proposed Land Use Code Article 4 uses in the Land Use Table on sheet 1. Also, listing other proposed primary uses for the historic building could be beneficial to do with this process so that they are approved for those Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 3 of 26 uses. Response: A “Potential Land Use List” table has been added to the cover sheet above the Land Use Table to list all potential uses noted under Land Use Code Article 4. Comment Number: 7 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Bike Parking: Need a fixed rack for the historic building so that bike parking is more convenient to this building’s entrance. Response: Additional bike rack has been added near entrance to building as noted. Comment Number: 8 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Landscape Plans: Along the alley, please line up the Jap. Tree Lilacs with the parking stripes. Response: : Please note that Japanese Maples have been replaced with Radiant Crabapples as requested by client. Crabapples have been aligned with parking stripes as noted. Comment Number: 9 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Landscape Plans: Please clarify/include what will be planted in the linear planter boxes along the building walls. Keeping these areas planted will be an important part of the design, given the constrained depth of this area and the hard surface transitions. Please use a detail enlargement if necessary, such as 1:10 or 1:8. Please include a variety of low evergreen material into the planter boxes such as dwarf spruce varieties and dwarf pines (and not just deciduous or per ennial material). I’d also suggest mixing in taller pyramidal forms such as dwarf Alberta Spruce. Response: The plants specified won’t survive in the planter boxes with wet feet. A mixture of shrubs has been added to the planters that are more suited to being kept in a wet climate. Comment Number: 10 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Landscape Plans: Thank you for not using juniper varieties for the small evergreen trees as these are not as good long-term as the varieties chosen. For the Baby Blue Eyes Spruce, while it is a smaller form than full-size spruce – these sometimes seem Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 4 of 26 to get fairly large. Will these constrain the public sidewalk long term? Also, if transplanting an 8’ spruce is going to be a problem, I’d be OK with a smaller size. Response: We do not believe the Baby Blue Eyes Spruce will constrain the public sidewalk where they are currently located. Comment Number: 11 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Landscape Plans -- Rock Mulch: Would you be willing to go with ¾ to 1-1/2 and in in a natural tone, such as a local river rock? This rock is slightly smaller range, and the buff tones look good and have a natural appearance. Eventually there really isn’t going to be a wood mulch ring around everything, and the smaller size works better with the 5 and 1 gallon plantings and in narrow rock mulch areas. Response: The chart has been changed as noted. Comment Number: 12 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Landscape Plans: Please include with the planting details a section detail that shows the finish mulch depth adjacent to sidewalks and concrete curbs. The intent is to have the finish grading in these areas designed so that the mulch surface is not too low to be a trip hazard or appear inadequately filled, but also not too high so that the mulch will spill out. We recommend that the top of mulch be not more than 1” below the adjacent surface. Please also include the same details as noted above for turf grass. Response: Both details have been added as requested. See Sheet 7. Comment Number: 13 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Landscape/Site Plans: Please include detail information indicating the proposed design character for the plaza area – walls, benches, tables, and surface design. Response: Precedent images for the plaza area have been added. See newly added Sheet 5 (Architectural Details) and sheet 8 (Site Furnishings). Comment Number: 14 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Modification Request justification criterion 2: The modification discusses the dedication of ROW facilities and the narrowness of the property (justification 2). The modification also discusses Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 5 of 26 how the design allows for a curb cut to be eliminated and enables single access from the alley (justifications 2 and 3), however this can be achieved without the modification. The modification proposes Criterion 2 which could be considered for alleviating existing, defined and described problem of city-wide concern, however the project does not meet this criterion because the development does not address an important community need. The transportation improvements do not rise to the level needed to meet this criterion. Staff is not supportive of this criterion. Response: Reference to Criterion 2 has been removed from Request for Modification. Comment Number: 15 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Modification Request justification criterion 3: Criterion 3 addresses exceptional narrowness unique to the property in which the strict application of the standards results in exceptional or undue hardship not caused by the owner. Duplicative drive aisles and consolidating access points are mentioned here again. This criterion needs to be evaluated further and should address if there is no site plan alternative to meet the code standard and the reasons why a landscaped setback that meets the standard cannot be met along the east/west axis. In addition to criterion 3, the application should address why the modification is not detrimental to the public good. This could also be through an evaluation of criterion 1 and/or 4 in which the proposed alternative landscaped design is roughly equivalent or nominal and will continue to advance the purposes of the Land Use Code as contained in Section 1.2.2. Response: Our request for modification has been revised to address alternative site plans as well as whether or not the proposed modification is detrimental to the public good. An evaluation of criterion 4 has also been incorporated into our request. Comment Number: 16 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Modification Request – alternative designs requested: If the landscaped setback along the lot line cannot be provided, are there other locations or design methods to provide vertical landscaping or screening elements that would improve the design, quality, and character of the development – in a roughly equivalent or nominally detrimental way? An example could be increasing the landscaping along the alley frontage by Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 6 of 26 adding an additional island. This would increase landscaping along the perimeter in a location that would be located in a similar location to the required landscaped setback. This would exceed the landscape island requirement which helps justify not meeting the setback requirement, and helps ensure that the proposal is sensitive to the character of the existing neighborhood by having fewer continuous commercial stalls along the alley and increasing landscaping and visual interest along the alley. Response: Revised landscape islands, median, and planters have been incorporated into this parking area along the eastern property line. Please note that we have incorporated an additional landscape island and subsequent shade tree into the overall design. We were also able to increase the width of the parking median and the head-in end of the stalls in in an effort to create a more substantial landscape buffer along the eastern edge of the property. Comment Number: 17 Comment Originated: 12/18/2020 FOR NEXT SUBMITTAL -- Modification Request – Evaluation of “detrimental to the public good” – safety and aesthetics: A related issue is addressing with the design how the proposed modification is not detrimental to the public good? How are landscaping or other measures employed to mitigate the visual impacts of the parking and drive-through vehicle use area? If the landscaped setback is replaced with parking as proposed, are there other measures to add landscaping using other code requirements such as islands to make the modification inconsequential? Would this landscaping have related benefits mentioned in the code such as reducing glare and heat build-up, increasing aesthetics, and improving continuity within and between developments? Response: Based on review of comments and follow-up discussions with staff we have revised the parking bay along the eastern property line to include a deeper landscape median as well as one additional landscape island between parking stalls. We believe these modifications meet the intent of the 5’ landscape set-back by providing a landscape buffer between the more intensive drive-through use and adjacent properties to the east. While the buffer is not right on the property line and buffer has been provided while simultaneously integrating the alley into the overall site design. Related to the Modification, and also addressing LUC 3.2.2 which discusses safety, attractiveness, and convenience -- staff needs to see additional design options that show how the landscape modification and proposed alley parking lot design are not detrimental. Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 7 of 26 Response: Enclosed plans include a modified parking bay with associated landscape median and islands as discussed with staff. 3.2.2(B) “The parking and circulation system within each development shall accommodate the movement of vehicles, bicycles, pedestrians, and transit, throughout the proposed development and to and from surrounding areas, safely and conveniently and shall contribute to the attractiveness of the development.” Response: We believe elimination of the 5’ landscaping set-back as shown and incorporation of parking accessible from the alley allows for a more efficient movement of vehicles, bicycles and pedestrians throughout both the proposed development as well as surrounding areas. 3.2.2(C) Safety Considerations for pedestrian circulation, emphasizing and placing priority on pedestrian access and safety. Response: By eliminating the 5’ landscaping set-back in lieu of parking accessible from the alley we are able to reduce potential vehicular pedestrian conflicts by separating pedestrians accessing vehicles from drive-through traffic. 3.2.2(D) Access and Parking Lot Requirements; 3.2.2 (E)(5) Points of Conflict; 3.2.2 (H)(1) Drive-in Facilities. Pedestrian/Vehicle Separation to the maximum extent feasible through the provision of a sidewalk or walkway and mitigating vehicle/pedestrian conflicts. How does the proposed design of the parking? spaces in the alley address pedestrian safety? Does adding the stalls with direct access to the alley still “protect the traffic-carrying capacity of the public street”? How do users of the parking stalls share the alley drive lane space and walk to/from the buildings safely and with this pedestrian access prioritized? What is proposed to mitigate vehicle/pedestrian conflicts? Response: Pedestrian safety is addressed by flipping these parking stalls so that access comes from the alley instead of the drive -through lanes. Traffic carrying capacity of the alley is expected to remain limited and therefore parking accessible directly from the alley is not expected to dimmish the existing condition. We have provided a median cut and cross-walk from the alley oriented parking stalls to better facilitate pedestrian circulation to the building. Department: Historic Preservation Contact: Maren Bzdek, 970-221-6206, mbzdek@fcgov.com Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 8 of 26 Topic: General Comment Number: 1 Comment Originated: 12/22/2020 12/22/2020: Based on your recent consultation with the Landmark Preservation Commission, your proposed relocation of the 1920s residence is on track for a recommendation of approval from them. Please continue to consult with staff regarding the details of the relocation, as well as a more detailed rehabilitation treatment plan (exterior alterations only) for the residential building, as well as the landscaping/site plan that will immediately surround it. Your project should go back to the LPC for a recommendation to the decision maker prior to hearing. Please contact me to get that on the schedule. Response: Noted. Thank you for your assistance to date. Comments received from the Landmark Preservation Commission during our conceptual review November 18, 2020 are being incorporated into an application for formal review by the Landmark Preservation Commission. We anticipate submittal of that application on January 25, 2021 for review at the regularly scheduled LPC hearing on February 17, 2021 Comment Number: 2 Comment Originated: 12/22/2020 12/22/2020: The design compatibility requirements found in Table 1 of section 3.4.7 of the code are also on track to be met by the design of the bank building. Please plan to provide a final summary of how the buildings dimensions, materials, and design features meet those requirements in your final materials for the LPC. They will also provide a recommendation to the decision maker regarding how your project meets this section of the code. Response: Noted. Thank you for your assistance to date. Comments received from the Landmark Preservation Commission during our conceptual review November 18, 2020 are being incorporated into an application for formal review by the Landmark Preservation Commission. We anticipate submittal of that application on January 25, 2021 for review at the regularly scheduled LPC hearing on February 17, 2021 Department: Engineering Development Review Contact: Spencer Smith, 970-221-6603, smsmith@fcgov.com Topic: General Comment Number: 1 Comment Originated: 12/22/2020 12/22/2020: FOR HEARING We will need to see a little more information on alley improvements associated Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 9 of 26 with this project. The plans do not really show what is proposed very well. Response: The extent of alley improvements has been clarified by thickening the sawcut line where asphalt replacement ends. No additional improvements are proposed in the alley other than the asphalt currently proposed to be removed and replaced for the site tie-in. Comment Number: 2 Comment Originated: 12/22/2020 12/22/2020: FOR FINAL PLAN We will want to look at modifying the design of the College Ave. sidewalk transition at the south end of the site. We would also like to see more hardscape proposed at the intersection, rather than have a narrow landscape strip between the walk and curb. Please see redlines for more details. Response: Sidewalk transition at south end of site has been modified to better accommodate future redevelopment and ROW improvements to the south. Revised design should allow for a straight connection of sidewalk between sites in the future with the full 10’ width. Comment Number: 3 Comment Originated: 12/22/2020 12/22/2020: FOR FINAL PLAN Please see redlines for additional comments regarding labels/callouts and other detail to be addressed on the final utility plans. Response: Thank you. Comments regarding labels/call-outs have been corrected as noted. Comment Number: 4 Comment Originated: 12/22/2020 12/22/2020: DEVELOPMENT AGREEMENT A Development Agreement will be required for this project. A draft of the agreement will be prepared by the City after the first final plan submittal. Prior to preparing the draft, I will need the development agreement information form to be completed by the developer. This form is available at: https://www.fcgov.com/engineering/devrev.php. This form can be submitted at any time. If the form is not submitted with the first final plan (FDP) submittal, it could delay preparation of the draft DA. Response: The requested Development Agreement Information Form has been included with this submittal. Comment Number: 5 Comment Originated: 12/22/2020 12/22/2020: DCP Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 10 of 26 A Development Construction Permit (DCP) will need to be obtained prior to starting any work on the site. Please visit the City Engineering web site for more information about the DCP permitting process at: https://www.fcgov.com/engineering/devrev.php Response: Noted. A Development Construction Permit will be applied for in advance of starting any construction. Comment Number: 6 Comment Originated: 12/23/2020 12/23/2020: FOR HEARING Please submit a formal variance request for the 10 -foot wide utility and access easement dedication along College Ave. Since the arterial roadway standard in LCUASS is 15 feet, we would want to document a formal variance request/approval. Please refer to LCUASS Section 1.9.4 for details on variance requests. You can find the LCUASS at: https://www.larimer.org/sites/default/files/ch01_2016.pdf Response: A request for variance has been included with this response submittal. Comment Number: 7 Comment Originated: 12/23/2020 12/23/2020: FOR FINAL PLAN The existing curb cut access to Prospect Rd. will need to be closed with this project if your Prospect access is via the alley. Be sure to indicate on the plans that you will remove existing curb and gutter, etc. and replace with vertical curb and gutter, walk, extend retaining wall, etc. Response: Applicable notes regarding removal and replacement of associated curb, gutter and sidewalk have been added to plans. The proposed site grading will not require a retaining wall, so no wall extension is proposed. Department: Traffic Operation Contact: Steve Gilchrist, 970-224-6175, sgilchrist@fcgov.com Topic: General Comment Number: 2 Comment Originated: 12/21/2020 12/21/2020: FOR HEARING: We understand the constraints with regards current location of the traffic signal pole and the underground utilities in the area, but we would like to have more details in regard to the ability of trucks/tractor trailers to make that turn without damaging the pole. Please provide a detailed Autoturn drawing depicting the Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 11 of 26 truck turning radius for the southeast corner with the addition of the new northbound right turn lane. Response: Truck Turn Exhibits have been included with this submittal to show that a WB-40 can navigate this corner with the added right turn lane. An exhibit showing the existing condition has also been included to show that a WB-67 cannot get around this corner without encroaching into the adjacent through lane, as is the case in the proposed condition as well. A WB-40 has been shown in the proposed condition since a WB-67 has not been able to navigate this corner in the past and is not anticipated based on truck route patterns in the area. An Exhibit with a WB-67 in the proposed condition has also been included for reference as requested. Comment Number: 3 Comment Originated: 12/21/2020 12/21/2020: FOR INFORMATION: Given the relocation of the historic home still needs approved, we would like to reiterate the importance of maximizing the length of the new right turn lane in order to attain the maximum queuing possible for this movement. While the proposed 190-foot turn lane would not meet the CDOT State Highway Access Control standard of 225-foot turn bay with a 120 taper, it is critical to maximize this for the future traffic growth and the overall operation of the intersection. Response: Understood. We have designed the northbound right turn lane to the maximum length possible as a continuous lane between Prospect Road and the proposed Alpine Bank access. It is important to note that a northbound right turn lane is not actually warranted at this location per the CDOT State Highway Access Code as three northbound through lanes exist. When there are three through lanes, separate right turn lanes are not mandatory. Therefore, this development is assisting above and beyond what would be required by providing this maximum length northbound right turn lane. Comment Number: 4 Comment Originated: 12/21/2020 12/21/2020: FOR INFORMATION: If there are any changes to the site plan or layout of this project, an updated queuing analysis for the drive-up windows may be needed in order to make sure vehicles will not end up queuing onto College or Prospect. Response: Acknowledged. We are not anticipating any significant changes to the site plan at this time. Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 12 of 26 Comment Number: 5 Comment Originated: 12/21/2020 12/21/2020: FOR INFORMATION: Signing and striping details: The City standards for a turn bay line are 8 -inch white and we would not install 4-inch dashed lines in advance of turn bay line. The City typically does not paint crosswalks across driveways (City would not maintain this.) Please replace the R6-1R "One Way" sign in the median on College with an R3-2 "No Left Turn" sign for westbound traffic exiting the bank and use an R3-5R "Right Turn Only" sign below Stop sign at same location. We would utilize R6-1R/L "One Way" signs (back to back,) and a standard R5-1 "Do Not Enter" signs at the alley where the drive-thru traffic will exit into the alley. Other signing and striping changes may be needed. Response: These comments have been addressed on the Intersection Plan sheet in the Utility Plan set. Comment Number: 6 Comment Originated: 12/21/2020 12/21/2020: FOR HEARING: We will need to coordinate the location of the pedestrian push button for the traffic signal pole at College and Prospect. With the realigned sidewalk this will need to be relocated from its current location and placed at a location that meets the ADA standards. Response: As discussed in our meeting on 1/8/2020, the existing pedestrian push button pole only needs to be relocated about 9” and has been depicted in a new location directly adjacent to the proposed sidewalk with this resubmittal. It is anticipated that moving the pole such a short distance will not require new conduit routing to the pole, but the pole will need to be re-set. Topic: Traffic Impact Study Comment Number: 1 Comment Originated: 12/21/2020 12/21/2020: FOR INFORMATION: The Traffic Impact Study has been received, reviewed, and the conclusions generally accepted by the City. One consideration not taken into account is the potential traffic utilizing the alley connecting to Parker south of the bank. While the City does not anticipate a significant amount of traffic will utilize this route, adjacent neighbors may have some concerns that might need to be acknowledged/addressed. Response: Although it is possible for bank traffic to travel to and from the south along this alley, it is believed it would be a very small amount. The only traffic that would benefit from traveling Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 13 of 26 the alley is anyone arriving to the bank or departing from the bank that lives in the immediate neighborhood to the southeast. As this would be a very low proportion of traffic (possibly at most 5 percent), it may equate to about 8 vehicles during the peak hour (one vehicle every 7 and half minutes). This volume would be easily accommodated with the existing alley. Department: PFA Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler@poudre-fire.org Topic: General Comment Number: 1 Comment Originated: 12/21/2020 12/21/2020: AUTOMATIC FIRE SPRINKLER SYSTEM > Please indicate location of fire line on the Utility Plans. > Please indicate location of the Fire Department Connection on the Utility Plans. > Required: one key box ("Knox Box") to be mounted in an approved, exterior location on every new or existing building equipped with a required fire sprinkler or fire alarm system. Response: A potential fire sprinkler service lateral location has been included on the Utility Plan if it is determined this will be required for this building when the Building Plans are further developed. A potential Knox Box location has also been labeled on the Utility Plan to go along with this. Per the project architect a fire sprinkler system is not required for this building, but these are being shown at the Owner’s request in case they decide to sprinkler the building when preparing to submit to the Building Department. Comment Number: 2 Comment Originated: 12/21/2020 12/21/2020: FIRE LANE DEDICATION > The fire lane shall be dedicated and labeled on the plat as an Emergency Access Easement (EAE). Response: This easement name has been revised to “Utility and Emergency Access Easement” as there are existing dry utilities within the easement area in the alley that also need to be accounted for. Comment Number: 3 Comment Originated: 12/21/2020 12/21/2020: FIRE LANE SIGNAGE > Fire lane sign locations or red curbing should be labeled and detailed on final Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 14 of 26 plans. Detail all signs or red curb on plans. > Refer to LCUASS detail #1419 for sign placement, and spacing. > Add LCUASS detail #1418 to plans. Appropriate directional arrows required on all signs. Response: Acknowledged. Fire lane signage will be added with Final Plans and will be provided on a separate Signage and Striping Plan if needed for clarity. Comment Number: 4 Comment Originated: 12/21/2020 12/21/2020: ADDRESS POSTING New buildings shall have approved address numbers placed in a position that is plainly legible, visible from the street fronting the property, and posted with a minimum of eight-inch numerals on a contrasting background. Response: Address numbers will be provided to comply. Comment Number: 5 Comment Originated: 12/21/2020 12/21/2020: FIRE DEPARTMENT TRAINING OPPORTUNITY Poudre Fire Authority is currently looking to acquire a commercial property to use for a major emphasis drill. Based upon needs of the owners’ group, the training can be tailored to be either invasive (eg. breaching walls, doors, or roof) or non-destructive in nature (eg. search operations for lost firefighter). Please contact me if your site may be willing to pursue a discussion along this line and I will put you in touch with our training division chief. Thank you. Response: Please reach out to Todd Goulding to discuss this request. (contact information below): Todd Goulding Goulding Development Advisors, LLC tgoulding@gda-co.com 970-331-1732 Department: Stormwater Engineering – Erosion and Sediment Control Contact: Basil Hamdan, 970-222-1801, bhamdan@fcgov.com Topic: Erosion Control Comment Number: 1 Comment Originated: 12/16/2020 12/16/2020: FOR FINAL: Please submit an Erosion Control Plans to meet City Criteria. Please submit an Erosion Control Escrow / Security Calculation based on the disturbed area and or the proposed erosion and sediment control measures. Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 15 of 26 Response: Erosion Control Plan and Escrow/Security Calculation will be submitted with Final Development Plan. Department: Stormwater Engineering Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com Topic: General Comment Number: 2 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: The StormTech system is being proposed with only one small section of isolator rows. Isolator rows are the only part of the system that can be counted as water quality treatment. This system should be primarily for water quality, since detention is not required with the reduction of impervious area in the proposed condition. Please clarify and revise, as necessary. Response: Understood. The ADS layout has been revised to utilize isolator rows throughout the entire system in order to be used entirely for water quality. Revised details have been provided by ADS and included with this submittal’s Preliminary Drainage Report. Comment Number: 3 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: Please change the wording "underground extended detention basin". This system is an underground filtration water quality system and the volume calculation is based on filtration methods in Urban Drainage and not extended detention. Response: The wording on Page 8 of the Drainage Report has been revised to refer to the ADS system as an “underground water quality filtration system.” Comment Number: 4 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: A drainage easement is required for the StormTech System. Response: A Drainage Easement has been added around the Stormtech system with a 5’ offset from the edge of the system. Please confirm the easement and proposed offset is acceptable as currently depicted. Also, if the final system footprint is adjusted during the FDP stage of the project this easement will be Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 16 of 26 adjusted accordingly. Comment Number: 5 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: Please state in the drainage report the amount of impervious area that will be draining over the landscape parkway. This will count towards standard water quality treatment, but not LID. This will help in the percentage of water quality treatment. Also, in addition to documenting a percent number of impervious area for LID treatment, please document for standard water quality, and total water quality treatment. Response: The impervious area draining over the landscape parkway is 0.08 acres and is stated in the 2nd paragraph of the Water Quality Enhancement section on Page 13 of the Preliminary Drainage Report. Please specify with a redline how the City would like to see this reduction reflected in the total water quality treatment required, as the ADS underground system will be providing all LID water quality treatment for the project. Comment Number: 6 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: Please provide 10 feet of separation between any proposed storm sewer and tree. Response: Acknowledged. Department: Water-Wastewater Engineering Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com Topic: General Comment Number: 1 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: Please relocate the water meter outside of the right-of-way. Response: Water meter location has been relocated outside the right-of-way. Comment Number: 2 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: Please label the size of the water service. Response: Anticipated water service size has been labeled – to be Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 17 of 26 confirmed with final building plumbing design during FDP. Comment Number: 3 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: Is a fire service line required? Response: A fire service line is assumed to not be required based on the 2018 IFC – however, a potential fire service location is now shown to indicate where this would be located if the Owner elects to sprinkler the building once the architectural plans are prepared. Comment Number: 4 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: Please label sanitary sewer to buildings as a service. This is to document that it is a "private" line. Response: These labels have been revised to state that these are “Service Laterals” Comment Number: 5 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: A cleanout cannot be located at a service connection into a sewer main. Response: Cleanouts have been replaced with manholes at sanitary sewer main connections. Comment Number: 6 Comment Originated: 12/18/2020 12/18/2020: FOR HEARING: Please label the size of sanitary sewer main. Response: Sanitary sewer main size has been labeled. Comment Number: 7 Comment Originated: 12/22/2020 12/22/2020: FOR HEARING: The proposed sanitary sewer service for the relocated historic structure is too close to the underground detention system. Please relocate to at least 6 feet away. This line is also under a tree right near the building and requires 6 feet of separation. Response: A minimum 6’ separation is now provided between this sanitary sewer service and the underground detention Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 18 of 26 system. Department: Light and Power Contact: Rob Irish, 970-224-6167, rirish@fcgov.com Topic: General Comment Number: 1 Comment Originated: 12/17/2020 12/17/2020: FOR HEARING: The proposed transformer location is considered out of access. Transformer location must be within 10 feet of the asphalt and accessible by a line truck. Please adhere to all clearance requirements in the Electric Service Standards at the following link. http://www.fcgov.com/utilities/business/builders-and-developers/development-fo rms-guidelines-regulations Response: Transformer has been relocated to within 10’ of the proposed drive aisle in the alley for access. Comment Number: 2 Comment Originated: 12/17/2020 12/17/2020: FOR HEARING: Power will need to come from a switching cabinet located a little south of the proposed building and along the east side of the alleyway. It looks like there is a fire line running along the west side of the alley toward prospect. Light & Power will need to have an easement running along the east side of Lot 1 to provide power to the proposed transformer location. Response: An easement is now shown running along the east side of the lot to accommodate the proposed electrical primary line to be routed from this existing cabinet in the alley. Comment Number: 3 Comment Originated: 12/17/2020 12/17/2020: FOR HEARING: Light & Power will need to install an above grade switching cabinet along the east edge of Lot 1 to bring power from. This will also need to be within an easement. Response: : A switching cabinet has been incorporated into the design per coordination with Light & Power. An easement has also been provided around all primary lines, transformers and switchgears with a 3’ offset as requested. Comment Number: 4 Comment Originated: 12/17/2020 12/17/2020: FOR HEARING: Please provide adequate space along the alley way to ensure proper utility installation and to meet minimum utility spacing Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 19 of 26 requirements. A minimum of 10 feet separation is required between water, sewer and storm water facilities, and a minimum of 3 feet separation is required between Natural Gas. Please show all electrical routing on the Utility Plans. Response: Acknowledged. All clearances are now met. Comment Number: 5 Comment Originated: 12/17/2020 12/17/2020: FOR HEARING: The secondary services to the buildings will be consider commercial; therefore, the service line from the transformer to the meter is required to be installed, owned, and maintained by the property owner. Response: Acknowledged. Comment Number: 6 Comment Originated: 12/17/2020 12/17/2020: FOR HEARING: This project will need to comply with our electric metering standards. Electric meter locations will need to be coordinated with Light and Power Engineering. Reference Section 8 of our Electric Service Standards for electric metering standards. A link has been provided below. https://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStanda rds_FINAL_18November2016_Amendment.pdf Response: Electric meters are shown for each building. A new service is proposed for the bank building, and reuse of the existing service from 1618 South College Avenue is proposed for the relocated historic building. Comment Number: 7 Comment Originated: 12/17/2020 12/17/2020: FOR FINAL: A commercial service information form (C-1 form) and a one-line diagram for all commercial meters will need to be completed and submitted to Light & Power Engineering for review prior to Final Plan. A link to the C-1 form is below: http://zeus.fcgov.com/utils-procedures/files/EngWiki/WikiPdfs/C/C-1Form.pdf Response: Acknowledged. This will be coordinated and provided at FDP. Comment Number: 8 Comment Originated: 12/17/2020 12/17/2020: INFORMATION ONLY: Any relocation or modification to existing electric facilities will be at the expense of the owner/developer. Response: Noted. Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 20 of 26 Comment Number: 9 Comment Originated: 12/17/2020 12/17/2020: INFORMATION ONLY: Electric capacity fee, building site charges, and any system modification charges necessary to feed the site will apply to this development. Please contact me or visit the following website for an estimate of charges and fees related to this project: http://www.fcgov.com/utilities/business/builders-and-developers/plant-investme nt-development-fees Response: Noted Comment Number: 10 Comment Originated: 12/17/2020 12/17/2020: INFORMATION ONLY: Any existing and/or proposed electric infrastructure that needs to be installed, relocated, or modified as part of this project, will be at the expense of the developer and will need to be located within Public Right-of-Way or a dedicated easement. Please coordinate relocations with Light and Power Engineering. Response: Noted. Comment Number: 11 Comment Originated: 12/17/2020 12/17/2020: INFORMATION ONLY: “The City of Fort Collins now offers gig-speed fiber internet, video, and phone service. Contact Julianna Potts with Fort Collins Connexion at 970-207-7890 or jpotts@fcgov.com for commercial grade account support, RFPs and bulk agreements.” Response: Acknowledged. Applicant is interested in receiving a proposal from the City of Fort Collins to review and will be reaching out to request this. Department: Environmental Planning Contact: Scott Benton, , sbenton@fcgov.com Topic: General Comment Number: 1 Comment Originated: 12/22/2020 12/22/2020: FOR APPROVAL: One of the shrubs are not on the City's approved plant list (http://www.fcgov.com/forestry/plant_list.pdf): Russian sage (Perovskia atriplicifolia). Please replace with an approved species. Response: The shrub has been replaced with an approved equal, Chamaebatiara millefolium, based on the city’s approved plant list. Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 21 of 26 Comment Number: 2 Comment Originated: 12/22/2020 12/22/2020: FOR APPROVAL: Please clarify specific turf species/varieties on the Landscape Plan. There are native turf species that provide acceptable turfs for low-traffic areas and also have minimal irrigation needs; additionally, there are improved bluegrass and fescue varieties that have decreased water needs compared to conventional bluegrass and fescue blends. Response: RTF Turf (Rhizomatous Tall Fescue) has been spec’d for this project. This turf is hardy, is self-repairing and requires minimal irrigation. Comment Number: 3 Comment Originated: 12/22/2020 12/22/2020: FOR APPROVAL: Thank you for submitting a photometric plan. Please provide cutsheets or other proof that the wall-mounted light fixtures (WP1 and WP2) are full cutoff and downshielded. Response: Fixtures WP1 and WP2 are full cutoff and down shielded. Fixture WP1 has been replaced with new cut sheets provided confirming this is addressed. Department: Forestry Contact: Christine Holtz, , choltz@fcgov.com Topic: Landscape Plans Comment Number: 3 Comment Originated: 12/21/2020 12/21/2020: Continued: The two proposed locations for the catalpa trees on the southwest corner of the site is within only a couple of feet of a water line. Please adjust the locations to adhere to the separation requirements listed below. Response: The trees have been relocated the appropriate distance from utilities based on comment. 07/31/20: INFORMATION ONLY FOR PDP Please include locations of utilities on the landscape plan including but not limited to water service/mains, sewer service/mains, gas, electric, streetlights and stop signs. Please adjust tree locations to provide for proper tree/utility separation. 10’ between trees and public water, sanitary, and storm sewer main lines 6’ between trees and water or sewer service lines 4’ between trees and gas lines 10’ between trees and electric vaults 40’ between canopy shade trees and streetlights 15’ between ornamental trees and streetlights Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 22 of 26 20-40’ between street trees and stop signs Response: Utilities have been included on Landscape Plan as noted. Comment Number: 5 Comment Originated: 12/21/2020 12/21/2020: INFORMATION FOR FINAL Continued: Please ensure, with the necessary adjustments for proper separation, that canopy shade tree still constitutes at lease (50%) of all tree plantings. 07/31/20: INFORMATION ONLY FOR PDP According to Land Use Code 3.2.1.(D)(c), canopy shade trees shall constitute at least (50%) of all tree plantings. Response: Shade trees are over 50% of all trees on site. Comment Number: 6 Comment Originated: 12/21/2020 12/21/2020: INFORMATION FOR FINAL Continued: Thank you for providing street trees along S. College Ave. Please note that shade trees need to be planted 30 – 40’ apart (forestry redlines). Ornamental trees can be 15’ from shade trees or other ornamentals. Response: Noted. 07/31/20: INFORMATION ONLY FOR PDP If the project is responsible for frontage improvements along College Avenue please incorporate new street trees within the right of way. If tree grates are necessary, please explore grates larger than the minimum required by code (5’x5’). Response: Street Trees have been incorporated into the frontage design along College Avenue. Street trees have been located in a tree lawn and therefore tree grates are unnecessary. Comment Number: 7 Comment Originated: 12/21/2020 12/21/2020: INFORMATION FOR FINAL Thank you for providing sufficient mitigation trees. Please call out which new tree plantings are mitigation trees both on the planting schedule and on the plants themselves Response: Trees being used for mitigation have been called out on both the plan and in the schedule with the symbol (M). Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 23 of 26 Department: Parks Contact: Aaron Wagner, aawagner@fcgov.com Topic: General Comment Number: 8 Comment Originated: 12/22/2020 12/22/2020: FOR INFORMATION The Parks department provided flowers and labor annually for a fee as part of an agreement between the city and the previous property owner for the planter pots located on the retaining wall along Prospect Road. The intent was to keep the look and feel of the landscape consistent throughout the intersection. Parks is interested to see if the applicant would like to continue with this same agreement. Response: Thank you. Alpine Bank has confirmed they will handle all landscaping construction and ongoing maintenance (labor and materials) as part of their upkeep of the remainder of the property. Comment Number: 9 Comment Originated: 12/22/2020 12/22/2020: FOR INFORMATION Regarding the retaining wall along Prospect Rd., if you are planning to modify the walls and/or planters, we would like to see some form of this put back with your plan that has the same rock/wall look and feel to the existing conditions. Response: Our goal is to not modify the existing wall or planters along E. Prospect and incorporate into the redevelopment as much as possible. That said, if modifications are required, our intent is to maintain the existing materials and look as much as possible. Department: Internal Services Contact: Russell Hovland, 970-416-2341, rhovland@fcgov.com Topic: Building Insp Plan Review Comment Number: 1 Comment Originated: 12/18/2020 12/18/2020: Construction shall comply with adopted codes as amended. Current adopted codes are: 2018 International Building Code (IBC) with local amendments 2018 International Existing Building Code (IEBC) with local amendments 2018 International Energy Conservation Code (IECC) with local amendments 2018 International Mechanical Code (IMC) with local amendments 2018 International Fuel Gas Code (IFGC) with local amendments Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 24 of 26 2018 International Swimming Pool and Spa Code (ISPSC) with local amendments 2018 International Plumbing Code (IPC) as amended by the State of Colorado 2020 National Electrical Code (NEC) as amended by the State of Colorado Copies of current City of Fort Collins code amendments can be found at fcgov.com/building. Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2017. Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF. Frost Depth: 30 inches. Wind Loads: Risk Category II (most structures): · 140mph (Ultimate) exposure B or · Front Range Gust Map published by The Structural Engineer's Association of Seismic Design: Category B. Climate Zone: Zone 5 Energy Code: 2018 IECC commercial chapter. INFORMATIONAL ITEMS: · 10% of all parking spaces must be EV ready (conduit in place) · This building is located within 250ft of a 4-lane road or 1000 ft of an active railway, must provide exterior composite sound transmission of 39 STC min. · Commercial occupancies must provide 10ft setback from property line and 20 feet between other buildings or provide fire rated walls and openings per chapter 6 and 7 of the IBC. · City of Fort Collins amendments to the 2018 IBC require a full NFPA-13 sprinkler system per IBC chapter 9 or when building exceeds 5000 sq.ft. (or meet fire containment requirements). · Prescriptive energy compliance with increased insulation values is required for buildings using electric heat. · A City licensed commercial general contractor is required to construct any new commercial structure. Building Permit Pre-Submittal Meeting: Please schedule a pre-submittal meeting with Building Services for this project. Pre-Submittal meetings assist the designer/builder by assuring, early on in the design, that the new projects are on track to complying with all of the adopted City codes and Standards listed below. The proposed project should be in the early to mid-design stage for this meeting to be effective. Applicants of new projects should email rhovland@fcgov.com to schedule a pre-submittal meeting. Applicants should be prepared to present site plans, floor plans, and elevations and be able to discuss code issues of occupancy, square footage, type of construction, and energy compliance method being proposed. Response: Thank you for information regarding current adopted codes. Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 25 of 26 We are currently anticipating scheduling a pre-submittal meeting with Building Services in late March or early April. It should also be noted that we have provided conduit for future EV charging stations as noted. Comment Number: 2 Comment Originated: 12/18/2020 12/18/2020: The relocated building on this site must meet separation distance to the south prop line. For single family residential 5ft separation is minimum and 10ft for multi-fam or commercial. Response: We are currently anticipating a commercial use for the relocated building and have therefore provided a minimum 10’ separation from the southern property line. Department: Technical Services Contact: Jeff County, 970-221-6588, jcounty@fcgov.com Topic: General Comment Number: 2 Comment Originated: 12/21/2020 12/21/2020: INFORMATION ONLY: Unless required during PDP, a complete review of all plans will be done at FDP. Response: Noted. Thank you. Topic: Plat Comment Number: 1 Comment Originated: 12/21/2020 12/21/2020: FOR FINAL APPROVAL: Please make changes as marked. If changes are not made or you disagree with comments, please provide written response of why corrections were not made. Please provide any responses on redlined sheets and/or in response letter. Response: Corrections made as noted. Thank you. Thank you again for comments received as well as follow-up discussions and coordination efforts. Please review our revised plans and let us know if you have any question or require additional information. Sincerely, GALLOWAY Alpine Bank Redevelopment SEC of S. College Avenue & E. Prospect Road January 20, 2021 Galloway & Company, Inc. Page 26 of 26 Zell O. Cantrell Senior Site Development Project Manager ZellCantrell@GallowayUS.com