HomeMy WebLinkAboutVALUE PLASTICS PUD, TIMBERLINE PLAZA (LOTS 3 - 5) - PRELIMINARY / FINAL - 26-94 - SUBMITTAL DOCUMENTS - ROUND 1 - GEOTECHNICAL (SOILS) REPORTValue Plastics Terracon
ELI Project No. 20945013
Field Exploration: A total of 10 test borings were drilled on February 1, 1994 to depths of 10 to
15 feet at the locations shown on the Site Plan, Figure 1. Eight borings were drilled within the
footprint of the proposed building, and two borings, were drilled in the area of proposed pavement.
All borings were advanced with a truck -mounted drilling rig, utilizing 4-inch diameter solid stem
auger.
The location of borings were positioned in the field by measurements from property lines and
existing site features. Elevations were taken of the ground surface at each boring location by
measurements with an engineer's level from a temporary bench mark (TBM) shown on the Site
Plan. The accuracy of boring locations and elevations should only be assumed to the level implied
by the methods used to determine each.
Continuous lithologic logs of each boring were recorded by the engineering geologist during the
drilling operations. At selected intervals, samples of the subsurface materials were taken by
means of pushing thin -walled Shelby tubes, or by driving split -spoon barrel samplers.
Representative bulk samples of subsurface materials were obtained from pavement borings.
Penetration resistance measurements were taken with each sampling with the split -spoon by
driving the sampler with a 140-pound hammer falling 30 inches. When properly interpreted, the
penetration resistance is a useful index to the consistency, relative density or hardness of the
materials encountered.
Groundwater conditions were evaluated in each boring at the time of site exploration, and one
days after drilling.
Laboratory Testing: All samples retrieved during the field exploration were returned to the
laboratory for evaluation by the project geotechnical engineer, and were classified in accordance
with the Unified Soil Classification System described in Appendix C. At that time, the field
descriptions were confirmed or modified as necessary, final boring logs prepared, and an applicable
laboratory testing program was formulated to determine engineering properties of the subsurface
materials. Boring Logs for the project are presented in Appendix A.
Selected soil and bedrock samples were tested for the following engineering properties:
• Water content • Expansion
• Dry density • Plasticity
• Consolidation • Soluble sulfate content
• Compressive strength
2
TI
I � i
a. I
a $v 120
MEOPP-Ml
i
f,1o• 5 �
�a. 2 —�+
c:::;Oj
T3•�. r! No•7 I
Tool.-
✓,=loo.o
ut
z
Jt`o.3 *L
O O o O O !—
��.Iv � I
i
I � JiL�b1 U
i
.�p�fJ�l f✓�� ao��
Empire Laboratories, Inc.
A Division of The Terracon Companies, Inc.
ABased on the material passing the 3-in.
(75-mm) sieve
'If field sample contained cobbles or
.'rCu=D /D Cc (DJ6)2
6o ro D10 x Dio
boulders, or both, add "with cobbles or
boulders, or both' to group name.
`Gravels with 5 to 12% fines require dual
`If soil contains > 15% sand, add "with
symbols:
sand" to group name.
GW-GM well -graded gravel with silt
Glf fines classify as CL-ML, use dual symbol
GW-GC well -graded gravel with clay
GC -GM, or SC-SM.
GP -GM poorly graded gravel with silt
"If fines are organic, add "with organic fines"
GP -GC poorly graded gravel with clay
to group name.
°Sands with 5 to 12% fines require dual
'If soil contains > 15% gravel, add "with
symbols:
.
gravel" to group name.
SW-SM well -graded sand with silt
'If Atterberg limits plot in shaded area, soil is
SW -SC well -graded sand with clay
a CL-ML, silty clay.
SP-SM poorly graded sand with silt
SP-SC poorly graded sand with clay
UNIFIED SOIL CLASSIFICATION SYSTEM
Sod Classification
Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests"
Group
Symbol
Group Name'
Coarse -Grained
Gravels more than
Clean Gravels Less
Soils more than
50% of coarse
than 5% fines`
Cu > 4 and 1 < Cc <3E
GW
Well -graded gravel`
50% retained on
fraction retained on
No. 200 sieve
No. 4 sieve
Cu < 4 and/or 1 > Cc > 3E
GP
Poorly graded graveP
Gravels with Fines
more than 12% fines c
Fines classify as ML or MH
GM
Silty gravel,G,H
Fines classify as CL or CH
GC
Clayey gravel`G•"
Sands 50'/9 or more
Clean Sands Less
Cu > 6 and 1 < Cc < 3E
SW
Well -graded sand'
of coarse fraction
than 5% fines'
passes No. 4 sieve
Cu < 6 and/or 1 > Cc > 3E
SP
Poorly graded sand'
Sands with Fines
Fines classify as ML or MH
SM
Silty sandQ"'
more than 12% fines°
Fines Classify as CL or CH
SC
Clayey sandy."'
Fine -Grained Soils
Silts and Clays
inorganic
PI > 7 and plots on or above "A line'
CL
Lean clay',Ll
50% or more
Liquid limit less
passes the
than 50
PI < 4 or plots below "A" line'
ML
Silt`.""
No. 200 sieve
organic
Liquid limit - oven dried
Organic clay' LMA
< 0.75
OL
Liquid limit - not dried
Organic siltK`-M-O
Silts and Clays
inorganic
PI plots on or above "A" line
CH
Fat cIW-`M
Liquid limit 50
or more
PI lots below "A" line
MH
Elastic Silt"uM
organic
Liquid limit - oven dried
Organic clay"1-1-"
< 0.75
On
Liquid limit - not dried
Organic silt"`-"-'
Highly organic soils Primarily organic matter, dark in color, and organic odor PT Peat
`If soil contains 15 to 29% plus No. 200, add
"with sand" or "with gravel", whichever is
predominant.
`If soil contains > 30% plus No. 200
predominantly sand, add "sandy" to group
name.
MY soil contains > 30% plus No. 200,
predominantly gravel, add "gravelly" to group
name.
"PI > 4 and plots on or above "A" line.
°PI < 4 or plots below "A' line.
'PI plots on or above "A" line.
°PI plots below "A" line.
rp de,wlko6en el IW-prvin,C roIb
�
ZVI.
OM nMp RIMQ igC110,1 01 Cprye-
9nMee
_
11Eo•
nlM e1R b U. 25.5;P
Q13 (u. m)
.J;',Ir
V��
-
i I
l
. P
EWaI=. el V - im
VMim
O.1
6R
N LL 16 10 R 7.
�
i
Q
O�
%
MH OR
OH
i
0 10 16 20 ]0
W W 60 M 60 99 Im 11c
LIQUID LIMIT (LL)
Empire Laboratories, Inc.
A Division of The Terracon Companies, Inc.
TABLE D2
RECOMMENDED PREVENTATIVE MAINTENANCE POLICY
FOR JOINTED CONCRETE PAVEMENTS
Distress
Distress
Recommended
Distress
Distress
Recommended
Type
Severity
Maintenance
Type
Severity
Maintenance
Low
None
No
Medium
Full -Depth
Blow-up
Polished
SeverityGroove
Surface
Concrete Patch/
Aggregate
Levels
or.
High
Slab Replacement
Defined
Overlay
Low
Seal Cracks
No
Medium
Full -Depth
Comer
Break
Popouts
Severity
None
Levels
High
Concrete Patch
Defined
Low
Seal Cracks
No
Underseal,
Medium
Divided
Pumping
Severity
Seal cracks/joints
Slab
Slab
Levels
and
High
Replacement
Defined
Restore
Load Transfer
Low
None
Low
Seal Cracks
Durability
Cracking
Medium
Full -Depth Patch
Punchout
Medium
um
Full -Depth
p
Concrete
High
Slab Replacement
High
Patch
Low
None
Low
No
Medium
Medium
Faulting
Railroad
Policy
Grind
Crossing
for this
High
High
Project
Low
None
Sing
Low
None
Medium
Reseal
Medium
Slab Replacement,
Seal
Map Cracking
Crazing
High
Joints
Full -depth Patch,
High
or Overlay
Low
Regrade and
No
Medium
Lane/Shoulder
Fill Shoulders
Shrinkage
Severity
Drop-off
to Match
Cracks
Levels
None
High
Lane Height
Defined
Linear Cracking
Low
Clean &
Low
. None
Longitudinal,
Medium
Medium
Transverse and
Seal all Cracks
Spalling
Diagonal
(Comer)
Partial -Depth
Cracks
High
Full -Depth Patch
High
Concrete Patch
Large Patching
Low
None
Low
None
Medium
Seal Cracks or
Medium
.
Partial -Depth Patch
and
Spallin(Joint)
Utility Cuts
High
Replace Patch
p
High
Reconstruct Joint
Low
None
Medium
Replace
Small
Patching
Patch
Empire Laboratories, Inc.
High
..... v..rvv,• vv,,,rmucO, II,V.
t,
TABLE D1
RECOMMENDED PREVENTATIVE MAINTENANCE POLICY
FOR ASPHALT CONCRETE PAVEMENTS
Distress
Distress
Recommended
Distress
Distress
Recommended
Type
Severity
Maintenance
Type
Severity
Maintenance
Low
None
Low
None
Alligator
Cracking
Patching &
Utility Cut
Patching
Medium
Full -Depth
Asphalt Concrete
Patch
Medium
Full -Depth
Asphalt Concrete
Patch
High
High
Low
None
Low
Bleeding
Polished Aggregate
None
Medium
Surface Sanding
Medium
High
Shallow AC Patch
High
Fog Seal
Low
None
Low
Shallow AC Patch
Block
Cracking
Medium
Clean &
Seal
All Cracks
Potholes
Medium
Full -Depth
Asphalt Concrete
Patch
High
High
Low
None
Low
Bumps &
Sags
Railroad
Crossing
No Policy
for
This Project
Medium
Shallow AC Patch
Medium
High
Full -Depth Patch
High
Low
None
Low
None
Medium
Full -Depth
Medium
Shallow AC Patch
Corrugation
Rutting
Asphalt Concrete
High
Patch
High
Full -Depth Patch
Low
None
Low
None
Medium
Shallow AC Patch
Medium
Mill &
Depression
Shoving
Shallow AC
High
Full -Depth Patch
High
Patch
Low
None
Low,
None
Edge
Cracking
Slippage
Cracking
Medium
Seal Cracks
Medium
Shallow
Asphalt Concrete
Patch
High
Full -Depth Patch
High
Low
Clean &
Low
None
Joint
Reflection
Seal
All Cracks
Swell
Medium
Medium
Shallow AC Patch
High
Shallow AC Patch
High
Full -Depth Patch
Low
None
Low
Lane/Shoulder
Drop -Off
p
Weathering
&Ravelling
Fog
Seal
Medium
Regrade
9
Medium
High
High
9
Shoulder
Low
None
Long-rtudinal &
Transverse
Medium
Clean &
Cracking
Seal
All Cracks
Em ire Laboratories Inc.
P �
High
A nivisinn of Tho i__
REPORT TERMINOLOGY
(Based on ASTM D653)
Expansive Potential The potential of a soil to expand (increase in volume) due to absorption of
moisture.
Finished Grade The final grade created as a part of the project.
Footing A portion of the foundation of a structure that transmits loads directly to the
soil.
Foundation The lower part of a structure that transmits the loads to the soil or bedrock.
Frost Depth The depth of which the ground becomes frozen during the winter season.
Grade Beam. A foundation element or wall, typically constructed of reinforced concrete,
used to span between other foundation elements such as drilled piers.
Groundwater
Subsurface water found in the zone of saturation of soils, or within fractures
in bedrock.
Heave
Upward movement.
Lithofogic
The characteristics which describe the composition and texture of soil and
rock by observation.
Native Grade
The naturally occuring ground surface.
Native Soil
Naturally occurring on -site soil, sometimes referred to as natural soil.
Optnnum Moisture
The water content at which a soil- can be compacted to a maximum dry unit
Content
weight by a given compactive effort.
Perched Water
Groundwater, usually of limited area maintained above a normal water
elevation by the presence of an intervening relatively impervious continuing
stratum.
Scarify
To mechanically loosen soil or break down existing soil structure.
Settlement
Downward movement.
Skin Friction (Side
The frictional resistance developed between soil and an element of structure
Shear)
such as a drilled pier or shaft.
Soil (earth)
Sediments or other unconsolidated accumulations of solid particles produced
by the physical and chemical disintegration of rocks, and which may or may
not contain organic matter.
Strain
The change in length per unit of length in a given direction.
Stress
The force per unit area acting within a soil mass.
Strip
To remove from present location.
Subbase
A layer of specified material in a pavement system between the subgrade and
base course.
Subgrade
The soil prepared and compacted to support a structure, slab or pavement
system.
Empire Laboratories, Inc.
A Division of The Terracon Companies, Inc.
REPORT TERMINOLOGY
(Based on ASTM D653)
Allowable Soil
The recommended maximum contact stress developed at the interface of the
Bearing Capacity
foundation element and the supporting material.
Alluvium
Soil, the constituents of which have beentransported in suspension by flowing
water and subsequently deposited by sedimentation.
Aggregate Base
A layer of specified material placed on a subgrade or subbase usually beneath
Course
slabs or pavements.
Backfill
A specified material placed and compacted in a confined area.
Bedrock
A natural aggregate of mineral grains connected by strong and permanent
cohesive forces. Usually requires drilling, wedging, blasting or other methods of
extraordinary force for excavation.
Bench
A horizontal surface in a sloped deposit.
Caisson (Drilled pier
A concrete foundation element cast in a circular excavation which may have an
or Shaft)
enlarged base. Sometimes referred to as a cast -in -place pier or drilled shaft.
Coefficient of
A constant proportionality factor relating normal stress and the corresponding
Friction
shear stress at which sliding starts between the two surfaces.
Colluvium
Soil, the constituents of which have been deposited chiefly by gravity such as
at the foot of a slope or cliff.
Compaction
The densification of a soil by means of mechanical manipulation.
Concrete Slab -on-
A concrete surface layer cast directly upon a. base, subbase or subgrade, and
Grade
typically used as a floor system.
Differential
Unequal settlement or heave between, or within foundation elements of a
Movement
structure.
Earth Pressure
The pressure or force exerted by soil on any boundary such as a foundation
wall.
ESAL
Equivalent Single Axle Load, a criteria used to convert traffic to a uniform
standard, (18,000 pound axle loads).
Engineered Fill
Specified material placed and compacted to specified density and/o'r moisture
conditions under observations of a representative of a geotechnical engineer.
Equivalent Fluid
A hypothetical fluid having a unit weight such that it will produce a pressure
against a lateral support presumed to be equivalent to that produced by the
actual soil. This simplified approach is valid only when deformation conditions
are such that the pressure increases linearly with depth and the .wall friction is
neglected.
Existing Fill (or
man-made fill)
Materials deposited through the action of man prior to exploration of the site.
Existing Grade
The ground surface at the time of field exploration.
Empire Laboratories, Inc.
A Division of The Terracon Companies, Inc.
LABORATORY TESTS
SIGNIFICANCE AND PURPOSE
TEST
SIGNIFICANCE
I PURPOSE
California
Bearing
Ratio
Used to evaluate the potential strength of subgrade soil, subbase,
and base course material, including recycled materials for use in
road and airfield pavements..
Pavement
Thickness
Design
Consolidation
Used to develop an estimate of both the rate and amount of both
differential and total settlement of a structure.
Foundation
Design
Direct
Shear
Used to determine the consolidated drained shear strength of soil
or rock.
Bearing Capacity,
Foundation Design &
Slope Stability
Dry
Density
Used to determine the in -place density of natural, inorganic, fine-
grained soils.
Index Property
Soil Behavior
Expansion
Used to measure the expansive potential of fine-grained soil and to
provide a basis for swell potential classification.
Foundation & Slab
Design
Gradation
Used for the' quantitative determination of the distribution of
particle sizes in soil.
Soil
Classification
Liquid &
Plastic Limit,
Plasticity Index
Used as an integral part of engineering classification systems to
characterize the fine-grained fraction of soils, and to specify the
fine-grained fraction of construction materials:
Soil
Classification
Oxidation-
Reduction
Used to determine the tendency of the soil to donate or accept
electrons through a, change of the oxidation state within the soil.
I Corrosion
Potential
otential
Permeability
Used to determine the capacity of soil or rock to conduct a liquid
or gas.
Groundwater
I Flow Analysis
pH
Used to determine the degree of acidity or alkalinity of a soil.
Corrosion
Potential
Resistivity
Used to indicate the relative ability of a soil medium to carry I
electrical currents.
Corrosion
Potential
Used to evaluate the potential strength of subgrade soil, subbase,
Pavement
R-Value
and base course material, including recycled materials for use in
I
Thickness
road and airfield pavements.
Design
Soluble
Sulphate
Used to determine the quantitative amount of soluble sulfates
within a soil mass.
Corrosion
Potential
Sulfide Content
Used to determine the quantitative amounts of sulfides within a I
soil mass.
Corrosion
Potential
Unconfined
Compression
To obtain the approximate compressive strength of soils that
possess sufficient cohesion to permit testing in the unconfined
state.
Bearing Capacity
Analysis for
Foundations
Water
Content
Used to determine the quantitative amount of water in a soil mass.
Index Property
Soil Behavior
Empire Laboratories, Inc..
_ A w4 TL_ T______
.. .........v... v• •.Ic leiia.V11 VVI11`1O111CJr 111u.
uRILLING AND EXPLORATION
DRILLING & SAMPLING SYMBOLS:
R : Ring Barrell - 2.42" I.D., 3" O.D., unless otherwise noted
S : Split Spoon - 1 %" I.D., 2" O.D., unless otherwise noted
PS : Piston Sample
ST : Thin -Walled Tube - 2" O.O., unless otherwise noted
WS : Wash Sample
PA: Power Auger
FT : Fish Tail Bit
HA: Hand Auger
RB : Rock Bit
DB : Diamond Bit = 4", N, B
SS : Bulk Sample
AS : Auger Sample
PM : Pressure Meter
HS : Hollow Stem Auger
DC : Dutch Cone
WB : Wash Bore
Penetration Test: Blows per foot of a 140 pound hammer falling 30 inches on a 2-inch O.D. split spoon, except where.
noted.
WATER LEVEL MEASUREMENT SYMBOLS:
WL :Water Level WS : While Sampling
WCI : Wet Cave in WD : While Drilling
DC] : Dry Cave in SCR : Before Casing Removal
AB : After Boring ACR : After Casting Removal
Water levels indicated on the boring logs are the levels measured in the borings at the time indicated. In pervious soils,
the indicated levels may reflect the location of groundwater. In low permeability soils, the accurate determination of
groundwater levels is not possible with only short term observations.
DESCRIPTIVE SOIL CLASSIFICATION:
Soil Classification is based on the Unified Soil Classification system and the ASTM Designations D=2487 and D-2488.
Coarse Grained Soils have more than 50% of their dry weight retained on a #200 sieve; they are described as: boulders,
cobbles, gravel or sand. Fine Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are
described as: clays, if they are plastic, and silts if they are slightly plastic or non -plastic. Major constituents may be.
added as modifiers and minor constituents may be added according to the relative proportions based on grain size. In
iddition to gradation, coarse grained soils are defined on the basis of their relative in -place density and fine grained soils
n the basis of their consistency. Example: Lean clay with sand, trace gravel, stiff (CL); silty sand, trace gravel, medium
dense ISM).
CONSISTENCY OF FINE-GRAINED SOILS:
Unconfined Compressive
Strength, Qu, psf
Consistency
< 500
Very Soft
500 - 1,000
Soft
1,001 - 2,000
Medium
2,001 - 4,000
Stiff
4,001 - 8,000
Very Stiff
8,001-16,000
Very Hard
RELATIVE PROPORTIONS OF
SAND AND GRAVEL
Descriptive Term(s)
(of Components Also
Percent of
Present in Sample)
Dry Weight
Trace
< 15
With
15 - 29
Modifier
> 30
RELATIVE PROPORTIONS OF FINES
Descriptive Term(s)
(of Components Also
Percent of
Present in Sample)
Dry Weight
Trace
< 5
With
5-12
Modifier
> 12
RELATIVE DENSITY OF
COARSE -GRAINED SOILS:
N-Blows/ft.
Relative Density
0-3
Very loose
4-9
Loose
10-29
Medium Dense
30-49
Dense
50-80
Very Dense
80+
Extremely Dense
GRAIN SIZE TERMINOLOGY
Major Component
of Sample
Size Range
Boulders
Over 12 in. (300mm)
Cobbles
12 in. to 3 in.
(300mm to 75mm)
Gravel
3 in, to #4 sieve
(75mm to 4.75mm)
Sand
#4 to #200 sieve
(4.75mm to 0.075mm)
Silt or Clay
Passing #200 Sieve
(0.075mm)
Empire Laboratories, Inc.
A Division of The Terracon Companies, Inc.
SUMMARY OF :ST RESULTS
Boring
No.
Depth
Ft.
Moisture
%
Dry
Density
(PCF)
Compressive
Strength
(PSF)
Swell
Pressure
(PSF)
Soluble
Sulfates
%
pH
Liquid
Limit
%.,
Plasticity
Index
%
Group
Index
Classification
AASHTO
USCS.
Resistivity
(OIIM-CM)
Penetration
Blow/In.
7
8-9
20.9
5/12
14-15
22.7
1
5/12
8
.5-1.5
15.7
13/12
3-4
17.0
97.4
4880
4-5
19.2
5/12
7-8
29.8
77.5
1230
8-9
21.5
6/12
14-15
24A
5/12
9
0-1
19.4
35.2
14.1
10.7
A-6(1); CL
18/12
1-2
19.2
19/12
4-5
11.8
6/12
9-10
11.9
5/12
10
0-1
18.9
33.9
14.7
10.0
A-6(10); CL
18/12
1-2
19.0
14/12
4-5
11.8
8/12
9-10
10.8
7/12
SUMMARY OF TEST RESULTS
Boring
No.
Depth
Ft.
Moisture
%
Dry
Density
(PCF)
Compressive
Strength
(PSF)
Swell
Pressure
(PSF)
Soluble
Sulfates
%
pH
Liquid
Limit
%
Plasticity
Index
%
Group
Index
Classification
AASHTO
USCS
Resistivity
(OHM -CM)
Penetration
Blow/In.
4
4-5
14.7
7/12
7-8
19.2
101.5
2620
8-9
18.4
6/12
14-15
26.4
6/12
5
.5-1.5
18.7
12/12
3-4
18.9
96.6
3950
170
.0018
4-5
20.7
6/12
7-8
25.5
80.6
1220
8-9
18.6
4/12
14-15
23.2
4/12
6
.5-1.5
16.8
10/12
3-4
17.0
96.6 .
2860
120
4-5
17.3
6/12
7-8
29.5
78.5
1110
8-9.
23.1
5/12
14-15
21.7
3/12
7
.5-1.5
14.0
20/12
3-4
17.8
86.1
4-5
17.9
4lt2
7-8
17.6
105.5
2100
SUMMARY OF '. ST RESULTS
Boring
No.
Depth
Ft.
Moisture
%
Dry ,
Density
(PCF)
Compressive
Strength
(PSF)
Swell
Pressure
(PSF)
Soluble
Sulfates
%
pH
Liquid
Limit
%
Plasticity
Index
%
Group.
Index
Classification
AASHTO
USCS
Resistivity
(OHM -CM)
Penetration
Blow/In.
1
.5-1.5
17.8
11/12
3-4
11'6
88.5
2810
4-5
12.2
5/12
7-8
15.7
105.8
12,600
8-9
13.2
7/12
14-15
17.5
7/12
2
.5-1.5
20.0
10/12
34
12.8
87.9
2300
295
4-5
12.8
8/12
7-8
24.8
89.2
3940
8-9
21.2
5/12
14-15
20.0
5/12
3
.5-1.5
16.4
20/12
34
12.1
84.6
1110
.0023
4-5
13.2
5/12
7-8
18.4
101.2
3230
8-9
13.8
4/12
14-15
26.0
5/12
.4
.5-1.5 1
16.6
10/12
34
14.0
107.1
8670
640
c Q f7l
.650
.640
.63cl
174
6 L
61:73 cl
.590
SWELL - ,CONSOLIDATION TEST
PRO. 20945-013
I�
e.1 e.25
Li..!:) 1.0 5 10
APPLIED PRESSURE — TSF
RTER RDDED
U. , 1.0
APPLIED PRESSURE — TSF
5 1 e
EMPIRE LHBORFITORIES INC.
� -a ,a
.75
.73
.71
.6tJ 9
.67
.65
.63
.6t
SWELL - CONSOLIDATION TEST PRO. 20945 .013
0
BORING NO.
DEPTH: 3.0
DRY DENSITY: 92.4 Pur
t-11,1STURE: 11.3 %
I
ITT
cl
El
0.1 Cl. 25 0.5 5
RPPLIED PRESSURE - TS-F
8.0
w
4.0
0)
0.0
RTER RDBED
.-16.0
0.1 0.25 0.5 1.0 5
RPPLIED PRESSURE - TSF
EMPIRE LHBORRTORIES INC.
LOG BORING No. lO Paee 1 of 1
CLIENT ARCHITECT/ENGLNEER
Value Plastics The Neenan Company
SITE ' NW Corner of Danfield & Timberline PROJECT
Fort Collins, Colorado Proposed Building
Lo
O
J
U I DESCRIPTION
H
0_
Q:
LD Approx. Surface Elev.: 99.4 ft.
0.5 FILL -Lean clay with
sand and gravel
Town, moist
10.0
Composite sample @ 0 to 2 ft
LEAN CLAY WITH SAND
Brown/tan, moist, stiff
BOTTOM OF
J
A
}
O
H
H
O
H
03
LL
H
W
It
>.
}
W
z2
0: H
v
w
z\
z
W
u}i
W
WED
mma
2
W
to
H
O
zz
O:HJ
H
W
m
W
O
3
Ln
O W
WHO_
0- -
U
E=
0.
U
HO
H
>-LL
UMLL
HS\
W
W
>
>-
W
0-J
O
CYU
zHtn
F_H-J
o
M
z
H
0:
WM
E
oa.
mcna-
¢-i-i
98.9 CL 1 SS 12" 18 18.9
2 SS 12' 14 19.0
PA
61
89.4
10-
CL 1 3 1 SS 1 12" 1 8 111.8
4 1 SS 1 12"1 7 110.8
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES
BETWEEN SOIL AND ROCK TYPES: IN -SITU, THE TRANSITION MAY BE GRADUAL.
WATER LEVEL OBSERVATIONS
IWL g None W D =None A.B. Empire Laboratories
WL, Incorporated
WL Checked 24 hrs. A.B. Division of Terracon
34/19/15 1
BORING STARTED 2-1-94
BORING COMPLETED 2-1-94
RIG CME-S5 FOREMAN DbIL
APPROVED NRS JOB H 2O945013
LOG BORING No. 9
Page 1 of 1
CLIENT ARCHITECT/ENGINEER
Value Plastics The Neenan Company
STPE NW Corner of Danfield & Timberline
PROJECT
Fort Collins, Colorado
Proposed Buildin
SAMPLES
TESTS
J
..
O
H
\
H
O
H
DESCRIPTION
r
z
z
z
H I=
W a
_
O.
2
H
v)
W
CO
W
�
O
I Cl)
3
F
O
O
zz
�Ly—J
Approx. Surface Elev.: 100.9 ft.
O.
o
U
�
E
z
O.
�
U
�
1--O
H
E
>-LL
ca
OW
0MLL
�(0aa
WHO.
!_=\
¢_j_j
vain
0.5 E -Lean clay with 100.4
sand and gravel
CL
1
SS
12"
18
19.4
Brown, moist
2
SS
12'
12
19.2
Composite sample p 0 to 2 ft.
PA
35/21/14
CL
3
SS
12"
6
11.8
LEAN CLAY WITH SAND
5
PA
Brown/tan, moist
Medium to stiff
4
SS
12"
5
11.9
10.0 90.9
10
BOTTOM OF BORING
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES
BETWEEN SOIL AND ROCK TYPES: IN -SITU, THE TRANSITION MAY BE GRADUAL.
WATER LEVEL OBSERVATIONS
Empire Laboratories
BORING STARTED 2-1-94
WL
g None WD•
= None A.B.
BORING
Incorporated
COMPLETED 2-1-9a
WL
Division of Tertacon
RIG CME_55
FOREMAN DML
W'
Checked 24 hrs. A.B.
APPROVED NRS
JOB # 20945013
1
LOG BORING No. 8 Page 1 of 1
CT/ENGINEER
CLIENT
ARCHITE
Value Plastics
The Neenan Company
SITE NW Corner of Danfield & Timberline
PROJECT
Fort Collins, Colorado
Pro sed Building
SAMPLES
TESTS
o
0
0
.,
o
J
L~L
E
Li.
W
N
z S
DESCRIPTION
}
yr
W
W
W
z\
Ot
M
z
W
HH
u.co
H
=
H
m
O
3
O
D_
U)zz
W
to
OW
cc
rL
U
d
U
HO
H
YrL
uwu_
W
fA
.>
>-
W
0_J
O
D:U
zFIA
Approx. Surface Elev.: 94.8 ft.
o
�
z
f-
W
tnm
>_
❑n
orna
rB
0.5 FILL -Lean clay with 94.3
sand
amoistanel
CL
1
SS
12"
13
15.7
own
CL 1 2 1 ST 1 12" 1 117.0 1 97 1 4880
LEAN CLAY WITH SAND 3 1 SS 1 12" 5 19.2
Brown/tan, moist
Medium to very stiff 5 1 PA
-jl
4
( ST
1 12"
II
f9.8
I 78
11230
5
SS
12"I1
6
21.5
PA
IM
6 SS 12" 5 24.1
79.8 15
BOTTOM OF BORING
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES
BETWEEN SOIL AND ROCK TYPES: IN -SITU, THE TRANSITION MAY BE GRADUAL.
WATER LEVEL OBSERVATIONS BORING STARTED 2-1-94
WL g None W.D. T None A.B. Empire Laboratories BORING COMPLETED 2_1_94
WL Incorporated RIG CME FO -55 REMAN DML
WL Division of Tertacon
Checked 24 hrs. A.B. APPROVED NRS JOB a 20945013
LOG BORING No. 7
CLIENT ARCHITECT/ENGINEER
Value Plastics The Neenan
SITE NW Comer of Danfield & Timberline PROJECT
Fort Collins. Colorado
DESCRIPTION
Approx. Surface Elev.: 94.8 ft.
FILL -Lean clay with
sand and gravel
1.5 Brown, moist
LEAN CLAY WITH SANT)
Tan/red, moist
Medium to stiff
BOTTOM OF BORING
U1
J
g
V
}
~
LL
m
E
}
LL
H
W
>
N
X
K
W
Z\
�
O
Z
W
HF
LL CD
d
OLL
LU
U
N
�
m
d
>-
U
to
F-O
a.j
H
O
XL)
ow
Z�_U)
o
M
Z
X
toad
E
oo-
=)mn.
CLI 1 I SS 1 12"1 20 14.0
PA
CL 2 ST 12" 17.8 86
3 SS 12" 4 17.9
5 PA
l
79.8 15
ri
12"1
r.61
106
11
5
SS
12"
5
20.9
6 1 SS 1 12"1 5 122.7
1of1
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES
BETWEEN SOIL AND ROCK TYPES: IN -SITU, THE TRANSITION MAY BE GRADUAL.
WATER LEVEL OBSERVATIONS BORING STARTED 2-1-94
WL g None WD IT None A.B. Empire Laboratories BORING COMPLETED 2-1-94
WL Incorporated RIG CME-J5 FOREMAN DML
WL Division of Terracon
Checked 24 hrs. A.B. APPROVED NRS 110111 20945013
LOG BORING No. 6 .
Page 1 of 1
CLIENT
ARCHITECT/ENGINEER
Value Plastics
The Neenan Company
SITE NW Corner of Danfield & Timberline
PROJECT
Fort Collins, Colorado
Proposed Building
SAMPLES
TESTS
\
>
O
J
L)
DESCRIPTION
z\
M
=
O-
2
N
W
w
:>
i co
F—
w
C]
H�
Z Z
j
J fA
cc
H
d
U
U
m
W
n.
O
U
3
F-O
to
H
YU.
ow
UM L
J U)
WWIL
LD
Approx. Surface Elev.: 96.2 ft.
o
�
z
�
M
uUim
E
oa
=)U)CL
u3iaa
FILL Lean clay with sand
CL
1
SS
12"
10
16.8
1.0 Brown, moist 95.2
PA
120
CL
2
ST
12"'
17.0
97
2860
LEAN CLAY WITH SAND
3
SS
12"
6
17.3
Tan/red, moist, medium to hard
5--PA
4
ST
12"
29.5
79
1110
5
SS
12"
5
23.1
PA
10
i
6
SS
12"
3
15.0 81.2
15
121.7
BOTTOM OF BORING
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES
BETWEEN SOIL AND ROCK TYPES: IN -SITU, THE TRANSITION MAY BE GRADUAL.
WATER LEVEL OBSERVATIONS
Empire Laboratories
Incorporated
BORING STARTED 2-1-94
` L
g None WD•
IT None A.B.
BORING COMPLETED 2-1-94
WL
Division of Terracon
RIG CME-SS
FOREMAN DML
��'I
Checked 24 hrs. A.B.
APPROVED NRS
JOB q 20945013
LOG BORING No. 5
Page 1 of 1
CLIENT
ARCHITECT/ENGINEER
Value Plastics
The Neenan Company
SITE NW Corner of Danfield & Timberline
PROJECT
Fort Collins, Colorado
Pro se,4 Building
SAMPLES
TESTS
>-
-1
F-
.m
l~i.
H
W
H
DESCRIPTION
.,
z�
HLL
0:
_
S
N
W
W
_>
i to
j
w
O
�
Z Z
J to
0-
2
F-
0-
to
U
in
W
a.
O
L)
3
F- O
to
H
} Iy
ow
t, 0: IL
Jto
W W w
W
Approx. Surface Elev.: 94.6 ft.
o
n
z
F}—
M
WM
E
oo0..
�t~nCL
CnnaNa
0.5 FILL -Lean clay with 94.1
sand and gravel
CL
1
SS
12"
12
18.7
Brown, moist
PA
170
CL
2
ST
12"
18.9
97
3950
LEAN CLAY WITH SAND
3
SS
12"
6
20.7
Brown/tan, moist
Medium to stiff
5
PA
4
ST
12"
25.5
81
1220
5
SS
12"
4
18.6
PA
10
6
SS
12"
4
23.2
15.0 79.6
15
BOTTOM OF BORING
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES
BETWEEN SOIL AND ROCK TYPES: IN -SITU, THE TRANSITION MAY BE GRADUAL.
WATER LEVEL OBSERVATIONS
Empire Laboratories
Incorporated
Division of Terracon
BORING STARTED 2-1-94
WL
g None W.D.
M
BORING COMPLETED 2-1-94
6.0 D-C.I.
RIG CME-J�
FOREMAN DNII,
wL
Checked 24 hrs. A.B.
APPROVED NRg
JOB a 20945013
LOG BORING No. 4
Page i of 1
CLIENT
ARCHITECT/ENGINEER
Value Plastics
The Neenan Company
SITE NW Corner of Danfield & Timberline
PROJECT
Fort Collins, Colorado
Pro sed Building
p..
SAMPLES
TESTS
X
>-
U
DESCRIPTION
N
w
z\
?
z
?�
CC
S
2
W
i N
F-
0
Zz
JN
n.
H
0-U
O
CO.
E
W
D_
O
U
3
HO
LA
H
YLL
ow
UcrLL
JN
WWLL'
CD
Approx. Surface Elev.: 95.7 ft.
0
z
M
Cl) m
E
o f
M W OL
ui a s
XXX
xW
0.5 FILL -Lean clay with 95.2
sand and gravel
CL
1
SS
12"
10
16.6
Brown; moist
i
I
PA
640
CL
2
ST
12"
14.0
107
18670
LEAN CLAY WITH SAND
3
SS
12"
7
14.7
Brown/tan, moist
Medium to hard
5
PA
4
ST
12"
119.2
102
1 2620
1
5
SS
12"
6
18.4
PA
10
4
=
6
SS
12"
6
26.4
Q
15.0 - 80.7
15
BOTTOM OF BORING
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES
BETWEEN SOIL AND ROCK TYPES: IN -SITU, THE TRANSITION MAY BE GRADUAL.
WATER LEVEL OBSERVATIONS
Empire Laboratories
Incorporated
BORING STARTED 2-1-94
WL
s 14.6 W.D.
i 14.2 A.B.
BORING COMPLETED 2-1-94
wL
Division of Terracon
RIG C1yjE_55
FOREMAN DMIL
WI
Checked 24 hrs. A.B.
APPROVED NRS
IJOB # 20945013
LOG BORING No. 3
CLIENT ARCHITECT/ENGINEER
Value Plastics The Neenan
SITE NW Corner of Danfield & Timberline PROJECT
Fort Collins: Colorado
t,
O
J
H
DESCRIPTION
x
0_
0:
Approx. Surface Elev.: 98.0 ft.
EILL-Lean clay with
1.0 sand and gravel
Brown, moist
LEAN CLAY WITH SAND
Brown/tan, moist
Medium to stiff
BOTTOM OF BORING
97.0
}
i
a7
OLL
N
W
Z\
�
Z
HH
H
0:
m
O
O
O-
fA
U
E
W
a-
U
3
F—O
W
H
}LL
OW
umu.
W
o
to
:3
O
z
}
W
z
a. —i
cn ao
O
E
K U
o o-
Z F_ Cn
=) to o-
5
10
15
CL I I I SS 112"1 20 116.4
CL
2
ST
12"
12.1
85
1110
3
SS
12"
5
13.2
4 ST_ 12" 18.4 101 3230
5 SS 12" 4 13.8
PA
6 1 SS 1 12"1 5 126.0
1of1
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES
BETWEEN SOIL AND ROCK TYPES: IN -SITU, THE TRANSITION MAY BE GRADUAL.
WATER LEVEL OBSERVATIONS BORING STARTED 2-1-94
WL s None a •D• Y- None A.B. Empire Laboratories BORING COMPLETED 2-1-94
Incorporated RIG CME-55 FOREMAN DNn
WL Checked 24 hrs. A.B. Division of Tecracon
APPROVED NRS JOB # 20945013
LOG BORING No. 2
Page 1 of 1
CLIENT
ARCHITECT/ENGINEER
Value Plastics
The Neenan Company
SITE NW Corner of Danfield & Timberline
PROJECT
Fort Collins, Colorado
Pro ed Building
SAMPLES
TESTS
►}-
o
O
0
o
W
'J
LLi
Z
Y
W
(HA
Z S
W
>.
W
?\
o:
z
HI--
M
HDESCRIPTION
N
�
H
O
ZZ
_
D-
=
F-
N
W
m
W
O
I (n
3
N
0111
J(n
J (n
(1
U
E
n.
V
Ho
H
>-4.
UD: LL
WWLL
Approx. Surface Elev.: 98.4 ft.
o
�
z
.�
x
vaim
F
oa
�(~n(L
(saa.
0.5 FILL -Lean clay with 97.9
sand and gravel
CL
I
SS
12"
10
20.0
rown, moist
PA.
295
CL
2
ST
12"
12.8
88
2300
LEAN CLAY WITH SAND
3
SS
12"
8
12.8
Brown/tan, moist, stiff
5
PA
4
ST
12"
24.8
89
3940
5
SS
12"
5
21.2
PA
10
6
SS
12"
5
20.0
15.0 83.4
15
BOTTOM OF BORING
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES
BETWEEN SOIL AND ROCK TYPES: IN -SITU, THE TRANSITION MAY BE GRADUAL.
WATER LEVEL OBSERVATIONS
Empire Laboratories
Incorporated
Division of Tertacon
BORING STARTED 2-1-94
W-
4 None W.D.i
None A.B.
BORING COMPLETED 2-1-94
„L
RIG CME-J5
FOREMAN DMIL
WL
Checked 24 hrs. A.B.
APPROVED NRS
JOB k 20945013
LOG BORING No. 1 Page 1 of 1
CLIENT
ARCHITECTIENGINEER
Value Plastics
The Neenan Company
SITE NW Corner of Danfield & Timberline
PROJECT
Fort Collins, Colorado
Pro sed Building
SAMPLES
TESTS
W
W
rn
E
z
W
(L
w
7
o
U
a
F-
W �
z
I (n
3
I— O
vain
\
(A
H
r
Y
F-
H
z
o
YIL
oa
O
W
LL
z z
ow
U O: W
�(~na
!�
O
J
H
x
a
0
DESCRIPTION
Approx. Surface Elev.: 99.1 ft.
F-
x
Q.
wo
J
O
(a
(n
W
U
=
0.5 FILL Lean clay with sand 98.6
Brown, moist
CL
1
SS
12"
11
17.8
PA
CL
2
ST
12"
I11.6
89
2810
LEAN CLAY WITH SAND
3
SS
12"
5
Tan/red, moist, medium to hard
112.2
5
PA
4
ST
12"
15.7
106
12600
5
SS
12"
7
13.2
PA
10
6
SS
12"
7
17.5
15.0 84.1
15
BOTTOM OF BORING
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES
BETWEEN SOIL AND ROCK TYPES: IN -SITU, THE TRANSITION MAY BE GRADUAL.
WATER LEVEL OBSERVATIONS
Empire Laboratories
Incorporated
Division of Ter acon
BORING STARTED 2-1-94
wL
g None W.D.
None A.B.
BORING COMPLETED 2-1-94
WL
RIG CIVIE_55
FOREMAN Dru
W-
Checked 24 hrs. A.B.
APPROVED NgS
I JOB # 20945013
Value Plastics
ELI Project No. 20945013
Terracon
The analyses and recommendations in this report are based in part upon data obtained from the
field exploration. The nature and extent of variations beyond the location of test borings may not
become evident until construction. If variations then appear evident, it may be necessary to
reevaluate the recommendations of this report.
Our professional services were performed using that degree of care and skill ordinarily exercised,
under similar circumstances, by reputable geotechnical engineers practicing in this or similar
localities. No warranty, express or implied, is made. We prepared the report as an aid in design
of the proposed project. This report is not a bidding document. Any contractor reviewing this
report must draw his own conclusions regarding site conditions and specific construction
techniques to be used on this project.
This report is for the exclusive purpose of providing geotechnical engineering and/or testing
information and recommendations. The scope of services for this project does not include, either
specifically or by implication, any environmental assessment of the site or identification of
contaminated or hazardous materials or conditions. If the owner is concerned about the potential
for such contamination, other studies should be undertaken.
17
Value Plastics Terracon
ELI Project No. 20945013
Additional Design and Construction Considerations:
• Exterior Slab Design and Construction: Exterior slabs -on -grade, exterior architectural
features, and utilities founded on, or in backfill may experience some movement due to the
volume change of the backfill. Potential movement could be reduced by:
• minimizing moisture increases in the backfill
• controlling moisture -density during placement of backfill
• using designs which allow vertical movement between the exterior features
and adjoining structural elements
• placing effective control joints on relatively close centers
• allowing vertical movements in utility connections
• Corrosion Protection: Results of soluble sulfate testing indicate that ASTM Type I Portland
cement is suitable for all concrete on and below grade. However, if there is no, or minimal
cost differential, use of ASTM Type II Portland cement is recommended for additional
sulfate resistance of construction concrete. Foundation concrete should be designed in
accordance with the provisions of the ACI Design Manual, Section 318, Chapter 4.
GENERAL COMMENTS
It is recommended that the Geotechnical Engineer be retained to provide a general review of final
design plans and specifications in order to confirm that grading and foundation recommendations
have been interpreted and implemented. In the event that any changes of the proposed project
are planned, the conclusions and recommendations contained in this report should be reviewed
and the report modified or supplemented as necessary.
The Geotechnical Engineer should also be retained to provide services during excavation, grading,
foundation and construction phases of the work. Observation of footing excavations should be
performed prior to placement of reinforcing and concrete to conform that satisfactory bearing
materials are present and is considered a necessary part of continuing geotechnical engineering
services for the project. Construction testing, including field and laboratory evaluation of fill,
backfill, pavement materials, concrete and steel, should be performed to determine whether
applicable project requirements have been met. It would be logical for Empire Laboratories, Inc.
to provide these additional services since we are most qualified to determine consistency of field
conditions with those data used in our analyses.
16
Value Plastics
ELI Project No. 20945013
Terracon
It also offers an opportunity to verify the stability of the excavation slopes during
construction.
Drainage:
• Surface Drainage:
1. Positive drainage should be provided during construction and maintained throughout
the life of the proposed facility. Infiltration of water into utility or foundation
excavations must, be prevented during construction. Planters and other surface
features which could retain water in areas adjacent to the building or pavements
should be sealed or eliminated.
2. In areas where sidewalks or paving do not immediately adjoin the structure, we
recommend that protective slopes be provided with a minimum grade of
approximately 10 percent for at least 10 feet from perimeter walls. Backfill against
footings, exterior walls, and in utility and sprinkler line trenches should be well
compacted and free of all construction debris to reduce the possibility of moisture
infiltration.
3. Downspouts, roof drains or scuppers should discharge into splash blocks or
extensions when the ground surface beneath such features is not protected by
exterior slabs or paving.
4. Sprinkler systems should not be installed within .5 feet of foundation walls.
Landscaped irrigation adjacent to the foundation system should be minimized or
eliminated.
Subsurface Drainage: Free -draining, granular soils containing less than five percent fines
(by weight) passing a No. 200 sieve should be placed adjacent to walls which retain earth.
A drainage system consisting of either weep holes or perforated drain lines (placed near the
base of the wall) should be used to intercept and discharge water which would tend to
saturate the backfill. Where used, drain lines should be embedded in a uniformly graded
filter material and provided with adequate clean -outs for periodic maintenance. An
impervious soil should be used in the upper layer of backfill to reduce the potential for
water infiltration.
15
Value Plastics Terracon
ELI Project No. 20945013
5. If a well defined maximum density curve cannot be generated by impact compaction
in the laboratory for any fill type, engineered fill should be compacted to a minimum
of 80 percent relative density by determined by ASTM D4253, D4254.
6. On -site clay soils should be compacted within a moisture content range of optimum
moisture to 2 percent above optimum below building areas.. Imported granular soils
and on -site clays below paved and open areas should be compacted within a
moisture range of 2 percent below to 2 percent above optimum.
• Compliance: Recommendations for slabs -on -grade, foundations and pavement elements
supported on compacted fills or prepared subgrade depend upon compliance with
"Earthwork" recommendations. To assess compliance, observation and testing should be
performed under the direction of the geotechnical engineer.
• Excavation and Trench Construction: Excavations into the on -site soils will encounter a
variety of conditions. Excavations into the clays can be expected to stand on relatively
steep temporary slopes during construction. However, caving soils may also be
encountered. The individual contractor(s) should be made responsible for designing and
constructing stable, temporary excavations as required to maintain stability of both the
excavation sides and bottom. All excavations should be sloped or shored in the interest
of safety following local, and federal regulations, including current OSHA excavation and
trench safety standards.
The soils to be penetrated by the proposed excavations may vary significantly across the
site. The preliminary soil classifications are based solely on the materials encountered in
widely spaced exploratory test borings. The contractor should verify that similar conditions
exist throughout the proposed area of excavation. If different subsurface conditions are
encountered at the time of construction, the actual conditions should be evaluated to
determine any excavation modifications necessary to maintain safe conditions.
As a safety measure, it is recommended that all vehicles and soil piles be kept to a
minimum lateral distance from the crest of the slope equal to no less than the slope height.
The exposed slope face should be protected against the elements.
The contractor should retain a geotechnical engineer to monitor the soils exposed in all
excavations and provide engineering services for slopes. This will provide an opportunity
to monitor the soil types encountered and to modify the excavation slopes as necessary.
14
Value Plastics
ELI Project No. 20945013
Terracon
No.4 Sieve .......................................... 50-100
No. 200 Sieve ......................... 35 (max)
• Liquid Limit ......................................... 35 (max) .
• Plasticity Index ..............:....................... 15 (max)
• Placement and Compaction:
1. Place and compact fill in horizontal lifts, using equipment and procedures that will
produce recommended moisture contents and densities throughout the lift.
2. Uncompacted fill lifts should not exceed 10 inches loose thickness.
3. No fill should be placed over frozen ground.
4. Materials should be compacted to the following:
Material
On -site soils:
Minimum Percent
Compaction (ASTM D698)
Beneath foundations ......:..................... 95
Beneath slabs ................................ 95
Beneath pavements ............................ 95
Utility trenches below building & paved areas .......... 95
Utility trenches below grassed areas .................. 90
Imported fill:
Beneath foundations ............................ 95
Beneath slabs 95
Beneath pavements ............................ 95
Utility trenches below building & paved areas 95
Utility trenches below grassed areas ................... 90
Aggregate base (beneath slabs) ......................... 95
Miscellaneous backfill................................ 90
13
Value Plastics
ELI Project No. 20945013
Terracon
3. Slabs supporting heavy loads should be underlain by a minimum of 6 inches of
crushed aggregate base course.
• Pavement Subgrade Preparation:
1. The subgrade should be scarified, moistened as required, and recompacted for a
minimum depth of 8 inches prior to placement of fill and pavement materials.
2. On -site clay soils may pump or become unstable or unworkable at high water
contents. Workability may be improved by scarifying and drying. Overexcavation
of wet zones and replacement with granular materials may be necessary.
Lightweight excavation equipment may be required to reduce subgrade pumping.
Use of lime, fly ash, kiln dust, cement or geotextiles could also be considered as a
stabilization technique. Laboratory evaluation is, recommended to determine the
effect of chemical stabilization on subgrade soils prior to construction.
• Fill Materials:
1.. Clean on -site soils or approved imported materials may be used as fill material for
the following:
• general site grading • exterior slab areas
• foundation areas • pavement areas
• interior floor slab areas • foundation backfill
2. Select granular materials should be used as backfill behind walls which retain earth.
3. Frozen soils should not be used as fill or backfill.
4. Imported soils (if required) should conform to the following:
• Gradation (ASTM C136):
percent finer by weight
6"................................................... 100
3.. ................................................ 70-100
12
Value Plastics
ELI Project No. 20945013
• Site Clearing:
Terracon
1. Strip and remove existing vegetation, debris, and other deleterious materials from
proposed building and pavement areas. All exposed surfaces should be free of
mounds and depressions which could prevent uniform compaction.
2. If unexpected fills or underground facilities are encountered during site clearing,
such features should be removed and the excavation thoroughly cleaned prior to
backfill placement and/or construction. All excavations should be observed by the
geotechnical engineer prior to backfill placement.
3. Stripped materials consisting of vegetation and organic materials should be wasted
from the site or used to revegetate exposed slopes after completion of grading
operations. If it is necessary to dispose of organic materials on -site, they should be
placed in non-structural areas and in fill sections not exceeding 5 feet in height.
4. All exposed areas which will receive fill, once properly cleared and benched where
necessary, should be scarified to a minimum depth of ten inches, conditioned to
near optimum moisture content, and compacted.
• Excavation:
1. It is anticipated that excavations for the proposed construction can be accomplished
with conventional earthmoving equipment.
2. Depending upon depth of excavation and seasonal conditions, groundwater may be
encountered in excavations on the site. Pumping from sumps may be utilized to
control water within excavations. Well points may be required for significant
groundwater flow, or where excavations penetrate groundwater to a significant
depth.
• Slab Subarade Preparation:
1. Where existing fill and clay soils will support floor slab, the soils should be scarified,
moisture -conditioned and compacted to a minimum depth of 12 inches.
2. A minimum 4-inch layer of clean -graded gravel should be placed beneath slabs
11
Terracon
Value Plastics
ELI Project No. 20945013
Future performance of pavements constructed on the clay soils at this site will be dependent upon
several factors, including:
• maintaining stable moisture content of the subgrade soils; and,
• providing for a planned program of preventative maintenance.
Since the clay soils on the site have shrink/swell characteristics, pavements could crack in the
future primarily because of expansion of the soils when subjected to an increase in moisture
content to the subgrade. The cracking, while not desirable, does not necessarily constitute
structural failure of the pavement.
The performance of all pavements, but in particular the recommended asphalt sections, can be
enhanced by minimizing excess moisture which can reach the subgrade soils. The following
recommendations should be considered at minimum:
• Site grading at a minimum 2% grade away from the pavements;
• Compaction of any utility trenches for lands aped areas to the same criteria as the
pavement subgrade;
• Sealing all landscaped areas in or adjacent to pavements to minimize or prevent
moisture migration to subgrade soils;
• Placing compacted backfill against the exterior side of curb and gutter; and,
• Placing curb, gutter and/or sidewalk directly on subgrade soils without the use of
base course materials.
Earthwork:
• General Considerations: The conclusions contained in this report for the proposed
construction are contingent upon compliance with recommendations presented in this
section.
Although fills or underground facilities, such as septic tanks, cesspools, basements, and/or
utilities, were not observed during site reconnaissance, such features might be encountered
during construction.
10
Value Plastics Terracon
ELI Project No. 20945013
The asphalt materials should be placed in maximum 3-inch lifts and should be compacted to a
minimum of 95% Hveem density (ASTM D1561.).
Plant -mixed bituminous base course should be composed of a mixture of aggregate, filler and
additives if required and approved bituminous material. The bituminous base should conform to
an approved mix design stating the Hveem properties, optimum asphalt content, job mix formula,
and recommended mixing and placing temperatures. Aggregate used in plant -mixed bituminous
base course should meet a particular gradation. Use of aggregates meeting Colorado Department
of Transforation Grading G or C specifications is recommended. The. mix design should be
submitted prior to construction to verify it adequacy. The asphalt material should be placed in
maximum 3-inch lifts, and should be compacted to a minimum of 95% Hveem density (ASTM
D1561).
Where rigid pavements are used, the concrete should be obtained from an approved mix design
with the following minimum properties:
• Compressive Strength @ 28 days ................... 3750 psi minimum
• Modulus of Rupture @ 28 days ........................ 650 minimum
• Strength Requirements ................................ ASTM C94
• Minimum Cement Content ......................... 5.5 sacks/cu. yd.
• Cement Type .................................... Type I Portland
• Entrained Air Content 6 to 8%
• Concrete Aggregate ................. ASTM C33 and CDOT Section 703
• Aggregate Size ................................. 1 inch maximum
• Maximum Water Content 0.49 lb/lb of cement
• Maximum Allowable Slump ............................... 4 inches
Concrete should be deposited by truck mixers or agitators and placed a maximum of 90 minutes
from time the water is added to the mix. Other specifications outlined by the Colorado
Department of Transportation should be followed.
Longitudinal and transverse joints should be provided as needed in concrete pavements for
expansion/contraction and isolation. The location and extent of joints should be based upon the
final pavement geometry and should be placed (in feet), at roughly twice the slab thickness (in
inches), on center in either direction. Sawed joints should be cut within 24-hours of concrete
placement, and should be a minimum of 25% of slab thickness plus 1/4 inch. All joints should
be sealed to prevent entry of foreign material and dowelled where necessary for load transfer.
Where dowels cannot be used at joints accessible to wheel loads, pavement thickness should be
increased by 25 percent at the joints and tapered to regular thickness in 5 feet.
7
Terracon
Value Plastics
ELI Project No. 20945013
Recommended Pavement Section, Thickness (inches)
Asphalt
Aggregate
Plant -Mixed
Portland
Traffic Area
Alternative
Concrete
Base
Bituminous
Cement
Total
Surface
Course
Base
Concrete
A
3"
6"
9^
Automobile
Parking
B
2„
2 Y2 „
4 �Y2 „
C
5..
5"
Parking and
A
3"
10"
13"
Driveway
B
2"
4 %2 "
6 y2 ^
Areas
Each alternative should be investigated with respect to current material availability and economic
conditions. In view of the subgrade soil conditions and projected traffic, either full -depth asphalt
or rigid concrete pavement sections should be considered in areas of main traffic corridors, drive
bays or truck access. Rigid concrete pavement is recommended at the location of dumpsters
where trash trucks will park and load.
Aggregate base course (if used on the site) should consist of a blend of sand and gravel which
meets strict specifications for quality and gradation. Use of materials meeting Colorado
Department of Transportation Class 5 or 6 specifications is recommended.
In addition, the base course material should be moisture stable. Moisture stability is determined
by R-value testing which shows a maximum 12 point difference in R-values between exudation
pressures of 300 psi and 100 psi. Aggregate base course material should be tested to determined
compliance with these specifications prior to importation to the site.
Aggregate base course should be placed in lifts not exceeding six inches and should be compacted
to a minimum of 95% Standard Proctor Density (ASTM D698), within a moisture content range
of 2 percent below to 2 percent above optimum. Where base course thickness exceeds 6 inches,
the material should be placed and compacted in two or more lifts of equal thickness.
Asphalt concrete should be obtained from an approved mix design stating the Marshall or Hveem
properties, optimum asphalt content, job mix formula, and recommended mixing and placing
temperatures. Aggregate used inasphalt concrete should meet a particular gradation. Use of
materials meeting Colorado Department of Transportation Grading .0 or CX specification is
recommended. The mix design should be submitted prior to construction to verify its adequacy.
L
Value Plastics Terracon
ELI Project No. 20945013
Additional floor slab design and construction recommendations are as follows:
• Positive separations and/or isolation joints should be provided between slabs and
all foundations, columns or utility lines to allow independent movement.
• Contraction joints should be provided in slabs to control the location and extent of
cracking. Maximum joint spacing of 15 to 20 feet in each direction is
recommended.
• Interior trench backf ill paced beneath slabs should be compacted in accordance with
recommended specifications outlined below.
• In areas subjected to normal loading, a minimum 4-inch layer of clean -graded gravel
should be placed beneath interior slabs. For heavy loading, 6 inches of crushed
aggregate base course should be used.
• If moisture sensitive floor coverings are used on interior slabs, consideration should
be given to the use of barriers to minimizepotential vapor rise through the slab.
• Floor slabs should not be constructed on frozen subgrade.
• Other design and construction considerations, as outlined in the ACI Design Manual,
Section 302.1 R are recommended.
Pavement Design and Construction: The required total thickness for the pavement structure is
dependent primarily upon the foundation soil or subgrade and upon traffic conditions. Based on
the soil conditions encountered at the site and the type and volume of traffic and using a group
index of 11 as the criterion for pavement design, the following minimum pavement thicknesses
are recommended:
7
Terracon
Value Plastics
ELI Project No. 20945013
Foundation excavations should be observed by the geotechnical engineer. If the soil conditions
encountered differ significantly from those presented in this report, supplemental recommendations
will be required.
Lateral Earth Pressures: For soils above any free water surface, recommended equivalent fluid
pressures for unrestrained foundation elements are:
• Active:
Cohesive soil backfill (on -site clay) .......................... 45 psf/ft
L
• Passive:
Cohesive soil backfill (on -site clay) ......................... 340 psf/ft
Where the design includes restrained elements, the following equivalent fluid pressures are
recommended:
• At rest:
Cohesive soil backfill (on -site clay) .......................... 65 psf/ft
The lateral earth pressures herein are not applicable for submerged soils. Additional
recommendations may be necessary if such conditions are to be included in the design.
Fill against grade beams and retaining walls should be compacted to densities specified in
"Earthwork". Compaction of. each lift adjacent to walls should be accomplished with hand -
operated tampers or other lightweight compactors. Overcompaction may cause excessive lateral
earth pressures which could result in wall movement.
Floor Slab Design and Construction: Low to moderately expansive soils, natural soils or
engineered fill will support the floor slab. Some differential movement of a slab -on -grade floor
system is possible should the subgrade soils become elevated in moisture content. Such
movements are considered within general tolerance for normal slab -on -grade construction. To
reduce any potential slab movements, the subgrade soils should be prepared as outlined in the
earthwork section of this report.
For structural design of concrete slabs -on -grade, a modulus of subgrade reaction to 100 pounds
per cubic inch (pci) may be used for floors supported on existing or engineered fill consisting of
on -site soils.
n
Terracon
Value Plastics
ELI Project No. 20945013
variations in the engineering properties of the on -site soils, foundation bearing levels, structural
loads, and possible final grades, the following foundation systems were evaluated for use on the
site:
• spread footings and/or grade beams bearing on undisturbed soils; and,
• spread footings and/or grade beams bearing on engineered fill.
Slab -on -grade construction is considered acceptable for use when subgrade soils consist of the
on -site clays, provided that design and construction recommendations are followed.
Foundation Systems: Due to the presence of low- to moderate -swelling soils on the site, spread
footing and/or grade beam foundations bearing upon undisturbed subsoils and/or engineered fill
are recommended for support for the proposed structure. The footings may be designed for a
maximum bearing pressure of 2,000 psf. In addition, the footings should be sized to maintain a
minimum dead -load pressure of 500 psf. Exterior footings should be placed a minimum of 30
inches below finished grade for frost protection. Interior footings should bear_a minimum of 12
inches below finished grade
Existing fill on the site should not be used for support of foundations without removal and
recompaction.
Finished grade is the lowest adjacent garde forperimeter footings and floor level for. interior
footings. The design bearing capacities apply to dead loads plus design live load conditions. The
design bearing capacity may be increased by one-third when considering total loads that include
wind or seismic conditions.
Footings should be proportioned to minimize differential foundation movement. Proportioning on
the basis of equal total settlement is recommended; however, proportioning to relative constant
dead -load pressure will also reduce differential settlement between adjacent footings. Total or
differential settlement resulting from the assumed structural loads are estimated to be on the order
of 3/4 inch or less, provided that foundations are constructed as recommended.
Additional foundation movements could occur if water from any source infiltrates the foundation
soils; therefore, proper drainage should be provided in the final design and during construction.
Foundations and masonry walls should be reinforced as necessary to reduce the potential for
distress caused by differential foundation movement. The use of joints at openings or other
discontinuities in masonry walls is recommended.
Terracon
Value Plastics
ELI Project No. 20945013
• Fill: The area tested is overlain by a Y2 to 1'/2 foot layer of fill material. The fill consists
of a mixture of lean clay with sand, sandy lean clay and gravel. It is not known if the fill
has been uniformly or properly compacted. The upper 6 inches of the fill has been
penetrated by root growth and organic matter.
• Lean Clay With Sand: This stratum underlies the fill and extends beyond the depths
explored. The lean clay contains varying amounts of sand, is moist, medium to hard.
Laboratory Test Results: Laboratory test results indicate that the clay subsoils vary from medium
to hard in consistency and have low to moderate expansive potential and moderate bearing
characteristics.
Groundwater Conditions: Groundwater was not encountered in any of the test boring except
Boring 4 at the time of field exploration, nor when checked one day after drilling. Groundwater
was encountered in Boring 4 at a depth of 14Yz feet. When checked one day after drilling,
groundwater was measured at depths of 14 feet below the surface in Boring 4. Boring 5 was
caved at a depth of 6 feet when checked one day after drilling. These observations represent only
current groundwater conditions, and may not be indicative of other times, or at other locations.
Groundwater levels can be expected to fluctuate with varying seasonal and weather conditions.
Based upon review of U.S. Geological Survey maps (ZHillier, et al, 1983), regional groundwater
is expected to be encountered in unconsolidated alluvial deposits on the site, at depths ranging
from 5 to 10 feet below. the existing ground surface at the project site.
Fluctuations in groundwater levels can best be determined by implementation of a groundwater
monitoring plan. Such a plan would include installation of groundwater monitoring wells, and
periodic measurement of groundwater levels over a sufficient period of time.
The possibility of groundwater fluctuations should be considered when developing design and
construction plans for the project.
CONCLUSIONS AND RECOMMENDATIONS
Site Development Considerations: The site is suitable for the proposed construction. Potentially
expansive soils will require particular attention in the design and construction. Because of
'Hillier, Donald E.; Schneider, Paul A., Jr.; and Hutchinson, E. Carter, 1983, Depth to Water Table f1979) in the Boulder -Fort
Collins -Greeley Area, Front Range Urban Corridor Colorado, United States Geological Survey, Map 1-855-I.
4
Value Plastics
ELI Project No. 20945013
Terracon
The significance and purpose of each laboratory test is described in Appendix C. Laboratory test
results are presented in Appendix B, and were used for the geotechnical engineering analyses, and
the development of foundation and earthwork recommendations. All laboratory tests were
performed in general accordance with the applicable ASTM, local or other accepted standards.
SITE CONDITIONS
The site consists of a vacant area currently vegetated with grass and weeds. A few trees are
growing in the southwest corner of the property. The site is relatively flat with generally poor
drainage. The property is bordered on the north by Vermont, on the east by Timberline Road, on
the south by Danfield Court and on the west by Eastbrook Drive. Existing office buildings are
located adjacent to the site.
SUBSURFACE CONDITIONS
Geology: The project area is located within the Colorado Piedmont section of the Great Plains
physiographic province. The Colorado Piedmont, formed during Late Tertiary and Early quaternary
time (approximately 2,000,000 years ago),. is a broad, erosional trench which separates the
Southern Rocky Mountains from the High Plains. Structurally, the site lies along the western flank
of the. Denver Basin. During the Late Mesozoic and Early Cenozoic Periods (approximately
70,000,000 years ago), intense tectonic activity occurred, causing the uplifting of the Front Range
and associated downwarping .of the Denver Basin to the east. Relatively flat uplands and broad
valleys characterize the present-day topography of the, Colorado Piedmont in this region. The site
is underlain by the Cretaceous Pierre Formation. It is estimated the Pierre shale underlies the site
at depths of approximately 20 to 25 feet below existing grade. The Pierre formation is overlain
by residual and alluvial soils of Pleistocene and/or Recent Age.
Mapping completed by the Colorado Geological Survey ('Hart, 1972), indicates the site in an area
of "Moderate Swell Potential". Potentially expansive materials mapped in this area include
bedrock, weathered bedrock and colluvium (surficial units).
Soil Conditions: As presented on the Logs of Boring, the subsurface soils were encountered in
order of increasing .depths as follow:
'Hart, Stephen S., 1972, Potentially Swelling Sal and Rock in the Front Range Urban Corridor, Colorado, Colorado
Geological Survey, Environmental Geology No. 7. .
3
GEOTECHNICAL ENGINEERING REPORT Terracon
VALUE PLASTICS ADDITION
NORTHWEST CORNER DANFIELD COURT & TIMBERLINE ROAD
FORT COLLINS, COLORADO
ELI PROJECT NO. 20945013
FEBRUARY 17, 1994
INTRODUCTION
This report contains the results of our geotechnical engineering exploration for the proposed
project to be located adjacent to the existing Value Plastics facility located between Eastbrook
Drive and Timberline Road north of Danfield Court in east Fort Collins, Colorado. The site is
located in the Southeast 1 /4 of Section 31, Township 7 North, 68 West of the 6th Principal
Meridian.
The purpose of these services is to provide information and geotechnical engineering
recommendations relative to:
• subsurface soil conditions
• groundwater conditions
• foundation design and construction
• lateral earth pressures
• floor slab design and construction
• pavement design and construction
• earthwork
• drainage
The conclusions and recommendations contained in this report are based upon the results of field
and laboratory testing, engineering analyses, and experience with similar soil and structural
conditions.
PROPOSED CONSTRUCTION
The proposed construction as we understand it will be a 45,000 square foot single -story, slab -on -
grade building. Parking areas are planned adjacent to the west and south sides of the structure.
SITE EXPLORATION
The scope of . the services performed for this project included site reconnaissance by an
engineering geologist, a subsurface exploration program, laboratory testing and engineering
analyses.
Value Plastics
ELI Project No. 20945013
TABLE OF CONTENTS (Cont'd)
Terracon
APPENDIX A
Figure No.
SITE PLAN 1
Logs of Borings ......................................... Al thru A10
APPENDIX B
Swell -Consolidation Test ............ ......................... B1 thru B2
Summary of Test Results ......................................... B3
APPENDIX C: GENERAL NOTES
Drilling & Exploration ............................................
C1
Unified Soil Classification
C2
.........................................
Laboratory Testing, Significance and Purpose ..........................
:.. C3
Report Terminology .............................................
C4
APPENDIX D
Recommended Preventative Maintenance -Asphalt Concrete Pavements ......... D1
Recommended Preventative Maintenance -Jointed Concrete Pavements ......... D2
Value Plastics
ELI Project No. 20945013
TABLE OF CONTENTS
Terracon
Page No.
Letter of Transmittal.................................................... ii
INTRODUCTION..................................................... 1
PROPOSED CONSTRUCTION ........................................... 1
SITE EXPLORATION................................................... 1
Field Exploration ............................................... 2
Laboratory Testing .............................................. 2
SITE CONDITIONS ................................................... 3
SUBSURFACE CONDITIONS ............................................ 3
Geology..................................................... 3
Soil Conditions ................................................. 3
Laboratory Test Results .......................................... 4
Groundwater Conditions .......................................... 4
CONCLUSIONS AND RECOMMENDATIONS ................................. 4
Site Development Considerations .................................... 4
Foundation Systems ............................................. 5
Lateral Earth Pressures ........................................... 6
Floor Slab Design and Construction .................................. 6
Pavement Design and Construction ................................... 7
Earthwork..:................................................ 10
General Considerations ................................... 10
Site Clearing ............................................ 11
Excavation............................................. 11
Slab Subgrade Preparation ................................... 11
Pavement Subgrade Preparation ............................... 12
Fill Materials ............................................ 12
Placement and Compaction .. 13
Compliance ............................................. 14
Excavation and Trench Construction ............................ 14
Drainage........: ........................................... 15
SurfaceDrainage ......................................... 15.
Subsurface Drainage ....................................... 15
Additional Design and Construction Considerations ...................... 16
Exterior Slab Design and Construction .......................... 16
Corrosion Protection ....................................... 16
GENERAL COMMENTS ............................................... 16
0
Value Plastics
ELI Project No. 20945013
Terracon
We have appreciated being of service to you in the geotechnical engineering phase of this project,
and are prepared to assist you during the construction phases as well. If you have any questions
concerning this report or any of our testing, inspection, design and consulting services, please do
not hesitate to contact us.
Sincerely,
EMPIRE LABORATORIES, INC.
A Division of The Terracon Companies, Inc.
Neil R. JShereba .
Senior Engineering Geologist
Reviewed by:
Chester C. Smith, P.E.
Division Manager
NRS/CCS/cic
2 5
`
-._=�
t
ER (`
_,.
V, . JLr A
Copies to: Addressee (2)
The Neenan Company - Mr. Steve Steinbicker (1)
l;
Empire Laboratories, Inc.
A Division of The Terracon Companies, Inc.
PO. Box 503 • 301 No. Hower
Fort Collins, Colorado 80522
(303) 484-0359
FAX No. (303) 484-0454
Chester C. Smith, P.E.
Neil R. Sherrod, C.PG.
February 17, 1994
Value Plastics
3350 Eastbrook Drive
Fort Collins, Colorado 80525
Attn: Mr. Kent Sampson
Re: Geotechnical Engineering Report, Value Plastics Addition
Northwest Corner Danfield Court & Timberline Road
Fort Collins, Colorado
ELI Project No. 20945013
Empire Laboratories, Inc. (ELI) has completed a geotechnical engineering exploration for the
proposed project to be located at Danfield Court between Eastbrook Drive and Timberline Road
in east Fort Collins, Colorado. This study was performed in general accordance with our proposal
number.D2094031 dated January 25, 1994. .
The results of our engineering study, including the boring location diagram, laboratory test results,
test boring records, and the geotechnical recommendations needed to aid in the design and
construction of foundations and other earth connected phases of this project are attached.
The subsurface exploration indicated conditions which are typical of soils commonly found in the
east Fort Collins area. The subsurface soils at the site consisted of lean clay with sand. The
information obtained by the results of field exploration and laboratory testing completed for this
study indicates that the soils at the site have low to moderate expansive potential and moderate
bearing characteristics.
Based on the geotechnical engineering analyses, subsurface exploration and laboratory test results,
we recommend that the proposed building be supported on a spread footing and/or grade beam
foundation system. Slab -on -grade may be utilized for the interior floor system provided that care
is taken in the placement and compaction of the subgrade soil.
Other design and construction details, based upon geotechnical conditions, are presented in the
report.
Offices of The Terracon Companies, Inc. Geotechnical, Environmental and Materials Engineers
Arizona: Tucson ■ Colorado: Colorado Springs, Denver, Ft. Collins. Greeley, Longmont ■ Idaho: Boise ■ Illinois: Bloomington,
Chicago. Rock Island ■ Iowa: Cedar falls. Cedar Rapids. Davenport. Des Moines, Storm Lake ■ Kansas. Lenexa. Topeka.
Wichita ■ Minnesota: St. Paul ■ Missouri: Kansas City ■ Nebraska: Lincoln, Omaha ■ Nevada: Las Vegas
■ Oklahoma: Oklahoma City. Tulsa ■ Texas: Dallas ■ Utah: Salt Lake City ■ Wyoming: Cheyenne
QUALITY ENGINEERING SINCE 1965
S�
I
GEOTECHNICAL ENGINEERING REPORT
VALUE PLASTICS ADDITION
NORTHWEST CORNER DANFIELD COURT & TIMBERLINE ROAD
FORT COLLINS, COLORADO
ELI PROJECT NO. 20945013
Prepared for:
VALUE PLASTICS
3350 EASTBROOK DRIVE
FORT COLLINS, COLORADO 80525
ATTN: MR. KENT SAMPSON
Empire Laboratories, Inc.
A Division of the TerracQn Companies, Inc..