Neighborhood Information Meeting Minutes
for
COTTONWOOD RIDGE
May 5, 1994
Applicant: Eric Thayer
31741 RCR #35
Steamboat Springs, CO 80487
City Planner: Steve Olt
The applicant, Eric Thayer, has expressed an interest in developing a single family residential
project on a vacant parcel of land, approximately 34 acres in size, located south of West
Harmony Road on the west side of South Shields Street.
The purpose of this meeting was to introduce Mr. Thayer to the affected property owners and
other potentially affected interests in attendance and enable them to: ask questions, express
concerns or voice support for the development proposal. The following questions, concerns,
comments and responses were expressed at the meeting:
1. Question: Will the ditches be left open or will they be covered?
Answer: That is yet to be decided.
2. Question: The area next to the lots at the southwest corner of the property is to be
open space?
Answer: Yes, that is the plan. There is a sensitive area that will probably be
identified by the Natural Resources Department.
3. Question: Where will the bike path go?
Answer: It will be located along the alignment of the PV&LC canal and connect to
the proposed alignment in Westbury to the north.
4. Question: How wide of an easement does the PV&LC canal have?
Answer: We think it is about 50 feet wide in the Westbury PUD and it is probably
the same on this property.
281 North College Avenue • P.O. Box 580 Fort Collins, CO 80522-0580 • (303) 221-6750
FAX (303) 221-6378 TDD (303) 224-6002
SCHOOL PROJECTIONS
PROPOSAL: COTTONWOOD RIDGE PUD-Preliminary
DESCRIPTION: 69 single family homes on 34.3 acres
DENSITY:
General Population
69 (units) x 3.5
2.01 du/acre
(persons/unit) = 241.5
SchoolAge Population
Elementary - 69 (units) x .450
Junior High - 69 (units) x .210
Senior High - 69 (units) x .185
Affected Schools
McGraw Elementary
Webber Junior High
Rocky Mountain Senior High
(pupils/unit) = 31
(pupils/unit) = 14.5
(pupils/unit) = 12.77
Design
CapacitEnrollment
568 449
900 977
1312 1404
•� .r � i I I I I I I I i 1 1 I I I I
Y
EF
XIAB
II
I
¢NL N.Qi
,N VICMY wlv
I
—
I
.dam
Ln-
i
i
-
k`*�a�'raa®l
\ �b
Miu.W.MO�.W Oslie[esvm/®.1W •
w•... •Iwlm•:aan mem nF m.e
PRELMMRY LAYOUT • �NO•NIm Im
COTTONWOOD RDGE • s"a`^e
SUM" SOLAR LAYOUT
JLLY L IM
TmAyst
D..• R
COTTONWOOD RIDGE
r • . rr FLAT - SITE PLAN
ET DESIGNS
m Iev e
mama swmm M roslswe
•¢TIY 1 6 6 .66TIO
:ia]LVA .` to
Commurnry Planning and Environmental IZA, . -ices
Planning Department
City of Fort Collins
MEMORANDUM
To: Planning and Zoning Board Members
From: Steve Olt, Project Planner
Rob Wilkinson, Natural Resources Division F-;40
Ref: Cottonwood Ridge Subdivision - Preliminary, #31-94
Date: July 25, 1994
Staff is recommending 4 conditions of preliminary approval (in
addition to the 3 conditions as stated in the Staff Report to the
Planning and Zoning Board dated 7/25/94) stating that:
1. The trees on lots 10, 11, 66, 67, 68, and 69 need to be
conserved as a grove to the extent possible to protect
wildlife habitat values. The applicant needs to work with the
City Natural Resource Division to delineate building sites
and develop appropriate language for notes on the Final
Subdivision Plat/Site Plan to assure acceptable conservation
of existing trees or mitigation of important trees removed as
a result of project development.
2. The applicant must provide documentation from the wetland
consultant that the wetland boundaries shown on the Final
Subdivision Plat/Site Plan accurately represent the existing
wetland boundaries as delineated in the field.
3. Issues associated with the impacts to the wetlands as a result
of the development of lots 8 and 9, parcel A, and the
management of water flow through the Applewood lateral, need
to be addressed. The applicant will work with the City Natural
Resource Division to develop acceptable wetland conservation
or mitigation measures prior to approval of the Final
Subdivision Plat/Site Plan.
4. The approval of the Preliminary Subdivision Plan is contingent
on the results of the rare plant survey. If the Ute Ladies
Tresses orchid is found on the property, modifications of the
site plan may be required to protect critical habitat.
281 North College Avenue • P.O. Box 580 Fort Collins, CO 80522-0580 • (303) 221-6750
FAX (303) 221-6378 TDD (303) 224-6002
Cottonwood Ridge Subdivision - Preliminary, #31-94
July 25, 1994 P & Z Meeting
Page 5
Findings of Fact/Conclusions:
In evaluating the request for the Cottonwood Ridge Subdivision -
Preliminary, staff makes the following findings of fact:
1. As a standard subdivision, this proposal is subject to all the
rules and regulations as set forth in Article III., Sections
29-146 through 29-148 and Article V., Sections 29-623 through
29-643 of the City of Fort Collins Zoning, Annexation and
Development of Land Regulations.
2. This development is in conformance with the applicable City
transportation policies.
3. A total of 29 of 44 lots that are subject to the requirements
of the City's Solar Orientation Ordinance are in compliance
with the ordinance. This equals 66%, exceeding the minimum 65%
requirement.
4. The applicant has not adequately considered and addressed
issues relating to the storm drainage for this development.
5. A reverter clause relating to bicycle/pedestrian trails is
inappropriate.
RECOMMENDATION:
Staff recommends approval of the Cottonwood Ridge Subdivision -
Preliminary, #31-94 with the following conditions:
1. The developer is responsible for the preparation of a
stability study of the Pleasant Valley & Lake Canal and ravine
area located in the southwesterly portion of the proposed
development. This study must be submitted for review and
acceptance by the City and the Pleasant Valley & Lake Canal
company prior to approval by the Planning and Zoning Board of
a final plan for Cottonwood Ridge Subdivision.
2. The developer must provide sufficient information to the City
to enable the Stormwater Utility to evaluate the effects of
potential increased stormwater runoff from this development
into the Pleasant Valley & Lake Canal. This information must
be submitted for review and acceptance by the City and the
Pleasant Valley & Lake Canal Company prior to approval by the
Planning and Zoning Board of a final plan for the Cottonwood
Ridge Subdivision.
3. The statement referencing an expiration date of the year 2004
for the bicycle/pedestrian trail easements (fourth sentence in
Note 3 on the Cottonwood Ridge Plat -Site Plan) must be
eliminated from the plan.
Cottonwood Ridge Subdivision - Preliminary, #31-94
July 25, 1994 P & Z Meeting
Page 4
a series of streets and cul-de-sacs, internal to the site and
designed as local streets, that will provide direct access to the
lots and homes. A second point of access will be on a shared street
(Westbury Drive) with the Westbury P.U.D. directly to the north of
this development. This street right-of-way will be on the Westbury
property but contiguous to Cottonwood Ridge, thereby enabling a
local street in this development to connect to Westbury Drive. The
developer of Westbury P.U.D. is providing an access easement on his
property to enable this street connection to be made in the event
that this portion of Cottonwood Ridge were to develop prior to any
filing in Westbury P.U.D. that would construct this portion of
Westbury Drive. The City's Transportation Department has reviewed
this proposal and considers this development to be feasible from a
traffic engineering point of view.
6. Storm Drainage:
The City's Stormwater Utility has reviewed this proposal and has
expressed concerns about potential erosion and stability problems
associated with the Pleasant Valley & Lake Canal's outfall and its
interface with the "natural" ravine area in the southwest portion
of the property. The developer of the Southridge Greens project, to
the east of South Lemay Avenue, had an agreement with the ditch
company to install a weir to divert water into the drainage system
to provide water for irrigation of the golf course in that
development. The agreement was implemented for two years, in 1984
and 1985, and during this time the stability problems were created.
A stability study, prepared by a qualified engineer, must be part
of the Final Subdivision submittal to the City by the developer of
Cottonwood Ridge Subdivision that identifies the impacts on the
ravine and how the instability and erosion could effect the lot
configuration of this development. Based on the stability study, it
may be necessary to phase this development.
The drainage report submitted to the Stormwater Utility does not
adequately address how much additional stormwater runoff from this
development will flow into the Pleasant Valley & Lake Canal. This
information will also be required with the submittal of the Final
Subdivision plans.
7. Resource Protection:
The ravine area at the south end of the Pleasant Valley & Lake
Canal, bounded by Lots 9-12 and 66-68, will be included in a
conservation & drainage easement and kept, essentially, in its
present form.
Cottonwood Ridge Subdivision - Preliminary, #31-94
July 25, 1994 P & Z Meeting
Page 3
Solar orientation:
There are 44 of the proposed 69 lots that are less than 15,000
square feet in size. These 44 lots are subject to the City's Solar
Orientation Ordinance that requires a minimum of 65% of these lots
to comply with at least one of the definitions of a solar lot in
the ordinance. A total of 29 of the 44 lots, equalling 66%, are in
compliance.
Bicycle/Pedestrian Trails:
The developer will provide 10' wide bicycle/pedestrian easements
along the east 1/2 of the Pleasant Valley & Lake Canal easement and
in the Applewood lateral easement. The developer has included a
statement on the Plat -Site Plan that says "If the City fails to
construct a suitable path by the year 2004 the ownership of the
easement will revert to the Homeowner's Association". Staff is not
in agreement with an expiration date on the trail easements and is
recommending the removal of this Subdivision Plat note.
4. Neighborhood Compatibility:
A neighborhood information meeting was held on May 5, 1994 to
discuss this development proposal. There were nine people in
attendance, including the property owners/developers, affected
property owners in the surrounding area, and other potentially
affected interests. Primary concerns expressed centered around:
* the impacts of the stormwater from this development along
the west side of South Shields Street and how they will
affect the Applewood irrigation ditch.
* how the Applewood irrigation ditch and Trilby irrigation
lateral will be treated and protected.
* the treatment of the "natural" areas in and around the
ravine in the southwest portion of the site.
The impacts of the stormwater on the Applewood ditch are being
addressed with the developer's drainage report. The Applewood ditch
will be piped for its entire length through this development. The
Trilby lateral will remain as an open ditch. The natural areas in
and around the ravine will be included in a conservation & drainage
easement and kept, essentially, in their present form. A copy of
the minutes of the meeting are attached to this memo.
5. Transportation:
This development will gain primary access from South Shields Street
at a point near the southeast corner of the property. There will be
Cottonwood Ridge
July 25, 1994 P
Page 2
COMMENTS:
1. Background•
Subdivision - Preliminary, #31-94
& Z Meeting
The surrounding zoning and land uses are as follows:
N: RLP; planned single family residential (Westbury P.U.D.)
S: RLP; existing single family residential (Chelsea Ridge, The
Ridge)
E: RLP; existing single family residential (Clarendon Hills)
W: RLP; existing single family residential (The Ridge)
This property was annexed into the City with the Ridge Annexation
in April, 1989.
2. Land Use•
This is a request for preliminary subdivision approval for 69
single family residential lots on 34.3 acres located on the west
side of South Shields Street approximately one -quarter south of
West Harmony Road. The gross residential density is 2.01 dwelling
units per acre. As a standard subdivision, this proposal is subject
to all the rules and regulations as set forth in Article III.,
Sections 29-146 through 29-148 and Article V., Sections 29-623
through 29-643 of the City of Fort Collins Zoning. Annexation and
Development of Land Regulations.
3. Design•
Landscaping:
The developer will provide street trees at 40' on -center along the
side lot lines, rear lot lines, and detention pond fronting on
South Shields Street. The developer is considering using a
combination of plant materials, berming, and fencing as buffering
along the rear and side lines of the double -frontage lots adjacent
to South Shields Street. The solutions will be determined with the
Final P.U.D.
Fencing:
Fences adjacent to open spaces, greenbelts, and irrigation ditches
will be limited to 6' in height, with the top 2' being an open
(lattice style) design. The developer is considering using some
fencing along the rear and side lines of the double -frontage lots
adjacent to South Shields Street. The design of this fencing has
not yet been determined.
ITEM NO. 2
MEETING DATE 7-25-94
STAFF Steve Olt
PLANNING AND ZONING BOARD
STAFF REPORT
PROJECT: Cottonwood Ridge Subdivision - Preliminary, #31-94
APPLICANT: Eric Thayer
ET Designs
31741 RCR #35
Steamboat Springs, CO. 80487
OWNER: Sanford Thayer, As Trustee
1827 Michael Lane
Fort Collins, CO. 80526
PROJECT DESCRIPTION:
This is a request for preliminary approval for 69 single family
residential lots on 34.3 acres located on the west side of South
Shields Street approximately one -quarter mile south of West Harmony
Road. The property is zoned RLP, Low Density Planned Residential.
RECOMMENDATION: Approval with conditions
EXECUTIVE SUMMARY:
This request for Preliminary Subdivision approval:
* Is subject to all the rules and regulations as set forth
in Article III., Sections 29-146 through 29-148 and
Article V., Sections 29-623 through 29-643 of the City of
Fort Collins Zoninq, Annexation and Development_,of Land
Regulations;
* Complies with the City's adopted Solar Orientation
Ordinance;
* Is in conformance with the applicable City transportation
policies.
COMMUNITY PLANNING AND ENVIRONMENTAL SERVICES 281 N. College Ave. P.O. Box 580 Fort Collins, CO 80522-0580 (303) 221-6750
PLANNING DEPARTMENT
Cottonwood Ridge
Neighborhood Information Meeting
Page 3
14. Comment:
15. Question:
Answer:
16. Question:
Answer:
17. Question:
Answer:
18. Question:
Answer:
I am fairly certain that the Applewood Board would want our irrigation
ditch put into a pipe through this property.
Do you have any idea about how much your lots will sell for?
No, we do not know yet.
Will you be doing this in phases?
Yes, we probably will be doing this development in three phases.
Do you know how big your homes will be?
We will not be building the homes, so I can't speak to that tonight.
Do you know the time frame you are projecting for development?
Hopefully, we can be through the review process and be under
construction sometime this fall (1994).
19. Comment: We are all going to miss the horses on this property.
Cottonwood Ridge
Neighborhood Information Meeting
Page 2
5. Comment: The water on this property now drains from this property and flows along
the west side of Shields Street. There are concerns about the effects this
drainage water will have on our irrigation ditch (Applewood).
6. Comment: The City or the County should have some responsibility for the
stormwater along the west side of South Shields Street.
7. Question: Could you speak to the covenants that you are planning for this
development?
Answer: We will have covenants, but they are not developed yet.
8. Question: What do you have in mind for the Applewood Ditch? How do you plan
to handle the ditch with your development?
Answer: We have not yet resolved this question. Chelsea Ridge put this ditch in
a pipe.
9. Question: What is your opinion as to how we should handle it?
(developer)
Answer: I worry about the ditch being piped and clogging up on us. The
(citizen) culvert at Shields Street is a problem. We just need to keep the
debris out of the ditch/pipe. An open ditch would be easier for us to keep
clean.
10. Question:
Answer:
11. Comment:
12. Comment:
13. Comment:
Will you be the primary developer & contact? [A: Yes.] Will you have
control over the siting of homes & preservation of trees?
Yes, it is possible to deal with the siting in our architectural controls.
The areas around the Trilby Lateral are of significant concern due to the
stands of trees and terrain.
Ridge Board supports this larger lot proposal and the subdivision concept
vs. a P.U.D.
This plan is good if you can do it.