HomeMy WebLinkAboutHARMONY SAFEWAY MARKETPLACE, LOT 6, FUEL FACILITY - PDP - 33-94F - CORRESPONDENCE - RESPONSE TO STAFF REVIEW COMMENTS (5)General Comments:
1. The existing Transfort bus pad is extended to eliminate any conflict at the intersection. Please see
above Planning Comments, Item 1
2. Please see Item 4 below (Utility Plan).
3. Advisory Comment — no action required at this time.
Utility Plan:
1. Plans are revised as requested.
2. The tower structure/picnic table have been eliminated per Planning's request. The trash enclosure is
outside the existing easement. The air and vacuum have been moved out of the 80' easement,
therefore no easement vacations are required.
3. Stubouts are existing and currently located within easements on the site.
4. A letter of agreement will be obtained from the adjacent property owner for offsite sidewalk
construction. This will be acceptable to Mark Virata per telephone conversations between Mark and
the project engineer.
5. Utility Plan Approval Blocks (Sheets 5 & 6) have been added, as requested.
6. General Note #4 has been amended per your request.
Site Plan:
1. The approval block has been changed as required.
Stormwater Utilities: (Donnie Dustin)
Please see attached Utility Comment Sheet with responses.
Enclosed in the resubmittal packet are thirteen sets of revised Project Development Plans, three sets of
Utility Plans, one, revised drainage report and the redlines provided by staff from the September 16
review. Please let me know if you need additional information at this time.
Sincer,�ly,
Pegi en
Project Manager
Enclosures
16. The 80' wide Harmony Road setback area was previously approved and installed per the City
requirements. We are not sure how the City and overall developer arrived at the design, but it is
consistent with all of the other pads along the Harmony Road frontage. None of the other PUD's
approved along Harmony modified the street frontage landscaping. We also understand there are
restrictions of plantings in this area due to the location of the water transmission line located within
the 80' setback. This was addressed as a potential conflict in the Harmony Corridor Standards and
Guidelines, page 10.
17. Although the previous lighting plan met the City of Fort Collins Code on lighting, we reduced the
lighting by approximately half the average foot candles. A revised photometric plan is included in
this resubmittal.
18. Manufacturer's specification sheets are attached for both the canopy lighting and the pole fixtures.
19. No wall pack lighting is proposed for the future convenience store.
20. The building envelope dimensions for the c-store and distance to the nearest property line have been
added to the revised plans per your request.
21. General Note 12 is amended, as requested.
22. Note 10, Sheet 1 of 5 states that all rooftop mechanical equipment will be screened from view.
23. General Note 19 on Sheet 1 of 5 restricts the hours of operation between 5:00 a.m. and 12:00 a.m.
Additional Comments:
Transportation Planning: (Mark Jackson)
1. The bike rack was moved closer to the building entrance per LUS 3.2.2.C.4 a,b,c as requested.
2. The island along the north property line was redesigned as agreed upon in the June 15 meeting with
Ted Shepard and Doug Moore. A sidewalk system is now provided along the northern property line,
plus landscaping.
3. The sidewalk.along the north property line is consistent with existing sidewalks internal to the center.
The service access from the back door of the convenience store to the trash enclosure is 5' and not
intended for public use. All other sidewalks are 8' connecting the existing path along Harmony to the
center. The area immediately in front of the store is 10' as per operational and ADA requirements of
the user.
4. The eastern access point should not present any safety problems. There are existing drive aisles and
parking aisles in the Safeway center closer than what is proposed at this location.
5. See above comments regarding the bus pad. The existing pad was originally designed, approved and
constructed per previous PUD approvals. The Safeway Fueling project will provide the bus shelter
per specifications provided by Ted Shepard. The revised plans extend the existing pad site to the west
to allow for clearance of the 45' bus without blocking the intersection. This should alleviate the safety
concerns.
Poudre Fire Authority Comments: (Michael Chavez)
1. A note is added on the elevation Sheets 3 and 4 of 5 regarding address numerals as required.
2. Conversations with Mr. Chavez confirms that the Hazardous Materials Impact Analysis had been
previously received.
3. A drawing is attached showing the route that a fuel truck will take as it enters and exits the premises
for unloading fuel.
Engineering Department Comments: (Marc Virata)
4. The Project Engineer spoke with Light and Power Department and agreed to remove the shrubs on the
north side of the transformer for access purposes. The City agreed to allow shrubs within the three
foot clearance area for screening. Shrubs will adequately screen the equipment, except where
prohibited by the governing agency.
5. Gas service location is noted.
6. A sketch plan is included with this submittal outlining the fuel truck circulation through the site.
7. Advisory comment regarding a weather -resistive barrier for EIFS construction is noted.
8. The request to rotate the canopy, kiosk, and future convenience store 20 degrees was presented to
Safeway and rejected. The buildings will remain in the same orientation to compliment the
orientation of the recently approved and constructed Blockbuster Video Store immediately east of this
site. The orientation was specifically discussed at our May 3, 2000 meeting with you. The site layout
was based upon direction given at that time. The current orientation was again submitted on May 22
for the Conceptual Review Meeting. Written comments from that meeting once again did not
mention any concern for the orientation, therefore formal drawings, utility plans, grading plans and
drainage calculations were prepared based upon information received to date. As stated in the June 15
meeting, the cost to prepare the detailed drawings required in the Fort Collins "formal submittal" for
this pad site was in excess of $40,000. To make this type of change at this point in design would add
an additional cost of $11,000. The request in itself is not unreasonable, but the timing of the request
is, especially since the orientation question was initially discussed for this reason.
9. A sidewalk has been added along the north property line and adjacent to the internal access drive, as
agreed upon in the meeting of September 15. One tree and shrubs have been added to the island
between the curb cuts. Additional trees and shrubs have been added at the northwest corner of the site
and along the eastern property line as requested in the same meeting.
10. Your request for a pitched canopy roof came as a shock to Safeway since this issue was discussed on
May 3 and at that time we were told that a pitched roof was undesirable since it "drew unwanted
attention" to the canopy. This comment was also consistent with the Neighborhood Convenience
Shopping Center Design Guidelines, which you gave to me at the April meeting. In Section 4.10 the
Guidelines state that Canopies in particular are discouraged from being designed as dominating or
overpowering architectural elements; smaller scale, lighter canopies are encouraged. The project
proceeded with design of the flat -roofed canopy as requested. Again, there was no discussion
contrary to that direction at the Conceptual Review Meeting or in the written comments. The
architect's cost estimate for the redesign and canopy construction is $70,000. This is unacceptable to
Safeway in light of the earlier discussions. The canopy will incorporate the stone columns and will be
painted to match the Blockbuster building, as requested.
11. The canopy fascia and convenience store will match the exterior color of the Lot 5 structure as
requested.
12. Wall signs on the north, west and south convenience store elevations were eliminated per your
requirement.
13. All pump signage has been eliminated.
14. The future convenience store will comply with the LUC Section 3.8.7 (E) 16 regarding any window
signage.
15. The landscaping is shown on the plan for the future convenience store. The convenience store
"parking lot" is 1,496 square feet. 89.76 square feet of landscaping are required to satisfy the 6%
interior parking lot landscaping requirement. The 128.5 square feet of landscaping provided exceeds
this requirement.
T` Galloway, Romero & Associates
iV Design Engineering Planning
5350 DTC Parkway
Englewood, Colorado 80111
(303)770-8884
(303) 770-3636 fax
October 4, 2000
Ted Shepard
City of Fort Collins Planning
281 North College Avenue
Fort Collins, CO 80522
RE: Safeway Fueling Facility at Harmony Safeway Marketplace
Dear Ted:
RECEIVED
0 C T 0 5 2000
CURRENT PLANNING
Thank you for your review comments dated September 15. The following is an itemized response
corresponding with those comments and the referral comments from other agencies:
Planning Department Letter: (Ted Shepard)
1. Engineering Department Comments:
A. The existing Transfort bus pad along Harmony Road has been extended to accommodate a 45'
long bus stopping without blocking the existing intersection. The existing pad is constructed 45'
from the intersection. The revised plans extend the pad to the west, allowing 45' as measured
from the point of curvature of the corner radius. The developer (Safeway fuel) will provide the
shelter. Please forward specifications of which shelter unit you require. We feel that the existing
location of the transit bus pad is the preferred location due to its orientation and accessibility to
the entire shopping center. It is more likely that users of the transit system will frequent the center
for service shops and retail businesses more than the grocery store. Therefore, moving the pad
west is more inconvenient and not the "most direct route" to the majority of businesses at this
center. The current alignment provides a pedestrian connection through the parking area to the
functional center of the overall site. It also is in alignment from the pedestrian plaza and
connection to the Golden Meadows Neighborhood located directly north of the center.
Conversations with Wyatt & Associates make it very clear that the currently approved and
constructed location of the transit stop, which was approved through much discussion at both
preliminary and final PUD stages through public hearings, was a very deliberate action.
B. The trash enclosure is outside of the existing easement. The tower structure has been removed per
Planning request. The air, vacuum and telephone have been relocated outside the platted
easement per your request.
The automatic spill containment system has been incorporated into the site design per City
requirements.
The existing six-inch water line extended to the site will not be used. Per discussion with Jeff Hill,
the line will be abandoned per City requirements.