HomeMy WebLinkAboutHARMONY SAFEWAY MARKETPLACE PUD - FINAL - 33-94B - CORRESPONDENCE - RESPONSE TO STAFF REVIEW COMMENTS (3)TEL NQ.97IT-27r-415Y sap 04,95 rul-21 r".us
Item No. 11 - It Is my understandia that there does not exist any design
drawings for these pi es, or so As Iluilt information regarding how the
were installed. Therefore, per City Comments, Northern Engineering will
As -Built this system end evaluate capacity of the isslating system. This
will also servo as the basis for the release rate of the north detention
pond. We requested that the City provide us with a developed release
rate from the Golden Meadows Ob Filing detention pond, but we will bass
our detailed storm analysis on the outlet pipe and the existing to pp of
pond (Stormwater indicated that they might not have documentation of
this pond). The survey work to verify elevations, slopes, and lengths of
pipes, and pond elevations has been ordered, and will be submttted with
the revised Final Drainage Study,
Item No. 22 - We will confirm all flows entering our site based on
approved drainage reports for the Rockbridge apartments and Courtney
Park. We have been basing our flows on the approved Master Plan for
this area, but Stormwater feels that additional documentation is
required. Since the Rockbridge apartments are still under construction,
we can only assume the approved design will be accurate.
Item No. 13 ; We will provide some additional documentation for the
capacity of these culverts, and eoordinate all Improvements with the
Ditch company.
In addition to the items specifically listed above, we will address all
other items noted in City comments.
Please feel free to call if you have any questions regarding this letter, or
have any other questions regarding this project.
Sincerely,
Roger A. Curtiss P.B.
ost Dennis Wyatts Wyatt and Assoclates
Linda Ripley, VaF/Ripley
Kerrie Ashbeck, City of Fort Collins
Basil Hamdan, City of Fort Collins
Roger Buffington, City of Fort Collins
TEL Na-.97U-271-4157 'Sep U-47o W IQ: TY PAM
study. We Will utilize some overtopping of Innovation Drive and
McMurray in the major storm event, as that is what was assumed
the master plan used.
We cannot explain why the current conditions do not reflect what was
approved in the Master Drainage Study, or why there are error in their
calculations.
Item No. 2 - We will include these detail items on our next submittal
Item No. 3 - We will coordinate our plans with the landscape plan. The
landscape architect does know of our need for the necessary onsite
drainage facilities. Their intent was to provide some berming around the
building to minimize the visual Impacts, based on their meeting with the
homeowners association.
Item No. 4 - We will revise the UDBewer Data.
Item No. s - We WILL provide in drains a summary table on Sheet 2. We will
add additional design points along the downstream conveyance channel
(particularly at Innovation Drive, at the westerly and of the City Sub
station, at the southeasterly corner of the substation, at the Warren Lake
Outlet Ditch crossing. and at the upstream and of the existing 36" pipe.
We will also generate a profile for the pipes crossing McMurray Avenue,
and also we Will profile the downstream conveyance system from
McMurray to the Golden Meadows Regional Pond.
Item No. 6 - After further review of the downstream conveyance system,
the idea of a Stormceptor is being abandoned. The downstream channels
are relatively fiat, as well as being lined with grass and other native
materials, which would provide adequate water quality protection.
Item No. 7 The orifice plate detail will be added to the plans. The
downstream conveyance of the outlet pipe will be verified.
Item No. 8 - The culverts under Innovation Drive will be profiled. and
detailed calculations of their capacity will be included In the final
drainage report.
Item No. 9 - An Brosion Control Escrow letter will be included In the Final
Drainage and Erosion Control Study,
Item No, 10 - Northern Engineering had a meeting with Stormwater
UtWties on or about Au ust 21, 1996. In the meeting we discussed our
verification of capacityin the existing regional pond. At that meeting. it
was agreed that we would provide some documentation regarding that
the developed runoff coefficient used in the approved Master Plan is
generally in conformance with the intensity proposed with this site. We
will do this documentation.
TEL NU.97U-22r-4-15'9 Sep CW,976 f(T:fS RAT
West easement.
Itmn No. 15 - Mo The revised site plan shows in general how the ramps
line up with the proposed crosswalks and stop bars.
Item No. 16 - Signage and striping plans will be included as a part of the
final utility plans
Item No. 17 - This item has been emphasized to the landscape architect.
The location of this main has been taken from design drawings obtained
from the City Water and Wastewater Department. Trees and landscaping
will be kept a minimum of 10' from this mein. Berming, and drainage
swales will be kept as far so possible from this main, Other responses to
additional oeatmenta will be coming from the project architect and the
landscape architect,
In addition, we offer the following response to comments by the
Stormwater Utility dated July 19, 1996. A revised drainage study will be
forthcoming. In general. we understood that all the necessary
downstream easements exist for the conveyance of stormwater flows.
Item No. 1- On August 21. Northern Engineering conducted a field
survey of the downstream channels. Northern Engineering stet with city
Stormwater to discuss the existing condition of these swales. In
particular:
That portion of the conveyance system between the Existing pond
and the City Substation - The channel has boon constructed, but is
in need of maintenance. Attached is a letter from the owner, Bill
Tiley to the homeowner association requesting that this channel be
cleaned Up and restored to its original condition. In addition, we
will analyze this section of ditch or combination of ditch and pipe)
to verify it capacity, and that it is capable of accommodating
undetalned developed flows from the proposed Safeway site.
That portion of the conveyance system adjacent to the City Light
and power Substation - Northern Engineering and the owner Bill
Tilay contacted Glen Schlueter regarding the channel in this area.
A compromise was reached to return this portion of the channel to
it's original condition, as per the Master plan, probably by the use
of berming along the boundaries of the substation,
That portion of the existing conveyance system from Innovation
Drive to the City Substation - This channel also has capacity, but is
in need of some maintenance. Sill Tiley's letter has also instructed
the homeowners association to clean up this channel. Some
additional piping will need to be installed to convey developed
stormweter under Innovation Drive, as well as McMurray. These
additional culverts will be profiled, and detail analysis of their
capacity will be included in the final drainage and erosion control
TEL NIT.97IT-22'1-4 W se p U4. 9b rU : rb P . u2-
Item No. 8 - The configuration and she of fire service lines will be
coordinated with the Architect, as well as the Poudre Fire Authority and
Water and Wastewater.
Item No. 4 + Ox
Item No. 10 - As far as we know, the 80' setback is a recorded easement,
and it was taken from the northerly Right-of-way of Harmony Road.
Widening Harmony Road does not require additional Right-af-Way,
therefore there should be no impact on the existing 80 buffer.
Item No. 11- The layout of Monte Carlo was redesigned to align
00aterlines, more or less.
Items No. 12 - The proposed driveway onto Wheston has been changed to
align with the driveway for Rockbrldge apartments to the west.
Item No. 13 - Monte Carlo Drive (This response is to Kerrie Ashbecks
cormments).1n general, we have eat with the City and the Golden
Meadows Hoomwners Association since we received comments. It was
resolved with the Neighborhood that we would leave the northerly
flowUne of Monte Carlo as is, and move the south flowline A' to the north.
The revised section in shown an our revised utility plans. This should
resolve many of Kerrie's comments. In addition, there will be 3 speed
undulations installed to "calm" traffic (a detail is included in our revised
utility plans). Thera will be a a' sidewalk located on the south side of
Monte Carlo, which will require an additional 3' pedestrian and bicycle
easement. The "bubbles" at the intersection of Monte Carlo and
McMurray have been design to match the existing bubbles located at
Whedbee and Laurel Streets.
As mentioned above, the southerly curb line will be moved to the north
by 4% Our design reflects that we will maintain as much of the existing
asphalt as puz1ble. The existing asphalt will be saweut approxim ate)y 6'
from the existing Up of gutter, and the new curb and gutter installed to
match the grade and cross slope of the existing asphalt. The location of
the existing water main, as shown on our final utility plans, was provided
to us by others (Landstar Garvey). The location shown is based on the
original desl a plans, and the locations as field verified of valve boxes.
At the time ocoastruation, this main will be potholed at certain locations
to verify that the wdsting main is not located under the new curb and
Sutter. Should this axistrng train be found to be closer than S' from the
new flowline (the City minimum), those portions of the main will either be
relocated, or a variance will be sought from the city based on the actual
distance from the new flowilne. Coordination will take place with City
Light & power on the location of their existing facilities. Us west and
Public Service are not currently on the south side of Monte Carlo.
Item No. 14 - An additional 3' pedestrian and bicycle easement will be
required along the south side of Monte Carlo Drive, as well as a 13' Us
M
i TEL W0.970-221-4159 Sep 04.96 10+15 P.01
September 3, 1996
Mr. Ted Shepard
Community Planning and Environmental Services
City of Fort Collins
PO Box 380
281 North College Avenue
Fort Collins, Colorado 80522-0590
RE: Harmony Safeway Marketplace P.U.D. Final
Response to City Comments
Dear Teds
This letter is in response to the comments regarding engineering issues
Northern Engineering Services Inc. (NES) received regarding Harmony
Safeway Marketplace P.U.D. final. Other items related to planning and
landscaping will be addressed under separate cover by -other
consultants. Primarily, our response will be to comments posed by City
Water and Wastewater. 9tormwater, and Engineering (Those items
discussed in Part One - Utility and Engineering comments)
Item No. i - We understand from our clients that they have received
approval for the Right-in/Right-out at Harmony Road. Northern
engineering has revised our plans to reflect a continuous turn lane from
McMurray to Wheaton.
Item No. 2 - The easements shown along Monte Carlo and McMurray have
been widened to 15', per the request of US West. Grading within these
easements will also be restricted to 10% maximum.
Item No. 3 - Sidewalk locations will be coordinated to match on all
subconsultants plans.
Item No. 4 - We will ensure that no grading within a US West easement
exceed 10%.
Item No. 3 - This sidewalk has been meandered slightly to avoid this
pedestal.
Item No. 6 - OK
Item No. 9 - OK
411 SOUTN NONES, SUITE III, FOIT COIUNS, (OIOIADO 11S21,1lf01221-4151, FAA (fll)1214IS9