HomeMy WebLinkAboutTHE RETREAT AT FORT COLLINS (FORMERLY REDWOOD STREET MULTI-FAMILY) - PDP - PDP180002 - CORRESPONDENCE - PROJECT NARRATIVEAll,
With the recent reversal of staffs decision regarding support for an alternative compliance plan that avoids vehicular connection to Lupine Drive, our schedule
for coordinating and completing revisions by July 25`h is very tight. It's very important for our client to be on the September P&Z agenda. Could you support a
2-week turn around for Staff Review which would allow us to submit on August 1" and have Staff Review on August 15`h?
Let us know if this scenario could work.
Thanks!
Linda Ripley, RLA, ULI
land planning/ landscape architecture
IPLEY
RIPLEY DESIGN, INC.
419 Canyon Avenue, Suite 200
Fort Collins, CO 80521
tel. 970.224.5828, ext. 2976
fax. 970.224.1662
linda. riolev ® riDlevdesianinc.com
Stephen Olt
From: Linda Ripley <Lnda.ripley@ripleydesigninc.com>
Sent: Monday, July 16, 2018 4:22 PM
To: Rebecca Everette
Subject: RE: Retreat
Rebecca,
That is great news!
We appreciate it.
Linda
From: Rebecca Everette [ma iIto: reverette@fcgov.com]
Sent: Monday, July 16, 2018 4:03 PM
To: Linda Ripley; Ted Shepard; Katie Andrews; Marc Virata; Heather McDowell
Cc: Klara Rossouw; Cody Snowdon
Subject: RE: Retreat
Hi Linda,
We are ok with a 2-week turnaround for the next review of The Retreat. As you know, this doesn't guarantee that the project will be ready for the September
P&Z, but it does keep the option open.
Thanks,
Rebecca
Rebecca Everette
Development Review Manager I City of Fort Collins
reverette@fcqov.com 1970.416.2625 direct
From: Linda Ripley [mailto:linda.ripley@ripleydesigninc.com]
Sent: Wednesday, July 11, 2018 4:47 PM
To: Ted Shepard <TSHEPARD@fcgov.com>; Katie Andrews <kandrews@fcgov.com>; Marc Virata <MVIRATA@fcgov.com>; Heather McDowell
<hmcdowell @fcgov.com>
Cc: Klara Rossouw <klara@ripleydesigninc.com>; Cody Snowdon <cody@northernengineering.com>; Rebecca Everette <reverette@fcgov.com>
Subject: Retreat