k. There are 60 trees proposed on the landscape plan. Section 3.2.1(0)(3)
specifies that no more than 15% of those trees can be any one species. This
would limit any one species to no more than 9. There are 10 Rocky Mountain
Junipers proposed (this is a repeat comment). Please reduce this amount by
one tree.
Be sure and return all the redlined items when you resubmit.
If you have any questions about these or any other issues related to this project
please feel free to call be at 221-6206.
Yours truly,
If� �
Tr b Y (ones
City Planner
N
s
landscape plan, or at least provide an extra copy of the grading plan (with
the revised building footprints) for planning review.
c. The Contextual Site Plan should not be part of the planning set. It is it's
own drawing that should be labeled 1 of 1. The site plan, landscape plan, and
elevations should be labeled 1 of 3, 2 of 3, and 3 of 3.
d. The Luminaire Schedule specifies that the lighting will be high pressure
sodium, yet the site plan note # 4 states that they will be medal halide.
Please specify on the site plan that the fixtures are high pressure sodium.
[LUC 3.2.41
e. Please enhance the symbol used to depict light fixtures. The symbol is too
small to read clearly.
f. In order to ensure that all buildings interior to the site are not viewable
from the street or adjacent sites, please clarify the detailing of the
screening associated with the fence gates along Manhattan (repeat of part
of comment "d" from Jan. 25 comments).
g. I need to see east elevations (repeat of part of comment "g" from Jan. 25
comments) of the building that used to be called building 10, but is now
called building 8. Keep in mind that this section of wall will also need some
sort of base treatment. _
h. Please include revision dates on the plat. Without these dates, it is hard to
keep track of which version of the plat we are looking at.
i. Section 3.5.1fl(3)(c) of the Land Use Code specifies that windows shall be
individually defined with detail elements such as frames sills and lintels. You
have done a good job at individually defining the windows on the mixed -use
building, but sills and lintels need to be added to the windows (this is a
repeat comment).
j. The "perimeter storage unit back elevation" does not meet the "Mixed -Use,
Commercial, and Institutional Building Standards" in Section 3.5.3 of the
Land Use Code as follows:
• Section 3.5.3(C)(1)&(2) requires that horizontal masses shall not
exceed a height:width ratio of 1:3 without substantial variation in
massing that includes a change in height and a projecting or
recessed elements. Building 8 faces the Carmike Theater
property. Since the height of the buildings are 11'-4", this
standard requires that every 34' along the east fagade of building
8, there be a substantial change in massing that includes both a
change in height and a projecting or recessed element. You have
provided the projecting and recessed elements, but without
elevations of building 8, there's no way to see if you are satisfying
the required change in height. Please provide an elevation of the
east side of building 8 and please ensure that the proper variation
in height (like you show for building 3) is shown on that elevation.
2
Commi ty Planning and Environmental .-vices
Current Planning
City of Fort Collins
STAFF REVIEW COMMENTS
Michael Chalona
Land Images, Inc.
408 Whedbee
Fort Collins, CO 80524
March 19, 2001
Staff has reviewed your re -submittal Park South Mini -storage, and we offer the
following comments:
COMMENTS:
1. Transportation Planning, Technical Services, Engineering, Transfort,
Water/Wastewater, Zoning, Public Service, AT&T Digital Cable, Natural
Resources:
a. Please see the attached comment sheets and/or redlined items from these
departments.
2. Stormwater:
a. I have not yet received comments from this department. As soon as I do, I
will forward them on to you.
3. Current Planning:
a. Section 2.2.11 of the Land Use Code requires that an applicant submit
revisions based on this letter within 90 days or the project application
becomes null and void. Your response to the City's concerns is due by
Friday, June 26, 2001. A 30 day extension to this deadline is available.
All requests for an extension should be directed to the Current Planning
Director. If remaining issues are those that do not require plan revisions, a
status report verifying continuing efforts toward resolving the issues is
required within the same timeline.
b. The existing topo lines are not helpful in the site and landscape plan review.
When I made comment "b" from the January 25rh comment letter, I didn't
realize the topo lines shown were not the proposed topo lines. At this point,
the proposed topo lines would be helpful in the review of the site and
landscape plans, but the existing lines don't help. Please put superimpose the
proposed topo lines reflecting the proposed grading on the site and
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6750 • FAX (970) 416-2020